Feb 2017 Buildability Site

The email exchange discusses revisions to a constructability score form and supporting documents for a building project. Fu Cai requests that Ong Lai Seong resubmit the revised form and documents, addressing comments on structure innovations using statrapid load testing and the removal of points for CCTV monitoring. Ong Lai Seong provides updated documents addressing the comments, including a productivity computation worksheet comparing conventional and statrapid load testing.

Uploaded by

Tun Lin Oo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
128 views21 pages

Feb 2017 Buildability Site

The email exchange discusses revisions to a constructability score form and supporting documents for a building project. Fu Cai requests that Ong Lai Seong resubmit the revised form and documents, addressing comments on structure innovations using statrapid load testing and the removal of points for CCTV monitoring. Ong Lai Seong provides updated documents addressing the comments, including a productivity computation worksheet comparing conventional and statrapid load testing.

Uploaded by

Tun Lin Oo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 21

"Fu Cai TOH (BCA)" To: "[email protected]" <[email protected].

SG>
<[email protected] cc: "[email protected]" <[email protected]>
ov.sg> Fax to:
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 9 of 9)
26/04/2017 10:19 AM

Dear Mr. Ong,

We spoke. Please submit the revised constructability score form together with its supporting documents to ensure that the documents are tag
to the project reference number.
Thank you.

Should you have any queries, feel free to contact the undersigned.

Thanks and Regards,

Toh Fu Cai – Executive Manager (Buildability Development)


Construction Productivity and Quality Group | Building and Construction Authority
Tel +65 6804 4227 Fax: +65 6334 3972

Privileged/Confidential information may be contained in this message. If you are not the intended recipient, you must not copy,
distribute or use it for any purpose, nor disclose its contents to any other person. Please delete the email and notify the sender
immediately if you receive this in error. Check out our website at www.bca.gov.sg.

From: [email protected] [mailto:[email protected]]


Sent: Wednesday, 26 April, 2017 8:28 AM
To: Fu Cai TOH (BCA) <[email protected]>
Cc: [email protected]
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 9 of 9)

Dear Fu Cai,

The system prompt successful submission; enclosed please find the system message for your easy reference.

I will call you shortly to clarify further. Thanks for the feedbacks.

(See attached file: Notification of online e-Su.pdf)


Thank you.

Best regards,
LC&T Builder (1971) Pte Ltd

ONG Lai Seong


Project Manager
Tel: 6363 3422 Fax: 6367 4429

"Fu Cai TOH (BCA)" <[email protected]>

"Fu Cai TOH (BCA)" < To: "[email protected]" <[email protected]>


cc: "[email protected]" <[email protected]>
[email protected]>
Fax to:
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part
25/04/2017 07:45 PM 9 of 9)

Dear Mr. Ong,

Please upload the c score form together with the supporting documents. If not the system will prompt rejection. Anyway, you should have some amendments
to the constructability form as well.
Kindly re-submit.

Thanks and Regards,


Fu Cai

From: [email protected] [mailto:[email protected]]


Sent: Tuesday, 25 April, 2017 4:14 PM
To: Fu Cai TOH (BCA) <[email protected]>
Cc: [email protected]; Willie KOH (BCA) <[email protected]>
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 9 of 9)
Dear Fu Cai,

We are pleased to inform that we have uploaded the revised C-Score and the supporting documents to C Score portal.

The ES Number is ES20170425-18387

For your easy reference please.

Thank you.

Best regards,
LC&T Builder (1971) Pte Ltd

ONG Lai Seong


Project Manager
Tel: 6363 3422 Fax: 6367 4429

"Fu Cai TOH (BCA)" <[email protected]>


"Fu Cai TOH (BCA)" <[email protected]> To: "[email protected]" <[email protected]>
cc: "[email protected]" <[email protected]>, "Willie KOH (BCA)" <[email protected]>
Fax to:
19/04/2017 05:08 PM
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 9 of 9)

Dear Mr. Ong,

Use of statrapid load test will be awarded 2 points in this project. Please revise and upload the constructability score form and its supporting documents to the
c score portal.
In turn, please get back to us for the ES submission numbers for our reference .

Thanks and Regards,


Fu Cai

From: [email protected] [mailto:[email protected]]


Sent: Wednesday, 15 March, 2017 10:46 AM
To: Fu Cai TOH (BCA) <[email protected]>
Cc: [email protected]
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 9 of 9)

Dear Fu Cai,

We are pleased to enclose herewith block pile layout plans indicating StatRapid and Kentledge Test for your easy reference please.

(See attached file: BLK-364A Locations - PDF.pdf)(See attached file: BLK-364B Locations - PDF.pdf)(See attached file: BLK-365 MSCP-1
Locations - PDF.pdf)(See attached file: BLK-365 MSCP-2 Locations - PDF.pdf)(See attached file: BLK-365A Locations - PDF.pdf)(See
attached file: BLK-365B Locations - PDF.pdf)(See attached file: BLK-365C Locations - PDF.pdf)(See attached file: BLK-366A Locations -
PDF.pdf)(See attached file: BLK-366B Locations - PDF.pdf)(See attached file: Test Pile Location Table.pdf)
Thank you.

Best regards,
LC&T Builder (1971) Pte Ltd

ONG Lai Seong


Project Manager
Tel: 6363 3422 Fax: 6367 4429

Ong Lai Seong


Ong Lai
To: "Fu Cai TOH (BCA)" <[email protected]>
Seong
cc: Clement Chan Kwok Ching <[email protected]>, "Jebalan Santhiramouleesan" <[email protected]>, "[email protected]" <
[email protected]>, "[email protected]" <[email protected]>, "[email protected]" <[email protected]>, "
11/03/20 [email protected]" <[email protected]>, "Willie KOH (BCA)" <[email protected]>
17 02:08 Fax to:
PM
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 9 of 9)

Dear Fu Cai,

We are pleased to re-submit herewith updated C-Score forms and Statrapid Load Test productivity computation sheet for your easy reference please.
Thank you.

Best regards,
LC&T Builder (1971) Pte Ltd

ONG Lai Seong


Project Manager
Tel: 6363 3422 Fax: 6367 4429

"Fu Cai TOH (BCA)" <[email protected]>


"Fu Cai TOH (BCA)" < To: "[email protected]" <[email protected]>
[email protected] cc: Clement Chan Kwok Ching <[email protected]>, "Jebalan Santhiramouleesan" <[email protected]>, "
[email protected]" <[email protected]>, "[email protected]" <[email protected]>, "[email protected]" <
g>
[email protected]>, "[email protected]" <[email protected]>, "Willie KOH (BCA)" <[email protected]>
Fax to:
10/03/2017 12:01 PM Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 9 of 9)

Dear Mr. Ong,

Please see our remaining comments on constructability, A1369-02177-2014.

1) Structure Innovation, Use of Statrapid Load Test – Under assumptions, to add in the amount of load used to test and the number of man hours
used per day. To provide information over the time taken to test the loads between the two methods.
2) Good Industry Practices – To remove the points for CCTV for real-time monitoring on site.

In addition, please check through the form for spelling errors on innovation items and to include full description on the use of system formwork.
Thank you.

Thanks and Regards,

Toh Fu Cai – Executive Manager (Buildability Development)


Construction Productivity and Quality Group | Building and Construction Authority
Tel +65 6804 4227 Fax: +65 6334 3972
Privileged/Confidential information may be contained in this message. If you are not the intended recipient, you must not copy,
distribute or use it for any purpose, nor disclose its contents to any other person. Please delete the email and notify the sender
immediately if you receive this in error. Check out our website at www.bca.gov.sg.

From: [email protected] [mailto:[email protected]]


Sent: Friday, 10 March, 2017 10:32 AM
To: Fu Cai TOH (BCA) <[email protected]>
Cc: Clement Chan Kwok Ching <[email protected]>; Jebalan Santhiramouleesan <[email protected]>; [email protected];
[email protected]; [email protected]; [email protected]; Willie KOH (BCA) <[email protected]>
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 9 of 9)

Dear Fu Cai,

We refer to our tele-discussion and tele-clarification last evening pertinent to the captioned matter.

We are pleased to re-submit herewith the updated documents for your easy reference please.

1) Structure Innovation – Site gantry with precast works to be awarded with 1 point (1 point added)
2) Structure Innovation – To remove points on tower crane for tip-load more than 10 ton at Blk 364A and Blk 365. (points removed at Blk 364A & Blk
365)
3) Structure Innovation, MSCP – Ride on troweler to be awarded with 2 points. (2 points added to MSCP)
4) Structure Innovation – To provide supporting documents for comparison of conventional pile load testing with statrapid load test. To list down the
assumptions made, sequence of work activities and their respective man hours for comparison. (please refer to enclosed Rapid Load Test productivity
computation worksheet)
5) Good Industry Practices – To remove trade productivity monitoring system points as there are no figures showing productivity improvement in
comparison with Sengkang project. (rental block and BTO blocks classification added to the respective blocks worksheet as per discussion and
clarification)
6) Good Industry Practices – To showcase how concrete monitoring will improve the work process on site, as well as if there are minimum wastage
shown in the excel table. To PDF the excel table for our review. (Some precast database report enclosed for your easy reference; this is claim under
Good Industry Practice - Real Time Monitoring)
7) Good Industry Practices – To provide method statement for false ceiling. (As attached)
8) Good Industry Practices – To provide CCTV images showing construction cycle of the project. (We do not have CCTV images)
(See attached file: BEV_CS01_V1.8.pdf)(See attached file: Good Industry Practice - Real Time Monitoring (Precast Database
Report).pdf)(See attached file: Good Industry Practice - Trade Productivity Monitoring System.pdf)(See attached file: MOS -
ALUMINIUM TILE CLIP-IN CEILING SYSTEM (False Ceiling).pdf)(See attached file: Productivity Computation Worksheet (Stat
Rapid Load Test).pdf)
Should you need further clarification, I can be contacted via mobile at 9188 8075.

Thank you.

Best regards,
LC&T Builder (1971) Pte Ltd

ONG Lai Seong


Project Manager
Tel: 6363 3422 Fax: 6367 4429

"Fu Cai TOH (BCA)" <[email protected]>


"Fu Cai TOH (BCA)" < To: "[email protected]" <[email protected]>
[email protected]: Clement Chan Kwok Ching <[email protected]>, "Jebalan Santhiramouleesan" <[email protected]>, "
[email protected]" <[email protected]>, "[email protected]" <[email protected]>, "[email protected]" <
g>
[email protected]>, "[email protected]" <[email protected]>, "[email protected]" <[email protected]>,
"Willie KOH (BCA)" <[email protected]>
09/03/2017 05:23 PM Fax to:
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 9 of 9)

Dear Mr. Ong,

Please find our remaining comments for constructability on project reference: A1369-02177-2014.

1) Structure Innovation – Site gantry with precast works to be awarded with 1 point.
2) Structure Innovation – To remove points on tower crane for tip-load more than 10 ton at Blk 364A and Blk 365.
3) Structure Innovation, MSCP – Ride on troweler to be awarded with 2 points.
4) Structure Innovation – To provide supporting documents for comparison of conventional pile load testing with statrapid load test. To list down the
assumptions made, sequence of work activities and their respective man hours for comparison.
5) Good Industry Practices – To remove trade productivity monitoring system points as there are no figures showing productivity improvement in
comparison with Sengkang project.
6) Good Industry Practices – To showcase how concrete monitoring will improve the work process on site, as well as if there are minimum wastage
shown in the excel table. To PDF the excel table for our review.
7) Good Industry Practices – To provide method statement for false ceiling.
8) Good Industry Practices – To provide CCTV images showing construction cycle of the project.

Thanks and Regards,

Toh Fu Cai – Executive Manager (Buildability Development)


Construction Productivity and Quality Group | Building and Construction Authority
Tel +65 6804 4227 Fax: +65 6334 3972

Privileged/Confidential information may be contained in this message. If you are not the intended recipient, you must not copy,
distribute or use it for any purpose, nor disclose its contents to any other person. Please delete the email and notify the sender
immediately if you receive this in error. Check out our website at www.bca.gov.sg.

From: [email protected] [mailto:[email protected]]


Sent: Monday, 6 March, 2017 4:42 PM
To: Fu Cai TOH (BCA) <[email protected]>
Cc: Clement Chan Kwok Ching <[email protected]>; Jebalan Santhiramouleesan <[email protected]>; [email protected];
[email protected]; [email protected]; [email protected]; [email protected]; Willie KOH (BCA) <[email protected]>
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 9 of 9)

Dear Fu Cai,

We are pleased to submit herewith constructablility (C-Score) documents for your reference please.

a) Part 1 - C-Score Form version 1.8 and Structural System (External Access)
b) Part 2 - Structural System (Formwork System) Part 1 of 2
c) Part 3 - Structural System (Formwork System) Part 2 of 2
d) Part 4 - Structrual Innovative Methods (Tower Crane)
e) Part 5 - Structrual Innovative Methods (Rapid Load Test, Ride On Power Trowel, Onsite Precast Yard with Gangtry Crane, Hydraulic Placing Boom)
f) Part 6 - Architectural and MEP System (Spray Painting, scissor lift and boom lift)
g) Part 7 - Good Industry Practice (BIM)
h) Part 8 - Good Industry Practice (Trade Productivity Monitoring, Monthly Working Session, Tool Box Meeting and Real Time Monitoring)
i) Part 9 - Good Indusctry Practice (MOS on various Wet Trades)

(See attached file: SBW N3C7 - Method statement of Waterproofing.pdf)(See attached file: SBW N3C7 - Trade Demo Report for Dry Wall
Installation.pdf)(See attached file: SBW N3C7 - Trade Demo Report for Window Installation.pdf)
Thank you.

Best regards,
LC&T Builder (1971) Pte Ltd

ONG Lai Seong


Project Manager
Tel: 6363 3422 Fax: 6367 4429

Ong Lai Seong


Ong Lai
To: "Fu Cai TOH (BCA)" <[email protected]>
Seong
cc: Clement Chan Kwok Ching <[email protected]>, "Jebalan Santhiramouleesan" <[email protected]>, "[email protected]" <
[email protected]>, "[email protected]" <[email protected]>, Low Huei Teck/Projects/LCT@LCT, "[email protected]" <
06/03/20 [email protected]>, SBWN3C7-CJ@LCT, "Willie KOH (BCA)" <[email protected]>
17 04:39 Fax to:
PM
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 8 of 9)

Dear Fu Cai,

We are pleased to submit herewith constructablility (C-Score) documents for your reference please.

a) Part 1 - C-Score Form version 1.8 and Structural System (External Access)
b) Part 2 - Structural System (Formwork System) Part 1 of 2
c) Part 3 - Structural System (Formwork System) Part 2 of 2
d) Part 4 - Structrual Innovative Methods (Tower Crane)
e) Part 5 - Structrual Innovative Methods (Rapid Load Test, Ride On Power Trowel, Onsite Precast Yard with Gangtry Crane, Hydraulic Placing Boom)
f) Part 6 - Architectural and MEP System (Spray Painting, scissor lift and boom lift)
g) Part 7 - Good Industry Practice (BIM)
h) Part 8 - Good Industry Practice (Trade Productivity Monitoring, Monthly Working Session, Tool Box Meeting and Real Time Monitoring)
i) Part 9 - Good Indusctry Practice (MOS on various Wet Trades)

Thank you.

Best regards,
LC&T Builder (1971) Pte Ltd

ONG Lai Seong


Project Manager
Tel: 6363 3422 Fax: 6367 4429

Ong Lai Seong


Ong Lai
To: "Fu Cai TOH (BCA)" <[email protected]>
Seong
cc: Clement Chan Kwok Ching <[email protected]>, "Jebalan Santhiramouleesan" <[email protected]>, "[email protected]" <
[email protected]>, "[email protected]" <[email protected]>, Low Huei Teck/Projects/LCT@LCT, "[email protected]" <
06/03/20 [email protected]>, SBWN3C7-CJ@LCT, "Willie KOH (BCA)" <[email protected]>
17 04:35 Fax to:
PM
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 7 of 9)

Dear Fu Cai,

We are pleased to submit herewith constructablility (C-Score) documents for your reference please.

a) Part 1 - C-Score Form version 1.8 and Structural System (External Access)
b) Part 2 - Structural System (Formwork System) Part 1 of 2
c) Part 3 - Structural System (Formwork System) Part 2 of 2
d) Part 4 - Structrual Innovative Methods (Tower Crane)
e) Part 5 - Structrual Innovative Methods (Rapid Load Test, Ride On Power Trowel, Onsite Precast Yard with Gangtry Crane, Hydraulic Placing Boom)
f) Part 6 - Architectural and MEP System (Spray Painting, scissor lift and boom lift)
g) Part 7 - Good Industry Practice (BIM)
h) Part 8 - Good Industry Practice (Trade Productivity Monitoring, Monthly Working Session, Tool Box Meeting and Real Time Monitoring)
i) Part 9 - Good Indusctry Practice (MOS on various Wet Trades)

Thank you.

Best regards,
LC&T Builder (1971) Pte Ltd

ONG Lai Seong


Project Manager
Tel: 6363 3422 Fax: 6367 4429

Ong Lai Seong


Ong Lai
To: "Fu Cai TOH (BCA)" <[email protected]>
Seong
cc: Clement Chan Kwok Ching <[email protected]>, "Jebalan Santhiramouleesan" <[email protected]>, "[email protected]" <
[email protected]>, "[email protected]" <[email protected]>, Low Huei Teck/Projects/LCT@LCT, "[email protected]" <
06/03/20 [email protected]>, SBWN3C7-CJ@LCT, "Willie KOH (BCA)" <[email protected]>
17 04:32 Fax to:
PM
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 6 of 9)

Dear Fu Cai,

We are pleased to submit herewith constructablility (C-Score) documents for your reference please.

a) Part 1 - C-Score Form version 1.8 and Structural System (External Access)
b) Part 2 - Structural System (Formwork System) Part 1 of 2
c) Part 3 - Structural System (Formwork System) Part 2 of 2
d) Part 4 - Structrual Innovative Methods (Tower Crane)
e) Part 5 - Structrual Innovative Methods (Rapid Load Test, Ride On Power Trowel, Onsite Precast Yard with Gangtry Crane, Hydraulic Placing Boom)
f) Part 6 - Architectural and MEP System (Spray Painting, scissor lift and boom lift)
g) Part 7 - Good Industry Practice (BIM)
h) Part 8 - Good Industry Practice (Trade Productivity Monitoring, Monthly Working Session, Tool Box Meeting and Real Time Monitoring)
i) Part 9 - Good Indusctry Practice (MOS on various Wet Trades)

Thank you.

Best regards,
LC&T Builder (1971) Pte Ltd

ONG Lai Seong


Project Manager
Tel: 6363 3422 Fax: 6367 4429

Ong Lai Seong


Ong Lai
To: "Fu Cai TOH (BCA)" <[email protected]>
Seong
cc: Clement Chan Kwok Ching <[email protected]>, "Jebalan Santhiramouleesan" <[email protected]>, "[email protected]" <
[email protected]>, "[email protected]" <[email protected]>, Low Huei Teck/Projects/LCT@LCT, "[email protected]" <
06/03/20 [email protected]>, SBWN3C7-CJ@LCT, "Willie KOH (BCA)" <[email protected]>
17 04:30 Fax to:
PM
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 5 of 9)

Dear Fu Cai,

We are pleased to submit herewith constructablility (C-Score) documents for your reference please.

a) Part 1 - C-Score Form version 1.8 and Structural System (External Access)
b) Part 2 - Structural System (Formwork System) Part 1 of 2
c) Part 3 - Structural System (Formwork System) Part 2 of 2
d) Part 4 - Structrual Innovative Methods (Tower Crane)
e) Part 5 - Structrual Innovative Methods (Rapid Load Test, Ride On Power Trowel, Onsite Precast Yard with Gangtry Crane, Hydraulic Placing Boom)
f) Part 6 - Architectural and MEP System (Spray Painting, scissor lift and boom lift)
g) Part 7 - Good Industry Practice (BIM)
h) Part 8 - Good Industry Practice (Trade Productivity Monitoring, Monthly Working Session, Tool Box Meeting and Real Time Monitoring)
Thank you.

Best regards,
LC&T Builder (1971) Pte Ltd

ONG Lai Seong


Project Manager
Tel: 6363 3422 Fax: 6367 4429

Ong Lai Seong


Ong Lai
To: "Fu Cai TOH (BCA)" <[email protected]>
Seong
cc: Clement Chan Kwok Ching <[email protected]>, "Jebalan Santhiramouleesan" <[email protected]>, "[email protected]" <
[email protected]>, "[email protected]" <[email protected]>, Low Huei Teck/Projects/LCT@LCT, "[email protected]" <
06/03/20 [email protected]>, SBWN3C7-CJ@LCT, "Willie KOH (BCA)" <[email protected]>
17 04:27 Fax to:
PM
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 4 of 9)

Dear Fu Cai,

We are pleased to submit herewith constructablility (C-Score) documents for your reference please.

a) Part 1 - C-Score Form version 1.8 and Structural System (External Access)
b) Part 2 - Structural System (Formwork System) Part 1 of 2
c) Part 3 - Structural System (Formwork System) Part 2 of 2
d) Part 4 - Structrual Innovative Methods (Tower Crane)
e) Part 5 - Structrual Innovative Methods (Rapid Load Test, Ride On Power Trowel, Onsite Precast Yard with Gangtry Crane, Hydraulic Placing Boom)
f) Part 6 - Architectural and MEP System (Spray Painting, scissor lift and boom lift)
g) Part 7 - Good Industry Practice (BIM)
h) Part 8 - Good Industry Practice (Trade Productivity Monitoring, Monthly Working Session, Tool Box Meeting and Real Time Monitoring)
Thank you.

Best regards,
LC&T Builder (1971) Pte Ltd

ONG Lai Seong


Project Manager
Tel: 6363 3422 Fax: 6367 4429

Ong Lai Seong


Ong Lai
To: "Fu Cai TOH (BCA)" <[email protected]>
Seong
cc: Clement Chan Kwok Ching <[email protected]>, "Jebalan Santhiramouleesan" <[email protected]>, "[email protected]" <
[email protected]>, "[email protected]" <[email protected]>, Low Huei Teck/Projects/LCT@LCT, "[email protected]" <
06/03/20 [email protected]>, SBWN3C7-CJ@LCT, "Willie KOH (BCA)" <[email protected]>
17 04:25 Fax to:
PM
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 3 of 9)

Dear Fu Cai,

We are pleased to submit herewith constructablility (C-Score) documents for your reference please.

a) Part 1 - C-Score Form version 1.8 and Structural System (External Access)
b) Part 2 - Structural System (Formwork System) Part 1 of 2
c) Part 3 - Structural System (Formwork System) Part 2 of 2
d) Part 4 - Structrual Innovative Methods (Tower Crane)
e) Part 5 - Structrual Innovative Methods (Rapid Load Test, Ride On Power Trowel, Onsite Precast Yard with Gangtry Crane, Hydraulic Placing Boom)
f) Part 6 - Architectural and MEP System (Spray Painting, scissor lift and boom lift)
g) Part 7 - Good Industry Practice (BIM)
h) Part 8 - Good Industry Practice (Trade Productivity Monitoring, Monthly Working Session, Tool Box Meeting and Real Time Monitoring)

Thank you.
Best regards,
LC&T Builder (1971) Pte Ltd

ONG Lai Seong


Project Manager
Tel: 6363 3422 Fax: 6367 4429

Ong Lai Seong


Ong Lai
To: "Fu Cai TOH (BCA)" <[email protected]>
Seong
cc: Clement Chan Kwok Ching <[email protected]>, "Jebalan Santhiramouleesan" <[email protected]>, "[email protected]" <
[email protected]>, "[email protected]" <[email protected]>, Low Huei Teck/Projects/LCT@LCT, "[email protected]" <
06/03/20 [email protected]>, SBWN3C7-CJ@LCT, "Willie KOH (BCA)" <[email protected]>
17 04:22 Fax to:
PM
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 2 of 9)

Dear Fu Cai,

We are pleased to submit herewith constructablility (C-Score) documents for your reference please.

a) Part 1 - C-Score Form version 1.8 and Structural System (External Access)
b) Part 2 - Structural System (Formwork System) Part 1 of 2
c) Part 3 - Structural System (Formwork System) Part 2 of 2
d) Part 4 - Structrual Innovative Methods (Tower Crane)
e) Part 5 - Structrual Innovative Methods (Rapid Load Test, Ride On Power Trowel, Onsite Precast Yard with Gangtry Crane, Hydraulic Placing Boom)
f) Part 6 - Architectural and MEP System (Spray Painting, scissor lift and boom lift)
g) Part 7 - Good Industry Practice (BIM)
h) Part 8 - Good Industry Practice (Trade Productivity Monitoring, Monthly Working Session, Tool Box Meeting and Real Time Monitoring)

Thank you.

Best regards,
LC&T Builder (1971) Pte Ltd
ONG Lai Seong
Project Manager
Tel: 6363 3422 Fax: 6367 4429

Ong Lai Seong


Ong Lai
To: "Fu Cai TOH (BCA)" <[email protected]>
Seong
cc: Clement Chan Kwok Ching <[email protected]>, "Jebalan Santhiramouleesan" <[email protected]>, "[email protected]" <
[email protected]>, "[email protected]" <[email protected]>, "[email protected]" <[email protected]>, "Willie KOH (BCA)" <
06/03/20 [email protected]>, SBWN3C7-CJ@LCT, Low Huei Teck/Projects/LCT@LCT
17 04:19 Fax to:
PM
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent) (Part 1 of 9)

Dear Fu Cai,

We are pleased to submit herewith constructablility (C-Score) documents for your reference please.

a) Part 1 - C-Score Form version 1.8 and Structural System (External Access)
b) Part 2 - Structural System (Formwork System) Part 1 of 2
c) Part 3 - Structural System (Formwork System) Part 2 of 2
d) Part 4 - Structrual Innovative Methods (Tower Crane)
e) Part 5 - Structrual Innovative Methods (Rapid Load Test, Ride On Power Trowel, Onsite Precast Yard with Gangtry Crane, Hydraulic Placing Boom)
f) Part 6 - Architectural and MEP System (Spray Painting, scissor lift and boom lift)
g) Part 7 - Good Industry Practice (BIM)
h) Part 8 - Good Industry Practice (Trade Productivity Monitoring, Monthly Working Session, Tool Box Meeting and Real Time Monitoring)
i) Part 9 - Good Indusctry Practice (MOS on various Wet Trades)

Thank you.

Best regards,
LC&T Builder (1971) Pte Ltd

ONG Lai Seong


Project Manager
Tel: 6363 3422 Fax: 6367 4429
"Fu Cai TOH (BCA)" <[email protected]>
"Fu Cai TOH (BCA)" < To: Clement Chan Kwok Ching <[email protected]>, "[email protected]" <[email protected]>, "ong laiseong" <
[email protected]>
[email protected]>
cc: "[email protected]" <[email protected]>, "Jebalan Santhiramouleesan" <[email protected]>, "
[email protected]" <[email protected]>, "Willie KOH (BCA)" <[email protected]>
14/02/2017 03:05 PM Fax to:
Subject: RE: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent)

Dear all,

Please see the attached file for the comments regarding the above-mentioned for your retention and actions.
th
Please submit through email the revised buildable design score and constructability score to us by 6 March 2017.

You may contact me at 6804 4227 if you need any clarifications.


Thank you.

Thanks and Regards,

Toh Fu Cai – Executive Manager (Buildability Development)


Construction Productivity and Quality Group | Building and Construction Authority
Tel +65 6804 4227 Fax: +65 6334 3972

Privileged/Confidential information may be contained in this message. If you are not the intended recipient, you must not copy,
distribute or use it for any purpose, nor disclose its contents to any other person. Please delete the email and notify the sender
immediately if you receive this in error. Check out our website at www.bca.gov.sg.

From: Clement Chan Kwok Ching [mailto:[email protected]]


Sent: Monday, 13 February, 2017 9:50 AM
To: Fu Cai TOH (BCA) <[email protected]>
Cc: Anissa AZLAN from.TP (BCA) <[email protected]>; [email protected]; Chew Kwek KONG (BCA) <[email protected]>; Chay Hong
FOO-LEOH (BCA) <[email protected]>; Jebalan Santhiramouleesan <[email protected]>; ong laiseong <[email protected]>;
[email protected]
Subject: Feb 2017 Buildability Site Check - A1369-02177-2014 (HDB Sembawang N3C7 at Sembawang Crescent)

Dear Mr Toh,

There is parking space avaliable on site.

Kindly note that entrance to site office is along Gambas Crescent.

Attached plan indicating entrance to site office for your easy reference.

cc. Mr Ong, pls take note.

Best Regards,
clement
92349176

www.ong-ong.com

a member of the ONG&ONG Group


Privileged or confidential information may be contained in this message. If you are not the intended recipient, do not copy, distribute or
use it for any purpose nor disclose its contents. Please delete this email and notify the sender immediately if you have received this in
error. Please consider the environment before you print this email. Reduce. Reuse. Recycle.

On 20/1/2017 12:05 PM, Anissa AZLAN from.TP (BCA) wrote:


Dear Mr Steven Low Kong Yen, Mr Lim Yan Ping and Mr Lim Lay Meng
please be informed that we would be conducting buildable design and constructability site check of the above-mentioned project on 13 Feb 2017 at
2.30pm.

Attached is the letter for your retention and necessary actions.

You may contact Mr Toh Fu Cai at 680 44227 if you need clarifications.

Thanks and regards


Nur
Anissa Bt Azlan (Ms)
Temporary Technical Executive (Buildability Development Department)
Building and Construction Authority
Tel +65 6804 4232 Fax +65 6334 3972

Privileged/Confidential information may be contained in this message. If you are not the intended recipient, you must not copy,
distribute or use it for any purpose, nor disclose its contents to any other person. Please delete the email and notify the sender
immediately if you receive this in error. Check out our website at www.bca.gov.sg.

Disclaimer: use of our emails are governed by terms viewed here