Testing and Commissioning of UPS System Method Statement
Testing and Commissioning of UPS System Method Statement
Statement
safeworkmethodofstatement.com/testing-commissioning-of-ups-system-method-statement
Webmaster
The UPS System located normally in the LV rooms supports critical telephone & data
room sockets, central equipment in the BMS, Server and security rooms etc. for a period
of 30 minutes until power is restored. The UPS system provides continuous, regulated
AC power to the loads under normal and abnormal conditions, including loss of the
utility AC power.
The purpose of this procedure is to define the step by step method to implement the
correct practices for the precommissioning & commissioning of “UPS System”through
the guidelines contained herein so as to ensure that the job execution complies with the
project requirements and serves the intended function to satisfactory level.
Required Tools
1/3
Commissioning Procedure for UPS System
1. Ensure that all the precommissioning checks are carried out successfully.
2. Ensure that the customer support representative from the
equipment manufacturer is present to check & start the UPS units.
Pre-Power checks:
– Verify that all UPS isolators & battery breaker are open
– Verify that correct voltage (415 VAC) is selected on power supply transformers T2 &
T3.
– Check & verify the UPS voltage output.
– Verify that control switches (Q1,Q2 & Q3) on UPS logic board are open.
Rectifier Section
– Apply mains voltage to input & record.
– Close input isolator
– Set Q3 on UPS logic board to ON position
– Check the rectifier output & record VDC (if necessary adjust by R21 on rectifier logic
board)
– Check battery voltage & polarity
– Check battery breaker
Inverter Section
– Set the inverter switch Q2 on UPS logic board to ON position, the inverter will ramp-
up to nominal voltage.
– Record the output voltage & frequency Output switch section
– Close by-pass isolator
– Set Q1 on UPS logic board to ON position
– Close output isolator
– Measure & record the output voltage
2/3
1. Simulate a power black-out by switching off the input isolator, the inverter will
run on batteries & following messages will be displayed: ‘Battery on load’
2. Close the input isolator
3. Turn off the inverter, the load will be transferred to by-pass.
4. Turn ON the inverter & verify that the load will be transferred automatically to the
inverter.
5. Ensure that proper cooling is taking place
Alarms Test
Attachments:
3/3