Draft Minute To Minute Program - GTPP Visit by Chairman & Directors On 22-10-2020 To 24-10-2020

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Office of the Chief Executive Officer,

Neyveli Uttar Pradesh Power Limited,

Tentative Schedule for NUPPL Project review by Directors chaired by Chairman/


NUPPL at GTPP on 22-10-2020 to 24-10-2020

Date Time Programme


21-10-2020 15:00 hrs Receiving at Lucknow Airport
20:00 hrs Accommodation at GTPP Guest House
21:00 hrs Dinner
08:00 hrs Breakfast
09:00 to 09:10 hrs Receiving at Gate Complex
09:10 to 09:30 hrs Inauguration of Gate complex & CMD addressing to all
NUPPL executives
22-10-2020 09:30 to 09:45 hrs Receiving at AO Building - Guard of Honour by CISF to
CMD & Directors
09:45 to 13:00 hrs Site Inspection – GA1 & GA2 Package
09:45 to 10.15 hrs Fuel Oil Pump House
10:15 to 10:35 hrs Auxiliary Boiler & Compressor House
10:35 to 10:55 hrs Unit-1 Boiler & ESP
10:55 to 11:15 hrs Unit-2 Boiler
11:15 to 11:35 hrs CCR “0” Mtr & 17 Mtr floor
Unit-2 TG & Unit-1 TG – 17Mtr floor & Aerial inspection
11:35 to 12.00 hrs
of Switch Yard/ GIS
Unit-1 Transformer Yard, Main Power House “0” Mtr
12:00 to 12:20 hrs
& Unit-2 Condenser area
12:20 to 12:40 hrs Unit-3 Boiler & TG Deck walk through along CD bay
12:40 to 13:00 hrs CPU Building & Service Building
13:30 to 14:30 hrs Lunch at Guest House
15:00 to 16:00 hrs NUPPL Progress Overview Presentation
16:00 to 18:00 hrs Review with L&T at NUPPL Conference hall
18:00 to 20:00 hrs Review with GE at NUPPL Conference hall
21:00 hrs Dinner at Guest House
23-10-2020 08:00 hrs Breakfast at Guest House
09:00 to 10: 00 hrs DAV-NUPPL School Opening Ceremony
10:00 to 13:00 hrs Site Inspection – GA3 Package

10:00 to 10:30 hrs Raw water Reservoir (On the way from Guest House)
10:30 to 11:30 hrs NDCT-1 & CWPH
11:30 to 11:50 hrs Fire & Filter water Pump House and RGF
11:50 to 12:00 hrs Chimney
12:00 to 12:15 hrs Piperack (PR113, PR14 & PR 15) & Ash Silo
12:15 to 12:30 hrs Crusher House
12:30 to 13:00 hrs Pent house, Tunnel & Wagon Tippler
13:30 to 14:30 hrs Lunch at Guest House
15:00 to 17:30 hrs Review with BGR at NUPPL Conference hall
Review of Infrastructure (Township, Land, Water Intake &
17:30 to 19:30 hrs
water carrier system, FGD)
21:00 hrs Dinner at Guest House
24-10-2020 08:00 hrs Breakfast at Guest House
09:00 to 11:00 hrs Site Inspection- Railway Siding
11:30 to 13:00 hrs Meeting with PAP village Pradhans
13:30 to 14:30 hrs Lunch at Guest House
15:00 to 20:00 Meeting with MP, Commissioner & DM at Kanpur
20:00 hrs Leaving for Lucknow & Night halt

CEO/NUPPL

Note:

1) The site visit & meetings will be conducted by following all the Statutory COVID-19 Guidelines
issued by GoI (Wearing of Mask, Social Distancing, Sanitization etc are mandatory)
2) Progress display boards to be presented at designated locations during site visit by respective
package contractors.
3) All the concerned executives are requested to follow the time schedule of visit & be ready
with the concerned contract package in charges, so as to explain to the Senior Management.

Visit Date- 22-10-2020

8 9
TG-2 (17 TG-1
CPU TG-3
Mtr) 7 (17Mtr)
12 10 Aux.
CCR Boiler
0
1 &2
Compress
Boiler-3 Boiler-2 Boiler-1 or House 2

6 4 3
11

5 ESP-1

FOPH

Visit Date- 23-10-2020 1

Fire & Filter


4
Raw water Water PH, RGF
Reservoir

1 3 Pipe
CWPH
rack

Chimney 5 Ash silo


NDCT-1

Crusher Pent House


House Tunnel
6 7
Trach WT
Hopper
9