Ball-Cement-Mill-Monitoring-Inspection-Evaluation Grinding Efficiency
Ball-Cement-Mill-Monitoring-Inspection-Evaluation Grinding Efficiency
Ball-Cement-Mill-Monitoring-Inspection-Evaluation Grinding Efficiency
FOR THE
PRODUCTION PROCESS
16/10/2007 Page 2 of 20
Valid Practice #10
Fine Outlet
Mill End Coarse Diaphragm
Grinding
Wall Grinding Media
Media
Maintaining the condition and effectiveness of the equipment relies on regular site
inspections and measurements around the system. Internal inspection of the mill
should take place on regular basis to assess the condition of the charge and the
liners. Periodically axial samples need to be taken in the mill to assess the
progression of fineness development along the grinding path. From this the
appropriateness of the media size grading for the fineness of the predominant
cement produced on the mill can be assessed. Samples also need to be taken
around the milling circuit to assess the recirculation load and the characteristics
and efficiency of the separator. Temperatures and pressures around the milling
system need to be measured to calculate air velocities and a mass and energy
balance. In combination this information will provide a comprehensive
assessment of the condition of the milling equipment. Periodic gathering of this
information is useful for detecting changes in the condition and the performance
of the mill.
Each ball mill should be inspected at minimum every month. Along with the
internal mill inspections, the ball charge should be monitored according to the mill
kilowatts. The mill should be inspected as soon as mill kW drops by 5% from the
targeted mill kW. During each inspection, a “Monthly mill ball charge inspection
sheet” should be filled out.
16/10/2007 Page 3 of 20
Valid Practice #10
16/10/2007 Page 4 of 20
Valid Practice #10
Sample
The result shows whether or not the grinding progress in the mill is good.
Furthermore, axial sampling can provide indications of possible causes in case of
disturbances.
A typical example of axial sampling is presented hereafter:
16/10/2007 Page 5 of 20
Valid Practice #10
vii. The grinding progress is not only influenced by the ball charge but also by the
material load.
viii. Parallel to the axial sampling and the material load evaluation, the mill internal
is being inspected for coating (on ball charge, liners and diaphragms) The
grading is presented hereafter:
16/10/2007 Page 6 of 20
Valid Practice #10
16/10/2007 Page 7 of 20
Valid Practice #10
70mm
Step
Height
ix. Finally the mill dimensions are checked by measuring the compartment length
and diameter.
x. After internal mill inspection and material (axial) sampling the maintenance
department will close the doors and turn the mill over to the production
department for restart.
16/10/2007 Page 8 of 20
Valid Practice #10
b. the chord length should be measured on top of the ball charge level
(minimum 3 locations in 1st compartment and 4 locations in 2nd
compartment).
c. the number of free liner plates should be measured (minimum 3
locations in 1st compartment and 4 locations in 2nd compartment). Make
sure that the first and last plates (% plate) are estimated with as much
accuracy as possible.
16/10/2007 Page 9 of 20
Valid Practice #10
vii. To check the ball charge quality and composition, ball charge sampling is
performed at the same principle as material axial sampling. Cement bags are
filled with balls after every 1m from the mill inlet to the mill outlet.
viii. After internal mill inspection and material (axial) sampling the maintenance
department will close the doors and turn the mill over to the production
department for restart.
16/10/2007 Page 10 of 20
Valid Practice #10
16/10/2007 Page 12 of 20
Valid Practice #10
16/10/2007 Page 13 of 20
Valid Practice #10
16/10/2007 Page 14 of 20
Valid Practice #10
16/10/2007 Page 15 of 20
Valid Practice #10
The ball charge should be confirmed (both periodically i.e. monthly or after every mill
inspection) by the power measurement using the FLS formula:
N=F*D*μ*a*n*g*π/60= F*D*μ*a*n*0,514
16/10/2007 Page 16 of 20
Valid Practice #10
It is important to realize that there is higher power consumption (kWh/t) when the
maximum production rate is the first priority.
Some mills will be limited to lower volume loading due to mill motor power, stress
on mill shell or stress on the gearing.
Mill inlet trunion size is another possible limiting factor. Ball level in the trunion
should not be higher than 2 to 3 inches.
With a volume loading above 34% classifying liners often lose their beneficial
effect.
This is the recommended minimum ball charge sorting. Some plants may require
sorting more often. For mills with very low utilization, the ball sorting may be less
frequent.
2.4.2. Ball Mill Loading
After sorting add 85 to 90% of ball charge initially. Run ~100 hours before
topping up the ball charge, this allows addition of larger or smaller balls according
to mill inspection and fineness obtained at the partition for the 1st compartment.
After monthly mill inspection
o Balls should be added to get back to the original ball charge design.
o The average size of added balls will be larger than the average size of the ball
charge design, unless the ball charge design is changed.
o A ball charge sampling should be done if the current ball charge is uncertain,
in order to determine what ball sizes to add.
o An important rule of thumb is that one metric ton of balls will increase the mill
power draw by 10kW. The required mill kilowatts must be available before
adding the balls to the mill.
Do not mix different types and metallurgical compositions of balls together, i.e.:
o forged steel and chromium
o low chrome and high chrome balls in the 1st compartment
o balls from different supplier, unless proven effective by extensive testing and
quality control
Exception: Used first compartment balls could be recycled in the second
compartment, if they have the appropriate size (Not mandatory)
Do not add balls that are wet or snow covered to cement mills.
16/10/2007 Page 17 of 20
Valid Practice #10
Add a layer of material to the first compartment only before adding balls to an
empty mill, in order to protect the shell liners.
Never exceed mill motor power.
2.4.3. Ball charge record keeping
The following items should be kept as records in plants for proper ball charge
management:
Monthly mill ball charge inspection sheet.
Ball additions.
Ball charge sorting results.
Ball charge design.
Any unusual occurrence or problem that affected mill performance.
Dates of liner and partition changes
16/10/2007 Page 18 of 20
Valid Practice #10
16/10/2007 Page 19 of 20
Valid Practice #10
2.5. Conclusions
Depending on the findings, the most possible actions may include:
Once per month, the chambers should be charged with the required grinding
media. The required grinding media can be calculated by 3 ways:
Mill motor kW trend
Monthly production combined with the statistical grinding media
consumption (g/t)
Check of the grinding media level at the two chambers
Increase the ball charge according to the Plant policy (either for minimum
energy consumption or for the maximum production capacity), based on the
installed motor power and the typical reference values.
Sorting the ball charge of the both chambers. Once per year, sorting of the
ball charge is required.
Based on axial sampling the ball charge composition or the location of the
intermediate diaphragm could be changed.
The specific electrical energy consumption is compared to the typical
references.
The separator performance could imply the presence of a mechanical failure.
The gas measurements should be used for identifying the source of false air
induction.
The impact flow-meter of separator rejects needs to be calibrated periodically.
The folafon indication should be calibrated periodically.
Based on the main reason for stoppages the run factor is being evaluated and
justified.
16/10/2007 Page 20 of 20