AppliedSimulation Examples Ch2 3
AppliedSimulation Examples Ch2 3
consumer products company that if they would simply change the transfer logic between
their batch operations and filling line, they could gain a needed 15% increase in production
without any capital outlay. Similarly, a shipbuilder gained 10% to 20% in throughput in a
bottleneck shop by re-sequencing work.
36
Chapter 1
The sizing of surge areas and buffers are not intuitively obvious as they are based on the
dynamic behavior of the operation. Simulation is used to identify where the surges are
needed and what size they should be so that a minimal amount of inventory is accumulated
in a production area.
37
Applied Simulation: Modeling and Analysis using FlexSim
38
Chapter 1
39
Applied Simulation: Modeling and Analysis using FlexSim
40
Chapter 1
41
Applied Simulation: Modeling and Analysis using FlexSim
Background
Problem statement
Operating data
98
Chapter 3
supervises loading the cars, and one supervises unloading the cars. Extra people can
be added.
The first additional person helps to unload the cars, the next helps to load the cars.
In each case the unloading or loading times are reduced.
The coaster is currently operating with a base of four cars, each with a capacity of
four riders. New cars can be added to the base with the depreciation costs added to
the operating expense.
Rider capacity of the cars can also be
increased with a retrofit paid for through a
depreciation charge. Other operating costs
include depreciation costs for the present
cars, hourly wages, and general maintenance
costs. A summary of the operating costs is
provided in Figure 3.6.
The following options are available to
increase financial performance:
• Increase number of cars
Figure 3.6: Coaster operating costs.
• Increase car capacity (upgrade)
• Increase staffing level for an hour
Expected results
Provide an operating plan that includes staffing levels. Determine if there is sufficient
return to request additional cars.
• How long should the simulation run? The simulation stop time
is set for 12 hours; selecting the run button will continue the
simulation from the stopped point.
• What variables should have the most impact?
• Is there a plan for trying different changes?
• What is most important about the financial report?
• While financial results are the primary metrics, do you feel long
wait times will reduce future riders?
99
Applied Simulation: Modeling and Analysis using FlexSim
Background
Problem statement
The stations are receiving increasing amounts of supplies—some of them with time-
critical contents. Can the work-in-process inventory be reduced by changing opera-
tional parameters?
Operating data
The transfer station has two working cranes. Empty pallets are delivered by a trans-
porter vehicle and transferred to the loading station with a shuttle. A crane will only
start loading the next box of supplies if there is a pallet in the appropriate transfer
station and the correct load is available.
Each pallet contains four crates. When a pallet is filled, it is moved to the distri-
bution side by the shuttle, and a call is made for pickup. When the transporter that
was called stops, the full pallet is loaded and taken to the experiment station. Trans-
porters already en-route will not stop for the pallet.
Only a certain number of transporters are available on the planet. They are sent out
at specific time intervals. After going through the transfer station, they continue to
one of the seven lab stations. After depositing any load, they continue to a transpor-
tation center, where they are brought back as a group to the sending station to once
again be sent to the transfer station.
The supply rocket is normally packed randomly on earth as supplies are brought to
the spaceport. Requests have been made to stage the rocket load first, and then group
them on the rocket by sequence, with several boxes grouped by their destination.
One time unit is one Martian01 second. As on Earth, there are 60 Martian seconds
per Martian minute and 60 Martian minutes per Martian hour.
100
Chapter 3
Expected results
• Run the simulation for a period of time and observe the system
dynamics. How do the cranes work to position crates on
pallets?
• Devise a plan to maximize the distribution of materials to
the laboratory stations. What are the tradeoffs with cost per
crate?
101
Applied Simulation: Modeling and Analysis using FlexSim
Background
As the new engineer working for Slime, Inc., you’ve been asked to familiarize yourself
with the company’s operations (see Figure 3.8). This plant only bottles the green variety
of slime and ranks in the middle of all plants in performance. Overall plant perfor-
mance across package sizes is a key metric, but performance of packing the popular
12-pack of slime is critical from a market perspective. You’ve found a simulation of
the plant that was built last year and decided to try it as a way of understanding the
operation.
Marketing is pushing the plant to agree to higher speeds and smaller tray pack units
because people can only handle so much slime at a time.
As an incentive, bonus points are awarded based on meeting production targets and
result in additional pay at the end of the fiscal year.
Problem statement
What are the best operating conditions to meet marketing and plant needs?
Operating data
Starting from raw plastic, the bottles are created with an injection molding machine.
The plastic forms are puffed into the bottle shape by a blow molder. The empty bottles
are put into baskets that transfer them to an un-scrambler, which in turn lines them
102
Chapter 3
up to go into the filler lines. There are two filler lines that clean, fill, cap, and label the
bottles. The two lines join at the single tray packer. Trays are conveyed to a case closer
and brought to an operator who loads a hand truck to put them into waiting trucks.
One operator is responsible for the molding and unscrambling operations. This
operator unloads the baskets of clean bottles and places the basket back on the return
conveyor. The operator also must attend to any downtime on the equipment in the
area. The second operator carries cases to the trucks and fixes any problems with the
filling and case packing operations. Operators are concerned about their workloads
under the higher production rates.
Once a truck is filled, the facility’s doors will close and re-open only when another
truck has arrived.
The plant can operate at molding speeds between 45 and 85 bottles per minute. At
higher speeds the machines become less reliable and jam more often. This requires the
operators to stop their production-related work and fix the equipment.
The tray packer can handle 12, 16, and 24 count trays. Production standards for the
plant were set based on the 24 count trays when the plant was built. At a given bottle
rate, more 12 count trays are produced, thus requiring the second operator to make
more trips into the trucks carrying 5 cartons per load.
Plant efficiency is rated at better than 97% based on their standard 24 count tray
and 55 bottles per minute. Lower efficiencies will result in lower bonus points.
Expected results
Considering changes in bottles per case and the production rate, prepare a recommen-
dation for the next engineering group meeting indicating what you’ve found out about
the operations and what might be done to improve performance and meet marketing
needs.
103
Applied Simulation: Modeling and Analysis using FlexSim
Background
The Danson Electronics plant (see Figure 3.9) in Pembroke has been assembling high
quality DVD players for two years. To improve their operations, they instituted a
continuous improvement program with teams active on the plant floor.
Problem statement
Operating data
The plant is divided into three buildings. In the first, double circuit boards are populated
with components and then sent to a wave soldering machine. After inspection they are
grouped onto a tray and manually transferred to the next building.
In the second building, the double boards are separated using a router, and the
individual boards are then put through a series of tests. After testing, the boards are
coated and put in racks to dry. Dry boards are manually transported to the third
building for final assembly.
In the assembly building the boards go through a series of assembly steps and tests.
The assembled units are placed on a table and moved to an aging box. After sitting in
the aging box, the units are tested again before moving on to shipping.
Four proposals have been put forth to improve plant productivity:
104
Chapter 3
• The first building team notices that boards are backed up through
the wave soldering machine. They attribute the backup to the
fact that the router operator only has another batch of boards
brought over when the current tray was empty. They want a
surge added before the router so that boards can be moved more
effectively.
• The second building team wants to purchase a new router that
would decrease the routing time by 20%.
• The third building team wants new assembly machines to increase
their throughput by 20%.
• The union wants another person hired for the second building to
help move boards between buildings 2 and 3.
Expected results
105
Applied Simulation: Modeling and Analysis using FlexSim
Background
Problem statement
Use the simulation to determine the best approach to finish the job under the quoted
price.
Operating data
The new breakwater will require 165,000 tons of rock carried by coastal barges
(coasters) for 833 nautical miles from the quarry to the town. The quarry is open for
the loading coasters 12 hours a day on weekdays only. The loaded coasters sail to a
position just outside the coastline where the rocks are transferred to a barge. The barge
then sails to the coastline and discharges the stones directly in front of the location.
Transfers can’t be made if the wave action is too high.
It is possible to use a pontoon to buffer rock material off shore. The coaster can
discharge to the pontoon while the barge is making a transfer so that the barge can
then load from the pontoon if the coaster has left. The pontoons are available in two
sizes.
The choices and costs associated with renting equipment are shown in Figure 3.11.
Site costs are $37,250 per day.
106
Chapter 3
The simulation has three views. One for the quarry, one for the coastal travel, and
one for the project site. Charts accumulate dynamically and the costs are calculated at
the end of the simulation when the transfer of rocks is completed.
107