Chapter 10 PDF
Chapter 10 PDF
Chapter 10 ! overview
In this chapter the basics of project monitoring and control are explained, including some
straightforward examples to illustrate the most common methods being applied on projects.
It becomes clear that adequate project controls are a critical part of project success and that
the project controls team has an important role to play. Adequate control means applying the
right level of control for each scope element and associated risks during the subsequent project
phases.
Being the conscience of the project manager, the project controls team needs to provide reliable
information for timely decision making. This requires input from many different disciplines and
external parties that needs to be analysed, integrated and reported. To perform this essential task,
the project controls team needs to proactively engage with the project team and various exter-
nal stakeholders, while realising that they all have their own interest in measuring and reporting
project performance.
This chapter starts by explaining how to establish the right cost and schedule baseline, followed
by controlling the project as it develops. Next progress reporting, the role of the project controls
team and the importance of effective communication is being described.
Chapter 10 ! outline
10.1 Introduction
10.2 Cost estimating
10.3 Planning and scheduling
10.4 Cost and Schedule control
10.5 Progress reporting
10.6 Project controls team
10.7 Fit-for-purpose project controls
176
925836-02_194_17-Feb-15_08:43:37_walter
the scene and money at work
Chapter 10
Project monitoring
and control
by Maurits Gerver
10.1 ! Introduction
Most project managers will at least feel somewhat uncomfortable when they are asked if they are
fully in control of their project. Being risk-averse by nature, a project manager will immediately
think about matters that could go wrong, wondering whether she might have missed an uniden-
tified risk and of course think about the weak spots already known.
According to the online Oxford dictionary control can be defined as ‘the power to influence or
direct people’s behaviour or the course of events’. This is the essence of controlling a project,
being able to influence the course of a project by knowing where to go, knowing how to get
there and knowing which steps should be taken in case the project derails.
If a project is not in control, a variety of things can go wrong. Below some statements are listed
that will sound familiar to most project managers:
• The agreed schedule to deliver the project was unrealistic from the start.
• The stream of scope changes during construction never seemed to stop.
• We have significantly underspent budget.
• It took months before producing at design capacity.
• The operational cost turned out to be much higher than predicted.
Realising that projects should add value to a business, the above samples illustrate that there
are many ways to erode that value. This can be caused by poor definition of the initial premises,
for example committing to an unrealistic budget or schedule. But it can also be caused by poor
scope definition, lack of planning, or poor cost control. In the worst case a project gets out of
control and the initial business value has vanished by the time the project is delivered.
As a project develops from initial business opportunity to design and engineering, construction
and handover to the end-user, project controls mature accordingly. As the level of project defini-
tion grows over time project controls will be performed on a more detailed level.
The next paragraphs describe the key elements to control project planning and execution. They
also discuss the impact that human behaviour can have on project controls, both from within the
project controls team as from stakeholders outside the team.
177
925836-02_195_17-Feb-15_08:43:37_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
10.2.1 Introduction
One of the most important elements to control during the lifetime of a project is cost, starting
with providing the right cost estimates.
The cost estimate covering the initial capital investment, also called Capital Expenditure (CAPEX),
is usually generated at the very beginning of a project, or even before project initiation, and is
subsequently updated and detailed during project development. The estimate covering the oper-
ational cost, also known as Operational Expenditure (OPEX) or Revenue Expenditure, includes
all cost incurred during normal operations once the project has been delivered. OPEX typically
includes the cost of operations, maintenance cost, consumables and cost of sales. Although this
chapter will primarily focus on estimating and controlling the capital investment, the operational
cost is also an important input to the project economics and can be used to make trade-offs
during design and procurement on the basis of lifecycle cost, also referred to as Total Cost of
Ownership.
The quality of a capital cost estimate is critical, as it impacts the economics of a project and can
determine the investment decision. Since funds and resources are constrained, a company can
only invest in a limited number of projects, depending on their business cases. Poor cost esti-
mates can either result in cancellation of economically sound projects, or in wasting money and
resources on non-profitable projects.
In this paragraph the different classes of estimates and their specific purposes are explained,
followed by describing a cost-estimate structure and the commonly applied estimating
methodologies.
178
925836-02_196_17-Feb-15_08:43:37_walter
the scene and money at work
Although there are many different cost estimate classifications used in the industry, the accuracy
ranges and required supporting project definition are comparable. However the end usage of
an estimate can vary per stakeholder. An owner’s company could use an estimate for project
sanctioning, while an EPCM contractor uses the same class of estimate to prepare a bid. Table
10.1 provides an overview of estimate classes, based on the Generic Cost Estimate Classification
Matrix as developed by AACE International (AACE, 2011).
Concept study or
Class 4 1 % – 15 % ± 20 %
feasibility
Budget authorisation or
Class 3 10 % – 40 % ± 10 %
control
It is important to realise that an estimate is never a single number, but it comes with a margin of
uncertainty or accuracy. Not seldom are cost estimate numbers treated as firm numbers, while
people forget the underlying risks and uncertainties.
Next each estimate class and its purpose will be explained in more detail.
179
925836-02_197_17-Feb-15_08:43:40_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
Building up the estimate requires input from the entire project team and even from outside the
180
925836-02_198_17-Feb-15_08:43:43_walter
the scene and money at work
project team. All disciplines are involved in defining the scope of work and the cost estima-
tor needs to interface with all of them to have a good understanding of this scope of work. In
practice it still happens too often that an estimator develops the estimate in isolation, without
proactively interfacing with the appropriate stakeholders. This can lead to an incomplete or mis-
understood basis of estimate and ultimately in surprises when the estimate is being released.
A Basis of Estimate document helps to document the collective understanding of the scope of
work, schedule milestones, key risks and underlying assumptions that impact the cost estimate.
Therefore an estimate should always be accompanied by a Basis Of Estimate document as a
reference.
Next it is explained how an estimate can be structured and which cost elements are typically
included.
WEP
Offshore Wind
Farm
Install export
power cables
Figure 10.1: Example Work Breakdown Structure
181
925836-02_199_17-Feb-15_08:43:43_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
In some industries a Product Breakdown Structure (PBS) instead of a WBS is being used. A PBS is
based on products and defines the hierarchy of products and sub-products, rather than tasks and
subtasks. In practice many combinations of WBSs and PBSs are used.
Once a WBS has been drawn up, a bottom-up estimate can be produced by costing the individu-
al work packages at the lowest level and adding them up at the levels above. The result is a Cost
Breakdown Structure (CBS). Similarly cost can be allocated top-down, starting at the top level of
the WBS. In practice both ways are being applied, also depending on the purpose of the estimate
and required accuracy. In Figure 10.1 an example of a WBS is shown for the design and construc-
tion of the offshore wind farm.
Next the main elements of a capital cost estimate are described, being a base estimate, allowances,
contingency and escalation.
Base estimate
A base estimate, also called point estimate, is built up from the activities and deliverables iden-
tified in a Work Breakdown Structure (WBS). The more detailed the WBS becomes as the project
matures, the more accurate the estimate becomes. The base estimate can be defined as an esti-
mate including allowances, but excluding escalation, foreign currency exchange, contingency
and management reserves (AACE, 2014).
The estimate consists of many different cost elements, depending on the scope of work and type
of project. It includes all equipment, materials and labour required to execute the scope of work,
also considering the execution approach and schedule. Cost elements to be considered can be
split up in direct and indirect cost (Burke, 2003):
• Direct cost. These are costs that can be directly allocated to a specific scope of work or an
activity. For example:
– Equipment and material cost.
– Cost of project management team.
– Direct labour cost, like scaffolding, welders, fitters etc.
– Direct expenses, such as 3rd party services or sub-contractor fees.
• Indirect cost or overhead cost. These are costs not directly attributable to the completion of an
activity, which are typically allocated or spread across all activities on a predetermined basis
(AACE, 2014). For example:
– Field in-directs during construction, such as field administration, supervision, capital tools,
start-up costs, etc.
– Company overhead cost, like senior management, IT, human resource department, finance,
etc.
– Training cost, depreciation, insurance, taxes…etc.
The cost elements may be estimated using different estimating techniques depending on the
level of scope definition and the size and complexity of the project.
Allowances
As part of the base estimate and on top of the base cost, allowances can be added to cover lack
of scope detail or the ‘known unknowns’. Below are some examples that are typically included in
estimates as allowances:
182
925836-02_200_17-Feb-15_08:43:46_walter
the scene and money at work
Contingency
Contingency is added to the cost estimate to cover the uncertainty and variability associated
with a cost estimate, and unforeseeable elements of cost within the defined project scope (AACE,
2013). Contingency covers inadequacies in project scope definition, estimating methods and
estimating data. The amount of contingency included in the estimate should be determined, as
well as the method used to derive the appropriate amount.
Contingency is typically estimated using statistical analysis or judgment based on past asset or
project experience. Contingency usually excludes:
• Major scope changes such as changes in end-product specification, capacities, building sizes,
and location.
• Unforeseen major events such as earthquakes, labour strikes, etc. Management reserves (addi-
tional budget to be allocated at management’s discretion).
The amount of contingency to add to the base estimate is usually related to the required confi-
dence level of an estimate. Management can for example choose for a certain confidence level to
fund a project. Most cost estimates have a P50 confidence level, which means that the amount of
contingency added to the base estimate results in a 50/50 chance to either overrun or underrun
budget.
In case a probabilistic risk analysis technique is applied to the base cost (see also Chapter 8), the
probability of achieving a certain point estimate can be determined. A Monte Carlo simulation
is the most commonly applied technique to analyse the impact of risks and uncertainties on
project cost and schedule. The simulation not only calculates the probability of achieving a cost
estimate, but it also calculates the associated required amount of contingency. It therefore uses a
cost estimate without any contingency as a starting point for the simulation (AACE, 2011).
Normally only the high risks are used for the simulation. Each risk is quantified by determining its
likelihood of occurring and potential cost impact. In more traditional approaches the impact of a
risk on the estimate is represented by a three-point estimate, resulting in a triangular distribution
as explained in Chapter 8.
According to Figure 10.2 there is a 30 % probability to achieve the base estimate (X). By adding
contingency C1 to the base estimate, the confidence level of the estimate (Y) increases to 50 %,
also called the P50 estimate. By adding even more contingency to the base estimate, for example
C2, the confidence level increases to 80 %, also called a P80 estimate. Sometimes part of the con-
tingency is allocated as a management reserve which is not freely available to the project team,
but instead will be allocated by management.
183
925836-02_201_17-Feb-15_08:43:49_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
Confidence level
Base estimate +
contingency C2
80%
Base estimate +
50% contingency C1
Base estimate +
30%
C1 C2
0%
As contingency is related to uncertainties and risks, it is also possible to run down contingencies
in case specific risks do not materialise during project execution. An example: the material selec-
tion for a gas treatment plant depends on the specific composition of the gas produced by new
wells. This risk has been identified in the risk assessment and has been included in the overall
contingency. After drilling the new wells it turns out that the gas composition allows for cheaper
material to be applied. In that case the remaining contingency required till project completion
can be lowered and associated budget can be freed up for other investments.
Escalation
Escalation is a provision in costs or prices for uncertain
changes in technical, economic, and market conditions over
time (AACE, 2014). It is important to consider this ‘time value
of money’, since it can have an impact on purchasing power
and earning potential. The two main components of escala-
tion are inflation (or deflation) and market factors. Inflation
is the rate at which the general level of prices for goods and
services is rising over a certain period of time in an econ-
omy. It reflects the future value of money. Market factors
reflect future market developments that, for example, can
influence equipment and material prices.
184
925836-02_202_17-Feb-15_08:43:49_walter
the scene and money at work
The capital cost estimate as presented is also referred to as the Total Installed Cost, or Total
Capital Investment. The capital estimate is an important input for the project economics as
explained in Chapter 11.
Now that the estimate classes, structure and main elements have been defined, the most com-
mon cost estimating methodologies are described.
Stochastic methods are often applied during the early project development phases, making use
of estimating factors, metrics and models. For example, multiplying a (statistical) factor with
equipment cost to calculate the total installed cost of a specific piece of equipment. It can be
used for class 3 to 5 estimates, ranging from screening to budget estimates.
Deterministic methods are usually applied at a later stage when more scope detail is available
(control or tender estimates). In practice it is possible to end up with a mix of these estimating
methodologies in the same estimate, depending on the level of detail available for specific parts
of the scope.
Four common estimating methodologies are briefly explained (Lester, 2014) (Burke, 2003).
Subjective
This methodology, sometimes called ‘guestimating’, is applied to provide a ‘ballpark figure’ at the
early stages of a project. As there is no detailed information available yet, the accuracy of the
estimate strongly depends on the estimator’s experience of similar projects.
As an example the Lang Factor can be applied, being the ratio of the total cost of installation, or
Total Installed Cost, to the cost of its major technical components. This factor is widely used in
the process industry to help estimate the cost of new facilities. A typical Lang Factor for a new
chemical unit would be in the range of 3.0 to 5.0. This means that the sum of all major equipment
multiplied by a factor 3.0 to 5.0 gives a rough estimate of the total installed cost of the plant,
including equipment, materials, construction and engineering.
Analogous
The analogous method, or comparative method, is using similar past projects to estimate the cost
of a new project. It is applied when there is not sufficient data available to generate a detailed
estimate yet, but sufficient technical definition to make adjustments of estimates made for sim-
ilar projects. It is preferred to use quantifiable changes and apply factors to make the estimate
adjustments, for example using scaling factors.
185
925836-02_203_17-Feb-15_08:43:49_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
Parametric
Parametric estimating, also called factoring or component ratio method, is a technique that develops
cost estimates based upon the examination and validation of the relationships between a project’s
technical, programmatic, and cost characteristics as well as the resources consumed during its devel-
opment, manufacture, maintenance, and/or modification (ISPA, 2008). These relationships are known
as the Cost Estimating Relationships (CERs). Parametric models range from simple to very complex,
depending on the number of CERs and the complexity of the algorithms used.
CERs can be based upon many different parameters like functional design parameters, quantities
of equipment, hardware sizes and weight or operational environment, for example onshore ver-
sus offshore.
Analytical
The analytical method, also referred to as the detailed or engineering build-up method, is typi-
cally applied to generate the control estimate or a ‘bid’ estimate required by a contractor before
submitting a bid. It is the most accurate, deterministic estimating method, and it requires the
project to be broken down to the lowest WBS level. For each individual component the material
and labour cost are then estimated and the sum of all pieces, including overhead, becomes the
project estimate. The analytical method can be time-consuming and requires close cooperation
between the cost estimator and the engineers who have developed all the details including the
part lists, bill of material etc.
186
925836-02_204_17-Feb-15_08:43:52_walter
the scene and money at work
Figure 10.4 illustrates the development of the cost estimate accuracy and estimating method as the
project matures from Front-End-Loading (FEL) to Execution. It also shows that the Subjective and
Analogous methodologies are typically applied in the early project phases, while the Parametric
and Analytical methodologies are used when there is a better project definition.
Human aspect
It is critical for an estimator to understand that estimating is not an activity to be performed in
splendid isolation. Understanding the project scope and assuring all project team members pro-
vide the right input, requires a very proactive and open approach. There needs to be a two-way
communication enabling the estimator to have a full understanding of the basis of estimate,
while the other project team members develop an understanding of the impact that their specific
scope or execution method has on the cost estimate. It should be an ongoing dialogue, start-
ing early in the project development phase to avoid misalignment amongst stakeholders and
unpleasant surprises when releasing the estimate. The discussed and agreed scope and execu-
tion assumptions need to be written down in a Basis of Estimate document.
It is also important to realise that stakeholders have different interests in the project and poten-
tially will try to influence the cost estimate or the way it is presented. For example, a business
manager is interested in submitting a competitive bid, aiming at winning a tender, so she will
push for a lower estimate. A project manager wants to deliver his/her project within budget, so
she will push for at least a realistic estimate, but perhaps even some additional pocket money.
Similar pressure can be experienced when classifying specific cost. Some would like to classify
training cost for operations as OPEX, while others would classify it as CAPEX. There are also
examples of estimates being decreased to an acceptable level by management to obtain project
sanctioning, resulting in a high chance of overrunning the approved budget.
187
925836-02_205_17-Feb-15_08:43:52_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
10.3.1 Introduction
As already explained in Chapter 1, a project lifecycle exists of a number of distinct phases. In
each project phase many activities are taking place and many deliverables are produced. To
control the planning and execution of a project, all scope and activities need to be broken down
into manageable activities, linked to a WBS as explained in the previous paragraph. The WBS
forms the basis for compiling a schedule and brings scope, cost and schedule together. The WBS
work packages can be broken down into lists of activities and events that form the basis for the
project schedule. For each activity and event the predecessors, successors and the duration are
defined and these interdependencies can be graphically displayed in a network planning. Next
the network planning can be analysed to optimise the work sequence and project duration. Not
all activities need to be scheduled at the same level of detail. It depends on the specific risk of an
activity or work package and the level of control required.
There are many books written on how to create a network planning, explaining the different
techniques in detail. The following part is only meant to give a high-level overview of the most
common techniques, followed by an introduction into Gantt charts as a commonly applied
method for schedule representation.
Activity Activity
• Activity-On-Node (AON): activities are presented as nodes (rectangles or circles) and arrows
are representing their relationships.
Activity 2
Activity 1 Activity 4
Activity 3
188
925836-02_206_17-Feb-15_08:43:55_walter
the scene and money at work
In general the AON format seems to be favoured over the AOA format, as it has some graphical
advantages which make it easier to analyse and optimise the network.
There are two well-known network planning techniques, commonly used in projects:
• Program Evaluation and Review Technique (PERT)
• Critical Path Method (CPM)
Both techniques will be briefly explained.
189
925836-02_207_17-Feb-15_08:43:55_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
In projects it is common to have many complex relationships between the activities. There can
be specific start and finish restrictions like:
• Finish to Start: this is the most straightforward restriction, dictating that an activity cannot start
before its predecessor has been completed.
• Start to Start: an activity cannot start before its predecessor has started.
• Finish to Finish: an activity cannot be completed until its predecessor has been completed first.
• Start to Finish: an activity can only finish after the predecessor activity has started. So the pre-
decessor must start first and then the successor can finish. This restriction does not appear
very often, since there are usually easier ways to describe the relationship.
Usually there are also lead and lag times between activities. A start-to-start lag for example,
determines the minimum amount of time that must pass between the start of an activity and the
start of its successor.
Next PDM will be explained looking at a simplified example for the wind farm case.
1 Soil investigation 3
2 Wind study 3
3 Design foundation 3 1
5 Soil preparation 12 3
190
925836-02_208_17-Feb-15_08:43:58_walter
the scene and money at work
The following network can be drawn using the AON format and connecting all activities
to their predecessors.
6 12 18
Soil preparation
6 0 18
0 0 3 3 3 6 18 0 27
Soil investigation Design foundations Install foundations
0 0 3 3 0 6 18 0 27 27 0 36 30 0 37 37 0 37
6 9 15
0 0 0 Fabricate Install WTG’s Test WTG’s End
foundations
Start 27 0 36 30 0 37 37 0 37
9 3 18
0 0 0
0 3 3 18 0 27 9 15 24 lag + 3 months
Wind study Design WTG Fabricate and test WTG’s
3 3 6 18 0 27 12 3 27
A forward pass analysis will determine the early start and early finish of each activity. First
determine the ES and EF for activities at the beginning of the network (Soil investigation
and Wind study), next determine the ES and EF of the other activities following the
network relations from left to right.
To determine the latest start and latest finish of each activity, a backward pass analysis
has to be performed. The backward pass starts with determining the LS and LF of the last
activity (Test WTG’s) on the right, to then determine the LS and LF of all predecessors
following the network relations from right to left.
From the analysis it becomes clear which chain of activities determines the overall
duration, being the critical path (dark blue activities and blue arrows). In this case it takes
37 months to design and construct the Wind Farm.
For all activities the float can be calculated, being the difference between LS and ES.
For example ‘Fabricate foundations’ has a float of 3 months. So the fabrication could be
delayed by 3 months and still finish on time to start the installation of the WTG’s.
191
925836-02_209_17-Feb-15_08:44:01_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
To complete the example, one simple change is made. After 5 months of soil preparation
an additional vessel becomes available. The installation of the foundations could now
start after 5 months of soil preparation instead of 12 months. Unfortunately the additional
vessel cannot be used to install WTGs due to limited lifting capacity.
6 12 18
Soil preparation
10 4 22
0 3 3 3 3 6 15 9 24
Soil investigation Design foundations lag + 5 months Install foundations
0 0 3 3 0 6 15 0 24 24 9 33 27 7 34 34 0 34
6 9 15
0 0 0 Fabricate Install WTG’s Test WTG’s End
foundations
Start 24 0 33 37 0 34 34 0 34
6 0 15
0 0 0
0 3 3 3 6 9 9 15 24 lag + 3 months
Wind study Design WTG Fabricate and test WTG’s
0 0 3 3 0 9 9 0 24
Now that the soil preparation is not on the critical path anymore, the overall project
duration is reduced to 34 months. However almost all activities are critical now which
probably indicates that the chance of meeting the 34 months is smaller as there is no float
left in the schedule, except for the soil preparation. It would require a proper schedule risk
analyses and cost/benefit analysis to decide if it is worth investing in the additional vessel.
As shown in the example, a simple adjustment can easily change the network analyses, resulting
in a different critical path and overall duration.
Next a commonly used method to present a schedule is described, being the Gantt chart.
192
925836-02_210_17-Feb-15_08:44:01_walter
the scene and money at work
It is also possible to show progress per activity for example by colouring the baseline or drawing
a progress bar underneath the activity bar. By combining all this information in an easy-to-read
chart, management can have a good impression of the project at a glance.
Gantt charts can also be used to allocate resources to the activities. They can then be used to
analyse and optimise resources and create a fully resource loaded schedule, showing all required
disciplines and contractors over time. A common way to display resources over time is a histo-
gram. In Figure 10.10 a Gantt chart example for the wind farm case is shown.
The figure represents all activities and their relationships by bars against a timeline on the top.
The actual progress is shown as progress bars inside the activity bars and the critical path shows
up in dark blue.
Nowadays most Gantt charts are generated automatically by planning or scheduling software
like Microsoft Project or Primavera.
The analysis requires a detailed, resource loaded schedule, including all work to be completed
and unbiased, most likely durations. The purpose of resource loading the schedule is to allocate
the entire ‘contingency-free’ budget to the scheduled activities. Experience shows that schedules
of 300 to 1000 activities can be used in the risk analysis. The number of risks is typically around
20 to 40.
193
925836-02_211_17-Feb-15_08:44:01_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
1
0,9
0,8
0,7
0,6
0,5
0,4
0,3
0,2
0,1
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
For each schedule risk the likelihood of occurring and the potential impact needs to be defined,
similarly to the cost risk as explained in Paragraph 10.2.3.
Next a Monte Carlo simulation will generate a great number of iterations, combining many
different cost and schedule impacts depending on their likelihood of occurring. This results in
probability distribution curves for both cost and schedule as shown in Figure 10.11.
Human aspects
Similar to cost estimating, scheduling requires a proactive approach to ensure all relevant inputs
are captured and that there is a good understanding of the execution assumptions and schedule
risks. Often reference is made to the difference between a ‘scheduler’ and a ‘planner’. A sche-
duler works in isolation and is very good at putting all activities in a scheduling software tool
to develop a ‘technically’ sound schedule. A planner continuously interfaces with all relevant
stakeholders to fully understand the phasing, priorities, execution approach, schedule risks and
underlying assumptions.
Also schedules are being influenced by stakeholders depending on their specific drivers. Some
stakeholders will have an interest to deliver the project as soon as possible, while a project mana-
ger would like to have a realistic schedule, taking into account specific schedule risks.
It is also not uncommon that some ‘wishful thinking’ creeps into the schedule during the early
development phases. When the project scope is not well developed yet and not all related sche-
dule risks are known, people tend to be too optimistic.
194
925836-02_212_17-Feb-15_08:44:04_walter
the scene and money at work
10.4.1 Introduction
A project needs to have appropriate controls in place to make sure it is completed against the
agreed targets. Besides safety performance, risk management, quality and stakeholder satis-
faction, these have been described in other chapters, the key aspects to control are cost and
schedule.
Project control includes the following primary steps:
• Perform project planning, including establishing project cost and schedule baselines
• Measure project performance
• Compare measurements against the project plan and baselines
• Take corrective actions as may be determined through forecasting and further planning.
In essence it comes down to applying the well-known Deming circle; Plan, Do, Check, Act
(PDCA-circle).
Sometimes additional topics, like document control or auditing, can be included, depending on
the tasks assigned to the project controls team.
It is also important to realise that there are possibly multiple contractors involved in the exe-
cution of the project, all performing their own project controls and reporting. Therefore large
complex projects require an integrated project controls plan that clearly describes the interfaces
with all contractors involved.
Another important aspect of project control is ‘management of change’. A project requires a for-
mal process to identify, assess and approve changes to the approved project plan and to capture
the impact on schedule and cost.
Next the basis of schedule control, cost control and management of change will be explained.
195
925836-02_213_17-Feb-15_08:44:04_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
very well possible that more detailed execution schedules will be developed after sanctioning,
schedule performance will be measured against the approved milestones.
The schedule is based on the WBS and progress will be monitored for the individual WBS ele-
ments. The level of schedule detail for each element and the WBS level at which progress is
measured, depends on the complexity of the scope and schedule risks. For example applying
a new technology which is on the critical path of your project requires more rigorous progress
monitoring than a routine task with significant float.
In a complex project there may be many parties involved in providing progress data. Contractors
involved will normally monitor and report progress for their specific scope of work. The project
planner must check and integrate all progress data to determine the overall project progress. The
amount of involvement of the owner’s planner also depends on the type of contracts. A lump
sum turnkey contract requires less involvement from the owner than managing a reimbursable
contract.
During project execution it can be decided to re-baseline the schedule if the original baseline
schedule has become obsolete due to changes. If there are major changes of the project scope,
or the actual progress deviates significantly from the original baseline schedule, it can be decided
to establish a new baseline to measure progress. A need to re-baseline often results from poor
project definition and/or poor project control. Reassessment of the project control process going
forward is typically an element of re-baselining (AACE, 2014).
Besides monitoring progress and measuring schedule performance against the baseline, it is also
common practice to forecast the remaining project duration.
The first step is to establish a baseline estimate, usually being the authorised budget at project
sanctioning. The cost performance will be measured against the initially authorised budget and
any budget changes that were approved during project execution.
196
925836-02_214_17-Feb-15_08:44:07_walter
the scene and money at work
The level of detail at which cost control needs to be performed, depends on the specific scope of
work and associated risk. Since the cost estimate is broken down according to the WBS elements,
it can be decided for each element how to perform cost control and which supporting data to
collect. For example a low risk WBS element being executed under a lump sum contract (see
Chapter 9 for further explanation about contract types) requires less stringent cost control than
high risk scope being executed on a reimbursable basis.
Since the same WBS activities and deliverables as included in the cost estimate are also in the
schedule, the cost (CAPEX) phasing over time can be determined. The cost phasing can be visual-
ised in a typical S-curve, also often used for cost control and reporting.
Cumulative cost
S-curve
Time
Besides an S-curve presenting cumulative cost over time, many different S-curves are used
for project control and reporting. For example showing actual man hours, earned man hours,
installed quantities or resources over time.
Next a commonly used integrated cost and schedule method will be described, the Earned Value
Analysis.
To explain the EVA method some key terms need to be defined (Dierick & Van Biezen, 2009).
• The Earned Value (EV) of a work package, or the whole project, equals the sum of budgeted
cost of the work performed to date. EV is also called the Budgeted Cost of Work Performed. So
EV is not the same as the actual cost of work performed.
197
925836-02_215_17-Feb-15_08:44:07_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
• The Planned Value (PV) equals the sum of budgeted cost of the work scheduled to date, also
called Budgeted Cost of Work Scheduled.
• Actual Cost (AC) is the sum of all actual cost to date, also called Actual Cost of Work Performed.
• Actual Time Spent (ATS) is the total duration from start to date.
• Budget At Completion (BAC) equals the sum of all budgeted cost till the end of the project.
• Time At Completion (TAC) is the planned overall duration from start till end of the project.
The definitions above can be used to analyse cost and schedule performance in the following
manner.
To analyse schedule performance the Schedule Variance (SV) or Schedule Performance Index
(SPI) can be determined. Both measures indicate whether the project runs ahead or behind
schedule.
• SV = EV – PV (positive number: ahead of schedule, negative number: behind schedule)
• SPI = EV/PV (number > 1: ahead of schedule, number < 1: behind schedule)
The cost performance can be analysed looking at the Cost Variance (CV) or Cost Performance
Index (CPI). Both measures indicate whether the project runs over or under budget.
• CV = EV – AC (positive number: under budget, negative number: over budget)
• CPI = EV/AC (number > 1: under budget, number < 1: over budget)
Next the overall project duration and cost can be forecasted, taking into account the project
performance to date.
The Estimated Time at Completion (ETAC) provides a forecast of the overall project duration,
taking into account the schedule performance to date.
• ETAC = TAC/SPI (a SPI > 1: forecasted duration shorter than planned, SPI < 1: forecasted dura-
tion longer than planned)
From the ETAC the Estimate To Complete (ETC) can be derived, being the remaining forecasted
time to complete the project.
• ETC = ETAC – Actual Time Spend (ATS)
The Estimated Cost at Completion (ECAC) gives a forecast of the total cost at completion of the
project, taking into account the cost performance to date.
• ECAC = BAC/CPI (a CPI > 1: forecasted cost at completion under budget, CPI < 1: forecasted
cost at completion over budget)
From the ECAC the CTC can be derived, being the remaining cost to complete the project.
• CTC = ECAC – Actual Cost (AC)
The importance of using Earned Value in the performance analysis will be illustrated by a simple
example, in which the contribution of the activities to the overall progress is weighted equally.
198
925836-02_216_17-Feb-15_08:44:10_walter
the scene and money at work
EVA example
The table below shows the planning of 5 activities over 10 months,
including the budgeted cost and planned spent per month for each activity.
€ 80,000
€ 60,000
€ 40,000
€ 20,000
Figure 10.13:
Cost curve EVA 0
0 2 4 6 8 10
example
Months
% complete EV PV AC
Activity 1 € 5.000 100% € 5.000 € 5.000 € 4.000
Activity 2 € 10.000 100% € 10.000 € 10.000 € 12.000
Activity 3 € 25.000 75% € 18.750 € 25.000 € 15.000
Activity 4 € 75.000 10% € 7.500 € 15.000 € 7.500
Activity 5 € 10.000 0% € - €-
€ 125.000 € 41.250 € 55.000 € 38.500
199
925836-02_217_17-Feb-15_08:44:13_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
So although the project is running behind schedule, the cost performance looks positive.
The schedule and cost forecast can also be calculated:
• ETAC = 10 / 0.75 = 13.3 months
• ECAC = 125,000 / 1.07 = € 116,667
Looking at the EVA analysis management might decide to take measures to reduce the sche-
dule delay. Obviously this depends on the project’s value drivers and possibilities to speed up the
work. Adding more people to the job or introducing double shifts might be a solution, but will
come at a cost.
Human aspect
Similar to the previous paragraphs on the human aspect, there are many stakeholders with differ-
ent interests when it comes to controlling a project. Just a few examples to illustrate situations
that have occurred in practice:
• Management decreasing the baseline cost estimate to have a project sanctioned.
• A construction contractor reporting more construction progress than is actually made to meet
a project milestone and receive an incentive fee.
• A project manager forecasting the overall project cost too optimistically to positively influence
his appraisal.
• An engineering contractor not making any effort to improve the engineering efficiency, aiming
to maximise the engineering man hours under a reimbursable contract.
200
925836-02_218_17-Feb-15_08:44:13_walter
the scene and money at work
It requires an experienced project team to recognise these different interests, and challenge the
data received for cost and schedule control.
Another known issue is the fact that most people are too optimistic about project execution
and resolving problems along the way. This often results in significant ‘wishful thinking’ when
forecasting project duration or the overall project cost. It takes experience to recognise these
situations and avoid over-optimistic estimates and schedules.
Management of change requires discipline from the project team and other parties involved.
All parties involved need to follow the formal change management process and all relevant
disciplines need to assess the impact of the change. It happens in practice that, due to time
pressure, changes do not follow the formal change process, which can lead to unsafe situations
or unpleasant schedule or cost surprises later on. A common reason not to follow the change
management process is simply because it is taking too long. Especially during construction there
is not much time to wait for the formal approval of a change before implementation. Therefore it
is key to structure the process such that the turnaround time is as short as possible, and at least
the relevant disciplines have reviewed a change prior to formal approval.
Various stakeholders need to be informed and might ask for different information. Depending
on their interest and management level, the specific information, aggregation level and report-
ing frequency can vary. It also depends on the project development phase, because progress
reporting can become much more complex as the number of external parties increases towards
execution.
Many project teams consider progress reporting as a burden that not necessarily adds any value
to the project. Especially the sometimes many ad hoc requests for information or progress data
are disrupting the day-to-day project activities. Besides disruption, this ad hoc reporting can eas-
ily lead to mistakes or the provision of incomplete information. On top of that this information
could start to ‘live its own life’, being used and presented by stakeholders in their own interest.
The trick is to produce one simple, formal progress report that satisfies most of the stakeholders.
However there can still be good reasons to compile tailor-made reports, but always using the
same data as included in the formal progress report. Ad hoc requests should be minimised to
limit the additional reporting burden of the project team at any time.
The positive thing about reporting is that it requires the project team and third parties to fre-
quently review project performance and to update the cost and schedule forecasts. It forces
communication between all parties to first collect the required progress data and next to explain
project performance and required recovery measures to the various stakeholders.
201
925836-02_219_17-Feb-15_08:44:14_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
Figure 10.14: Example of a progress report of the Wind Farm Energy Polder
202
925836-02_220_17-Feb-15_08:44:16_walter
the scene and money at work
Progress reports can also have a contractual purpose, for example to formally document approved
scope changes or to document the status of earned incentives. The reports could even end up in
court, in case a claim needs to be settled after project completion.
The data and information in the progress report needs to be highly reliable as the project team
and other stakeholders must be able to take decisions based on this report. Example: A pro-
ject manager decided to introduce working shifts to catch up, following a progress report that
showed a poor construction progress. Two months later it turned out that there was a significant
delay in collecting and reporting construction progress data and that the actual
Construction progress was even ahead of schedule. Accurate progress reporting could have
prevented the additional cost of working shifts.
A progress report typically includes the following topics:
• Management summary
• HSE performance
• Project Key Performance Indicators (KPIs)
• Key risks and mitigation actions
• Schedule
• Cost control
• Quality
• Engineering
• Contracting and Procurement
• Construction
• Commissioning and Start-up
• Scope changes
For schedule and cost most reports include progress and cost curves, showing the planned,
actual and forecasted data. An example of a typical monthly progress report for the Wind Farm
project is given in Figure 10.14.
Human aspect
The quality of a progress report strongly depends on the competencies of the project controls
team and their understanding of the scope and execution. The team must be able to challenge
the received data and information and should understand how to integrate it into one overall
progress report. The project manager should take full ownership of the progress report, being
able to explain all information included.
For the project controls team it is important to realise that informal communication can be as
important as formal communication. For example a cost controller who really connects with
the project team, who understands the scope of work and knows what is going on during con-
struction, can fulfil his role much more proactively than a cost controller sitting behind his desk
all day.
The way progress is being presented and communicated can be influenced by many parties. A
project manager can benefit from presenting a success story, while a contractor would like to
report all mistakes and omissions from the owner. It is therefore important to ensure the report
reflects the actual situation and represents issues in a fair way. In the end it comes down to trust
between all parties involved, particularly between the owner and contractors. Since conflict-
ing interests will exist at all times, making money versus saving money, it works best to openly
203
925836-02_221_17-Feb-15_08:44:16_walter
M a n a g e m e n t o f e n gi n e e r i n g P rojects
acknowledge these differences and to focus on the common interests and goals, like for example
a good safety performance.
The PC team is normally led by a Project Controls lead or manager and the size of the team will
vary depending on the size and complexity of the project. The PC manager is normally a mem-
ber of the project management team.
The PC team plays a vital role in providing management information to the project team and
various stakeholders. To fulfil this role the PC team needs to:
• Establish a clear project baseline, including a proper understanding of the business drivers.
• Compile a fit-for-purpose project controls plan.
• Proactively collect and challenge project information and data.
• Integrate and analyse the information from all sub-projects, disciplines and third parties.
• Provide reliable management information to the project team to help them take the right
decisions.
• Consolidate all relevant progress information and data in a formal progress report.
• Support management of change and assess the impact of changes on cost and schedule.
• Facilitate risk management.
The PC team can only succeed if they are involved from the start of the project, if they are being
recognised for their critical role and provided they communicate and engage with the right peo-
ple at the right time. This requires full support from project management and the right mix of
analytical and people skills in the PC team.
204
925836-02_222_17-Feb-15_08:44:19_walter
the scene and money at work
Below some examples are given to illustrate the need for fit-for-purpose project controls.
Cost estimate
Depending on the project phase and the level of project definition, the completeness and accu-
racy of the estimates varies. Sometimes stakeholders are asking for a very accurate estimate in
the early development phases of a project, while the required level of project definition is not
available yet. This can result in an extensive exercise and expenditure, to obtain the necessary
detail required to establish the desired level of accuracy. The issue with producing very accurate
estimates too early, lies in making too many assumptions and trying to collect reliable cost data
while there are still a lot of unknowns and uncertainties. A famous one-liner applies here: ‘It is
better to be roughly right, than precisely wrong.’ So unless there is a clear need for an accurate
(deterministic) estimate early in the development, likely related to risk, stakeholders should really
focus on the objective of an estimate and on which decisions it should support.
Schedule
Same as for the cost estimate it is important to make sure that the level of scheduling detail is
aligned with the purpose of the schedule. It is no use to develop a detailed, fully resource loaded
schedule, if you only need rough milestones and lead times to compare different design con-
cepts in the early project phases.
Similarly it is highly unlikely that the small-size pedestrian bridge requires a fully integrated cost
and schedule Monte Carlo risk analysis. On the flip side, the multi-billion chemical plant does
require this integrated analysis since the complexity and associated risks are entirely different.
In summary, applying fit-for-purpose project controls requires full understanding of the project
value drivers, risks and the specific purpose of estimates and schedules in each project lifecycle
phase.
205
925836-02_223_17-Feb-15_08:44:19_walter