ENGINEERING STANDARD FOR PIPING and INST PDF
ENGINEERING STANDARD FOR PIPING and INST PDF
ENGINEERING STANDARD FOR PIPING and INST PDF
ENGINEERING STANDARD
FOR
ORIGINAL EDITION
OCT. 1996
This Standard is the property of Iranian Ministry of Petroleum. All rights are reserved to the owner.
Neither whole nor any part of this document may be disclosed to any third party, reproduced, stored in
any retrieval system or transmitted in any form or by any means without the prior written consent of the
Iranian Ministry of Petroleum.
Oct.1996 IPS-E-PR-230
0. INTRODUCTION ............................................................................................................................. 3
1. SCOPE ............................................................................................................................................ 4
2. REFERENCES ................................................................................................................................ 4
3. DEFINITIONS AND TERMINOLOGY ............................................................................................. 5
4. SYMBOLS AND ABBREVIATIONS ............................................................................................... 6
5. UNITS .............................................................................................................................................. 6
6. GENERAL ....................................................................................................................................... 6
6.1 Definition.................................................................................................................................. 6
6.2 Representation ........................................................................................................................ 6
6.3 Drafting .................................................................................................................................... 6
6.4 Equipment Location Index ..................................................................................................... 9
6.5 Drawing Number ..................................................................................................................... 9
6.6 Arrangement............................................................................................................................ 9
7. MINIMUM INFORMATION TO BE SHOWN ON P&I DIAGRAMS............................................... 10
7.1 General ................................................................................................................................... 10
7.2 Equipment Indication............................................................................................................ 10
7.3 Instrumentation ..................................................................................................................... 17
7.4 Piping ..................................................................................................................................... 18
7.5 General Notes........................................................................................................................ 20
8. DESIGN CRITERIA FOR PREPARATION OF P&I DIAGRAMS ................................................. 21
8.1 Assembly Piping of Pumps.................................................................................................. 21
8.2 Steam-Out, Drain and Vent for Vessels .............................................................................. 22
8.3 Bypass for Safety/Relief Valve ............................................................................................ 23
8.4 Block and Bypass Valves for Control Valve ...................................................................... 23
8.5 Line Numbering..................................................................................................................... 23
8.6 Philosophy of Instrumentation Installation ........................................................................ 24
8.7 Utility Connections ............................................................................................................... 24
8.8 Unit Battery Limit Installation .............................................................................................. 25
8.9 Sample Connections............................................................................................................. 27
8.10 Steam Trap Assembly......................................................................................................... 27
9. CRITERIA FOR UTILITY FLOW DIAGRAMS .............................................................................. 29
10. ABBREVIATIONS/GRAPHICAL SYMBOLS/IDENTIFICATIONS ............................................. 30
11. PREPARATION OF P&I DIAGRAMS......................................................................................... 31
11.1 General................................................................................................................................. 31
11.2 Establishment of P&IDs Preparation Steps .................................................................... 31
11.3 Handling of Licensed Process........................................................................................... 36
11.4 Revisions of P&I Diagram .................................................................................................. 37
11.5 Approval of P&I Diagram.................................................................................................... 38
1
Oct.1996 IPS-E-PR-230
APPENDICES:
2
Oct.1996 IPS-E-PR-230
0. INTRODUCTION
The Standard Practice Manuals titled as "Fundamental Requirements for the Project Design and
Engineering" is intended for convenience of use and pattern of follow-up and also a guidance.
These Standard Engineering Practice Manuals, also indicate the check points to be considered by
the process engineers for assurance of fulfillment of prerequisitions at any stage in the
implementation of process plant projects.
It should be noted that these Iranian Petroleum Standards (IPS), as Practice Manuals do not
profess to cover all stages involved in every process project, but they reflect the stages that exist in
general in process projects of oil, gas and petrochemical industries of Iran.
These preparation stages describe the following three main phases which can be distinguished in
every project & include, but not be limited to:
Phase II: Detailed Design, Engineering and Procurement Stages (containing two
Standards)
Phase III: Start-Up Sequence and General Commissioning Procedures (containing two
Standards)
The process engineering standards of this group include the following 11 Standards:
3
Oct.1996 IPS-E-PR-230
1. SCOPE
This Engineering Standard Specification covers the format and technical basis for the Piping and
Instrumentation Diagrams (P&IDs) and Utility Distribution Flow Diagrams (UDFDs) for process,
offsite and utility plants. Namely, the purpose of this manual is to indicate in general terms, the
extents of detailing, valving philosophy and instrumentation requirements of similar process
designs.
This Standard is also intended to establish uniform symbols for equipment, piping and
instrumentation on P&IDs and UDFDs throughout the Oil, Gas and Petrochemical (OGP) projects.
Note:
This standard specification is reviewed and updated by the relevant technical committee on
Oct. 2002. The approved modifications by T.C. were sent to IPS users as amendment No. 1
by circular No. 175 on Oct. 2002. These modifications are included in the present issue of
IPS.
2. REFERENCES
Throughout this Standard the following dated and undated standards/codes are referred to. These
referenced documents shall, to the extent specified herein, form a part of this standard. For dated
references, the edition cited applies. The applicability of changes in dated references that occur
after the cited date shall be mutually agreed upon by the Company and the Vendor. For undated
references, the latest edition of the referenced documents (including any supplements and
amendments) applies.
4
Oct.1996 IPS-E-PR-230
- Company or Employer/Owner:
Refers to one of the related and/or affiliated companies of the Iranian ministry of petroleum
such as National Iranian Oil Company (NIOC), National Iranian Gas Company (NIGC),
National Petrochemical Company (NPC), etc.
- Contractor:
Refers to the persons, firm or company whose tender has been accepted by the Employer,
and includes the Contractor’s personnel representative, successors and permitted assigns.
- Licenser:
Refers to a company duly organized and existing under the laws of the said company’s
country and as referred to in the preamble to the contract.
- Project:
Refers to the equipment, machinery and materials to be procured by the "Contractor" and
the works and/or all activities to be performed and rendered by the "Contractor" in
accordance with the terms and conditions of the contract documents.
- Unit(s):
Refer to one or all process, offsite and/or utility Units and facilities as applicable to form a
5
Oct.1996 IPS-E-PR-230
5. UNITS
This Standard is based on International System of Units (SI), except where otherwise specified.
6. GENERAL
6.1 Definition
The Piping and Instrument Diagram (P&ID), based on the Process Flow Diagram (PFD), represents
the technical realization of a process by means of graphical symbols for equipment and piping
together with graphical symbols for process measurement and control functions.
The Utility Flow Diagram (UFD) is a special type of a P&ID which represents the utility systems
within a process plant showing all lines and other means required for the transport, distribution and
collection of utilities. The process equipment in the UFD can be represented as a box with
inscription (e.g., identification number) and with utility connections.
6.2 Representation
The representation and designation of all the equipment, instrumentation and piping should comply
with the requirements of this Standard. Auxiliary systems may be represented by rectangular boxes
with reference to the separate diagrams.
Dimensions of the graphical symbols for equipment and machinery (except pumps, drivers, valves
and fittings) should reflect the actual dimensions relative to one another as to scale and elevation.
The graphical symbols for process measurement and control functions for equipment, machinery
and piping, as well as piping and valves themselves, shall be shown in the logical position with
respect to their functions.
All equipment shall be represented such that the consistency in their dimensions is considered if not
in contrast to the good representation of the equipment.
6.3 Drafting
6
Oct.1996 IPS-E-PR-230
6.3.3.1 The following requirements shall be shown on the title block of each drawing (see Appendix
B):
- revision table;
- main Company’s name (e.g., National Iranian Oil Company);
- name of Company Relevant Organization, (if any), (e.g., Refineries Engineering and
Construction);
- name of refinery or plant (in English and Persian words);
- Company’s emblem;
- Contractor’s name;
- drawing title;
- Company’s project No.;
- Contractor’s job No. (optional);
- Contractor’s drawing No. (optional);
- Company’s drawing No.
6.3.3.2 Title block sizes and drawing dimensions shall be as follows:
7
Oct.1996 IPS-E-PR-230
6.3.7 Connections
Connections between flow lines or pipelines shall be drawn as shown in Figs. 1 and 2 below:
Fig. 1 Fig. 2
Figs. 3 and 4 show two flow lines or pipelines, which are not connected:
Fig. 3 Fig. 4
6.3.8 Inscriptions
8
Oct.1996 IPS-E-PR-230
a) Equipment
Identification numbers for equipment should be located close to the relevant graphical
symbol, and should not be written into it. Further details (e.g., designation, design capacity,
design pressure, etc.) may also be placed under the identification numbers.
6.6 Arrangement
6.6.1 The preferred arrangement is such that towers, vessels and fired heaters be shown in the
upper half of the diagram, heat exchange equipment in the upper three quarters as practical, and
machinery equipment in the lower quarter. The spacing of equipment and flow lines shall permit
identification and tracing of the lines easily.
6.6.2 The area above the title block on each sheet shall be completely left open for notes.
6.6.3 The general flow scheme shall be from left to right. Unnecessary line crossing should be
avoided.
6.6.4 Process lines entering and leaving the diagram from/to other drawings in the Unit shall be
terminated at the lefthand or righthand side of the drawing. Lines from/to higher number drawings
shall enter and leave the drawing on the righthand end and vice versa.
6.6.5 Each process line entering or leaving the side of the drawing should indicate the following
9
Oct.1996 IPS-E-PR-230
6.6.6 Process lines to/from other Units shall be terminated at the bottom of the drawing at a box
indicating (see also
Appendix C):
a) The service
b) Source or destination Unit name and number
c) The drawing number of the connecting flow diagrams with the relevant coordinates.
6.6.7 All utility lines entering or leaving the diagram shall be terminated at any convenient location
at a box indicating the relevant utility service abbreviation (e.g., CWS, CWR, ISA, etc.). See IPS-E-
PR-308, "Numbering System" and Appendix A of this Standard for utility services abbreviations. A
"Utilities Identification Table" Showing utility services with the reference drawings should be
provided at top or left hand side of each drawing title block (see Appendix D).
6.6.8 Instrument, control system and software linkage signals from sheet to sheet shall be
terminated preferably at the side of sheet or in an appropriate location at a box indicating the
continuation instrument number, location, and drawing number (see Appendix C).
6.6.9 Equipment descriptions of towers, vessels, tanks, furnaces, exchangers, mixers and other
equipment except machinery shall be located along the top of the flow diagram. Machinery
descriptions shall be along the bottom.
7.1 General
7.1.1 Each P&ID shall present all information as required herein below during implementation of a
project in detailed design phase. Extent of information shown on each P&ID in the basic design
stage shall be agreed by Company in advance.
7.1.2 Vendor supplied packages with an outline of the main components shall be shown in a
dashed/dotted box. Letter "P" referring to package shall be indicated adjacent to each equipment
and instrument of the package.
7.1.3 Equipment, instruments or piping which are traced or jacketed, shall be shown.
7.1.4 The identification number and service presentation shall be shown for each piece of
equipment. This information shall be indicated in or adjacent to towers, drums, heaters, tanks and
heat exchangers, etc.
10
Oct.1996 IPS-E-PR-230
b) top and bottom trays, and those trays which are necessary to locate feed, reflux and
product lines;
c) all draw-off trays with tray number and diagrammatic representation of the downcommer
position (e.g., side or center);
d) all nozzles, manholes, instrument connections, drains, vents, pump-out and steam-out
connections, blank-off ventilations, vortex breakers, safety/relief valve connections, sample
connections and handholes;
e) skirt or legs, top and bottom tangent lines;
f) elevations above base line to bottom tangent line of column or to bottom of horizontal
drum;
g) the position of high high liquid level (HHLL), high liquid level (HLL), normal liquid level
(NLL), low liquid level (LLL) and low low liquid level (LLLL);
Notes:
1) For draw-offs only "NLL" shall be shown. The other liquid positions will be shown
as required.
2) Indication of "HHLL" and "LLLL" shall be made only when they are actuating
start/stop of an equipment or machinery through a switch.
3) "HLL", "NLL" and "LLL" shall be shown for all cases except as specified under
Note 1 above.
h) all flanged connections; [all connections whose purpose is not readily evident shall
indicate the purpose (e.g., spare inlet, catalyst draw-off, etc.).];
i) catalyst beds, packings, demisters, chimney trays, distributors, grids, baffles, rotating
discs, mixers, cyclones, tangential inlet and all other internals;
j) water drop-out boots;
k) maintenance blinds for the vessel nozzles.
11
Oct.1996 IPS-E-PR-230
f) The valved vent with blind flange for all columns and vessels provided on the top of the
vessel should be indicated.
g) Relief valves generally located on the top outlet line downstream of the vessel blinding
location or directly connected to the vessel should be indicated.
h) Utility connections on all vessel/columns shall be shown.
i) One local PI shall be indicated on top of vessel/column.
j) One local TI shall be indicated on the top outlet line of vessel/column.
k) Nozzles identifications on vessels, reactors and towers shall be according to Appendix E
of this Standard.
7.2.2 Tanks
12
Oct.1996 IPS-E-PR-230
13
Oct.1996 IPS-E-PR-230
d) At exchangers with circulating heat transfer media, the outlet valve shall be of a throttling
type for control of heat duty.
e) An inlet and outlet, temperature indicator shall be provided on each exchanger (on either
shell or tube side) so that to facilitate checking of heat balance around exchanger.
Type of temperature indicator shall be as follows:
- A board mounted temperature indicator (TI) shall be provided at the inlet and
outlet of all shell and tube process/process exchanger.
- For water coolers, the water side outlet shall be provided with a local TI only. The
shell side in and out shall be provided with board mounted TIs.
- Thermowells (TWs) shall be provided between each shell side and tube side of
the same services when the exchangers are in series.
- Local indicator type shall be provided for the requirement of local temperature
control, such as manual bypass control.
14
Oct.1996 IPS-E-PR-230
b) service;
c) duty (kJ/s);
d) tube side design pressure (internal and external) and design temperature.
7.2.6.1.1 Pumps
a) all nozzles including instrument connections;
b) pump suction valve and strainer, and discharge valve and check valve. Provision of
wafer type check valve should be avoided unless otherwise specified;
c) pump drains and vents piping and destination.
d) the type of pump;
e) pump auxiliary system connections such as, cooling water, seal oil and lube oil, steam,
etc.;
f) detail of lube and seal oil /sealing systems, cooling water piping arrangement, and
minimum flow bypass line requirement for pumps;
g) winterization and/or heat conservation (steam or electrical) where required;
h) warm-up and flushing oil lines detail; a DN20 (¾ inch) bypass/drain from the check valve
to the pump discharge line shall be provided as warm-up line for the cases specified in item
8.1.4 of this Standard;
i) pressure gage located on the discharge of each pump; the gage shall be installed
between the pump discharge nozzle and the check valve;
j) pressure relief safety valves (if any);
k) automatic start-up of standby unit (if required);
l) balanced or equalized line for vacuum service.
15
Oct.1996 IPS-E-PR-230
7.2.6.2.1 Pumps
a) pump item number (this number also appears below the pump);
b) service;
c) capacity, (m³/h, dm³/h for injection pumps);
d) differential pressure, (kPa);
e) relative density (specific gravity) of pumped fluid at pumping temperature;
f) indication of insulation and tracing;
g) miscellaneous auxiliary piping (CW, flushing oil, seal oil, etc.).
7.2.6.2.2 Compressors and blowers
a) equipment item number and stage (this number also appears below the compressor);
b) service:
c) capacity, (Nm³/h);
d) suction pressure, and temperature, [kPa (g)], (°C);
e) discharge pressure, and temperature, [kPa (g)], (°C);
f) miscellaneous auxiliary piping (CW, lube, oil, seal oil / sealing system, etc.);
g) gas horse power, (kW).
16
Oct.1996 IPS-E-PR-230
b) Stage numbers are shown only for multistage compressors. All compressor data for the
first stage shall be indicated. For subsequent stages only N m³/h may be omitted.
7.3 Instrumentation
The following requirements shall be shown:
7.3.1 all instrumentation including test points;
7.3.2 isolation valves connecting to instruments (primary connection valve);
7.3.3 control valve sizes and air failure action (FC, FO, FL);
7.3.4 block and bypass valve sizes at control valve stations;
7.3.5 level gages connection type and range, and level controllers connection type, range and
center of float (where NLL is not shown). Type, material and tracing requirement of level gages shall
be shown (see IPS-E-PR-308);
7.3.6 sequence of opening and closing for the split range control valves;
7.3.7 solenoid shut-down devices at control valves/shut-off valves;
7.3.8 tight shut-off valves requirements (where required);
7.3.9 handwheels when provided on control valves;
7.3.10 limit switches on control valves when required;
7.3.11 mechanical stopper and/or signal stopper on control valves when required;
7.3.12 push buttons and switches associated with shut-down systems;
7.3.13 the instrument tag number for each instrument;
7.3.14 analyzer loop details and special notes as required;
7.3.15 winterization of instruments;
7.3.16 compressor local board mounted instrumentation;
7.3.17 software linkage and alarm and shut-down logic system. Complex shut-down systems shall
be shown as a "black box" with reference made to the logic diagram shown on a separate sheet. All
actuating and actuated devices shall be connected to the "black box";
7.3.18 all elements of advance control and optimization systems;
7.3.19 indication of "Readable From" for all local indicators and/or gages which shall be readable
from a designated valve.
17
Oct.1996 IPS-E-PR-230
7.4 Piping
7.4.1 General
18
Oct.1996 IPS-E-PR-230
7.4.1.14 Safety relief valves type, inlet and outlet size and rating and set pressure should be shown.
7.4.1.15 For pressure ratings designations-nominal size and pipe component-nominal size see
Appendices F & G of this Standard respectively.
7.4.2.1 High point vents and low point drains are shown only when they are connected to a closed
system, or are required for process reasons.
7.4.2.2 Utility lines originate and terminate adjacent to the equipment involved shall be shown. Only
the length of line necessary for valving, instrumentation and line numbering is shown. Utility line
origin and terminus is indicated by reference symbol or abbreviation only. Main utility headers are
not shown on the P&IDs; they are shown on the utility system flow diagrams
7.4.2.3 Pertinent information regarding a line such as "do not pocket" or "slope", etc., shall be noted
adjacent to the line.
7.4.2.4 Typical air cooler manifold piping arrangement should be shown.
7.4.2.5 Connections on process lines which require to be blanked or deblanked for flow direction
under special circumstances to be shown on P&ID.
7.4.2.6 Reduction and enlargement in line size are indicated by line size designation, and reducer
and expander symbols.
7.4.2.7 Calculated wall thicknesses and/or schedules not already prespecified in the individual line
classes shall be shown on the flow diagrams.
7.4.2.8 Corrosion allowances other than the nominal allowances indicated in the individual line
classes shall be shown on the diagrams.
7.4.2.9 All operating drains shall be noted and sized on the flow diagrams and shall be routed to a
drain funnel. Destination of the drains shall be according to the relevant specifications (see IPS-E-
PR-725). All drains carrying light hydrocarbons (Reid vapor pressure 34.5 kPa absolute or greater)
shall be segregated from the oily sewer system, and shall be connected to the flare system.
7.4.2.10 Sample and test connections shall be shown on the diagrams where required. Samples
which require cooling and connections to the flare, shall be shown with the cooling and flare lines
connections.
7.4.2.11 Emergency showers, eye wash fountains and utility stations shall be shown on the Utility
Distribution Flow Diagrams.
7.4.2.12 Any locations where slopes, straight runs, minimum mixing runs, etc., are required for
process reasons must be indicated.
7.4.2.13 The necessary instrumentation and piping for start-up, control and shut-down, etc., should
be shown for any equipment on P&ID wherever applicable.
7.4.2.14 Break points between underground and aboveground piping with insulating flanges (if
required) shall be shown.
7.4.2.15 Minimum distance requirement for in line blending to be indicated.
7.4.2.16 Weep hole requirement to be shown.
7.4.3.1 Piping components not identified by instrument or mechanical equipment numbers, etc., and
not covered by the piping material specification, shall be identified by assigning a Specialty Item
Number or an Item Code Number for identification symbol and shall be shown on the diagrams.
7.4.3.2 Symbol "M" standing for "Monel Trim" should be mentioned on the valves on the P&IDs in
19
Oct.1996 IPS-E-PR-230
services where there is a possibility of condensed water and H2S being present except for the line
classes which provide monel trim valves and other features. Where it is intended that the whole line
should have monel trim valves it should also be indicated on the line list.
7.4.3.3 ASME and non ASME Code change should be indicated for connection wherever
applicable.
20
Oct.1996 IPS-E-PR-230
21
Oct.1996 IPS-E-PR-230
DISCHARGE
8.1.2.1 The suction strainer of pumps shall be selected in accordance with the following criteria:
8.2.1 Size and requirement of steam-out, vent and drain nozzles of vessels shall be according to
the requirements stipulated in IPS-E-PR-200, "Basic Engineering Design Data". The vent valve shall
be directly mounted on the vent nozzle with blind flange.
8.2.2 In addition to the vents required in article 8.2.1 above, a blanked off ventilation nozzle shall be
provided on the top of the all horizontal vessels near the end opposite the manway. See IPS-E-PR-
200 for size of the blanked off ventilation nozzle.
8.2.3 Vent connections must be located on top of the vertical and horizontal vessels.
8.2.4 The drain valve will be provided as follows:
- For low pressure services, up to design pressure of 3800 kPa, provide single block valve
with blind plate.
- For high pressure services over design pressure of 3800 kPa, or where the nature of liquid
requires it, provide double block valves with blind plate.
22
Oct.1996 IPS-E-PR-230
8.3.1 Vessels
Bypass shall be provided unless otherwise specified in the relevant Company’s specifications.
8.3.2 Piping/Equipment
23
Oct.1996 IPS-E-PR-230
g) Line numbers shall be selected so that consecutive line numbers are grouped first by
common service. Spare line numbers may be left between the groupings.
h) All process lines routed from Unit to Unit shall be assigned on interconnecting line
number. Within the process Unit(s), Unit line numbers are to be assigned. The
interconnecting Unit P&I Diagram is to show every interconnecting process line and indicate
the line numbers inside the process Units at the Units battery limits.
8.6 Philosophy of Instrumentation Installation
Reference to be made to Appendix J of this Standard.
24
Oct.1996 IPS-E-PR-230
Fig. 7
Fig. 8
8.8 Unit Battery Limit Installation
25
Oct.1996 IPS-E-PR-230
Fig. 9 Fig. 10
26
Oct.1996 IPS-E-PR-230
27
Oct.1996 IPS-E-PR-230
Fig. 14
The following symbol can be used to demonstrate the steam trap assembly configuration as
shown in Fig. 14 above on P&IDs and UFDs in order to avoid duplication.
Fig. 15
The following symbol can be used in place of the steam trap assembly shown in Fig. 15
above on P&IDs and UFDs.
8.10.2 Steam trap assembly with external strainer (see Fig. 16):
28
Oct.1996 IPS-E-PR-230
Fig. 16
9.1 The Utility Flow Diagram(s) (UFDs) shall be prepared as separate drawing titled as "Utilities
Distribution Flow Diagram". The distribution of utilities for plant operation shall be shown on the
drawing. The utilities for plant operation are generally classified as follows where applicable:
- several grades of steam;
- several grades of condensate;
- boiler feed water;
- cooling water and sea water ;
- raw (fresh) water;
- plant and potable water;
- fuel oil and fuel gas;
- instrument and plant air;
- nitrogen;
- inert gas;
- seal oil/flushing oil;
- closed circuit hot oil system;
- flare and blow-down;
- chemical system such as caustic and ammonia.
The above utilities are classified into several groups and shown on diagram(s) in accordance with
the next articles. A dedicated drawing shall be prepared for "Flare and Blow-down".
9.2 Utility Flow Diagrams shall be presented in accordance with the requirements stipulated in this
Standard for P&IDs where applicable.
9.3 Utility Flow Diagrams shall show main distribution/collection headers and finger headers with
their isolating facilities and instrumentation. The branch line and subheader arrangement shall be
shown as practical as possible.
9.4 Indication criteria of connection between P&IDs and UFDs is according to the following general
philosophy:
a) The indication of isolation valve shall not be duplicated on P&ID and UFD.
b) Valve and instrument which will be used for the normal operation shall be indicated on
P&ID, such as:
- block valves for water cooler inlet and outlet;
- block valves for snuffing steam of heater;
29
Oct.1996 IPS-E-PR-230
10.1 Graphical symbols presented in Appendix A shall be used throughout the Oil, Gas and
Petrochemical projects in order to establish uniform symbols for equipment, piping and
instrumentation on P&IDs and UFDs. This include also Vendor drawings with the same purpose.
10.2 The graphical symbols shown for equipment may be turned or mirrored, if their meaning does
not depend on the orientation. The representation of some graphical symbols (i.e., columns,
vessels, etc.) can be adjusted to the actual scale with respect to the process plant.
The instrumentation symbol size may vary accordingly as required and as per type of document.
However, consistency should be followed in all similar documents.
10.3 For complete equipment codes, instrument identification and instrumentation legends,
reference should be made to IPS-E-PR-308, "Numbering System".
10.4 For all instrumentation symbols, logic diagrams, loop diagrams and graphical symbols not
shown in this Standard and/or in IPS-E-PR-308, reference should be made to the latest revision of
the following ISA standards:
S5.1, "Instrumentation Symbols and Identification"
S5.2, "Binary Logic Diagrams for Process Operations"
S5.3, "Graphical Symbols for Distributed Control/Shared Display Instrumentation,
Logic and Computer Systems"
S5.4, "Instrument Loop Diagrams"
S5.5, "Graphic Symbols for Process Displays"
S18.1, "Annunciator Sequences and Specs"
S50.1, "Compatibility of Analogue Signals for Electronic Industrial Process
Instruments"
S51.1, "Process Instrumentation Terminology"
10.5 Reference should be made to IPS-E-PR-308, "Numbering System" for the following
requirements:
30
Oct.1996 IPS-E-PR-230
11.1 General
As the P&I Diagram contains a large amount of plant design information, its revision will have a
great effect on the subsequent engineering works.
Accordingly for the purpose of minimizing the revisions and avoiding unnecessary works, the steps
for preparing the P&I Diagrams shall be established. The following steps should be realized in
preparing the P&I Diagrams. Upon the information which can be prepared as engineering work
proceeds, steps 2, 3 and 4 may be combined or extended to more steps as required.
In the case where the P&I Diagrams are prepared by the Licensor, only a part of the above-
mentioned steps is applied and the main Contractor shall be responsible to complete the P&IDs
preparation steps. The extent of Licensor’s and Contractor’s scope of work will be according to the
relevant contracts.
31
Oct.1996 IPS-E-PR-230
b) Numbering System
- drawing No.;
- equipment No.;
- instrument tag No.;
- line No.
c) Symbol
- equipment;
- piping components;
- instrument symbol;
- process stream symbol;
- utility symbol.
e) Piping
- piping classification standards;
- valve arrangement at the battery limit;
- valve arrangement for drain, vent, purge and steam-out on piping;
- valve arrangement around the steam trap;
- valve arrangement around the sample point/sample connections;
- blow-down;
- valve type selection criteria/standards;
- strainer type selection standards;
- pipe line sizing criteria.
f) Instrumentation
- valve arrangement around the control valve;
- valve arrangement around the safety/relief valve;
- valve arrangement around other instruments;
- instrument type selection standards;
- mode of indication concerning computer control;
- software linkage and DCS presentation.
g) Miscellaneous
- winterizing and heat conservation;
- recovery of steam condensate;
32
Oct.1996 IPS-E-PR-230
2) Normal operation:
- recorder and indicator points;
- stream analyzer point;
- sampling point and type;
- control valve block and bypass;
- driver type;
- chemical injection point and types of chemical;
- batch operation;
- local start;
- instrumentation and control system needed for optimization and/or process
control.
3) Shut-down operation
- depressuring;
- feed cut-out;
- cooling;
- purging;
- steaming-out and flushing;
- decoking;
- catalyst regeneration.
4) Safety operation
- location of safety/relief valves;
- failure action of control valves;
- prealarm system;
-emergency shut-down system;
-auto start of equipment/system.
Results of hazard analysis and operability (HAZOP) study (if any) note :contractor shall perform the
33
Oct.1996 IPS-E-PR-230
HAZOP study (if required by the owner) using PFD, p&ID and plot plan together with equipment
data sheets and related safety equipment checklist. Contractor shall provide information about the
reported accidents in similar process units in the world during HAZOP meetings.
The Contractor should prepare both the draft of the basic items for preparation of the P&I Diagrams
and all necessary operation and safety features as mentioned above to Company’s review and
approval before issuance of official revision of P&I Diagram for engineering start.
1) Equipment
- number of equipment;
- type of equipment;
- equipment No. and name.
2) Piping
- size of main piping;
- winterizing/heat conservation requirement;
- valve type;
- provision of drain and vent;
- provision of purge, steam-out, chemical injection and water injection connections
and valving;
- line No.;
- utility services connected to each equipment, piping and packaged Unites.
3) Instrumentation
- type of instrument and location of the primary element;
- location and discharge destination of the safety/relief valve;
- location, type and valve functioning (failure action) of the control valve;
- measurement and control method;
- instrument tag No.
The draft of the P&I Diagram for engineering start shall be sent to the Company’s review. After the
joint meeting between the Company and Contractor, the P&I Diagram for engineering start can be
officially issued based on the established Company’s comments as per the agreed items mentioned
in the relevant minutes of meeting.
1) Equipment
- elevation of equipment;
- size of equipment;
- internal of equipment.
2) Piping
- line class;
- miscellaneous piping size (except around the safety/relief valve and control valve);
- thermal and cold insulation;
- precautions concerning piping layout;
- correct orientation of piping around equipment.
34
Oct.1996 IPS-E-PR-230
3) Instrumentation
- size of main control valves;
- additions and revisions on the basis of detailed design.
1) Piping
- piping around the safety/relief valve and control valve;
- size of all valves;
- additional review of the pipe size and branch by the checking of the piping layout;
- hydraulic of system (checking and implementation of the necessary notes).
2) Instrumentation
- sizes of the safety/relief valves;
- sizes of the control valves;
- details concerning level transmitters and level gages;
- logic diagram for heaters, incinerators, compressors, and all other main
equipment (where applicable).
- Consequences of details of cause and effect tables.
3) Vendors information
- The necessary information concerning the Vendors, equipment shall be indicated.
11.2.5.1 At a stage where detailed design has been nearly completed, upon approval of the
Company, the P&I Diagram shall be frozen for the purpose of smooth execution of the construction
work.
11.2.5.2 The P&I Diagram shall be issued for construction after completion of the following
activities:
- piping material table;
- piping class and all relevant job specifications;
- all job specifications and standard drawings in relation to the preparation of P&I
Diagrams;
- logic diagram of the main equipment;
- hydraulic of system;
- size of all piping, valves and instrumentation components;
- vendor’s information.
11.2.5.3 Absolutely, required revisions after freezing of the P&I Diagram shall be made only by
conducting of design activities using the relevant field sketches and executing the required
modifications approved by the Company. This is applicable to revisions called for at the design
department. The frozen P&I Diagram shall not be revised.
11.2.6.1 The P&I Diagram as-built shall be prepared upon completion of the project for filing and
submission to the Company. Since the P&I Diagram is intended for use in conducting operation
35
Oct.1996 IPS-E-PR-230
control, maintenance or revamping, therefore, the prepared drawing shall be entirely in conformily
with the completed facilities.
11.2.6.2 The P&I Diagram as-built shall be prepared in accordance with the results of line checking
and the final edition of the field sketches.
11.2.6.3 The specified piping and instrument take-off and branch points shall be observed as strictly
as possible and shall be implemented on the P&I Diagram. Although bearing no relationship to
piping layout, none of the flange, cap, drain pot, spectacle blind and other miscellaneous piping
designed for installation at the ends of the drain and vent required for operational purposes shall be
omitted.
36
Oct.1996 IPS-E-PR-230
11.4.1 General
Generally P&I Diagram can be revised in the following conditions if complied with the requirements
as outlined in Section 11 of this Standard:
- for correction of typographical and/or engineering errors;
- as per the Company’s instructions;
- implementation of pertinent information in the course of execution of the relevant
engineering work on P&I Diagram;
- addition of information concerning vendors.
Upon agreement with the Company, revisions made after the issuance of the "P&I Diagram for
piping layout" may not be needed by directly revising the P&I Diagram but by issuing the NPIC
"Notification of P&I Diagram Change".
11.4.2 Revisions
The P&I Diagram shall be revised depending on necessity at each step in addition to the required
edition(s) which shall be issued per each step. Accordingly it does not follow that the step No. and
revision No. coincide with each other. At the time of revising the P&I Diagram the NPIC issued up to
that time and information concerning vendors obtained up thereto shall be incorporated on the P&I
Diagram.
11.4.3 NPIC
Issuance of Notification of P&I Diagram Change (NPIC) and manner of presentation shall be agreed
in advance with the Company. NPIC shall be issued in a NPIC form finalized with the Company. In
general issuance of NPIC should consider:
- minimization of P&I Diagram revisions;
37
Oct.1996 IPS-E-PR-230
38
Oct.1996 IPS-E-PR-230
APPENDICES
APPENDIX A
ABBREVIATIONS/GRAPHICAL SYMBOLS/IDENTIFICATIONS
CONTENTS: PAGE No.
39
Oct.1996 IPS-E-PR-230
APPENDIX A
ABBREVIATIONS/GRAPHICAL SYMBOLS/IDENTIFICATIONS
A.1 Abbreviations
A.1.1 General
See IPS-E-PR-308, "Numbering System" for:
- instrumentation identifications;
- equipment abbreviations (codes);
- fluid abbreviations;
- painting, insulation and heat tracing designations.
See IPS-D-AR-010, "Abbreviations & Symbols for HVAC&R Drawings" and IPS-D-AR-011,
"General Notes for HVAC & R System" for:
- Abbreviations & Symbols for HVAC & Refrigeration Systems.
See Appendix D of this Standard for:
- Utilities Identifications Table (Typical).
See Appendix E of this Standard for:
- Nozzles Identifications on Vessels, Reactors and Towers.
40
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
41
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
XCV Steam Trap with Integral Strainer
XV Shut-off Valve
xx 18-8 Stainless Steel Trim Valve
CM Chrome Moly
CS Carbon Steel
DN Diameter Nominal
FF Flat Face
FS Forged Steel
HB Hammer Blind
LJ Lap Joint
MI Mallable Iron
PB Pressure Blind
PN Pressure Nominal
PTP Pipe Tap Plugged
RF Raised Face
RS Removable Spool
RSP Ring Spacer
RTJ Ring Type Joint
SF Socket Weld Line Blind with Flexitallic Gaskets
SB Spectacle Blind
SPB Spade Blind
SO Slip on
SS Stainless Steel
ST(W) Steam Trap (Winterizing)
ST(H) Steam Trap (Heat Conservation)
SV Socket Weld Line Blind with Viton Gaskets
SW Socket Weld
VB Vapor Blind
WN Weld Neck
AG Above Ground
BL Battery Limit
COF Center of Float
DCS Distributed Control System
F Furnished
RO Restriction Orifice
F&P Furnished & Piped
HCB Hydrocarbon
HCH Hydrocarbon with Hydrogen
HHLL High High Liquid Level
HIL High Interface Liquid Level
HLL High Liquid Level
LF Liquid Foam
LG Level Gage
(to be continued)
42
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
LIL Low Interface Liquid Level
LLL Low Liquid Level
LLLL Low Low Liquid Level
LSHH Level Switch High High
LSLL Level Switch Low Low
MW Manway
NIL Normal Interface Liquid Level
NLL Normal Liquid Level
P Pressure
PB Push Bottom
PFD Process Flow Diagram
PG Pressure Gage
PI Pressure Indicator
P&ID Piping & Instrumentation Diagram
PO Pump Out
PT Pressure Test Connection
RES Residue
RG Refrigerant Gas
RL Refrigerant Liquid
RO Restriction Orifice
RS Remote Setpoint
RTD Resistance Temperature Detector
RVP Reid Vapor Pressure
SC Sample Connection
SCL Sample Cooler
SG Sight Glass
SF Solution Foam
SP Set Point
SP.GR. Relative Mass Density (Specific Gravity)
STO Steam Out
TI Temperature Indicator
T/T Tangent to Tangent
TW Thermo-Well
UFD Utility Flow Diagram
UG Under Ground
VB Vortex Breaker
A.1.6 Utility Services Abbreviations
43
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
FOR Fuel Oil Return
FOS Fuel Oil Supply
FWA Fire Water
HBW High Pressure Boiler Feed Water
HPC High Pressure Condensate
HPS High Pressure Steam
ISA Instrument Air
LLPS Low Low Pressure Steam
LPC Low Pressure Condensate
LPS Low Pressure Steam
MBW Medium Pressure Boiler Feed Water
MPC Medium Pressure Condensate
MPS Medium Pressure Steam
NG Natural Gas
NIT Nitrogen
PLA Plant Air
PTW Potable Water
PWA Plant Water(service water)
QHW Quench Water
RFO Refinery Fuel Oil
RFW Refrigerated water
RWA Raw Water
SWA Sour Water
TWA Treated Water
WAT Water
A.2.1 Instrumentation
- Electric Signal
- Electric Binary Signal
- Pneumatic Signal Line
- Heat Traced Line
- Steam Jacketed Line
The following abbreviations shall be used to denote the types of power supply. These designations
may also be applied to purge fluid supplies:
AS Air Supply
- ISA Instrument Air
- PLA Plant Air
ES Electric Supply
GS Gas Supply
(to be continued)
44
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
HS Hydraulic Supply
NS Nitrogen Supply
SS Steam Supply
WS Water Supply
The supply level may be added to the instrument supply line, e.g., ISA-600 "a 600 kPa instrument
air supply; ES-24 VDC " a 24-volt direct current power supply".
(to be continued)
45
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.1.3 Programmable logic controller (PLC) function symbols
(to be continued)
46
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.1.5 Distributed control/shared display symbols
(to be continued)
47
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
Note:
1) For specific logic symbols, see ANSI/ISA standard S5.2.
A.2.1.7 Function identification (Note 1)
(to be continued)
48
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
49
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
50
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
Notes:
1) The function designations associated with controllers, computing devices, converters and
relays may be used individually or in combination (also, see Table 1, Note 14 of ISA-S5.1).
The use of a box avoids confusion by setting off the symbol from other markings on a
diagram and permits the function to be used as a stand-alone block on conceptual designs.
2) See ISA-S5.1, Table 3 for math equation, graphic representation and definition.
A.2.1.8 Control valve body and damper symbols
Reference to be made to article 6.4 of ISA-S5.1 with the following additions:
51
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.2.1 General
SYMBOL DESCRIPTION
Underground pipeline
Existing line
Future line
Vendor package
(to be continued)
52
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
Lines junction
Dripe funnel
Platform
Removable spoolpice
Minimum distance
a)change in sloop
c)change in responsibility
(to be continued)
53
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
SYMBOL DESCRIPTION
Slope
Level reference
Limit , general
Contractor/ vendor
Battery limit
Hood , general
(to be continued)
54
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
SYMBOL DESCRIPTION
Open vent
Butsting disc
Sight glass
Level gage
(to be continued)
55
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
SYMBOL DESCRIPTION
Flanged joint
Compression joint
Swivel joint
Union
Concentric reducer
(to be continued)
56
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
SYMBOL DESCRIPTION
Ring spacer
Spade blind
Hammer blind
expansion bellow
sleeve extension
expansion loop
(to be continued)
57
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
SYMBOL DESCRIPTION
Desuperheater
Ejector
Jet mixer
Ring header
Silencer
(to be continued)
58
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
SYMBOL DESCRIPTION
T-type strainer
Duplex strainer
Pulsation dampener
Filter (general)
Propeller mixer
Turbine mixer
(to be continued)
59
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
SYMBOL DESCRIPTION
Hydrocarbon detector
Portable extinguisher
Wheeled extinguisher
Foam chamber
Insulation on equipment
Spray
(to be continued)
60
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
SYMBOL DESCRIPTION
Manway
Swing elbo
Breather
Vortexx breaker
Exhaust head
(to be continued)
61
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
SYMBOL DESCRIPTION
(to be continued)
62
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.2.2 Symbols for manually operated and miscellaneous valves and monitors
SYMBOL DESCRIPTION
Globe valve
Angle valve
Ball valve
Fourway valve
Butterfly valve
Hydraulic control
Metering cock
Needle valve
Plug valve
S=solenoid valve
Diaphragm valve
(to be continued)
63
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
SYMBOL DESCRIPTION
Treeway valve
Rotary valve
Slide valve
Knife valve
Piston valve
Float valve
(to be continued)
64
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
SYMBOL DESCRIPTION
Stop check
(to be continued)
65
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
SYMBOL DESCRIPTION
Foot valve
Fire hydrant
Deluge valve
Fire monitor
Yard hy drant
Hose reel
Hose house
(to be continued)
66
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
SYMBOL DESCRIPTION
Foam monitor
(to be continued)
67
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.3 Equipment
A.2.3.1 Tower, column, vessel and reactor
(to be continued)
68
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
69
Oct.1996 IPS-E-PR-230
APPENDIX.A (continued)
(to be continued)
70
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
71
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
Note:
All tanks and spheres on each flow diagram are to be shown in Approximate relative size to
each other.
(to be continued)
72
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
73
Oct.1996 IPS-E-PR-230
(to be continued)
74
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
75
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
76
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
77
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
78
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.3.3.3 Air coolers
Note:
1) Indicate percentage of fans with automatic-variable pitch.
A.2.3.3.4 Film evaporator
(to be continued)
79
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.3.4 Machinery
A.2.3.4.1 Pumps
(to be continued)
80
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
81
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
82
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
83
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
84
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.3.5 Miscellaneous mechanical equipment
A.2.3.5.1 Crusher
(to be continued)
85
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.3.5.2 Screen
(to be continued)
86
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
87
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.3.5.4 Drier
(to be continued)
88
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
89
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
90
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.3.5.6 Mill
(to be continued)
91
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
92
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.3.5.9 Separator
(to be continued)
93
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.3.5.10 Filter
(to be continued)
94
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
95
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
96
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.3.5.12 Other miscellaneous equipment
(to be continued)
97
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
98
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
99
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
(to be continued)
100
Oct.1996 IPS-E-PR-230
APPENDIX A (continued)
A.2.4 Concrete/Birck/Soil
SYMBOL DESCRIPTION
Brickwork
Concrete (reinforced)
Refractory clay,
Refractory bricks
Soil
101
Oct.1996 IPS-E-PR-230
APPENDIX B
P&IDs/UFDs TITLE BLOCK (TYPICAL)
102
Oct.1996 IPS-E-PR-230
APPENDIX C
REFERENCE BLOCKS ON P&IDs
1. Reference blocks at the bottom of the drawing (only to be used for process and instrument lines
routing over the subject Unit battery limit).
2. Reference blocks at the side of drawing (only to be used for process and instrument lines inside
the same Unit).
3. Reference arrows for instrument, control system and software linkage signals at the inside of
drawing (for the signals terminating or originating at the side or bottom of drawing see items 1 and
2 above).
103
Oct.1996 IPS-E-PR-230
APPENDIX D
UTILITIES IDENTIFICATION TABLE (TYPICAL)
104
Oct.1996 IPS-E-PR-230
APPENDIX E
NOZZLES IDENTIFICATIONS ON VESSELS, REACTORS AND TOWERS
A,A2 Inlets
B Outlet
C Condensate
D Drain or Draw-off
E*
F Feed
G Level gage or gage glass
H Handhole
J Pumpout
K*
L Level instrument (also LT, LI)
M Manhole
N Reboiler connection
P Pressure connection (also PT, PI)
R Reflux
S Steam or sample connection
T Temperature connection (also TI, TE, TW)
V Vapor or vent
W Relief valve connection
(Oversize unless actual size known)
105
Oct.1996 IPS-E-PR-230
APPENDIX F
PRESSURE RATINGS DESIGNATIONS-NOMINAL SIZE (IMPERIAL-METRIC)
Equivalent pressure ratings designations. Rating designations which have not exact equivalents
Notes:
106
Oct.1996 IPS-E-PR-230
APPENDIX G
PIPE COMPONENT-NOMINAL SIZE
The purpose of this Appendix is to present an equivalent identity for the piping components nominal
size in SI system and imperial unit system, in accordance with ISO 6708-1980 (E).
107
Oct.1996 IPS-E-PR-230
APPENDIX H
TYPICAL SAMPLE CONNECTION DETAILS FOR GASES AND LIGHT LIQUIDS
(RVP 34.5 KPa)
108
Oct.1996 IPS-E-PR-230
APPENDIX I
BLOCK AND BYPASS VALVES FOR CONTROL VALVE
I.1 Without Block and Bypass valves
Block and bypass valve system may not be necessary where the process can be shut-down to
repair the control valve without significant economic loss or where the process can not be feasibly
operated through the bypass. However, the consequences of shutting down a process Unit to
perform a simple task ( such as replacing control valve packing) should always be considered. In
cases where the block and bypass valves are not used, the control valve should be equipped with a
handwheel or other operating devices.
Block and bypass valves are not always necessary in the following cases:
a) In instances where it is desirable to reduce the sources of leakage of hazardous fluids,
such as hydrogen, phenol, or hydrofluoric acid;
b) In clean service where the operating conditions are mild, and mission of valves will not
jeopardize the safety or operability of the Unit;
c) In temporary services such as start-up or shut-down, and where the other operation
modes are possible while the repairing of control valve, such as blending system of oil;
d) Pressure self regulating valves;
e) Shut-off valves
I.2 With Block and Bypass Valves
The following services should be provided with block and bypass valves:
a) Services where omission of valves will jeopardize the safety or operability of the Unit;
b) Services containing abrasive solids or corrosive fluids result in damage of trim of control
valve, and require the repair;
c) In lethal services;
d) In product rundown and feed supplying services;
e) In fuel supply system;
f) In cooling medium supply service;
g) Control valves less than DN 50 (2 inch) size. The block and bypass valves are required
due to small diameter of trim, and may have a possibility of plugging of sludge or
foreign matters;
h) In services that are flashing or at high differential pressure.
I.3 Additional Requirements for Control Valves
Notwithstanding the requirements outlined in article I.1 and I.2 above the following notes should
also be considered:
a) Provide an upstream isolation valve for all control valves unless the upstream system is
to be shutdown on control valve failure.
b) Provide a downstream isolation valve whenever the downstream side of the control
valve can not be isolated from other continuously operating pressure sources.
d) Provide a drain valve downstream of the control valve only when the process fluid is
toxic or corrosive and for tight shut-off services.
For sizes of block and bypass valves, reference should be made to IPS-G-IN_160,”Control Valves”.
109
Oct.1996 IPS-E-PR-230
APPENDIX J
PHILOSOPHY OF INSTRUMENTATION INSTALLATION
Sufficient flow metering, temperature and pressure indications shall be installed in feed, rundown,
and utility streams to provide information for the operation and the calculation of heat, pressure and
material balances for each individual Unit.
If failure of any piece of plant equipment or its associated instrumentation may give rise to hazards
for personnel, to consequence with considerable economic loss, or to undue environmental
pollution, alarm and/or safeguarding instruments shall be installed. Where appropriate,
safeguarding equipment shall be automatically bring the relevant plant or part of the plant to a safe
condition when a desired measurement reaches an unacceptable value.
Separate connections are especially required for instrument of shut-down systems, such as:
- High High or Low Low Level connection which actuate shut-down system.
110