Dcu Revamp For Capacity and Efficiency Increase
Dcu Revamp For Capacity and Efficiency Increase
Dcu Revamp For Capacity and Efficiency Increase
Presented By:
Hardeep Singh - Bharat Oman Refineries Limited, Bina, India
Virendra Manral - Chevron Lummus Global, Bloomfield, USA
Unit Introduction
DCU Revamp
Objectives
Design Basis
Methodology
Coke Drum
Heater
Equipment Adequacy check
Other Proposed Modifications
Conclusion
© 2015 Chevron Lummus Global. All Rights Reserved. Company Confidential 2
Unit Introduction
Extraneous streams :
a) Filter backwash stream from the hydrocracker
b) Black slop from refinery
c) Refinery sludge from ETP
Products :
Coke
After successful operation of the DCU at design levels, BORL noted the potential to
Other considerations :
Design Basis :
Capacity Increase : 170 MT/h to 220 MT/h (23,500 BPSD to 30,550 BPSD)
Turndown 50%
kg/cm2g is required for 130% throughput, however the superficial velocity exceeds
the design limits at these conditions
To meet the superficial velocity design criteria, a higher coke drum overhead
Higher pressure coke drum operation will decrease liquid yield and increase coke
make
C5+ Liquid and Coke yield - 1.52 kg/cm2g vs 2.5 kg/cm2g operation
Yield (wt% of feed)
1.52 kg/cm2g
2.5 kg/cm2g
The increase in pressure results in a C5+ liquid yield loss (~ 2 wt.%) equivalent to
about 12 MMUSD/year
Hence, there was merit in investigating options of retaining lower coke drum
overhead pressure
To retain lower coke drum pressure, the addition of a single new coke drum vs.
The benefits of adding a new single drum vs. another pair of coke drums are :
Based on the above, it was decided to install a single new coke drum.
CB&I’s Vertical Plate Coke Drum Technology (VPCD) was selected for the new drum.
Thermal rating of the Coker Heater was carried out for the revamp conditions
Modifications proposed :
Add roof tubes to each cell to keep the radiant flux within the allowable limit
Allows an increase in the End of Run (EoR) Tube Metal Temperature (TMT),
Causes EoR pressure drop to be within the allowable limit, minimizing the
Replace both forced draft and induced draft fans to accommodate higher flow
and static pressure
Reuse the existing burner with new tip drillings and new oil gun
further rating of the APH is to be carried out by the supplier during detailed
engineering phase of the project
Equipment Adequacy :
Wet Gas Compressor : A new wet gas compressor to be installed in parallel with
existing WGC
Center Feed Device (CFD) : New coke drum feed piping configuration has been
designed considering the installation of a CFD in the future if deemed necessary
Delayed Coking units add a lot of flexibility to a refinery operation. It is one of the
most versatile units in terms of “its ability to process a broad range of” feed quality.
The refiner can shift the product slate to a different type of coke or to a different
yield structure based on shifts in the market demand, with minimal changes to the
unit infrastructure.
A successful DCU revamp must be done in a planned manner, with a close working