Expense Report: NO Katagori Harga Penawaran Rapp Realisasi Bobot

The document is an expense report for a construction project with a contract value of Rp 1,101,500,000. It includes categories for indirect non-technical costs, preparation costs, direct non-technical costs, direct technical costs, and subtotals for each category. The direct technical construction cost is Rp 492,693,210.93, accounting for 44.73% of the total budget. With other costs, the total projected project cost is Rp 900,080,710.93, leaving a projected savings of Rp 201,419,289.07.

Uploaded by

Kiki Varel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
76 views5 pages

Expense Report: NO Katagori Harga Penawaran Rapp Realisasi Bobot

The document is an expense report for a construction project with a contract value of Rp 1,101,500,000. It includes categories for indirect non-technical costs, preparation costs, direct non-technical costs, direct technical costs, and subtotals for each category. The direct technical construction cost is Rp 492,693,210.93, accounting for 44.73% of the total budget. With other costs, the total projected project cost is Rp 900,080,710.93, leaving a projected savings of Rp 201,419,289.07.

Uploaded by

Kiki Varel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

EXPENSE REPORT

NO KATAGORI HARGA PENAWARAN RAPP REALISASI BOBOT

NILAI KONTRAK Rp 1.101.500.000,00 Rp -


NILAI KONTRAK TAMBAHAN Rp - Rp -
TOTAL NILAI KONTRAK Rp 1.101.500.000,00 Rp -
BIAYA TIDAK LANGSUNG NON TEKNIS
1 Pajak Total Rp 137.687.500,00
2 Biaya Taktik Rp 178.725.000,00
Sub Total Rp 316.412.500,00 Rp -
ANGGARAN PELAKSANAAN MURNI
BIAYA PERSIAPAN
1 Biaya Persiapan Awal Rp 28.700.000,00
2 Biaya Persiapan Lapangan Rp 35.275.000,00
Sub Total Rp 63.975.000,00 Rp -
BIAYA LANGSUNG NON TEKNIS
1 Salary Cost Staf Rp 18.000.000,00
2 Pajak Galian C Rp 5.000.000,00
3 Job Mix Design dan Uji Kuat Tekan Beton Rp 4.000.000,00
Sub Total Rp 27.000.000,00 Rp -
BIAYA LANGSUNG TEKNIS
1 Material for Construction Cost Rp 264.679.370,40
2 Pekerjaan Atap Rp 54.000.000,00
3 Pekerjaan Instalasi Air Bersih dan Air Kotor Rp 4.500.000,00
4 Pekerjaan Instalasi Listrik dan Bahan Beserta Pemasukan Arus Baru Rp 9.000.000,00
5 Pekerjaan Pengecatan (Bahan) Rp 13.500.000,00
6 Biaya Konsultan (MC-0) Rp 10.000.000,00
7 Ongkos Tukang Rp 128.013.840,53
8 Biaya Hutang Bunga Bank Dari 150 Jt Rp 9.000.000,00
Sub Total Rp 492.693.210,93 Rp -
TOTAL BIAYA LANGSUNG DILUAR PEKERJAAN UTAMA Rp 407.387.500,00 Rp -0 36,98%
BIAYA PEKERJAAN UTAMA (CONSTRUCTION COST) Rp 492.693.210,93 Rp - 44,73%
TOTAL BIAYA PEKERJAAN Rp 900.080.710,93 Rp - 81,71%
PROVIT (SAVING) Rp 201.419.289,07 Rp - 18,29%
GRAND TOTAL Rp 1.101.500.000,00 Rp - 100,00%
DETAILS
PERSIAPAN AWAL
1 Jaminan Pelaksanaan 1 Ls Rp 1.500.000 Rp 1.500.000,00
2 Jaminan Pemelihaaan 1 Ls Rp 1.000.000 Rp 1.000.000,00
3 Biaya Penawaran 1 Ls Rp 2.000.000 Rp 2.000.000,00
4 Biaya Pendukung Penawaran 1 Ls Rp 14.200.000 Rp 14.200.000,00
5 Biaya Loby Pekerjaan 1 Ls Rp 10.000.000 Rp 10.000.000,00

Rp 28.700.000,00
PERSIAPAN LAPANGAN
1 #REF! 1 Ls Rp 3.000.000 Rp 3.000.000,00
2 Pembelian Solar Molen 1 Ls Rp 1.000.000 Rp 1.000.000,00
3 Perbaikan Motor (Service) 1 Ls Rp 1.350.000 Rp 1.350.000,00
4 Biaya Makan Minum Lembur Tukang 1 Ls Rp 1.000.000 Rp 1.000.000,00
5 Penyewaan Skalfolding 3 Bulan Rp 975.000 Rp 2.925.000,00
6 Biaya Air Besrsih 1 Ls Rp 1.000.000 Rp 1.000.000,00
7 Operasional Direktur 3 Bulan Rp 5.000.000 Rp 15.000.000,00
8 #REF! 1 Ls Rp 10.000.000 Rp 10.000.000,00

Rp 35.275.000,00

SALARY COST STAF


1 Kodok 3 Bulan Rp 1.500.000 Rp 4.500.000,00
2 Muhammad Rizki Maulana 3 Bulan Rp 3.000.000 Rp 9.000.000,00
3 Makan Staf 3 Bulan Rp 1.500.000 Rp 4.500.000,00

Rp 18.000.000,00
BIAYA LANGSUNG NON TEKNIS
1 Biaya Pajak Galian C 1 Ls Rp 5.000.000 Rp 5.000.000,00
2 Biaya Konsultan (MC-0) 1 Ls Rp 10.000.000 Rp 10.000.000,00
3 Hutang Bunga Bank Dari 150 Jt 3 Bulan Rp 3.000.000 Rp 9.000.000,00

Rp 24.000.000,00

PAJAK TOTAL
PPN (10%) 1 Ls Rp 110.150.000 Rp 110.150.000
PPh (2%) 1 Ls Rp 22.030.000 Rp 22.030.000
Infaq (0,5%) 1 Ls Rp 5.507.500 Rp 5.507.500

Rp 137.687.500,00
REKAPITULASI MATERIAL DAN BAHAN
HARGA JUMLAH HARGA
NO ITEM SATUAN VOLUME
SATUAN (Rp.)

1 BESI
- Besi Dia. 12 Batang 95,00 Rp 77.000 Rp 7.315.000,00
- Besi Dia. 10 Batang 14,00 Rp 56.000 Rp 784.000,00
- Besi Dia. 7 Batang 90,00 Rp 36.000 Rp 3.240.000,00

2 SEMEN
- Portland Semen Zak 245,00 Rp 57.000 Rp 13.965.000,00
- Semen Warna Kg 17,58 Rp 15.000 Rp 263.632,67

3 MATERIAL
- Kerikil M3 6,27 Rp 400.000 Rp 2.507.219,96
3
- Pasir Pasang M 34,72 Rp 166.667 Rp 5.786.497,68
3
- Batu Gunung M 18,03 Rp 200.000 Rp 3.606.750,00
- Batu Bata Buah 15.000,00 Rp 750 Rp 11.250.000,00
- Tanah Timbun M3 30,00 Rp 116.667 Rp 3.500.000,00

4 BEKISTING
- Kayu Lat Seng Batang 49,00 Rp 25.000 Rp 1.225.000,00
- Kayu 5/5 Batang 19,00 Rp 95.000 Rp 1.805.000,00
- Kayu Papan Lembar 14,00 Rp 86.000 Rp 1.204.000,00
- Kayu Bulat Batang 20,00 Rp 15.000 Rp 300.000,00
- Kayu Profil 5/5 M 120,68 Rp 21.250 Rp 2.564.356,50
- Triplek 12 mm Lembar 14,00 Rp 165.000 Rp 2.310.000,00
- Triplek 6 mm Lembar 0,00 Rp 90.000 Rp -
- Paku Triplek Kg 0,00 Rp 20.000 Rp -
- Paku 2 1/2 Inchi Dus 1,00 Rp 185.000 Rp 185.000,00
- Paku 3 Inchi Dus 1,00 Rp 185.000 Rp 185.000,00
- Paku 5 Inchi Dus 1,00 Rp 185.000 Rp 185.000,00
- kawai Ikat Kg 50,00 Rp 20.000 Rp 1.000.000,00

5 BAHAN
- Keramik 40 x 40 (Polish) Dus 60,00 Rp 64.000 Rp 3.840.000,00
- Keramik 20 x 20 (Unpolish) Dus 5,00 Rp 45.000 Rp 225.000,00
- Keramik 20 x 25(Dinding) Dus 20,00 Rp 84.000 Rp 1.680.000,00

6 KUSEN PINTU DAN JENDELA


- Kusen Pintu dan Jendela Ls 1,00 Rp 2.650.000 Rp 2.650.000,00
- Daun Pintu, Jendela dan Ventilasi LS 1,00 Rp 6.750.000 Rp 6.750.000,00

7 INSTALASI LISTRIK
- Pemasukan Arus Baru Ls 1,00 Rp 1.200.000 Rp 1.200.000,00
- Instalasi dan Bahan Ls 1,00 Rp 1.800.000 Rp 1.800.000,00

8 INSTALASI AIR BERSIH


- Instalasi WC dan Bahan Ls 1,00 Rp 300.000 Rp 300.000,00

9 INSTALASI AIR KOTOR


- Instalasi WC dan Bahan Ls 1,00 Rp 1.200.000 Rp 1.200.000,00

10 PEKERJAAN PLAFOND
- Borongan Plafond Ls 1,00 Rp 9.900.000 Rp 9.900.000,00

11 PEKERJAAN ATAP
- Borongan Atap Ls 1,00 Rp 18.000.000 Rp 18.000.000,00

12 PEKERJAAN PENGECATAN
- Cat Kg/ Liter 4,00 Rp 800.000 Rp 3.200.000,00
- Siler Kg/ Liter 2,00 Rp 500.000 Rp 1.000.000,00
- Alat Cat Ls 1,00 Rp 300.000 Rp 300.000,00
JUMLAH TOTAL Rp 115.226.456,80
ONGKOS TUKANG
PEKERJAAN : PEMBANGUNAN RUMAH DINAS PUSKESMAS
LOKASI : KOTA SABANG
TAHUN : 2020

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp) (Rp)

(1) (2) (3) (4) (6) (7)

I. PEKERJAAN PERSIAPAN
1 Perataan dan Pembersihan lapangan (Awal dan Akhir) 1,000 Ls 500.000,00 Rp 500.000,00
2 Pengukuran dan Pemasangan Bowplank 1,000 Ls 500.000,00 Rp 500.000,00

II PEKERJAAN TANAH
2
1 Galian tanah pondasi Menerus 36,204 M 60.000,00 Rp 2.172.240,00

III. PEKERJAAN PONDASI


3
1 Pasangan pondasi batu gunung / batu kali 15,112 M 110.000,00 Rp 1.662.313,13

IV. PEKERJAAN BETON BERTULANG


1 Pondasi Tapak 80x80 cm 2,00 Unit 200.000,00 Rp 400.000,00
2 Sloop 18/25 63,650 M 40.000,00 Rp 2.546.000,00
4 Kolom Praktis 13 x 13 cm 22,000 Unit 100.000,00 Rp 2.200.000,00
5 Kolom 30 x 30 cm 2,000 Unit 100.000,00 Rp 200.000,00
6 Balok 13 x 15 cm 6,000 M 40.000,00 Rp 240.000,00
7 Balok Latai 13 x 20 cm 18,500 M 40.000,00 Rp 740.000,00
8 Balok 20 x 30 cm 6,000 M 40.000,00 Rp 240.000,00
9 Ring Balok 13 x 20 cm 56,650 M 40.000,00 Rp 2.266.000,00
10 Balok Top Gevel 13 x 13 cm 30,000 M 40.000,00 Rp 1.200.000,00
11 Plat Daag T = 12 cm 2,188 M2 160.000,00 Rp 350.000,00

V. PEKERJAAN DINDING DAN PLESTERAN


1 Pasangan dinding bata 1 : 2 30,947 M2 40.000,00 Rp 1.237.860,00
2
2 Plesteran dinding 1 : 2 61,893 M 20.000,00 Rp 1.237.860,00
2
3 Pasangan dinding bata 1 : 4 165,152 M 40.000,00 Rp 6.606.096,00
4 Plesteran dinding 1 : 4 311,941 M2 20.000,00 Rp 6.238.816,00

VI. PEKERJAAN LANTAI PINTU DAN JENDELA


1 Pasang Kusen Pintu 7,000 Unit 50.000,00 Rp 350.000,00
2 Pasang Kusen Jendela 6,000 Unit 50.000,00 Rp 300.000,00
3 Pasang daun Pintu 7,000 Unit 100.000,00 Rp 700.000,00
4 Pasang Daun Jendela dan Vent 6,000 Unit 70.000,00 Rp 420.000,00

VII. PEKERJAAN LANTAI DINDING KERAMIK


1 Cor Lantai kerja t=7cm 4,251 m3 25.000,00 Rp 106.270,15
2 Keramik lantai 40x40 (polished) 56,692 M2 40.000,00 Rp 2.267.680,00
2
3 Keramik lantai toilet 20x20 (unpolish) 4,034 M 50.000,00 Rp 201.690,00
2
4 Keramik dinding toilet 20x25 18,364 M 50.000,00 Rp 918.200,00

VIII. PEKERJAAN PENGECATAN


2
1 Cat Dinding tembok setara vinilex 373,83 M 10.500,00 Rp 3.925.254,90
2
2 Cat Plafond setara vinilex 90,000 M 10.500,00 Rp 945.000,00

IX. PEKERJAAN INSTALASI AIR BERSIH DAN KOTOR


1 Septitank, Pipa, Kloset dan Kran Air 1,00 Ls 2.000.000,00 Rp 2.000.000,00

JUMLAH TOTAL Rp 42.671.280,18


BIAYA TAKTIK

1 ULP 1 Ls Rp 33.045.000 Rp 33.045.000,00


2 Polisi 1 Ls Rp 5.000.000 Rp 5.000.000,00
3 Jaksa 1 Ls Rp 5.000.000 Rp 5.000.000,00
4 Dinas 1 Ls Rp 22.030.000 Rp 22.030.000,00
5 KD 1 1 Ls Rp 110.150.000 Rp 110.150.000,00
Rp 175.225.000,00

6 Ajudan KD 1
- Ajudan I 1 Ls Rp 1.000.000 Rp 1.000.000,00
- Ajudan I 1 Ls Rp 1.000.000 Rp 1.000.000,00

Rp 2.000.000,00

7 Wartawan 1 Ls Rp 500.000 Rp 500.000


8 Kepala Kampung 1 Ls Rp 1.000.000 Rp 1.000.000
Rp 1.500.000

TOTAL Rp 178.725.000,00