West Seattle Bridge Cost-Benefit Analysis
West Seattle Bridge Cost-Benefit Analysis
West Seattle Bridge Cost-Benefit Analysis
FINAL
WEST SEATTLE HIGH-RISE
BRIDGE SAFETY PROJECT
COST-BENEFIT ANALYSIS
SEATTLE DEPARTMENT OF TRANSPORTATION
TEL.: +1 206-431-2300
WSP.COM
October 19, 2020
Please find the Cost-Benefit Analysis Report conducted as part of the West Seattle High-Rise
Bridge Safety project enclosed. This report is intended to support the City as it makes the decision
related to rehabilitation and/or replacement. As we understand through discussions with the City,
the CBA is just one element out of many in making that decision. As such, the CBA presents
findings in the form of value indices, which is a measure of return on investment, but does not
provide any recommendations or conclusions.
The CBA was conducted in an accelerated time frame and with limited information due to the
emergency nature of the work. As such, we needed to make a number of assumptions.
Understanding the limitations and impacts of these assumptions within the CBA is important. We
conducted sensitivity studies on key assumptions, and have provided a list of limitations and key
next steps, at the end of this document (Sections 6 and 7).
Thank you for giving WSP the opportunity to support the City on this project. Should you have
any questions as you review or use the document, please contact me via email at
[email protected] or by phone at 253.906.3757.
Sincerely,
XXX:GAB:nb
Attachment
WSP ref: 160424C
EXECUTIVE SUMMARY ......................................................... X
INTRODUCTION ............................................................1
1.1 Objective of the Cost-Benefit Analysis .................................... 3
1.2 Scope ........................................................................................... 3
1.3 Assumptions ............................................................................... 4
1.4 Process ........................................................................................ 5
1.4.1 Definition (Decision Matrix) ..................................................................... 5
1.4.2 Multiple Entity Involvement ..................................................................... 6
1.4.3 CBA Phases and Workshops.................................................................. 6
ROUGH-ORDER-OF-MAGNITUDE CONCEPTUAL
COSTS......................................................................... 50
4.1 Capital Costs.............................................................................50
4.2 Life Cycle Costs........................................................................52
FINDINGS .................................................................... 61
6.1 Result methodology .................................................................61
6.2 Sensitivity Studies....................................................................62
6.3 Summary of findings ................................................................67
Page iv
CBA LIMITATIONS & FUTURE STUDIES ...................... 69
ACKNOWLEDGEMENTS ............................................ 71
REFERENCES ............................................................. 72
Page v
TABLES
TABLE 1. DECISION MATRIX SHOWS THE KEY QUESTIONS
WE STARTED WITH, AS WELL AS SOME OF
THE ANSWERS DEVELOPED DURING THE
CBA PROCESS ............................................................. 6
TABLE 2. ALTERNATIVES ....................................................................... 7
TABLE 3. ALTERNATIVE/BASELINE RATING SCALE .........................16
TABLE 4. AVERAGE PERFORMANCE SCORES AFTER
ATTRIBUTE WEIGHTING IS APPLIED ......................49
TABLE 5. WORK ACTIVITY CONTINGENCY ASSUMPTIONS ............51
TABLE 6. BASE PROJECT ROM CAPITAL COSTS..............................52
TABLE 7. ANNUALIZED INSPECTION, OPERATING, AND
MAINTENANCE COSTS .............................................53
TABLE 8. BASE PROJECT ROM LIFE CYCLE COSTS (0%
NET DISCOUNT RATE) SUMMARY ..........................54
TABLE 9. RISK RATING FACTOR .........................................................56
TABLE 10. CBA MONETIZED RISK ITEMS ...........................................57
FIGURES
FIGURE 1. ELEVATION OF MAIN-SPAN SEGMENTAL BOX
UNIT............................................................................... 1
FIGURE 2. CROSS-SECTION VIEWS OF TWIN BOX
GIRDERS, NEAR PIER TABLE (LEFT) AND
NEAR MIDSPAN (RIGHT) ............................................. 1
FIGURE 3. TIMEFRAME OF WORK ........................................................ 2
FIGURE 4. ALTERNATIVE 1, TEMPORARY SHORING
SCHEME........................................................................ 8
FIGURE 5. CONSTRUCTION SCHEDULE FOR ALTERNATIVE
1, TEMPORARY SHORING SCHEME .......................... 8
FIGURE 6. ALTERNATIVE 2, DIRECT STRENGTHENING TO
RESTORE LIVE LOAD .................................................. 9
FIGURE 7. CONSTRUCTION SCHEDULE FOR ALTERNATIVE
2, DIRECT STRENGTHENING TO RESTORE
LIVE LOAD .................................................................... 9
FIGURE 8. ALTERNATIVE 3, PARTIAL SUPERSTRUCTURE
REPLACEMENT TO RESTORE LIVE LOAD..............10
FIGURE 9. ALTERNATIVE 4, ACCELERATED
SUPERSTRUCTURE REPLACEMENT ......................11
FIGURE 10. CONSTRUCTION SCHEDULE FOR
ALTERNATIVE 4, ACCELERATED
SUPERSTRUCTURE REPLACEMENT ......................11
FIGURE 11. ALTERNATIVE 5, ACCELERATED BRIDGE
REPLACEMENT ..........................................................12
Page vi
FIGURE 12. CONSTRUCTION SCHEDULE FOR
ALTERNATIVE 5, ACCELERATED BRIDGE
REPLACEMENT .......................................................... 12
FIGURE 13. ALTERNATIVE 6, IMMERSED TUBE TUNNEL ................ 13
FIGURE 14. CONSTRUCTION SCHEDULE FOR
ALTERNATIVE 6, IMMERSED TUBE TUNNEL ......... 13
FIGURE 15. BLANK PERFORMANCE ATTRIBUTE
WEIGHTING MATRIX ................................................. 15
FIGURE 16. ALTERNATIVE 2 SERVED AS THE BASELINE,
RECEIVING A 5 FOR EVERY ATTRIBUTE
(THIS FIGURE SHOWS THE
SEISMIC/SAFETY ATTRIBUTE FOR
DEMONSTRATION PURPOSES.) .............................. 16
FIGURE 17. SUBJECT MATTER EXPERTS FROM THE TAP,
SDOT, AND WSP SCORED EACH
ALTERNATIVE RELATIVE TO EACH
ATTRIBUTE TO DETERMINE AN AVERAGE
PERFORMANCE RATING .......................................... 16
FIGURE 18. BRIDGE MAINTENANCE, INSPECTION, AND
OPERATIONS ATTRIBUTE’S MEASURABLES
APPLIED TO ALL FIVE ALTERNATIVES ................... 17
FIGURE 19. CONSTRUCTABILITY ATTRIBUTE’S
MEASURABLES APPLIED TO ALL FIVE
ALTERNATIVES .......................................................... 18
FIGURE 20. ENVIRONMENTAL ATTRIBUTE’S MEASURABLE
APPLIED TO ALL FIVE ALTERNATIVES ................... 20
FIGURE 21. EQUITY ATTRIBUTE’S MEASURABLE APPLIED
TO ALL FIVE ALTERNATIVES ................................... 23
FIGURE 22. WEST SEATTLE BRIDGE DIVERSION ROUTES
AND PERCENTAGE OF PEOPLE OF COLOR
BY CENSUS TRACT ................................................... 25
FIGURE 23. FORWARD COMPATIBILITY ATTRIBUTE’S
MEASURABLES APPLIED TO ALL FIVE
ALTERNATIVES .......................................................... 25
FIGURE 24. FUNDING OPPORTUNITIES ATTRIBUTE’S
APPLIED TO ALL FIVE ALTERNATIVES ................... 27
FIGURE 25. BUSINESS AND WORKFORCE IMPACTS
ATTRIBUTE’S MEASURABLES APPLIED TO
ALL FIVE ALTERNATIVES ......................................... 29
FIGURE 26. MAJOR RETAIL OUTLETS IN WEST SEATTLE ............... 31
FIGURE 27. TEMPORARY CONSTRUCTION EASEMENTS
THAT WOULD BE REQUIRED FOR
ALTERNATIVE 1 ......................................................... 32
FIGURE 28. TEMPORARY CONSTRUCTION EASEMENTS
THAT WOULD BE REQUIRED FOR
ALTERNATIVE 2 ......................................................... 33
FIGURE 29. TEMPORARY CONSTRUCTION EASEMENTS
THAT WOULD BE REQUIRED FOR
ALTERNATIVE 4 ......................................................... 34
Page vii
FIGURE 30. TEMPORARY CONSTRUCTION EASEMENTS
THAT WOULD BE REQUIRED FOR
ALTERNATIVE 5 .........................................................35
FIGURE 31. TEMPORARY CONSTRUCTION EASEMENTS
THAT WOULD BE REQUIRED FOR
ALTERNATIVE 6 .........................................................36
FIGURE 32. ALL ALTERNATIVES REQUIRE SOME LEVEL OF
UTILITY DISRUPTIONS, DURING
DEMOLITION, CONSTRUCTION, OR BOTH .............37
FIGURE 33. ECONOMIC IMPACT OF WSHB CLOSURE
BASED ON IMPLAN ANALYSIS .................................39
FIGURE 34. MAP OF MAJOR EMPLOYERS .........................................40
FIGURE 35. MOBILITY IMPACT ATTRIBUTE’S MEASURABLE
APPLIED TO ALL FIVE ALTERNATIVES ...................41
FIGURE 36. MULTIMODAL IMPACTS ATTRIBUTE’S
MEASURABLE APPLIED TO ALL FIVE
ALTERNATIVES ..........................................................43
FIGURE 37. ASSUMED ROUTE FOR EMERGENCY
VEHICLES PRIOR TO THE WEST SEATTLE
HIGH-RISE BRIDGE CLOSURE .................................45
FIGURE 38. SEISMIC/SAFETY ATTRIBUTE’S MEASURABLES
APPLIED TO ALL FIVE ALTERNATIVES ...................46
FIGURE 39. ATTRIBUTE PERFORMANCE: SUBJECT
MATTER EXPERTS FROM THE TAP, SDOT,
AND WSP RATED EACH ALTERNATIVE FOR
EACH ATTRIBUTE. THESE SCORES WERE
THEN AVERAGED ACROSS ENTITIES TO
SHOW OVERALL ATTRIBUTE
PERFORMANCE. ........................................................47
FIGURE 40. SDOT, THE TAP, AND THE CTF’S AVERAGED
RANKINGS DETERMINED ATTRIBUTE
WEIGHTING. ...............................................................48
FIGURE 41. THE CBA MULTIPLIED ATTRIBUTE WEIGHTS BY
ATTRIBUTE PERFORMANCE SCORES TO
DETERMINE THE OVERALL PERFORMANCE
SCORE. .......................................................................48
FIGURE 42. TAP BASELINE INDEPENDENT SCORING .....................49
FIGURE 43. ALTERNATIVE WORK ACTIVITIES AND YEARS
OF OCCURRENCE .....................................................50
FIGURE 44. CAPITAL COST CONTINGENCY, ALLOWANCE,
AND RISK SUPERPOSITION .....................................51
FIGURE 45. LIFE-CYCLE COST RANGES ............................................55
FIGURE 46. MONETIZED RISK RANGE ...............................................60
FIGURE 47. PICTORIAL VIEW OF EVALUATION PROCESS ..............61
FIGURE 48. RESULTING VALUE INDICES (0% NET
DISCOUNT RATE) ......................................................62
FIGURE 49. LIFE CYCLE VALUE INDEX SENSITIVITY
(OPPORTUNITY VALUE)............................................63
Page viii
FIGURE 50. LIFE-CYCLE VALUE CHANGE (3 PERCENT
VERSUS 0 PERCENT NET DISCOUNT RATE)
– SENSITIVITY STUDY............................................... 64
FIGURE 51. ALTERNATIVE 2 SERVICE LIFE IMPACTS –
SENSITIVITY STUDY.................................................. 64
FIGURE 52. SEISMIC/SAFETY PERFORMANCE –
SENSITIVITY STUDY.................................................. 65
FIGURE 53. LIFE CYCLE VALUE INDICES WITHOUT
CONTINGENCIES ....................................................... 65
FIGURE 54. LIFE CYCLE VALUE INDICES WITHOUT
MONETIZED RISK ...................................................... 66
FIGURE 55. POTENTIAL DURATIONS BASED ON
ACCELERATED CONSTRUCTION
(MINIMIZED CORRIDOR CLOSURES) ...................... 66
FIGURE 56. CBA REPORTED FINDINGS - GRAPHICAL ..................... 67
FIGURE 57. CBA REPORTED FINDINGS - TABULARIZED ................. 68
APPENDICES
Appendix A: Alternative Sketches
Appendix B: Preliminary Geotechnical Information
Appendix C: ROM Cost Backup
Appendix D: Risk Assessment Matrix
Appendix E: Evaluation Matrix
Appendix F: Construction Schedules
Appendix G: Temporary Shoring and Demolition Concepts Memo
Appendix H: Preliminary Structural Rehabilitation Memo
Appendix I: Preliminary Seismic Assessment
Appendix J: Superstructure Replacement Feasibility Memo
Appendix K: Bridge Replacement Concepts Memo
Appendix L: Preliminary Tunnel Concept Development Memo
Appendix M: Funding Options Matrix
Appendix N: Workshop Presentations
Page ix
EXECUTIVE SUMMARY
Because of observed accelerating crack growth in the West Seattle High-Rise Bridge (WSHB), the Seattle
Department of Transportation (SDOT) made the decision to close the bridge to traffic on March 23, 2020,
commencing the West Seattle High-Rise Bridge Safety Project. This project, which is part of a larger program,
comprises designing and installing an intelligent monitoring system, conducting non-destructive testing, developing
an emergency response plan, designing and constructing bridge stabilization measures, and conducting a cost-benefit
analysis (CBA) — the results of which are presented herein.
Project Overview
SDOT did not make the decision to close an arterial route upon which the people of West Seattle and the region
depend lightly. Its closure has disrupted lives, as well as the mobility of freight, services, and goods through the
region. The closure has negatively impacted already marginalized communities. It has affected the maritime industry
and the operations of the Port of Seattle. The closure’s effects cannot be understated, nor can the consequences,
should the bridge have failed during rush hour. From the outset, that this has been a public safety project. It
continues to be a public safety project.
The intelligent monitoring system and non-destructive testing determined that it is technically feasible to continue
further investigating if the bridge can be rehabilitated to restore live traffic. The bridge’s continued positive
responses to ongoing stabilization work and the findings of the structural assessment of further rehabilitation and
retrofit concepts, echo that feasibility. However, there remain key stabilization work activities, including the release
of the restrained lateral bearing at Pier 18 and the installation and tightening of the external post-tensioning system.
These measures, to be completed in the coming month, are import to confirm these trends hold true.
The purpose of the CBA is to provide objective information and context to help the City decide between investing in
further rehabilitation of the existing bridge or pivoting towards a replacement structure. The methodology
incorporated multiple alternatives within that apparent binary choice. We assessed five alternatives using both
quantitative and qualitative analyses for value determination and for risk and cost. Section 6 presents findings in the
form of value indices (performance divided by cost, with costs inclusive of monetized risk).
WSP conducted the CBA on an accelerated schedule. We needed to make several assumptions, including selecting
five conceptual alternatives based on apparent low cost. As such, the CBA does not represent a type, size, and
location (TS&L) study. Should the ultimate decision be to replace the bridge, we anticipate that the City would
explore yet-to-be-determined alternatives, some of which may be similar to the concepts presented here, but some of
which will be different in type, size, and location, as well as in construction means and methods and material
composition. Section 7 provides a detailed list of considerations for future studies that were beyond the scope of this
CBA, because, as important as the findings are, so, too, is an understanding of what was not considered but should
be in future studies.
This CBA addresses some of the questions we have all grappled with since March 23 – What long-term impacts will
this closure have? Can the City afford to wait for a replacement? What is the life span of a rehabilitated structure?
What benefits does rehabilitation offer? What benefits does replacement offer? While the purpose of this report is to
objectively present the benefits and drawbacks of multiple alternatives, to help inform the decision to rehabilitate or
replace the bridge, its findings will not, and should not, dictate that decision.
The CBA is, in fact, just one factor in this decision, focused on helping to support decisions being made around
public safety and technical risk. The decision will also be informed by external exigencies and current events, by the
recommendation of the asset owner, SDOT, as well as by the guidance provided by the Technical Advisory Panel
(TAP) and Community Task Force (CTF). Ultimately, the imminent decision to rehabilitate or replace the structure
will be a City decision based on a value judgment for the safety and well-being of the people of Seattle.
While not a perfect tool, the CBA did allow us to draw several conclusions using the assumptions outlined in
Section 1. Section 2 discusses the five alternatives evaluated, with concept drawings, descriptions, and estimated
timelines. Figure A below summarizes the alternatives.
Scheme Scenario Description
Shoring 1 Temporary Shoring to Restore Live Load (3 to 5 years)
2 Direct Strengthening to Restore Live Load (40 years)
Strengthening
3 Partial Superstructure Replacement to Restore Live Load (15 to 50 years)
4 Accelerated Superstructure Replacement (75 years)
Replacement 5 Accelerated Bridge Replacement (75+ years)
6 Immersed Tube Tunnel (75+ years)
Section 3 outlines how we qualitatively evaluated each alternative using weighted attributes (selected by the CTF,
the TAP, SDOT, and WSP during the CBA process) to develop an overall performance score. Figure B illustrates
how we developed the overall performance score for each alternative.
Section 4 details how we developed and calculated rough-order-of-magnitude conceptual costs for each alternative’s
initial capital project costs and life cycle costs, and presents costs developed from the base assumptions informed by
SDOT’s input. Section 5 highlights the primary risks we identified and discusses how we monetized some of them.
Section 6 puts all the information together – the performance scores divided by costs, inclusive of monetized risks,
to develop the CBA findings, or “value indices.” These value indices represent the overall return on investment for
each alternative (higher values represent a better return on investment). Value indices are presented as a “base
value,” without considering assumptions on key variable sensitivity, and also as “reported findings,” which do
consider assumptions on key variable sensitivity (reported average values).
Figure C shows us how the inputs – performance and cost – resulted in value indices for both the “base values” and
“reported findings” for each alternative, while Figure D shows the potential range in the value indices based on the
sensitivity studies.
Page xi
Figure C – Summary of Base CBA Values and Reported Findings (Value Indices)
NOTES:
- Higher value indices represent better returns on investment.
- X’s –base values; value indices based solely on assumptions within the CBA.
- Orange Dots – reported findings; average value indices based on findings of the sensitivity studies conducted.
- Blue Bars – potential range in value indices based on the sensitivity study findings.
Figure D – Range in Summary of Findings Values
Section 7 then highlights some of the limitations of the CBA and suggests areas where further study is necessary.
The CBA had to choose five alternatives to compare, but we recognize that there are many options within the repair
and replace categories. We recommend that a TS&L study investigate other options, as well as other considerations.
For example, while the CBA qualitatively and quantitatively addressed socioeconomic impacts in multiple attributes
(Equity, Mobility Impacts, and Multimodal Impacts) in Section 3, they were not included in monetized risks, capital
costs, or life-cycle costs.
Page xii
INTRODUCTION
The WSHB is a multi-span concrete bridge comprising prestressed concrete multi-girder approaches and twin cast-
in-place, post-tensioned segmental concrete box girders (Figure 1 and Figure 2). The structure was constructed using
balanced cantilever segmental techniques in the early 1980s and placed into service in 1984.
Figure 2. Cross-Section Views of Twin Box Girders, near Pier Table (left) and near Midspan (right)
In May 2019, the City asked WSP to perform a federally mandated load rating of the bridge with consideration to
the effects of the known cracking. SDOT had observed limited hairline cracking for many years, first noting unusual
cracking in 2013, near the quarter points of the main span (i.e., Joint 38). This cracking was seen at four primary
locations. SDOT hired a national consulting firm in 2013 to investigate the cracking and its implication on safety.
They concluded that the cracks were not a safety issue, although they did recommend that SDOT set up some
monitoring and undertake epoxy injection of the larger cracks. SDOT completed this work in the summer of 2019.
In March 2020, while in the process of load rating the WSHB, the inspection team (WSP and SDOT) discovered
rapid crack propagation in the webs of the bridge’s main span. The City closed the bridge on March 23, 2020 as a
public safety measure because of this rapid crack propagation – combined with the sensitivity of the analysis
findings; the observation that the detailing within the distressed region of the bridge would not permit force transfer
mechanisms upon which standard code provisions rely to form; and the unknown condition of the post-tensioning
and cracking within the bridge.
From the analytics conducted up through February 2020, we learned that the bridge capacity was sensitive to the
amount of degradation the bridge had experienced. We did not know the widths of the cracks prior to epoxy
injection. With the bridge continuing to crack, SDOT determined that leaving the bridge in its current state was
unsafe: thermal loads and force redistribution within the bridge were causing further degradation, jeopardizing the
bridge’s ability to carry its own self-weight. Removal of live load alone did not remove the crack propagation
problem, further validating the decision to close the bridge.
Page 1
Since the bridge closure in March 2020, multiple activities have been conducted concurrently, as illustrated in
Figure 3 and discussed further below.
Reconnaissance: The team learned about the condition of the bridge and how it was behaving. This work included:
— Daily field inspections
— Installation of an automated bridge monitoring system
— Holistic analysis of data from an automated bridge monitoring system
— Non-destructive testing of concrete cracks and post-tensioning to identify voids and measure crack depths
We conducted field inspections daily for months until the automated structural health monitoring system came
online on May 18, 2020 and enough data was accumulated to be validated/understood. Visual field inspections,
including crack mapping and width measurements, continue on a biweekly basis to better understand the condition
of the bridge relative to the automated structural health monitoring system. The automated structural health
monitoring system has allowed us to correlate our analytical modeling to environmental loadings. This has in turn
allowed us to correlate bridge behavior to historic environmental data and gather an understanding of how seasonal
(thermal) effects impact the bridge. In addition, we have been able to correlate analytical predictions to actual
measured data for the specific work activity loadings occurring as part of the bridge stabilization measures. These
correlations provide confidence that the bridge behavior is predictable and give a better understanding of the
magnitude of force redistribution that has occurred within the structure.
We completed the non-destructive testing in the first part of June. This milestone marked the first decision point in
the project and answered the question, “Is there anything systemic that would technically preclude further
investigation into repair/rehabilitation options?”
The non-destructive testing yielded encouraging results regarding the condition of the various types of cracking. It
did not identify any corrosive conditions of the post-tensioning grout; any widespread void patterns with the post-
tensioning ducts; or any corrosion of the post-tensioning strands. The sample set of tests would indicate that the
bridge is likely not suffering from systemic problems beyond the crack propagation between Piers 15 and 18, in the
main span and end spans.
As information is received in real time through the biweekly in-person inspections and 24-hour monitoring system,
we learn more about the bridge and how it is behaving, allowing us to make more informed decisions. What we have
learned to date has yielded confidence that the bridge behavior is predictable and that it is technically feasible to
rehabilitate the bridge and restore its remaining service life, or more. However, we will continue to perform
reconnaissance work to see if trends change as we finalize stabilization measures this fall.
Bridge Stabilization: WSP designed stabilization measures to provide a missing link through the distressed regions
of the bridge to allow the bridge to resist loads as it was originally intended, arrest further crack growth, and remove
unintended restraints to bridge movements. Bridge stabilization measures currently being constructed include:
— Construction/installation of carbon fiber reinforced polymer (CFRP) sheets and external post-tensioning
— Construction of Pier 18 transverse bearings restraint release
The bridge stabilization design was released for construction on June 5, 2020, and construction started soon
thereafter. With the monitoring system online, we continue to watch how the bridge reacts during bridge
Page 2
stabilization measure implementation, and, as Figure 3 shows, we will continue to do so for a period of time after
construction.
Cost-Benefit Analysis (CBA): The team developed a spectrum of remedial action concepts with the purpose of
illustrating the benefits and drawbacks of each alternative. The CBA included developing:
— Bridge demolition concepts
— Temporary shoring concepts
— Near- and longer-term rehabilitation concepts
— A preliminary seismic assessment
— Replacement concepts
1.2 SCOPE
The CBA investigated multiple variables to illustrate the benefits and drawbacks of rehabilitation and replacement
alternatives. As previously noted, the purpose is to objectively provide the City with information pertinent to the
decision as to whether to further invest in rehabilitating the existing structure or pivot towards a replacement. Its
findings illustrate the alternative yielding the apparent best return on investment within the context of the CBA;
however, this may not necessarily be the best return on investment with consideration to the wider context of the
City.
ALTERNATIVES DEVELOPMENT
The CBA began with five alternatives, all of which were on-alignment and fit the same grade/profile as the current
bridge. In response to community feedback, the study adopted a sixth alternative – an immersed tube tunnel (ITT).
This is the only alternative that deviates from the current alignment and grade/profile. During this process, we also
eliminated the third alternative, a partial superstructure replacement, from consideration as it was determined that it
was not the apparent low-cost option for a rehabilitation alternative. Section 2 of this report includes full alternative
descriptions and details of each concept.
WSP chose five representative alternatives based on apparent low cost to fit within the scope and schedule confines
of the CBA. There exist other options within each category, many conceptually mentioned within the appendices
that could and should be further explored or developed.
1
It should be noted that SDOT, TAP, and CTF input was invaluable in WSP’s development of the CBA. The Port of Seattle and
Northwest Seaport Alliance were other important contributors.
2
All costs are ROM costs. They are estimates based on historic data, similar projects, and City-specified rates of discount and
inflation. All costs are calculated in 2021 dollars.
Page 3
CONCEPTUAL DESIGNS
Sketches for each alternative include demolition options, shoring options, future construction considerations, and
potential right-of-way needs for the alternatives. WSP developed the concepts with sufficient detail to support
associated ROM cost estimates.
ATTRIBUTES AND MEASURABLES
With guidance from the TAP and the CTF, SDOT and WSP developed a list of ten attributes to define the
performance of the alternatives.3 For each attribute, subject matter experts from the TAP, SDOT, and WSP defined
measurables that quantify the differences (positive and negative) between each of the alternatives. The attributes
were first compared relative to each other using direct input from the advisory groups to determine attribute weight
factors. Subject matter experts then scored each alternative relative to the others for each attribute, based on the
measurable results.
COST ESTIMATES
For each alternative, WSP developed ROM estimates for initial capital cost (inclusive of monetized risk items) and
for life cycle costs. Life cycle costs include allowances for initial capital investments, operation and maintenance
costs, inspection costs, and future repair/rehabilitation costs.
RISK REGISTER
Many risks, challenges, and opportunities lie within each alternative. The risk register identifies those risks;
qualitatively assesses each one based on the likelihood of occurrence and its impact; identifies how the risk will be
addressed, monitored, and controlled; and determines whether the risk is monetized or not. The risk register is
considered a “living document” – risks are added as they are identified, throughout the life of the project.
COST-BENEFIT ANALYSIS REPORT
Beyond the measured data captured in the attributes, costs, and risks exist the nuances inherent in a project of this
magnitude, which affects as many people as it does. Subject matter experts have prepared this report to provide a
qualitative study, and contextual information, to support the quantified portion of the analysis within the scope and
schedule of the CBA.
1.3 ASSUMPTIONS
This CBA is founded on certain assumptions:
— The CBA does not quantitatively assess off-alignment bridge replacement alternatives.4
— The approach structures are beyond the scope of this study. The CBA does not assess their vulnerabilities, nor
does it include any associated costs.
— An apparent low-cost approach dictated the development of alternatives. For the replacement alternatives, a
type, size, and location (TS&L) study should be conducted to determine the actual layout and type of the
replacement alternatives.
— A future TS&L study should conduct detailed constructability reviews for replacement alternatives.
— The WSHB corridor will be closed during construction of a given alternative.
— Construction closure durations are cumulative for a given alternative.5
— Sound Transit will have an independent Duwamish Crossing for light rail by 2032.
— Preliminary geotechnical input was limited to pile axial capacities, preliminary lateral soil design parameters
(including liquefaction considerations), and preliminary seismic hazard information. See Appendix B.
3 Reference TAP CBA Part 1 Recommendation memorandum and City/WSP response memorandum for background discussions.
4 Alternative 6, the Immersed Tube Tunnel, would necessitate replacing the approach structures and matches neither the existing
alignment nor grade/profile, but we have not included those costs in this CBA. The ITT should be explored in greater depth in the
TS&L study that will follow upon this CBA.
5
Alternatives 1 and 2 each assume two phases of construction: one for the initial shoring or rehabilitation; one for the eventual
replacement.
Page 4
— A preliminary corrosion assessment was used to define assumptions for the condition of the existing
foundations.
— Seismically, the rehabilitated bridge will have an operational classification of “normal,” while a replacement
bridge will have an operational classification of “essential.”6
— Alternative 2 (direct rehabilitation) includes additional external post-tensioning and CFRP sheets, beyond that
which is taking place during stabilization work.
— Alternative 4 (superstructure replacement) is assumed to be a girder structure composed of either steel tub
girders or concrete box girders. Following an apparent low-cost approach, WSP eliminated other structure
types, such as extradosed, cable-stayed, or network tied-arch superstructures. For cost purposes, the CBA
assumed a concrete box girder.
— Immersed Tube Tunnel Assumptions – See Appendix L for an in-depth discussion of ITT assumptions.
— “Year one” for life cycle cost analysis (LCCA) is 2021. The LCCA extends to 2100. A salvage value was
assigned to alternatives with remaining service life beyond the year 2100.
— The CBA does not capture all COVID-19-specific impacts.
— The CBA does not capture the costs of Reconnect West Seattle, of rehabilitating or replacing the approach
structures, or of any other projects associated with the West Seattle Bridge Program.
— Socioeconomic impacts are qualitatively addressed as they pertain to general trends between alternatives.
Certain measurables within each attribute are quantified.
— WSP based costs for civil/roadway, utilities, general traffic, and general preparation costs on rough metrics
associated with the structure cost, and not on quantified values for specific items of work.
— Only Alternative 1 assumes a $300,000 lump sum for an intelligent transportation system.
— Each alternative assumes a $300,000 lump sum signal modification cost.
— Mobilization: 10 percent
— Other variable (soft) costs: 30 percent. These costs represent expenditures on owner management and
administration, design engineering, construction administration and inspection, third-party reviews, utility
relocations/protections, and other costs.
— The Forward Compatibility attribute assumes that the existing 6 percent approach grades can accommodate
future Sound Transit light rail.
1.4 PROCESS
SDOT outlined the CBA as a step in the decision-making process after the corridor was closed in late March 2020.
The CBA commenced in tandem with the design and construction of the bridge stabilization measures; the design
and deployment of a comprehensive structural health monitoring system; and the non-destructive testing. By the
nature of this process, inputs into the CBA were dynamic, becoming more informed with time.
6
“Essential” in this sense refers to the WSDOT Bridge Design Manual operational category. Alternative 2 was classified as normal;
however, preliminary seismic analysis indicates that it meets the essential bridge performance defined for the replacement
alternatives.
Page 5
Table 1. Decision Matrix shows the key questions we started with, as well as some of the answers developed
during the CBA process
Key Questions CBA-Determined Answers
1. Can the bridge be rehabilitated sufficiently to allow 1. Yes (see Section 4).
a return to full capacity for an additional 10+ years
at approximately 25% of the replacement cost? 2. None identified. Further investigation of other parts
of the substructure and approach could yield
2. What other potential deficiencies exist? different results.
3. How many more years of useful life would the 3. Estimated to be 40 years.
bridge have?
4. Unknown.
4. What is the useful life of the approach structures?
5. See Section 4.
5. What is replacement cost (In-Kind and Arterial
Realignment)? 6. See Section 4.
11. How would Sound Transit enter and exit the 12. This requires further investigation in a TS&L study.
corridor? 13. See Section 3.2.6 Funding Opportunities
12. Would a combined bridge be compatible with the
other Sound Transit alignments being studied?
13. What are various funding/financing methods
available?
Page 6
ALTERNATIVE DESCRIPTIONS
The CBA’s purpose is to help inform the decision as to whether to rehabilitate or replace the damaged WSHB. WSP
developed alternatives based on an apparent low-cost approach. Its intent is not to determine an alternative within
those two scenarios; we anticipate that SDOT will further explore this in the TS&L study to be undertaken under a
separate contract.
With a firmly established intent to help make a binary decision, WSP developed the CBA’s alternatives with the
assumptions outlined in Section 1.3. Critically, we initially developed the rehabilitate and replace alternatives to be
compared directly against one another, so they were founded on the assumptions that all alternatives would be on-
alignment (in the footprint of the current structure); would not change the approach structures or the bridge
profile/elevation; and would not incorporate light rail (other than to determine whether the structure would or would
not be able to accommodate it in the future).
ADDING THE IMMERSED TUBE TUNNEL ALTERNATIVE
Based on public feedback, WSP added an immersed tube tunnel (Alternative 6) to the CBA in July 2020. Because of
the inherent differences between this and the other replacement alternatives (Alternatives 4 and 5), there are several
crucial variances between Alternative 6 and Alternatives 4 and 5:
1. The tunnel is not on-alignment, as it would not be able to be placed on top of the existing bridge’s
foundations, even after demolition and excavation.
2. The tunnel requires significant modifications to or replacement of existing approach structures, because it is
off-alignment and requires a downward rather than upward trajectory.
3. The tunnel requires different permits and environmental considerations from an above-water replacement
alternative.
4. The tunnel’s massive components need to be cast off site and transported in by barge; a casting facility would
likely need to be built, increasing cost and duration.
5. The tunnel is forward compatible because the section could be designed to include extra lane width and light
rail if desired. The tunnel concept explored here does not include light rail, as it is compared directly to other
alternatives, which do not incorporate it.
Section 2.6 provides more detailed information on the immersed tube tunnel (ITT) concept. The major differences
between the ITT and other replacement and rehabilitation alternatives are further explored throughout Sections 3, 4,
5, and 6.
Table 2. Alternatives
Scheme Scenario Description
Shoring 1 Temporary Shoring to Restore Live Load (3 to 5 years)
2 Direct Strengthening to Restore Live Load (40 years)
Strengthening
3 Partial Superstructure Replacement to Restore Live Load (15 to 50 years)
4 Accelerated Superstructure Replacement (75 years)
Replacement 5 Accelerated Bridge Replacement (75+ years)
6 Immersed Tube Tunnel (75+ years)
Page 8
2.2 ALTERNATIVE 2: DIRECT STRENGTHENING TO
RESTORE LIVE LOAD
Figure 7. Construction Schedule for Alternative 2, Direct Strengthening to Restore Live Load
Page 9
2.3 ALTERNATIVE 3: PARTIAL SUPERSTRUCTURE
REPLACEMENT TO RESTORE LIVE LOAD
Page 10
Figure 9. Alternative 4, Accelerated Superstructure Replacement
Page 11
Figure 11. Alternative 5, Accelerated Bridge Replacement
Page 12
While the tunnel could be built to accommodate light rail, the purpose of this CBA was to compare options as fairly
as possible. Because the bridge replacement concepts discussed in the CBA are forward compatible with light rail
but do not feature light rail, the tunnel concept advanced here does not include light rail, but we do consider the
tunnel to be forward compatible with it (see Appendix L for more information).
Page 13
PERFORMANCE EVALUATION
CRITERIA
3.1 PERFORMANCE EVALUATION PROCESS
The findings of the CBA are presented as value indices, a measure indicating return on investment, and
mathematically represented by dividing the performance score by the cost of a given alternative. This section of the
report discusses the process for developing the alternative performance score, which is independent of cost.
The first step of the CBA assessed the rehabilitate and replace alternatives using a formal three-phase evaluation
process:
1. Definition and process
2. Findings
3. Reporting
The CBA evaluation process used for the WSHB was developed, refined, and implemented in conjunction with
Washington State Department of Transportation (WSDOT) on past WSDOT projects. The intent of this process is to
minimize subjective evaluation of the alternatives.
Workshops with SDOT and WSP and meetings with the TAP and CTF refined the alternatives and key evaluation
criteria. For example, during Workshop No. 2, SDOT and WSP discussed potential attributes, and decided to add
another attribute (Equity) to the list. And, during the September 9 CBA presentation to the CTF, members of the
task force raised concerns that the CBA was not capturing long-term workforce impacts, so WSP added another
measurable to Business and Workforce Impacts (Section 3.2.7).
7 Reference TAP CBA Part 1 Recommendation memorandum and City/WSP response memorandum for background discussions.
Page 14
3.1.3 WEIGHTING OF PERFORMANCE ATTRIBUTES
Once we identified the ten performance attributes, along with how they are measured, the next step was to weight
each individual attribute against the other attributes. SDOT, the TAP, and the CTF independently filled out the
attribute matrix spreadsheet (Figure 15). The highest-ranking attributes were Mobility Impacts, Seismic/Safety, and
Constructability. These attributes were then given the most weight for the next step of the CBA.
3.1.4 MEASURABLES
Within each attribute falls several measurables to quantify (and/or qualify) the value of each alternative in that
particular context. These allow us to objectively measure the different components that subject matter experts chose
as representative of each attribute. Depending on the unit of measure, results could be quantitative or qualitative.
Once data is input, subject matter experts give each alternative a score of 1, 3, 5, 7, 9 for each attribute, as defined in
the following subsection.
Page 15
Table 3. Alternative/Baseline Rating Scale
Figure 16. Alternative 2 served as the baseline, receiving a 5 for every attribute (This figure shows the
Seismic/Safety attribute for demonstration purposes.)
Specific items of measure for each attribute objectively assessed the difference between alternatives with respect to
each attribute. Subject matter experts from SDOT, WSP, and the TAP independently rated each alternative relative
to the baseline (see Figure 17). We then used these ratings to calculate overall performance scores and value indices
(discussed further in Section 6).
Figure 17. Subject matter experts from the TAP, SDOT, and WSP scored each alternative relative to each
attribute to determine an average performance rating
3.2 PERFORMANCE
The following subsections discuss in greater detail each attribute’s measurables and resulting values, as well as the
performance of different alternatives with respect to each of the performance attributes. Within each attribute lies
several “measurables” and “units of measure.” Subject matter experts determined (a) what these measurables should
Page 16
be and (b) how to measure them. They then used various methodologies to calculate values for each of the five
alternatives.
Figure 18. Bridge Maintenance, Inspection, and Operations attribute’s measurables applied to all five
alternatives
INSPECTION REQUIREMENTS
We examined the frequency and level of effort required for inspections, as well as the need for any special
inspections. Alternative 4 performs best for this measure, as it requires only a medium level of effort, with 24
months between inspections from the outset and no special inspection requirements.
Alternative 6 also has 24-month inspections; however, the tunnel does require special inspections. Alternatives 1 and
2 would initially require a greater level of effort, with special inspections required every 6 to 12 months. Once these
alternatives were superseded by their in-kind replacements (Alternative 5), those inspections would drop to every
24 months but would still require special inspections.
Alternative 5 performs moderately better than Alternatives 1 and 2 based on frequency of inspection. For this
measurable, replacement (except for the tunnel) performs better.
INTELLIGENT TRANSPORTATION SYSTEMS REQUIRED
The only alternatives to require Intelligent Transportation Systems are Alternative 1 and Alternative 6, making
rehabilitation (Alternative 2) or a bridge replacement (Alternatives 4 and 5) equally viable. Shoring and a tunnel
replacement are less preferred.
STRUCTURAL HEALTH MONITORING SYSTEMS REQUIRED
If the existing superstructure elements remain in service (Alternatives 1 and 2), a number of systems would have to
be installed to monitor the health of the rehabilitated or shored structure. Given the expense and manpower required
to implement a structural health monitoring system, this makes replacement a better alternative for this measurable.
PAINTING/UV PROTECTION REQUIRED
Any structure containing structural steel elements, requires periodic painting. Alternative 5 (this would include
Alternatives 1 and 2 eventual in-kind replacement) would need to be painted every 25 years. Before replacement,
Alternative 2 would require painting every 10 years, as UV protection is required when using CFRP. Submersed
elements of Alternative 6 would not require painting. As such, a replacement (specifically, Alternatives 4 and 6) is
preferred for this measurable.
3.2.2 CONSTRUCTABILITY
The Constructability attribute measures the ease and efficiency with which each alternative can be built, relative to
schedule and potential construction means and methods.
This attribute was the third highest ranked in the combined scores of the CTF, the TAP, and SDOT. It thus has the
third highest weighting in the analysis. The constructability of each alternative was based on its impacts to the
following measurables as discussed below. Subject matter experts from the TAP, SDOT, and WSP scored
Alternative 4 (superstructure replacement) as the preferred alternative for this attribute, with an overall score of 5.22.
Page 17
Figure 19. Constructability attribute’s measurables applied to all five alternatives
SCHEDULE IMPACTS
For each alternative, WSP estimated an approximate duration (shown in months), based on the work required and
the potential risk for schedule delays.
Alternative 2 has the shortest initial schedule duration, as it does not require significant amounts of demolition or
major construction of new bridge components. We can estimate durations based on similarities in work items to the
current stabilization measures.
It is our understanding that federal funds could be used in rehabilitation or replacement of the bridge. This will
likely require all permanent steel materials to be manufactured domestically. Therefore, alternatives that require
much greater amounts of structural steel, such as the trusses required for the Alternative 1 shoring option or the steel
superstructure used for the Alternative 5 cable stay, will have increased procurement duration, risk of delays, and
risk of higher or unpredictable cost. Alternative 6, with a construction duration of 66 months, would have the
greatest impact. It is likely that it would also run the greatest procurement risks, with the potential need to build an
off-site casting basin for fabricating the components.
For this measurable, rehabilitation is preferred.
CONSTRUCTION COMPLEXITY
The complexity of each alternative is based on the use of standard construction methods. We consider an alternative
to be more complex if the work requires less common or reliable means of construction, increasing the contractor’s
risk and/or costs.
For Alternative 1, the two trusses that would have to be constructed are larger than any locally constructed trusses in
recent history, making this alternative complex. There is a wealth of local experience in the use of post-tensioning,
and the similarity to the current work being performed reduces Alternative 2’s risk. However, this work would still
require retrofitting an existing structure, and retrofitting is complex.
Alternative 4 assumes that the means and methods for replacing the superstructure would be like those used to
construct the existing bridge. However, balanced cantilever construction has become more common than in the early
1980s, and regionally, contractors are experienced in that method. Therefore, the construction of a new
superstructure on existing foundations is somewhat complex, but the assumed means and methods are frequently
used in the region. If future studies explore other superstructure replacement options, complexity could change
accordingly.
Alternative 5 does not require as much reuse of the existing structure, making substructure work more traditional
than retrofitting existing substructures. However, the concept features a cable-stay bridge which is somewhat
regionally uncommon and has construction methods that are considered complex.
Alternative 6’s construction is complex, because segments need to be set and leveled underwater. It is also complex
because of the amount of temporary works and dewatering needed for the cut-and-cover portion, and the low
frequency of similar projects in the region. In addition, the tunnel would require the construction of an entirely new
structure, along with approaches.
For this measurable, rehabilitation, specifically Alternative 4, is preferred.
SPECIALTY CONTRACTORS AND EQUIPMENT
Any alternatives requiring post-tensioning, primarily Alternatives 2 and 4, would require specialty contractors.
Alternative 2 would also require a specialty contractor for CFRP placement.
Page 18
The construction methods for the cable-stay bridge proposed for Alternative 5 would require specialty contractors
and materials. Ground improvements would likely be needed near the new foundations, consisting of groupings of
large-diameter drilled shafts. Ground improvements and drilled shafts would both require specialty contractors and a
fairly large footprint for mobilizing and storing construction equipment and materials.
Alternative 6 would require a contractor experienced in the construction methods needed for dredging the channel
and setting and aligning the tunnel segments, as well as a specialty fabricator and facility for casting segments.
For this measurable, rehabilitation, specifically Alternative 4, is preferred.
UTILITY RELOCATION
As alternatives are only conceptual at this point, we have only considered utility impacts in a general sense. Future
studies should further investigate specific impacts. For bridge superstructure work only, we expect that impacts
would be less severe, giving an advantage to Alternative 2 as far as initial work items are concerned. We would
expect Alternatives 1 and 4 to have greater impacts due to the amount of work outside of the box.
Alternatives 5 and 6 would have the greatest impact on existing utilities, as the new foundations would be large, and
exact locations are yet to be determined. This is also assumed to be the case for any foundation work, such as
foundation retrofits for Alternatives 2 and 4. For Alternative 6, it is expected that there will be utility conflicts both
within the footprint of the tunnel alignment and those utilities that may be impacted by any anchors or similar
methods that may be used to support excavation for the tunnel.
For this measurable, repair is preferred, but long-term impacts would be similar to replacement alternatives.
IN-WATER WORK
Any alternative that requires work below the wetted perimeter is by default more challenging because of the
constraints that the river poses — from marine traffic to environmental considerations, such as fish migration.
Alternatives 2 and 4 are expected to require some in-water work for foundation retrofits. The advantage of the new
foundations Alternative 5 would require is they can be located further from the river, thus minimizing or eliminating
permit constraints when working in or near the water. Alternative 6 requires the most in-water work as the channel
would have to be dredged and then segments of tunnel sunk into place and connected. There is likely to be at least
some disruption to river operations to perform this work; however, full extents of the disruption have not yet been
assessed.
For this measurable, a full in-kind replacement is preferred.
DEMOLITION
Demolition would be over an active river, and all demolition activities would need to accommodate the operation of
the adjacent swing bridge. The CBA’s current assumption is that any superstructure demolition would be top-down.
For Alternative 1, the shoring trusses could support the main span during demolition. For all the other alternatives, it
is assumed that the demolition of the existing bridge superstructure would be performed in a reverse order of how it
was constructed – balanced cantilever.
While several bridges in the region have been demolished over waterways and roadways, this would be one of the
region’s first balanced cantilever bridges to be demolished, adding another level of uncertainty to this activity.
Current work, such as post-tensioning and carbon fiber wrap, to stabilize the bridge could also add more complexity
to structure demolition.
There is no clear “winner” for this measurable.
POOR SOIL CONDITIONS
As stated in the assumptions, a limited amount of geotechnical information is available for the site at this time.
Unforeseen geotechnical conditions are likely to cause additional cost and schedule delay, adding risk to all
alternatives. The more foundation work that an alternative requires, as well as expected increases in superstructure
weight, can be anticipated to have greater impacts due to poor soil conditions. Alternatives 1 and 4 require that
existing Piers 16 and 17 foundations be retrofit in the future. Poor soil conditions could have a large impact in these
cases, as the options for strengthening existing structure are limited. Alternative 5 requires full replacement piers,
which provide more opportunity to design for poor soils. However, this alternative would potentially require ground
improvements, which can be costly and impact the schedule. Alternative 6 may require targeted ground
improvements needed to support the final structure, and to reduce seepage and provide lateral excavation support
during construction.
Page 19
There is no clear winner for this measurable, as all alternatives are impacted by poor soil conditions in one way or
another.
STAGING AND LAYDOWN AREAS REQUIRED
A minimal construction footprint is needed to perform the strengthening work for Alternative 2. Alternatives 1 and 5
would likely need larger laydown areas to facilitate the storage and erection of steel elements. Any work on the
existing foundations (Alternatives 2 and 4) would require coffer cells with a large footprint to avoid existing battered
piles. The construction footprint for Alternative 6 is an order of magnitude larger than any of the other alternatives,
requiring direct impacts to most of the alignment, as the on-land portions will be constructed by cut-and-cover
methods. It also requires a dedicated site for construction of the prefabricated elements.
Either rehabilitation or the superstructure replacement alternatives are preferred.
3.2.3 ENVIRONMENTAL
The Environmental attribute measures each alternative’s potential adverse effects to the built or natural
environments. Using the following measurables, it seeks to answer the question: What kind of temporary and
permanent impacts will this rehabilitate/replace concept have on the Duwamish River and surrounding area?
Subject matter experts from the TAP, SDOT, and WSP scored Alternative 2 (rehabilitation) as the overall preferred
alternative for this attribute (with the baseline score of 5), with Alternative 4 (superstructure replacement) a close
second with a score of 4.78.
8
While not assessed in the CBA, dredging for the tunnel has the potential to disturb hazardous materials in the Duwamish River,
which is classified as a Superfund site. This renders Alternative 6 particularly worrisome from an environmental impact standpoint.
Page 21
with Alternatives 2, 4, and 5 could also have a permanent or temporary use of the Nucor Steel property or the
Pacific Forge Historic District. With all the alternatives, the new piers with the in-kind bridge replacement, when it
occurs, may also have a potential use of these two Section 4(f) resources. The tunnel alternative could have a
permanent or temporary use of both the Terminal 18 public access park and the public shore access across the East
Duwamish River.
For this measurable, the replacement alternatives are preferred, as they have only one construction event that could
result in a use of a Section 4(f) resource and that potential use would be limited to the area of a new pier.
AIR QUALITY
We measured air quality by evaluating the additional tons of greenhouse gas (GHG) emissions emitted because of
increased vehicle miles traveled (VMT) from detour routes while the bridge is closed, as compared to the VMT if
the bridge were open to traffic. This measurable took into account emissions from additional VMT for each phase
and duration of construction by primary vehicle classification (personal vehicle, medium truck – 3 axle vehicle, and
large truck – 4+ axle vehicle) and emissions profile. For Alternative 1, the estimated emissions were an additional
210,000 tons. Alternative 2 had an estimated additional 128,000 tons of emissions, and Alternatives 4 and 5 had an
estimated additional 161,000 tons of emissions. Alternative 6 has an estimated 213,000 tons of emissions.
With the fewest tons of emissions, rehabilitation has the least impact on the built and natural environments for this
measurable.
WILDLIFE IMPACTS
We measured the timing and duration of construction to identify potential impacts to wildlife, as this could impact
the breeding season of falcons, which have been known to nest on the bridge, and great blue herons, with a known
heron rookery in the greenway south of the bridge. As the exact duration of construction for the different work
activities is not yet defined, we assessed construction impacts based on the number of phases of construction (i.e.,
demolition, shoring or strengthening, or replacement) and the total duration of construction. High levels of
construction noise, such as from pile driving, can also disrupt wildlife, particularly nesting birds during the breeding
season.
With Alternative 1, pile driving is not initially anticipated; however, three phases of construction are anticipated
with a total construction duration estimated between six to eight years and eventual pile driving during the
replacement. Alternative 2 anticipates three phases of construction over five to six years. Alternatives 4 and 5
assume two phases of construction, including foundation retrofit pile-driving work, with an estimated duration of
construction between four to five years. Alternative 6 assumes only one construction phase; however, the total
construction time is between eight and nine years. Alternative 6 would also include pile driving with high noise
levels that can affect nesting birds.
As Alternatives 4 and 5 offer a shorter duration than Alternatives 1 and 6 and require two phases of work (instead of
Alternative 2’s three phases), replacement (with the exception of Alternative 6) is preferred for this measurable.
3.2.4 EQUITY
The City of Seattle has a long-standing Race and Social Justice Initiative, which is the City’s commitment to
eliminate racial disparities and achieve racial equity in Seattle. Most City departments, including SDOT, have a
Race and Social Justice Initiative Change Team and use Racial Equity Toolkits to evaluate programs and projects
using a broader equity lens.
The Equity attribute applies both quantitative and qualitative measurements to the rehabilitation and replace
alternatives presented in the CBA, based on many of the underlying methodologies presented in the Racial Equity
Toolkits. The WSHB closure impacts the surrounding area, including traffic movements, access to employment
opportunities, and operating local businesses. The equity attributes are specific to impacts on marginalized
communities, as determined by evaluating primary diversion routes during bridge closures. Sections 3.2.6 Funding
Opportunities and 3.2.7 Business and Workforce Impacts cover revenue generation measures that can be based on
regressive taxes and fees and impacts on employment and economic activity that often disproportionately impact
lower-wage professions.
Using closure duration as the foundation for examining Equity attributes, the CBA looked at both how to best frame
a definition of equity and identify specific measurables to capture incremental impacts that disproportionally affect
Page 22
historically and currently marginalized communities.9 There are a number of potential sociodemographic factors that
could be considered for an equity analysis: race, income status, disability, populations that do not speak English as
their first language, among others.
Within the West Seattle peninsula and in South Seattle, the range of median household incomes and the
demographic characteristics of their approximately 20 neighborhoods illustrate the diversity of affected populations.
Compared to the median household income in Seattle, the median household income in neighborhoods around the
WSB range from 47 percent below the city average in South Park to 21 percent above the city average in Alki
Beach. The median household income in 12 neighborhoods is below the city average.
The change in traffic patterns could result in social externalities for neighborhood residents and local businesses. For
example, the detour route over the First Avenue South Bridge diverts road traffic through three of four
neighborhoods with the lowest median household income in the project area. This results in increased environmental
and social impacts from the increase in passenger and truck traffic. In the long term, the accumulation of these
impacts could result in undesirable effects on personal health, the degradation of the environment and physical
infrastructure, decreased effectiveness of social services, and stagnant growth in property values (See Sections 3.2.6
Funding Opportunities, 4.2.6 Business and Workforce Impacts, 4.2.7 Mobility Impacts, and 4.2.8 Multimodal
Impacts for further discussion of equity and economic impacts due to the bridge closure). Furthermore, components
that may be attributed to work-related equity concerns, for example the impact of increases in travel time delay on
independent owner-operators of commercial trucks serving the port, are assessed within the framework of the
Business and Workforce Impacts.
Subject matter experts from the TAP, SDOT, and WSP scored Alternative 2 (rehabilitation) as the overall preferred
alternative for this attribute, with a baseline score of 5.
The CBA’s Equity attribute focused on race to examine the impact of the closure diversion routes through
communities with relatively high percentages (23 to 89 percent) of people of color.10
9
It should be noted that the Equity attribute captures primarily the impact of detour routes through marginalized communities. It
does not delve into impacts on members of those communities who might see their travel times increase or find it more difficult or
unreliable to get to work.
10
A note on methodology: VMT differs based on the timing of the closure. It is assumed that light rail will be in service after 2032,
reducing impacts on vehicle travel thereafter. As such, if a replacement were to be built for the rehabilitated bridge in 2066, the VMT
would be lower than it is for a pre-2032 closure.
Page 23
INCREMENTAL VEHICLE MILES TRAVELED11
This measurable is intended to capture associated incremental emissions – air quality impacts and GHG, road safety
impacts, noise and other negative indirect externalities associated with vehicular travel. Again, this measure depends
on both the duration of the bridge closure, as well as the timing of the closure. Vehicle miles traveled (VMT) are
modeled by vehicle classification and aggregated for the incremental VMT measure.
With the highest overall closure duration, Alternative 6 has the highest incremental VMT through marginalized
communities. While Alternatives 2, 4, and 5 have similar closure durations, Alternative 2’s second phase is assumed
to be in 2066, which would impact travelers less than in 2022 because one of the CBA’s assumptions is that light
rail would be available at that time, reducing reliance on vehicles.
In terms of incremental VMT through marginalized communities, rehabilitation is the better option.
INCREMENTAL VEHICLE TRAVEL
Similar to above, the unit of measure for this measurable, intended to capture the increased VMT through
marginalized communities, is vehicle trips (all types) crossing the Duwamish River through diversion routes
(through marginalized communities) multiplied by construction duration. With Alternatives 1 and 6 adding more
than 80 million more trips through marginalized communities, Alternatives 4 and 5 adding 62.5 million more trips,
and Alternative 2 adding 58.8 million more trips, rehabilitation is the more equitable option for incremental vehicle
travel, with bridge replacement alternatives scoring similarly.
INCREMENTAL TRAVEL TIME
This measurable, which is also dependent on closure duration and timing, evaluates cumulative person hours
traveled (PHT) through marginalized communities on SDOT diversion routes and PHT in the final configuration.
PHT measures all travel time – pedestrian, transit, bicycle, and vehicle – while VMT captures only the distance
traveled in vehicles, including longer distances due to diversion routes. The measurable is also intended to
qualitatively capture incremental vehicular delays through marginalized communities. To derive PHT, we used the
modeled vehicle hours traveled (VHT) based on vehicle classification (single occupant passenger vehicle (SOV),
multiple occupant passenger vehicle (HOV+), medium truck, heavy truck) and adjusted for the average number of
occupants per vehicle to derive aggregated PHT values.
With Alternatives 4 and 5 scoring Low, while Alternatives 1 scored High and Alternatives 2 and 6 Medium, the
replacement alternatives (except the tunnel) are preferred for this measurable.
NUMBER OF CONSTRUCTION EVENTS/COMMUNITY DISRUPTION
This measurable evaluates how the number of repeated long-term construction events over time may impact
marginalized communities over 75 years. Alternatives 1, with two events and 7.5 years’ total closure, and 6, with
one event and 9 years’ total closure, have the greatest potential for community disruption. Alternative 2, with two
events and 5.25 years’ total closure, has the same overall duration as Alternatives 4 and 5, but the timing is different.
It is assumed that light rail will be available for Alternative 2’s second construction event, minimizing its impacts on
marginalized communities.
As such, rehabilitation and replacement offer similar levels of disruption, with rehabilitation causing less disruption
in the short term, but similar disruption in the long term.
A NOTE ON EQUITY
One of the CBA’s key findings was that 59 percent of WSHB’s current diversion routes are through communities
with high representation of people of color (23 to 89 percent) (Figure 22). In some cases, the entire diversion route is
through communities of color; in other cases, none of the diversion routes were, or a percentage of the route was.
Overall, these communities are currently disproportionately impacted by the bridge closure. It should be noted that
WSP recommends further study on impacts to marginalized communities’ economies from more than a perspective
focused on detour routes through the identified neighborhoods below.
11
For more information on how we calculated VMT, see Section 3.2.8 Mobility Impacts.
Page 24
Figure 22. West Seattle Bridge Diversion Routes and Percentage of People of Color by Census Tract
After evaluating all alternatives with regards to these five measurables, we concluded that overall, Alternatives 2, 4,
and 5 have the least impact on communities of color. This had to do with both a shorter closure duration and less
VMT relative to Alternatives 1 and 6. Alternatives 1 and 6 rated as the least-preferred alternatives, in large part due
to longer overall closure durations.12
For Equity in general, rehabilitation and bridge replacement alternatives are preferable to shoring and the tunnel
replacement alternative.
Figure 23. Forward Compatibility attribute’s measurables applied to all five alternatives
12
It is important to acknowledge that there are limitations to the equity framework and definition used in this analysis. A more robust
equity analysis and framework that incorporates greater community input and other demographic factors is recommended for future
studies.
Page 25
FUTURE ROADWAY CONFIGURATIONS
This measurable evaluated the time it would take to achieve full standard lane/shoulder widths. To accommodate the
necessary shoring structure, Alternative 1 would limit the entire structure to three to five lanes, until the bridge is
replaced (opening in 2033). This is the only alternative that would not restore the full seven lanes. Alternative 2
would restore all seven lanes in 2022, which is sooner than both Alternatives 4 and 5. Alternative 6 would be built
with all seven lanes, but it would not be open to traffic until 2030.
For this measurable, rehabilitation is preferred.
ACCOMMODATE LIGHT RAIL
Sound Transit’s current plan is to build its own structure for the West Seattle to Ballard Light Rail Extension
(WSBLE) However, noting the opportunity for synergy between agencies, this measurable examined the technical
feasibility of adding light rail to the WSHB structure, now or before 2032, when it is assumed that the WSBLE
would be complete. Coordination between Sound Transit and the City has commenced to determine if a joint
structure is desired. To date, Sound Transit and SDOT have discussed:
— Design life
— Capital costs
— Sound Transit O&M cost data
— Geometric considerations (vertical curves)
— Seismic design spectra
— Design loads (any plans for future increase?)
In addition to these discussion topics, SDOT has requested the following items from Sound Transit to support the
planning of a replacement structure:
— USCG Navigation Impact Report (NIR)
— Topographic surveys and mapping of the ground and waterway
— Geotechnical information logs and borings
— Environmental reports/studies
— Traffic data, forecasting, and modeling used for the WSBLE DEIS
— Preferred alignment drawings and cross sections
— Anticipated construction schedule
— List of planned temporary and permanent property acquisitions
For the purpose of the CBA, WSP assessed which alternatives could accommodate light rail. Alternatives 1 and 2 do
not reconstruct the bridge superstructure until after 2032, while Alternatives 4, 5, and 6 would be able to
accommodate light rail prior to 2032.
For this measurable, replacement is preferred.
Page 26
Note: Values shown are the weighted 1 to 9 scores. We applied each measurable to each funding source and then aggregated
those scores before applying them to each alternative.
Figure 24. Funding Opportunities attribute’s applied to all five alternatives
ELIGIBILITY
This initial criterion evaluated whether each alternative would be eligible to receive funds from each of the
identified funding sources. With 42 funding sources evaluated and 33 applicable and available for each of the
alternatives, except Alternative 6 with 32 sources, there is no clear preferred alternative.
REVENUE POTENTIAL
This measurable looks at the estimated revenue a given funding source may yield. Revenue potential, coupled with
other measurables within this attribute, can help the project sponsor determine whether a funding source is worth
pursuing.
Revenue Potential Score
— (5) revenue potential equal to or greater than $75 million
— (3) revenue potential between $26 million and $74 million
— (1) revenue potential equal to or below $25 million
With Alternative 2 receiving a weighted score of 5.4, Alternative 6 receiving 5.6, and Alternatives 1, 4, and 5 each
receiving 5.7, replace or shore are the slightly preferred choices for this measurable.
STABILITY/PREDICTABILITY
The predictability of a funding source is scored based on its known future revenue potential. For example, federal
funding sources authorized in the FAST Act are only guaranteed through fiscal year 2021. It is possible that the
future transportation act will create new requirements and different funding levels for each program, or it may
dismantle a program all together. Similarly, other sources, such as gas taxes or value capture revenue, may fluctuate
based on various market forces (i.e., lower gas tax revenues due to COVID-19 or vehicle fuel efficiency
improvements).
Stability/Predictability Score
— (5) known continuation and stability of a funding source
— (3) likely continuation and stability but possible changes to a funding source
— (1) likely elimination of a program or no future funds available during the project period
With Alternative 2 receiving a weighted score of 5.9, Alternative 6 receiving 6.0, and Alternatives 1, 4, and 5 each
receiving 6.2, replace or shore are the slightly preferred choices for this measurable.
LIKELIHOOD OF FUNDING
Looking beyond baseline eligibility, this criterion determines the likelihood of SDOT’s securing funds in the near
term for the project. This measurable evaluates the likelihood of securing federal discretionary funds by reviewing
project competitiveness for each program and assesses the local political/voter appetite for any new fees or revenue
sources that may require voter approval. It also determined if existing programs have the capacity to fund new
projects, or if funds have already been dedicated to an established program of projects.
Page 27
Likelihood of Funding Score
— (5) it is highly likely the project will secure funding through this source (~75% or greater)
— (3) it is possible to secure funding
— (1) it is highly unlikely the project will secure funding (~25% or lower)
With Alternatives 2 and 6 receiving a weighted score of 1.7, and Alternatives 1, 4, and 5 each receiving 1.8, replace
or shore are the slightly preferred choices for this measurable.
TIMING FOR AVAILABILITY
The timing of funding availability is an important consideration in creating a realistic funding program for the next
10 years. Issues that could impact timing include legislative requirements (such as obligation periods and
construction start date requirements), election cycles for new voter-approved levies, or existing funding
commitments in approved multi-year capital plans.
Timing for Availability Score
— (5) funding is available within a year
— (3) funding will be available in the next 1 to 5 years
— (1) funding will be available in the next 5 to 10 years
With Alternative 2 receiving a weighted score of 5.5, Alternative 6 receiving 5.8, and Alternatives 1, 4, and 5 each
receiving 6.0, replace or shore are the slightly preferred choices for this measurable.
ADMINISTRATIVE AND COLLECTION REQUIREMENTS
All funding sources require administrative oversight, some more than others. Most discretionary programs at the
federal, state, and local levels come with a different set of reporting requirements, environmental requirements, and
possible local match requirements. Some of these administrative processes can be burdensome for relatively small
funding awards. An alternative source of funding, such as a new levy or value capture revenues, can come with a
large administrative effort if the project sponsor is looking to create a new program. However, if funding is from an
established revenue source, the administrative burden would not be significantly increased by this project.
Administrative and Collection Requirements Score
— (5) the fee or tax is already being collected at some level or otherwise has a low cost of collection/the project
sponsor has a dedicated staff person who oversees grant reporting requirements
— (3) administration and collection requirements would entail some degree of incremental hours but not dedicated
staff
— (1) administration and collection would require the creation of a costly new mechanism and/or involve many
dispersed points of collection with higher associated staffing costs
With Alternative 2 receiving a score of 6.6, Alternative 6 receiving 6.8, and Alternatives 1, 4, and 5 each receiving
7.0, replace or shore are the slightly preferred choices for this measurable.
LEGAL AUTHORITY/AUTHORIZATION REQUIREMENTS
To implement each funding source, the state legislature may be required to authorize the use of the funding
mechanism, and the City of Seattle must be authorized to either implement a new tax or fee, and/or be eligible to
apply for a funding program administered through the federal or state government.
Legal Authority to Implement Score
— (5) authorized at the state level, and the City of Seattle has legal authority to implement a tax or fee and/or apply
for a funding program
— (3) authorized within the state, but the City of Seattle is not directly authorized to use it and/or they must partner
with another project sponsor to be eligible to apply for a funding program
— (1) not authorized within the State and, as such, City of Seattle has no authority to implement the tax or fee,
and/or they are ineligible to apply for a federal or state funding program
With Alternative 2 receiving a weighted score of 7.5, Alternative 6 receiving 7.7, and Alternatives 1, 4, and 5 each
receiving 7.9, replace or shore are the slightly preferred choices for this measurable.
Page 28
EQUITY IMPACTS
Any funding strategy for the rehabilitation and/or replacement of the WSHB has to consider mitigating the impact
on low-income households. Washington State has the most regressive tax structure in the nation, with a
disproportionate tax burden falling on the lowest income groups. Any funding mechanisms for infrastructure should
be evaluated within the context of reducing or mitigating the disproportionate burden on low-income households
include user fees, tolls, property taxes, and sales taxes.
Equity Impact Score
— (5) progressive and burden increases with income level
— (3) measure is progressive or regressive, but the implementation of the measure could include items that would
allow for the measure to be applied more regressively/progressively (examples: toll exemptions for low income
users, corporate exemptions for a head tax)
— (1) regressive and disproportionately impacts low income communities
With Alternative 2 receiving a weighted score of 6.1, Alternative 6 receiving 6.3, and Alternatives 1, 4, and 5 each
receiving 6.5, replace or shore are the slightly preferred choices for this measurable.
Note: FTE stands for full-time employee; this is a measurement of construction- and maintenance-related job creation.
Figure 25. Business and Workforce Impacts attribute’s measurables applied to all five alternatives
We expect that the change in travel patterns due to the WSHB closure will affect how and where residents and
commuters in West Seattle spend their household income on goods and services. The closure primarily affects
commuter and personal trips between West Seattle and the rest of Seattle; the increase in trip length and travel time
is expected to increase home-based work and local trips, while discouraging longer trips to other areas of Seattle.
Based on the traffic data detailed in the Mobility Impacts attribute, the change in trips associated with each
alternative also represents a shift in spending behaviors throughout the Seattle area, affecting businesses and
employment opportunities at the neighborhood level. Figure 26 shows several, though not all, of the local business
areas in West Seattle that may be impacted; businesses east of West Seattle are also likely to be impacted by West
Seattle residents’ limiting discretionary trips.
The long-term changes in household expenditures throughout the Seattle area could significantly change the local
economy, including business investment, business diversity, spending patterns, and employment opportunities and
Page 29
access. Latent effects of the closure could include a disruption in opportunistic spending, the interchangeability of
retail purchases and value-added goods and services, and the shift from brick-and-mortar retail to online retail. For
example, a shift from vehicle to pedestrian traffic in West Seattle could result in higher spending on local retailers,
hospitality establishments, and service businesses by residents, but less spending by non-resident consumers.
In addition, the detour routes and changes in road congestion resulting from the closure could affect the supply
chains of businesses operating in and around the West Seattle area, potentially resulting in long-term closures or
reduced operations, specifically in the Duwamish valley. Negative impacts will likely disproportionately impact
smaller businesses and independent operators who have less resources to mitigate the financial impacts from a long-
term closure. According to a survey of truckers serving the Port of Seattle, conducted by the City of Seattle and Port
of Seattle, 81 percent are independent owner-operators, many of whom associate with minority communities. The
Business and Workforce Impacts attribute considers the disproportionate economic impact faced by smaller
employers or independent operators through the business categories and income levels included in our quantitative
analysis, as well as in the qualitative evaluation
It is important to note that many of the Business and Workforce Impacts could be viewed as positive or negative, as
local businesses may see increased spending while businesses outside of the immediate vicinity could see decreases
in spending.
BRIDGE CLOSURE IMPACTS
Using the breakdown of average household expenditures provided in the Consumer Expenditure Survey published
by the Bureau of Labor Statistics, we can attribute an estimated 7 percent of expenditures of an average household in
the West region to commuter and recreational trips between West Seattle and other areas of Seattle.
The affected population’s annual expenditures were divided by the number of annual trips they would have taken,
and an approximate dollar value per trip was calculated. We estimated average annual household expenditures at
$69,981. Expenditure groups included food prepared by consumers on out-of-town trips; food away from home;
gasoline, other fuels, and motor oil; fees and admissions; and apparel and services. We used these expenditures as a
subset for estimating the impact – a total $9,589, or 13.7 percent of total annual household expenditures. Assuming
an average of two wage earners per household in West Seattle, the average percent impact per household earner
would be half or $4,829 (6.9 percent).
Page 30
The average number of trips per household is 1,500,
with approximately 45 percent attributed to local
discretionary trips. Dividing the amount of
expenditures per person by the number of trips results
in an average expenditure per trip of $7.15. We then
multiplied the dollar per trip amount by the net change
in trips for each of the alternatives.
Alternative 2, the rehabilitation alternative, shows a
net increase of $6.7 million, while both bridge
replacement alternatives show a net reduction of
$0.9 million. Alternative 1 shows a net decrease of
$3.5 million, and the final replacement alternative,
Alternative 6, shows a net reduction of $2.2 million.
In the case of this measurable, rehabilitation is the
better option.
DIRECT/INDIRECT ECONOMIC CONSTRUCTION
IMPACTS
The positive impacts of additional spending related to
construction activities include direct and indirect
employment and business expenditures in the regional
economy. The analysis of the economic impact of
construction activities, independent of the consumer
spending changes outlined above, tracks the
transactions linked to regional labor and materials
expenditures. These direct expenditures on labor and
materials support employment in the supplier market
and the goods and services market. Direct expenditures
are in turn supported by employee household
expenditures, resulting in indirect employment and
economic output.
Using the IMPLAN economic analysis software, we
calculated direct and indirect employment, labor
income, and economic output from construction- Figure 26. Major Retail Outlets in West Seattle
related expenditures for construction and operations of
each alternative.
With the potential for 15,108 FTEs, Alternative 6 offers the greatest positive impacts, with Alternative 5, at 9,548
FTEs, as second best. With 6,766 FTEs, Alternative 4 offers the least. Alternatives 1 and 2 could bring, respectively,
7,451 and 7,976 FTEs.
For this measurable, full replacement is the best option, with the tunnel offering the most FTEs during construction.
TEMPORARY CONSTRUCTION EASEMENTS
The temporary construction easements (TCEs) measurable evaluated the assumed space necessary for construction,
as well as an approximate construction duration for each alternative (Figure 27 to Figure 31). For all alternatives,
we assumed that the space under the east approach would not require a TCE, while the west approach would. These
evaluations did not consider waterway impacts.
Page 31
Figure 27. Temporary construction easements that would be required for Alternative 1
Page 32
Figure 28. Temporary construction easements that would be required for Alternative 2
Page 33
Figure 29. Temporary construction easements that would be required for Alternative 4
Page 34
Figure 30. Temporary construction easements that would be required for Alternative 5
Page 35
Figure 31. Temporary construction easements that would be required for Alternative 6
For Alternatives 4 and 5, the durations of 3.83 years and 3.67 years are very similar; however, Alternative 5 would
require an additional TCE across West Marginal Way, as that alternative would require six spans rather than three.
Alternatives 1 and 2 have similar TCE requirements: a TCE of one year for preliminary work, and then the same
TCE requirements for Alternative 4 or 5. However, Alternative 1 would not require the same demolition TCE for
Page 36
shoring for the full bridge replacement, as demolition could occur from gantry cranes and a barge. Alternative 6
would require the most TCEs for the longest duration – multiple TCEs over an estimated 5.5 years.
For this measurable, replacement, with the exception of Alternative 6, is the better option.
UTILITY INTERRUPTION
Utility interruptions for the on-bridge utilities include the control cables for the Spokane Street swing bridge; WSHB
navigation lights, power, drainage and fire protection; and fiber lines for various communication companies. The
main power transmission crosses the Duwamish north of the bridges, and should therefore not be impacted;
however, there are numerous overhead distribution lines on either end of the bridge that will likely be impacted (see
Figure 32). The CBA did not investigate underground utilities on the east and west sides of the bridge. We assumed
that early work would not impact utilities; however, the ultimate replacement of the bridge would.
The Alternative 5 bridge replacement (and thus Alternatives 1 and 2, which would require a first phase followed by
a full replacement) would have more impact on utilities due to the expanded limits of construction. Alternative 6
would necessitate major permanent and temporary impacts utilities. Overhead transmission lines crossing the
Duwamish, as well as distribution lines, would further complicate these impacts. Further evaluation is required to
identify all underground utilities, and construction methods should be analyzed for a true comparison.
Figure 32. All alternatives require some level of utility disruptions, during demolition, construction, or both
With interruptions to utilities for demolition and new bridge construction in an expanded footprint, Alternatives 1, 2,
5, and 6 are the most impactful, while Alternative 4, with interruptions for demolition and construction between
Piers 15 and 18, is less so. For this measurable, there is no clear winner between shore and replace (with the
exception of Alternative 6).
Page 37
ACCESS IMPACTS TO LOCAL PROPERTIES
This measurable evaluates impacts to property access during construction and then in final configuration. It should
be noted that access impacts would also affect bicycles and pedestrians. We based these impacts on the TCEs
assumed necessary for each alternative (see Figure 27 to Figure 31).
We assumed that the work zones for Alternative 2 would not extend into West Marginal Way or Klickitat Avenue,
with no additional restrictions. However, the TCEs for Alternative 1, which requires shoring between Piers 15 and
16 and Piers 17 and 18, could impose some restrictions to South Harbor Island along SW Manning.
Alternatives 4 and 5 both include shoring extending into Klickitat Avenue, with Alternative 5 including a bridge
replacement over Klickitat Avenue. While the south end of Harbor Island would still be accessible from the east side
of the island, the west entrance via SW Manning would likely be closed or restricted. Alternative 1, as well as
Alternatives 4 and 5, would likely require laydown space between Klickitat Avenue and 11th Avenue, impacting
some elements of the WSHB Trail at the south end of Harbor Island. Future studies will need to further evaluate the
trail connections. As it would keep current foundations, Alternative 4 would be less impactful to properties than
Alternative 5.
Building the portals for Alternative 6 on Harbor Island and near the west portal would create severe restrictions to
property access on both sides of the Duwamish River.
The results of this qualitative evaluation indicate that shoring or a bridge replacement is the preferred alternative for
minimizing access impacts to local properties.
ECONOMIC AND WORKFORCE IMPACTS ON REGIONAL INDUSTRY
WSP developed this measurable, especially relevant to maritime industry, in conjunction with the CTF and SDOT
after receiving feedback at the September 9 CTF meeting. The WSHB closure significantly impacts the movement
of traffic throughout the region. Evaluating the specific near- and long-term economic impacts on the Port of Seattle
and industry along the Duwamish River is crucial. We used a combination of quantitative and qualitative evaluation
to assess the impact on the local industrial and maritime economy.
WSP evaluated regional models to understand and quantify impacts on the freight traffic that supports operations at
the Port of Seattle and industry along the Duwamish River. The geography assessed for the metric included Harbor
Island, Industrial District West (Terminal 5), and businesses on both banks of Duwamish River, extending south, to
the First Avenue South drawbridge.
We established the geographic coverage based on the Puget Sound Regional Council’s (PSRC) 1K zonal system.
Medium and heavy truck trip activity to and from the area served as a proxy to establish maritime business
impacts. This included calculating the change in vehicle hours traveled (VHT) for medium and heavy trucks. Future
studies could assess individual quadrants in the selected geography, based on overall results of truck VHT.
To capture travel time-related delays, we can use the USDOT standardized values for value of time for passenger
vehicles and freight drivers cited in the WSHB Economic Impacts Memo.13
The Transportation Research Institute recommended a full marginal cost values, including the value of freight to be
closer to $66.70 per hour of travel time in 2017 dollars. Furthermore, adjustments for freight vehicle value of
reliability considers the incremental travel time built into delivery schedules to account for potential delay beyond
the modeled VHT impacts. Using the 95th percentile delay, the National Cooperative of Highway Research Program
Research Report 925 recommends $160 per shipment per hour or $9.40 per ton per hour.
Using the change in freight vehicle-hours traveled for each alternative and the value of time for freight truck drivers,
we estimated that the annual economic cost resulting from travel delays would be between $0.7 million and $1.2
million per year. Adding the impact of the overall shipment costs would bring the annual costs to close to $3.0 to
$4.0 million and with travel time reliability could potentially double the cost range, although further analysis would
13
Page 38
be required to verify specific economic cost values. These do not include the travel delay for non-freight vehicles
traveling through the project area.
The quantified economic impact of any change in freight traffic can be estimated using industry-level data from the
IMPLAN economic impact analysis software and the forecasted changes in VHT. For the analysis, the economic
output of industries operating on the Port of Seattle facilities in the Industrial District, Industrial District West and
Harbor Island areas, including wholesale retailers, water transportation services and manufacturing services, can be
proportionally attributed to the representative freight trips. The economic categories included are consistent with the
economic categories evaluated by the City of Seattle as part of the Industrial Lands Land Use and Employment
Study conducted in 2017. We measured the relative economic output attributed to the Port of Seattle and other
industrial and commercial facilities on a per-unit basis of VHT; a change in the values for freight trips would be
equivalent to a change in direct economic output by those businesses, which relates to the direct employment of
those operations.
The overall impact of the freight delays on the percent of annual industry employment in the study area is relatively
minor, at 1.8 percent in the worst-case scenario (Alternative 2). However, total economic output impacted by freight
delays would be the highest under Alternatives 1 and 6, largely due to construction timing and duration.
The IMPLAN software evaluates only the total economic output and employee compensation of the businesses
within the study area; therefore, it may not capture the total value of economic output if the businesses providing
those goods and services are located outside of the study area. Further qualitative considerations were made based
on the perceived risk on long-term employment of maritime businesses operating in the identified area.
Page 39
Figure 34. Map of Major Employers
We evaluated risk based on the closure duration and the perceived operational dependency on both the WSHB and
the Lower Bridge. Figure 34 indicates the location of major employers with the specific subareas that were
evaluated for changes in traffic patterns and increased VHT.
We determined that employers located in the yellow and green subareas were most at risk of long-term economic
impacts from prolonged construction closures; however, some of the employers are in the construction sector and
could potentially directly benefit from construction work. Employers on Harbor Island and the northeast and
northwest subareas were the least exposed to long-term economic impacts, as they would see only minor changes to
VHT based on the construction closures, and in some cases would benefit from lower VHT due to lower congestion
as passenger vehicles reroute to other arterials.
Scoring was based on a 50 percent qualitative and 50 percent quantitative weighting, with the former based on
impact to job losses as compared to the baseline Alternative 2, and the latter based on perceived risk, as measured by
the number of businesses severely impacted by the anticipated closure durations in each of the identified subareas.
Based on the results, Alternative 2 has the largest potential impact on jobs, as well as a medium risk of business
closures. Alternatives 4 and 5 show the least potential impact on employment and a low risk of closures, and
Alternatives 1 and 6 fell in between. In all of the alternatives, the southwest and southeast subareas were at the
highest risk.
Replacement, with the exception of Alternative 6, is the preferred option for this measurable.
14
A note on methodology: For purposes of modeling traffic impacts from the WHSB closure, WSP leveraged the PSRC model using regional
land use vision forecast (LUV.2), using the Puget Sound Gateway program with tolling, and the Sound Transit WSBLE service in 2032. WSP
was able to validate model results with the Port of Seattle-provided Dynamic Traffic Assignment (DTA) model output. The PSRC outputs are
Page 40
Subject matter experts from the TAP, SDOT, and WSP determined that the baseline, Alternative 2 (rehabilitation),
was the overall preferred alternative for this attribute.
Figure 35. Mobility Impact attribute’s measurable applied to all five alternatives
TRAVEL TIME
Vehicle Person Hours Traveled: We calculated vehicle PHTs by multiplying the passenger volumes by mode with
time spent traveling in the four-county PSRC region. This measure captures the effect of congestion/delay during
peak periods. We calculated PHTs assuming a 2+HOV15 occupancy factor of 2.4. We considered all auto modes in
the PSRC model: SOVs16, 2+HOVs, light trucks, medium trucks, and heavy trucks.
Transit Passenger Hours Traveled: We derived transit PHT by multiplying the transit passenger volumes on a
transit segment with transit travel times in the four-county PSRC region. This measure accounts for transit mode
shift and delays associated with the bridge closure. It includes both bus and rail passengers, as we expect that the
bridge closure would impact rail passenger volumes as much as buses.
Bike and Pedestrian Hours Traveled: These hours primarily increase as a result of a mode shift to active
transportation methods, including cyclists who have access to the lower bridge crossing, and increased pedestrian
traffic as more work and recreational trips are occurring close to home. Increased bike and pedestrian PHT can be
seen as a benefit.
The variance in travel time from the no-build base to the selected alternative base for the modeled years are
annualized and then interpolated between years to derive an annual forecast. We made further adjustments for
COVID-19 impacts on travel behavior and major capital projects that are anticipated to impact travel behavior
to/from West Seattle, such as Sound Transit’s West Seattle to Ballard Link Extension (WSBLE). Resulting annual
variances are applied only for the years when the bridge is closed for construction.
While Alternatives 1, 2, and 6 have increases of approximately 41 million hours, Alternatives 4 and 5 see increases
of approximately 30 million hours. For this measurable, replace (with the exception of Alternative 6) is the better
option.
TRAVEL DISTANCE
Vehicle Miles Traveled: We calculated VMT by multiplying the daily vehicle volumes of a road segment with its
mileage. It includes freeways, arterials, and local roads in the four-county PSRC region by the following auto
modes: SOVs, 2+ HOVs, light trucks, medium trucks, and heavy trucks.
Transit Vehicle Miles Traveled: Similar to auto VMT except calculated for transit vehicles. This calculation
includes only buses; for the purpose of this study, transit VMT does not include rail-car miles traveled. Again,
increased transit use is often considered a positive effect. WSP recommends that rail-car impacts and VMT be
explored in future studies.
approximately 16 percent higher than the DTA results for the primary Duwamish crossings. The higher volumes used in the analysis are largely
due to the DTA model’s timing, which was developed in 2014, prior to the higher than expected growth experienced in the past six years.
15
HOV=high-occupancy vehicle
16
SOV=single-occupancy vehicle
Page 41
Corridor Level VMTs: We estimated corridor-level VMTs for the identified detour routes. We then calculated
daily VMTs by multiplying the corridor length with daily auto volumes at a representative location. Some corridors
leading to the bridge will see a reduction in vehicular traffic due to the closure and could show a reduction in VMT.
Similar to travel time, the variance in travel distance from the no-build base to the selected alternative base for the
modeled years is annualized and then interpolated between years to derive an annual forecast. We made further
adjustments to account for COVID-19 impacts on travel behavior and major capital projects that are anticipated to
impact travel behavior to and from West Seattle – such as the completion of Sound Transit’s WSBLE (assumed to
be complete by 2032). We applied the resulting annual variances only for the years when the bridge would be
closed.
Alternative 1 increases travel distance by 564 million miles; Alternative 6 increases travel distance by 551.5 million
miles; Alternatives 4 and 5 increase travel distance by 399 million miles; and Alternative 2 increases travel distance
by 354 million miles. These results indicate that rehabilitation is the preferred alternative for the travel distance
measurable.
NON-VEHICLE TRIPS
One of the more noticeable impacts from the combination of the WSHB closure and COVID-19 was the shift in
transportation modes from driving to walking and biking. There is a quantified and monetized approach for
calculating the health benefits from more active forms of transportation. For the purposes of this study, we used the
non-vehicle trips calculated in the PSRC model as the basis for the non-vehicle adjustment factor and scoring.
Alterative 1 increases non-vehicle trips increase by 60.9 million trips. Alternative 6 sees non-vehicle trips increase
by 58.3 million trips. Alternative 2 is slightly lower at 45.7 million, and Alternatives 4 and 5 are 44.1 million more
trips.
This is a multifaceted measurable. On the one hand, increased non-vehicle trips are better for the environment from
an emissions standpoint and better for humans from a health standpoint. However, an increase in non-vehicle trips
also indicates that mobility via vehicle has been reduced.
Because of the complexity of the measurable, as well as the similarity in results for Alternatives 2, 4, and 5, this
measurable has no clear “winner” as pertains to the rehabilitate versus replace decision.
REGIONAL MOBILITY IMPACTS
The Regional Mobility Impacts measurement evaluated how the timing of the WSHB closure could impact other
regional projects due to more surface street traffic. For example, the CBA assumes that SDOT’s East Marginal Way
project will be in construction between 2021-2023, and that Sound Transit’s WSBLE would be in construction
between 2027-2032.17 If the bridge is closed during work on these projects, the surface streets on either side of the
Spokane Street lower ridge will likely see heavier-than-usual traffic.
Comparing the preliminary construction schedules for each alternative with the assumed construction periods for
both the East Marginal Way and WSBLE shows that the WSHB would be closed during the East Marginal Way
construction for Alternatives 1, 4, and 5. For Alternative 2, the bridge would be closed for only half of the East
Marginal Way construction, which is more desirable.
For Alternatives 1 and 6, the WHSB would be closed for half of the construction for the WSBLE construction.
Alternatives 2, 4, and 5 would be open during construction on that project, lessening the traffic impacts on nearby
surface streets. Based on these assumed schedules, Alternative 2 would have less impact on construction of these
other regional projects.
Rehabilitation is the preferred alternative for this measurable, as it would allow the WHSB to be open for half of
East Marginal Way construction and all of WSBLE construction. Shoring and a tunnel replacement would be the
most impactful, while bridge replacement would be in the middle.
17
SDOT’s E Marginal Way project and Sound Transit’s WSBLE project are not yet fully funded or in construction. WSP has
assumed that they will be under construction during these years, but neither the projects nor the dates/durations are definitive as of
October 2020. WSP recommends that future studies address this once more detail is known about these projects.
Page 42
SAFETY
Subject matter experts evaluated safety by reviewing the existing collisions and five years of history along the City-
identified diversion routes on the West Seattle side of the Duwamish River. We then applied the increase in VMT to
identify the potential for additional crashes versus the crashes expected if the West Seattle bridge were open.
Safety was estimated as 541 more crashes with Alternative 6, 553 more crashes in Alternative 1, 347 in Alterative 2,
and 391 more crashes in Alternatives 4 and 5. As such, both rehabilitation and replacement are safer than shoring,
but rehabilitation is slightly safer than the bridge replacement options. Replacement Alternative 6 is less safe than
shoring.
Figure 36. Multimodal Impacts attribute’s measurable applied to all five alternatives
Page 43
PEDESTRIAN TRAFFIC ACCOMMODATION
We evaluated potential impacts to pedestrian access as a result of construction along West Marginal Way and
Klickitat Avenue under the Access Impacts to Local Properties measurement. See Section 4.2.7 Business and
Workforce Impacts. For the purposes of the Multimodal Impacts attribute, all alternatives scored “Low,” with no
clear preferred alternative.
EMERGENCY ACCESS
Information provided by SDOT for 2019 indicates that there were 2,097 emergency calls that could have used the
WSHB (749 from Battalion 7, 54 from Ladder 11, and 1,294 from other calls). While we were not able to evaluate
the exact route for each call, we did review the travel distance and assumed travel times between Fire Station 14
(near the intersection of Fourth Avenue South and South Horton Street) and the intersection of the WSHB and 35th
Avenue SW. While not all emergency trips would have used these routes, we considered it to be a reasonable
comparison route to assess the effects of the WSHB closure on emergency access and response.
Based on the distances, speed limits, and assumed delays at signalized intersections, rail crossings, and the Spokane
Street lower bridge’s openings, it is estimated that an average trip using the WSHB would have taken 6.25 minutes,
while an average trip using the Spokane Street lower bridge in combination with local streets would have taken
approximately 15 minutes. See Figure 39 for the assumed routes.
We ranked each alternative based on closure durations and the cumulative increase in emergency vehicle response
time during the closure.18 With the longest closure period, Alternative 6 had the lowest score, with a 46-hour
increase in emergency response time. Alternative 1 had a 38-hour increase, while Alternatives 2, 4, and 5 each had a
cumulative 27 hours’ increase in emergency response time. Rehabilitation and replacement (with the exception of
the tunnel replacement) have similar increases in emergency response time and are preferred to shoring, which has
the poorest results.
18
The potential for an increase of emergency calls in the future was not considered in this study. WSP recommends that this be
further explored in future studies.
Page 44
Figure 37. Assumed route for emergency vehicles prior to the West Seattle High-Rise Bridge closure
FREIGHT MOBILITY
We measured freight mobility as increases in travel time for medium and heavy trucks as a result of the bridge
closure. As described in Section 3.2.8 Mobility Impacts, the increase in freight travel time is the result of PSRC-
modeled results with and without the closure of the WSHB, using detours as provided by SDOT, include the
Spokane Street Low Bridge.
The resulting freight adjustment factor, measured in hours, shows an increase of 422,000 hours for Alternative 1,
397,000 for Alternative 6, 360,000 hours for Alternative 2, and 295,000 hours for Alternatives 4 and 5. Replacement
(except for the tunnel) is clearly the preferred option for freight mobility.
3.2.10 SEISMIC/SAFETY
This attribute evaluates anticipated post-earthquake service and damage levels relative to the design seismic event,
including consideration of implementation. It seeks to ask the questions: What design seismic hazard level will the
rehabilitation and replacement alternatives be analyzed for? For the design seismic hazard, what performance level
(operational classification) is desired? When will the corridor meet the specified seismic design criteria? The
measurements here serve to answer these questions as pertains to the assumptions made for the CBA; however,
future phases of work should determine the actual seismic design criteria.
Subject matter experts from the TAP, SDOT, and WSP scored the replacement alternatives as preferred for this
attribute, with Alternative 5 (full replacement) receiving an 8.78 overall score.
Page 45
Figure 38. Seismic/Safety attribute’s measurables applied to all five alternatives
For the replacement alternatives, it is assumed that the City will elect to classify the bridge as “essential,” which
would allow for the full operation of the bridge directly after a 210-year design earthquake, and limited service
(service restored within three months) after a 975-year design earthquake.
From an operational classification perspective, the replacement alternatives would be required to perform better than
either shoring or rehabilitation alternatives.
VERTICAL EXCITATIONS CONSIDERED
The CBA assumed that the project-specific seismic design criteria would include vertical excitations for the design
of a replacement structure. To comply with the assessment approach, and allow for direct comparison of other
bridges within the City’s inventory, we did not include vertical excitations in the assessment of the rehabilitation
alternative.
Subject matter experts scored alternatives that considered vertical excitations higher than those that did not consider
vertical excitations. As such, either shoring or replacement are preferred over rehabilitation for this alternative.20
SEISMIC COMPLIANCE ESTABLISHED
All the alternatives have specified design criteria. This measurable defines when the specified design criteria are
assumed to be met based on when the improvements will have been incorporated into the constructed corridor. We
assigned higher value to those alternatives that can meet their specified criteria sooner.
The replacement alternatives are preferred to the rehabilitation or shoring concepts for seismic compliance.
19 Although the rehabilitation alternative is classified as “normal,” the CBA assessment of the existing bridge indicates that it would
meet the essential bridge performance criteria that a replacement bridge would offer once the superstructure is rehabilitated.
20 The CBA assessed the existing bridge for vertical excitations. Alternative 4 would address any identified superstructure
deficiencies. With this consideration, all alternatives would be considered equal for this measurable.
Page 46
3.3 SUMMARY OF ATTRIBUTE FINDINGS
Three schemes – shoring, rehabilitation, and replacement – encompassing five alternatives – shoring, rehabilitation,
superstructure replacement, bridge replacement, and an off-alignment tunnel – were scored from a performance
perspective across ten attributes and more than four dozen measurables.
Alternative 1, the shoring concept, performed poorly overall, as did Alternative 6, the immersed tube tunnel concept.
Alternatives 2, 4, and 5 performed similarly, but Alternative 4 (superstructure replacement) was the overall best
performer. Alternatives 1 and 2 performed particularly poorly from a Seismic/Safety perspective; however, upon
completion of the CBA, WSP determined that the existing bridge performs quite well from a seismic/safety
perspective (see sensitivity study in Section 6.2).
The results from the performance phase of the CBA indicate that, while rehabilitation and bridge replacement are
both viable options, bridge replacement alternatives offer slightly better performance (with the exception of a tunnel
replacement). Subject matters assigned a value of 1, 3, 5, 7, or 9 to each alternative for each attribute relative to the
baseline (Alternative 2, with a score of 5). Scores are thus shown on a scale of 1-9, with 9 being most preferred, and
1 being least preferred (Figure 39). The fact that decimal values are reported is the result of averaging scores
between the City, WSP, and the TAP.
Figure 39. Attribute Performance: Subject matter experts from the TAP, SDOT, and WSP rated each
alternative for each attribute. These scores were then averaged across entities to show overall attribute
performance.
However, as previously mentioned, performance is just an input to the overall findings, which look at the value of
the return on investment. To do this, cost and risk input is required, which is outlined in Sections 4 and 5. Section 6
presents the overall findings.
As discussed in Section 3.1, once we identified performance attributes, the next step was to weight each individual
attribute against the other attributes. SDOT, the TAP, and the CTF jointly determined this weighting by ranking
attributes relative to one another. Mobility Impacts, Seismic/Safety, and Constructability were the most highly rated
and thus the most heavily weighted (Figure 40).
Page 47
Figure 40. SDOT, the TAP, and the CTF’s averaged rankings determined attribute weighting.
Figure 41. The CBA multiplied attribute weights by attribute performance scores to determine the overall
performance score.
Once we calculated attribute weight and attribute performance averages, we were able to determine performance
scores by multiplying the two (Figure 41).
Page 48
Table 4 shows the overall combined performance scores, which the CBA then used to ultimately determine value
indices for life cycle costs and capital costs (see Section 6).
The TAP independently scored the alternatives independent of a baseline alternative using a 1 to 10 scoring system
for each attribute for each alternative. Figure 42 shows the resulting absolute performance scores, as well as a scaled
version of the absolute scores. Scaling set the score for Alternative 2 to 500 so that the findings could be compared
to the CBA’s process, which used Alternative 2 as the baseline. The TAP’s independent scoring system resulted in a
larger magnitude of difference in scores between the rehabilitation and replacement alternatives; however, the trend
relative to their scoring stayed the same. In the CBA process, the TAP favored Alternative 2 from a performance
standpoint, with Alternative 1 scoring the lowest. The TAP’s independent scoring exercise favored Alternative 2,
but Alternative 6 scored the lowest.
21This table does not show results for Alternative 6 because the TAP performed their alternative scoring exercise before it had
been fully developed.
Page 49
ROUGH-ORDER-OF-MAGNITUDE
CONCEPTUAL COSTS
WSP developed rough order of magnitude (ROM) cost estimates for capital project costs and life cycle costs. The
costs presented within Section 4 of this report represent “base” ROM costs, which are based on a series of
assumptions informed by SDOT. We show them to illustrate how costs are incorporated into the CBA evaluation
process. The actual findings of the CBA evaluation process are represented by value indices, or the measure of
performance over cost. Value indices measure return on investment. Capital ROM cost estimates inform short-term
investments, and life cycle costs inform long-term investments. Section 6 outlines the CBA findings, explains how
we developed the value indices, and presents the ranges in potential costs based on an evaluation of the sensitivity of
key assumptions.
As stated, the reported capital ROM cost estimates represent project costs for the given work activities. Each
alternative comprises multiple work activities occurring in time. For example, Alternative 2 initially includes the
rehabilitation work in 2021-2022. It then assumes a foundation retrofit in 2032, the existing bridge’s demolition in
2063, and a full replacement in 2063-2066. Capital costs account for only a given alternative’s initial work
activities. These activities take place in the bolded years in Figure 43.
We determined actual alternative ROM costs for all work activities, reported in present value, through a life cycle
cost analysis, as described in Section 4.2. Alternatives 1 and 2 assumed a bridge replacement (i.e. Alternative 5)
would ultimately be required.
Page 51
As previously noted, each alternative comprises multiple work activities, and so the aggregate contingency within an
alternative is some combination of the work activity contingencies shown in Table 5. The effects of the aggregate
contingency is illustrated in Section 6.2, which provides a discussion on the sensitivity in the reported life-cycle
value index based on assumed cost contingencies.
Right-of-Way (Temporary Construction Easements and Property Acquisition)
Right-of-way costs considered potential temporary easement needs, aerial easements, and permanent acquisitions.
They were based on values of the assumed affected parcels’ values. The easement and acquisition needs are not yet
known, but some were assumed to provide an allowance in the ROM capital cost estimates. WSP developed figures
of anticipated impacted parcels and the duration of impacts and provided them to SDOT. SDOT provided an
estimated value of the impacts.
Monetization of Risk
The ROM cost ranges did not use WSDOT’s Cost Estimate Validation Process for formal risk modeling. Future
phases of the project may consider more robust analytical tools for assessing and monetizing risk. However, we
developed a risk registry and identified a series of risks to monetize and include in the ROM capital cost estimate.
Section 5 provides further details related to the CBA’s risk assessment.
The noted cost escalation items included are intended to recognize the preliminary nature of the CBA and capture
the potential impacts associated with project complexities; this is just an allowance and not necessarily an accurate
reflection of actual costs. Estimating the magnitude of the actual costs associated with the project and its
complexities would be difficult to estimate without conducting the next steps identified in the CBA report and
conducting a formal risk analysis. For the purpose of the CBA, Table 6 shows the resulting capital cost ROM
estimates, which we then used to inform the capital cost value indices reported in Section 6.
*$171M of the $175.5M of Alternative 2’s monetized risks is associated with the risk of a reduced service life. See Section 6.2 for
details.
** Right-of-Way costs for Alternative 6 are not included
Page 52
Determining the discount rate significantly impacts the reported life cycle costs. Low discount rates favor larger
current investments (such as a replacement), and high discount rates favor larger future investments (such as
rehabilitate now and replace later). National standards for net discount rates on bridge structures are between 2 and 4
percent. Through consultation with SDOT, the CBA uses a net discount rate of 0 percent; in other words, the rate we
used assumes that the value of a dollar in the future is the same as the value of a dollar today. Recognizing the
uncertainty in the actual net discount rate, Section 6.2 of this report illustrates the effects that potential changes in
the discount rate would have on the resulting value indices.
The LCCA estimated overall costs for each alternative between 2021 and 2100. The end of the life cycle cost
assessment (i.e., 2100) is the same as the end of the 75-year service life for Alternative 4, which we expect to come
into service around 2026. The LCCA was informed by four different types of costs: capital costs of various work
activities; inspection, operating, and maintenance (O&M) costs; future repair and rehabilitation (R&R) costs, which
include the cost of a future replacement for Alternatives 1 and 2; and salvage costs.
Capital Costs
Section 4.1 describes capital costs for the various work activities. We specified a duration for each capital cost work
activity, as well as the actual years of work. When applied to the LCCA, the total capital cost was equally distributed
over the duration of construction. Thus, with the time effect of money (i.e., discounting), the recognized capital costs
may be different if other discount rates are used.
Inspection, Operating, and Maintenance Costs
Table 7 illustrates the assumed annualized inspection, operating and maintenance costs utilized in the LCCA.
Table 7 reflects the SDOT-provided ideal (not actual) annual maintenance and inspection costs for the current
WSHB, totaling approximately $500k. We divided this amount between the maintenance and inspection for each
alternative, with $350k going towards routine maintenance and $150k towards inspection on an annual basis. This
was applied to Alternatives 1 and 2 (before the assumed replacement with Alternative 5) and assumed that the
existing structural health monitoring system would remain operational while the bridge was in service. After the
replacement structure is constructed, the maintenance and inspection costs would be reduced.22 The operating and
maintenance costs are less for the replacement structures relative to the existing structure because they are new;
however, the CBA assumed that an asset management system would be included in the design and would require
annual operation and maintenance expenditures. In addition, Alternative 1 assumes that SDOT would install an
intelligent transportation system during the shoring period.
We assumed that the new structures, in-kind replacement (Alternative 1, 2, and 5) and full-superstructure
replacement (Alternative 4), would require inspections less frequently (every two years) than currently required for
the existing bridge (annually). However, this is offset to some degree with more expensive inspection costs for a
cable stayed bridge than a concrete box girder bridge. The drainage costs for all alternatives increased with the
assumption that the current bridge’s drainage requirements would increase, as there may be more drains to maintain.
SDOT provided drainage values.
22 Based on the structures types assumed for the replacement structures within the CBA. Some replacement structures, such as
fracture critical and seismically isolated structures, would require more frequent and enhanced inspection efforts.
Page 53
The CBA assumed that Alternative 6 would require annual O&M costs at $250k per lane mile. This estimate was
informed by databases developed for the SR 99 Alaskan Way Tunnel, I-90 Mt. Baker Tunnel, and the Mercer Island
Lid. We chose these projects because they are local and provide recent knowledge of fire, life, and safety features in
a representative scale. Outside of the tunnel’s fire life safety systems O&M, we assumed an O&M cost of $250k per
year.
Future Repair and Rehabilitation Costs
The LCCA incorporated a series of future repair and rehabilitation costs. We assumed that the cable-stayed
alternatives (i.e., Alternative 5 and eventually Alternatives 1 and 2) would have to be painted every 25 years to
protect the steel cables. Alternative 2 also assumed that the CFRP strips would receive a UV protection coating
every 10 years until the bridge was replaced.
The bridge replacement alternatives (i.e., Alternatives 4 and 5) assumed a lump sum repair/rehabilitation value of
$50 million for bridge strengthening in the year 2076 (i.e., after 50 years of service). We applied contingencies and
allowances as noted in Table 5. We then inflated the costs to 2076 dollars and discounted back to present value.
For Alternative 6, the R&R costs were taken as 8.47 percent of the total construction costs annualized. This number
was based on recent estimates for the SR 99 Alaskan Way Tunnel construction costs, including lid elements such as
ventilation, fire suppression, and other tunnel-related items.
Salvage Costs
The salvage costs represent a fraction of the initial capital costs based on the remaining years of service at the end of
the life cycle cost assessment, brought back to present value. The end of the life cycle cost assessment was taken as
the end of the service life for Alternative 4 (i.e., 2100), so Alternative 4 shows zero salvage value. However, all
other alternatives had remaining service life to varying levels in 2100:
• Alternative 1 – 8 years
• Alternative 2 – 41 years
• Alternative 5 – 1 year
• Alternative 6 – 5 years
Table 8 below summarizes the estimated base total ownership costs for each of the five alternatives (assuming a net
discount rate of zero percent). Again, the base total ownership costs shown in
Table 8 illustrate how life-cycle cost value indices are reported (see Section 6.1), whereas the potential ranges in
life-cycle costs are illustrated in Figure 46 and discussed in the summary of findings (Sections 6.2 and 6.3).
Table 8. Base Project ROM Life Cycle Costs (0% Net Discount Rate) Summary
Page 54
NOTES:
The X’s in the figure represent the base LCCA costs identified in Table 8. The blue bars illustrate the range in potential life
cycle costs based on the sensitivity studies defined in Section 6.
Page 55
RISK ASSESSMENT
There is inherent risk in all design and construction work. Risks could result in scope, schedule, and/or budget
impacts or change. It is important to try to identify the risks associated with rehabilitation and replacement
alternatives to avoid surprises and ensure adequate plans are in place should a risk arise. As part of the CBA, WSP,
in conjunction with SDOT, the TAP, and the CTF, created a risk registry for the WSHB project (see Appendix D).
The risk registry is a living document that should be managed throughout the life of the project. To date, the risk
registry has been informed by various subject matter experts within WSP, SDOT, and the TAP. This consultation
has included risk registry presentations in multiple TAP meetings and workshops, and a formal review by the TAP
and SDOT. The risk registry has also been presented to the CTF for their review and input. As a result, it is based on
a comprehensive contribution from experts and non-experts alike, with the objective of capturing intrinsic, technical
risks, as well as extrinsic risks situated within the broader context of this project.
Risks are never removed from the registry; however, they may be closed out if a management strategy or solution
has been identified. The risk registry is structured as follows:
— Identification: identifying the possible risks that may have significant impacts on the project.
— Qualitative Analysis: determining a risk factor rating based on a qualitative assessment of the probability of
the identified risk occurring, and the associated impact of the identified risk. The assessment assigns ratings of
very high, high, medium, low, or very low, and answers the following questions:
— Probability: What is the likelihood of the identified risk occurring?
— Impact: What level of impact would the identified risk have on the project if it occurred?
The relationship between the answers to the above questions, as it relates to determining a risk factor rating, is
shown in Table 9 below.
Table 9. Risk Rating Factor
VL L M H VH
IMPACT
— Strategy: developing a strategy, or strategies, for managing the identified risk items. Items could involve
primary and secondary plans, and could be dependent upon the level of severity. The team discusses and agrees
upon strategies. Risk strategy categories include avoiding, transferring, mitigating, and accepting, as defined
below:
— Avoid: changes the project plan to eliminate the risk. This would be done by adjusting the scope, schedule,
and/or budget.
— Transfer: shifts, but does not eliminate, the risk and responsibility to a specialized third party.
— Mitigate: reduces the probability and/or effect of the risk to an acceptable level.
— Accept: accepts a “do nothing strategy” until/if the risk occurs, at which point it would be dealt with.
Contingencies are considered within this strategy.
The register identifies a planned response, or action, to address each risk. Planned responses may change
throughout the life of the project as more details become available and the design progresses.
Page 56
— Monitor: developing a plan to monitor and control the risk. Monitoring and controlling risk continues through
the life of the project. As the design progresses, details become more evident. This allows the team to reassess
and monitor the planned responses, add/re-analyze/edit the identified risks, and evaluate the registry. The
registry identifies actions taken to-date, planned actions and when the actions are anticipated to occur, and who
is responsible for the actions.
— Monetization: identifying risks as monetized or not. Monetized risks are assigned a dollar value. Non-
monetized risks may be schedule-related and intended to be mitigated as the design progresses; stakeholder
coordination-related intended to be mitigated through a detailed coordination plan; etc. Some risks that could be
monetized may not be monetized, because they are indirect costs to the project, or covered by assumptions
made in the cost estimating for the project. These are noted in the risk registry. Where risks are monetized, the
approach to monetizing the risk is included in the registry. All monetized risk values include an absolute cost
calculation, and then a factored value, which is the product of the risk factor rating and the absolute cost
calculation.
The CBA’s risk registry includes more than 40 items, eight of which have been monetized (Table 10). This list will
likely grow in future project phases, once a rehabilitation or replacement decision is made and there is a clear path
forward. The list of monetized risk items is tabularized below, along with the alternatives to which those risks apply
– from both an initial capital investment perspective and a life cycle cost perspective.
Applicable Alternatives…
Probability of
Risk Item
Occurring
1 2 4 5 6
Page 57
of components. This relates to subduction
zones, near-fault effects, basin effects, etc.
Note: The risk registry includes other items that could have been monetized, however, those were either considered captured
by allowances made in the cost estimates or considered beyond the scope of the CBA. We recommend that future phases
further investigate construction- and design-specific risks. For details, see Appendix D.
The primary, and most critical, risk associated with further rehabilitation of the existing bridge (Alternative 2) is that
it doesn’t perform as intended, requiring another bridge closure after being put back into service (see Rehabilitated
Service Life risk above). This risk could materialize because:
• “We got the wrong answer” – We know that soffit tensile stresses were imparted on the soffit of the bridge at
the locations where bottom slab tendons terminate within the spans. We think we understand how the tensile
stresses could have been generated; however, we don’t know every load the bridge has seen nor the exact stress
distribution within the structure. This could emerge once the repairs are constructed and the bridge put back in
service.
• Incomplete Rehabilitation Design – To date, we have conducted preliminary rehabilitation concept (Alternative
2) analyses and design to support the CBA evaluation; however, there is a risk that we may find something
wrong in the preliminary engineering during the final design process that could preclude the feasibility of
rehabilitation.
• Remaining Stabilization Work – There remains a risk that, once stabilization measures are complete in a few
months, the bridge does not behave as expected, indicating that there is a systemic issue with the bridge that
neither monitoring nor non-destructive testing have identified to date.
Page 58
The existing bridge service life risk was monetized, as noted in Table 10 above, through the CBA process. We used
a risk factor of 25 percent; however, based on the work done to-date and the correlation of analytical modeling to
measured behavior, the technical risk of the bridge not behaving as intended, thus limiting the service life of the
rehabilitation, likely has a very low probability (less than 5 percent) of occurrence. This probability assumes that the
bridge continues to exhibit the same trend as the stabilization measures are completed in the coming weeks.
The risk registry identifies more risk items - monetized and not monetized - associated with the replacement
alternatives than with the rehabilitation alternative. The list of monetized risk items associated with the replacement
are noted in Table 10 above. There are also a handful of other risk items that we could have monetized; however, we
wanted to avoid double-counting costs already monetized by the selected list (i.e., formal seismic analysis
identifying additional seismic deficiencies within the existing bridge foundations was not monetized for Alternative
4). Some of the biggest non-monetized risks associated with the replacement (or more heavily applicable to)
alternative are related to schedule: Specific schedule risk items include:
• Inability to get regulatory approvals – the demolition and construction of the bridge will require construction
in, and if not in, on and around the wetted perimeter of the ordinary high water. Considerations will include
barge work within the river impacting fishing, containment requirements, noise, dust, in-water work (if
required), relocation of avian habitat, etc. This will require close coordination with the agencies to avoid delays
to the project schedule.
• Stakeholder coordination issues - the bridge exists within a built environment. There are many businesses and
facilities that operate in and around the project site, including the Port of Seattle, Harbor Island, and BNSF, or
those with plans to extend their services through the project site (i.e., Sound Transit). The Port of Seattle has
plans to expand their Terminal 5 services, with a loss in revenue if not operational by 2024. It will be important
that the project is coordinated with the project stakeholders to avoid delivery delays of a replacement bridge,
and to maximize opportunities, such as collaboration with Sound Transit on a multimodal crossing.
• Inability to secure adequate funding for a replacement structure - the capital investment of a replacement
structure is significantly more than that of rehabilitation. The City will likely have to borrow funds to fund a
replacement structure. Problems with securing these funds could delay the design and construction of a
replacement.
• Potential public and community scrutiny and associated impacts - as stated, the CBA does not quantify the
costs of socioeconomic impacts. The closure duration has a significant impact on the community and businesses
within West Seattle and the surrounding area. The CBA has shown that minimizing the duration of immediate
closures is far more important than future closures based on the assumption of light rail availability after 2032.
This gets exacerbated when considering opportunity costs with time. WSP recommends that this be explored in-
depth in future studies.
• Unknown design criteria – SDOT needs to specify the bridge seismic design criteria; if they classify the
bridge as “essential” or “critical,” as SDOT has stated as likely (reference the “high” probability of occurrence
in the “bridge seismic importance classification” risk item in Table 7). This takes time, and careful thought
should be given towards current changes within industry, both geotechnically and structurally. It is important
that any investment needs to meet newly adopted, and potentially soon to be adopted, design procedures.
• Approach structures - a limitation of the CBA is that it does not assess the approach structures. This is needed
to understand potential corridor deficiencies and would be advantageous to understand ahead of conducting the
design of a high-rise replacement structure (i.e. avoid designing-in an unintended constraint). A better
understanding of corridor needs will also help in making investment decisions. There is limited space, and, with
Sound Transit’s future expansion plans, a need to better understand the corridor needs. This would help
determine if investing a joint structure makes sense. Future studies and joint discussions between the City and
SDOT should further explore these opportunities and invest in further investigations into approach structures.
• When to demolish the existing bridge – due to the potential schedule risks identified above, it may be
advantageous to wait to demolish the existing bridge until the replacement bridge design is more fully
developed, and potential schedule risks are better defined. If the replacement design does not progress as
intended, the existing bridge could be rehabilitated to restore service to the corridor. However, the existing
bridge would need to be monitored until this decision was made. The CBA does not capture these costs.
Figure 46 illustrates the cumulative monetized risk accounted for within the CBA for each alternative. Monetized
risk values include the contingencies and allowances that we applied to the ROM capital construction cost estimates.
The red bolded bars indicate the monetized risk values incorporated into the initial capital investment ROM cost
Page 59
estimate, and the gray bolded bars represent the cumulative monetized risk recognized in the LCCA. The bolded
portion of the bars represents the factored monetized risk, whereas the lighter colored portion of the bars represent
the total, or absolute, monetized risk value. The difference is the application of the risk factor rating and indicates
the potential range in risk.
• The Factored values represent monetized risk values that were incorporated into the project costs. The factor is
based on the product of the probability of occurrence and impact should the risk occur; reference Table 9. The
lighter shaded portion of each column represents the recognized monetized risk without the risk factor (shown for
reference; not applied to the project costs).
• The risk values labeled as Initial Capital (red bars) are only associated with capital investments (bolded items within
Figure 43), and not future work activities within an alternative. Risks associated with future work activities (including
risks not associated with future implementation of another alternative) are captured in the Life Cycle (gray bars). If
Initial Capital (red bars) and Life Cycle (gray bars) show the same value, then we have not included any risks
associated with future work activities as part of the currently monetized risk values.
• Alternative 1 Risks – Life cycle risks incorporate Alternative 5 risks, as Alternative 1 will be replaced in 2029, 71
years before 2100.
• Alternative 2 Risks – Initial capital investment risk is primarily associated with the limited service life of the
rehabilitation. Although this has a very low (less than 5 percent) probability of occurrence, the CBA did recognize a
25 percent risk factor due to the major impacts should the risk occur. Life cycle risks incorporate Alternative 5 risks,
as Alternative 2 will be replaced in 2063, 37 years before 2100.
• Alternative 4 Risks – Initial capital investment risk is primarily associated with foundation cost uncertainty and
potential USCG height clearance requirements. Reported monetized risks for this alternative do not include FAA
structure height limitations, potential schedule lag, or closure-related socioeconomic impacts.
• Alternative 5 Risks – Initial capital investment risk is primarily associated with foundation cost uncertainty, potential
USCG height clearance requirements, and FAA structure height limitations. Potential schedule lag and socio-
economic impacts have not been included in the reported monetized risks. Reported monetized risks for this
alternative do not include potential schedule lag or closure-related socioeconomic impacts.
• Alternative 6 Risks – Initial capital investment risk is primarily associated with a lack of existing casting yards able to
construct the tunnel segments. The base estimate uses allowances to address other risks such as contaminated
soils, dredging depths, etc.
Page 60
FINDINGS
6.1 RESULT METHODOLOGY
The CBA evaluation process entailed a phased approach. During the first phase, we selected the attributes and then
weighted the attributes relative to each other. This was done in conjunction with SDOT, the TAP, and the CTF23.
The second phase determined performance scores for each alternative, for each attribute, and added the per-attribute
performance scores together to get an overall performance score for an alternative. This was done in conjunction
with subject matter experts from WSP, SDOT, and the TAP. Section 3 examines the first two phases in more detail.
The third phase, addressed in this section, delivered the CBA findings, presented as value indices. We developed
these value indices by dividing the performance scores by first, the capital costs of the alternatives, and then by the
life cycle costs. The capital cost value index yielded the initial return on investment of a given alternative, and the
life cycle cost value index yielded the long-term return on investment. This is shown pictorially in Figure 47 below.
The initial “base” value indices are based solely on the assumptions made within the CBA (Section 1.3), and are
shown in Figure 49. Findings are shown as entity-specific (i.e., for the City, TAP, and WSP, individually), and then
combined (an average for all entities).
23 Reference TAP CBA Part 1 Recommendation memorandum and City/WSP response memorandum for background discussions.
Page 61
Figure 48. Resulting Value Indices (0% Net Discount Rate)
Interpretation of the base value indices requires an understanding of the sensitivity of key assumptions made within
the CBA, and an understanding of the limitations of the CBA, which are discussed in Sections 6.2 and 6.3 below.
Page 62
NOTES:
• Higher value indices represent better returns on investment.
• X’s – “base value” indices based solely on assumptions within the CBA.
• Blue Bars – potential range in value indices based on the sensitivity study findings (Studies 1 to 3 – taken as the base
value index for an alternative multiplied by the product of the ratio of each study value index-to-the base value index).
Alternative 2 has the highest potential for increased value indices.
• Black Line – relative trend in potential additional value index increase if contingency and risk were removed from the
assessment. Alternative 2 has the highest potential for increase.
Page 63
Figure 50. Life-Cycle Value Change (3 percent versus 0 percent Net Discount Rate) – Sensitivity Study
24 WSP originally selected a lower-bound service life of 15 years for the sensitivity study based on initial unknown seismic bridge
deficiencies (i.e. lowest end of anticipated service life defined by the Federal Highway Administration Seismic Retrofitting Manual).
Based on findings from the CBA seismic assessment, the existing bridge behaves well seismically, and the risk the bridge does not
serve its remaining service life based on inadequate seismic performance, is low, once the Phase II rehabilitation is conducted.
Page 64
deformation, so that the bridge could be returned to service within a defined timeframe after the earthquake, likely
two to three months. As a result of this difference in seismic performance requirements, the replacement alternatives
scored higher relative to the rehabilitation alternative.
The CBA classified Alternative 2 as “normal” for consistency with standards used to evaluate all other bridges
within the City’s bridge inventory. However, after a preliminary seismic evaluation of the existing WSHB structure,
we have concluded that the structure appears to be very well detailed and can accommodate deformations beyond
both the “normal” and “essential” classification limits. Thus, since the existing bridge technically meets the
“essential” criteria, it could have been classified as “essential,” achieving the same required performance level as the
replacement alternatives. As a result, the relative performance score of the rehabilitation alternative to the
replacement alternatives would be less. FIGURE 52 illustrates the difference if the CBA scored the replacement
alternatives as “7” versus “9” for the seismic/safety attribute, as was reported for the “base” performance scores.
Since Alternative 2 represents the baseline alternative, its performance score did not change as part of the study.
Instead, the other alternative scores decreased relative to Alternative 2. Looking at Alternative 4, the highest
performing alternative, its performance score reduced by approximately 7 percent as compared to the values
reported in the base CBA performance scores. This trend in adjustments to the performance scores and resulting
value indices favors Alternative 2 when compared to those developed around the base set of assumptions.
Developing cost information during preliminary design stages is difficult. In consultation with the City, WSP
applied allowances to ROM cost estimates to address incomplete designs, unknown project issues, incomplete
coordination with project stakeholders, etc. Developing cost information for multiple alternatives at different stages
of design adds another layer of complexity to an already complicated analysis. For example, we advanced
Alternative 2’s design to a level beyond the design for the other alternatives, because of its technical similarities to
current stabilization work (which WSP designed).
Figure 53 below illustrates the trend shift in LCCA value indices when we removed cost contingencies. Alternative
4 shows the best long-term return on investment, with the best life cycle cost performance. Alternative 1 shows the
best short-term return investment.
Page 65
SENSITIVITY STUDY 5: RISK MONETIZATION IMPACTS
The CBA attempted to monetize risks that would directly impact project costs and that could be approximated
within the CBA’s accelerated timeframe. We avoided double-counting monetized risk (i.e., monetizing multiple risk
items that would add cost for the same bridge component). We did not monetize risks such as socioeconomic
impacts, which are associated with the project but have an indirect impact. WSP recommends that this be
investigated in future studies. The magnitude of the captured monetized risk items is relatively high, and cost
percentages differ for each alternative.
Figure 54 below illustrates the trend shift in the LCCA value indices, per alternative, if the monetized risk were
removed from the CBA. Alternative 2 shows the best short- and long-term return on investment, scoring higher than
any other alternatives for the capital value index and the LCCA value index.
Figure 55. Potential Durations Based on Accelerated Construction (Minimized Corridor Closures)
Although using an accelerated schedule resulted in no net change in the reported CBA findings, the CBA does not
quantitatively address socioeconomic impacts caused by schedule. Significant socioeconomic impacts are associated
with the WSHB closure – we anticipate that an accelerated schedule would decrease negative impacts. The
additional duration required to design and construct a replacement structure, along with potential schedule slip risks,
as compared to rehabilitating the bridge, would likely favor rehabilitating the bridge versus replacing the bridge,
especially when considering the opportunity cost of time.
Page 66
6.3 SUMMARY OF FINDINGS
Figure 56 and Figure 57 present a summary of the CBA’s findings. Findings are reported in the form of a value
index – the ratio of performance to cost – which measures return on investment: a higher value index correlates to a
higher return on investment, and vice versa.
To illustrate the process, we determined a base set of values using the performance scores and costs presented in
Sections 3 and 4. We developed these “base values” purely on the assumptions made within the CBA (base values
are represented by the X’s in Figure 56).
The “reported findings” take into account the sensitivity of key assumptions made within the CBA (Section 6.2).
The “reported findings” are represented by the orange dots in Figure 56. These represent the subject matter experts’
conservative best estimation of the value indices for each alternative –the averaged results of the sensitivity studies.
Figure 56 and Figure 57 illustrate that Alternative 2 has the highest value index and the highest potential for an
increase in value index as compared to the other alternatives.
NOTES:
- Higher value indices represent better returns on investment.
- X’s – “base value” indices based solely on assumptions within the CBA.
- Orange Dots – “reported findings” conservatively taken as the average of the sensitivity studies conducted.
- Blue Bars – potential range in value indices based on the sensitivity study findings. Alternative 2 has the highest
potential for increased value indices.
- Black Line – relative trend in potential additional value index increase if contingency and risk were removed from the
assessment. Alternative 2 has the highest potential for increase.
Page 67
Figure 57. CBA Reported Findings - Tabularized
Page 68
CBA LIMITATIONS & FUTURE STUDIES
The scope of this CBA was limited, as WSP has not advanced the five alternatives presented here to the level of
design that would allow for an exhaustive analysis of costs, risks, or other forms of quantitative or qualitative study.
particularly for attributes and performance. The CBA is, first and foremost, a tool to help illuminate some of the
benefits and drawbacks of rehabilitation and replacement. While it is true that there are multiple alternatives
contained herein, the output of this report is by nature binary.
WSP anticipates that, regardless of the decision to rehabilitate the existing structure or replace it with a new one, the
City will pursue future studies. As future studies and phases commence, WSP, with input from the Port of Seattle,
the Northwest Seaport Alliance, the CTF, the TAP, and the City, identified the following, non-exhaustive list of
items we recommend be further explored:
• Funding Opportunities The CBA identified funding opportunities as a key attribute. Future work/studies
on the project should consider not only a list of expanded funding opportunities, but also include how they
relate to decisions related to rehabilitation versus replace and the timing of those decisions, as it pertains to
available funding, and the necessary funding for the rest of the City’s transportation infrastructure.
• Approach Structure Assessment The CBA did not consider modifications to the approach structures, as
WSP did not do an in-depth analysis of their condition. Replacing the high-rise structure without assessing
the condition of the approach structures may limit future corridor investment opportunities and
understanding of funding needs ahead of coordinating with key project stakeholders.
• Bridge Type Selection The CBA identified an in-kind (i.e., concrete box girder) superstructure
replacement for Alternative 4. Selection of alternate superstructure types and framing could have a negative
impact on the existing bridge components to remain (especially the foundations). Concepts could also
include increased inspection and maintenance costs (i.e. selection of a fracture critical structure and/or use
of seismic isolation bearings). These costs have not been monetized in the CBA and should be investigated
as part of future phases of work.
• Duration of Service Life Assessment The CBA service life assessment ended in 2100, which
corresponded to the end of the design life for Alternative 4. The salvage value of alternatives with
remaining service life were accounted for within the CBA; however, variations in the duration of the
service life assessment may change the value of the life-cycle cost assessment. It may be desirable to
investigate this further in future phases of work, however, it is anticipated to have minor impacts on the
findings (resulting value indices) based on sensitivity studies conducted as part of the CBA.
• Construction Uncertainties The alternatives have differing levels of construction risk (i.e. in-water work
activities, utility work, construction of foundations, etc.) that could lead to risks of claims, cost escalation,
and schedule lag. These are more prevalent with the replacement alternatives than the rehabilitation
alternative. For the purpose of the CBA, a constant 20-percent value was included for each alternative.
This should be further investigated in future phases of work.
• Quantification of Socioeconomic Impacts The CBA qualitatively addressed socioeconomic impacts such
as road-user costs; subject matter experts used this information in the performance scoring part of the CBA.
The socioeconomic impacts were not monetized as part of the risks, capital costs, or life-cycle costs. The
analysis did underscore the importance of minimizing the closure duration to reduce socioeconomic
impacts, especially the duration of immediate closures.
• Federal Aviation Administration Height Restrictions The project site’s proximity to Boeing Field may
require height restrictions on the structure and its appurtenances, limiting the types of bridge replacement
concepts. WSP recommends that the City and future studies coordinate with Boeing Field to eliminate this
risk.
• Equity Impacts The CBA qualitatively assessed equity impacts, focusing primarily on the effects of the
closure’s detour routes through marginalized communities. There remains a multitude of other equity-
related factors that should be considered, including the impacts on vehicle and transit users from
marginalized communities, namely, the users of these detours. Other studies could also focus on the
closure’s impacts on small or local businesses specific to these communities.
• Defining Marginalized Communities The CBA focused on race in its definition of marginalized
communities, as 59 percent of SDOT’s diversion routes are through communities with relatively high
percentages (23 to 89 percent) of people of color. Future studies could assess the closure’s effects on
communities based on income status, disability, immigrant population, and/or populations that do not speak
English as a first language, and others.
Page 69
• Equity in Final Configuration The CBA focused on equity impacts during the closure. Future studies
should also assess equity in the crossing’s final configuration.
• Utility Service Impacts We developed the CBA in an accelerated manner and did not do a detailed review
of all utilities and their services throughout the project site. Future phases of work should develop a
detailed understanding of the utility services and their potential impacts to minimize risks and potential
schedule delays.
• Environmental Impacts The CBA was not a type, size, and location study. Alternatives were concepts
developed based on apparent low cost. We identified conceptual construction schedules and potential site
impacts, but future studies should develop a detailed understanding of all environmental impacts, including
design and construction means and methods that could exacerbate them.
• Environmental Impacts from Dredging As stated above, the CBA was not a TS&L. We recommend that
any future studies assessing the feasibility of the immersed tube tunnel focus on environmental impacts and
potential hazardous materials from dredging the Duwamish River, which is a Superfund site.
• Seismic Classification All bridges within the current SDOT bridge inventory are classified as normal, and
their assessment is covered by national standards augmented with City standards. A normal classification
means that the bridge will maintain life safety after the design earthquake, but may not be serviceable
afterwards, requiring replacement. Investment in a replacement structure on a key corridor such as the West
Seattle corridor may require consideration of a higher performance criteria so the bridge could be
serviceable immediately after the design earthquake, or shortly thereafter. The City and their consultants
would need to develop project-specific criteria to specify higher performance criteria (i.e., “essential”).
This requires time, and careful consideration of pending industry code changes, both geotechnical and
structural (i.e. upcoming changes in USGS hazards, M-9 effects, NCHRP-12-106, etc.). There is also an
added layer of complexity if multi-agency input is required.
• Formal Risk Assessment The CBA includes a risk registry, however, does not follow any formal risk
modeling process, such as WSDOT’s Cost Estimate Validation process. Future phases of work should
consider the merit of more robust analytical tools for assessing and monetizing risks.
• Condition Assessment of Key Corridors Identifying the City’s key corridors and how they currently
compare to the West Seattle corridor in regards to importance, average daily traffic, number of bridge
structures, their age, condition, and approximate cost to repair/replace the bridge structures; to determine
priority for the City’s infrastructure investments and to support decisions related to potential multi-agency
operated structures.
• Multi-Agency Development Plans The project is constrained within a built environment that is key to the
local and regional economy. Both the Port of Seattle (Terminal 5 Expansion) and Sound Transit (West
Seattle to Ballard Link Extension) have development plans that could be affected by this project due to
proximity and usage. Coordination amongst the agencies will be important to avoid placing further
constraints on development plans. Future studies could provide an opportunity to optimize the potential for
all agencies.
• Forward Compatibility with Heavy Rail The CBA did not explore opportunities for a replacement’s
forward compatibility with BNSF rail.
• Future Coordination with Sound Transit Future studies, particularly the TS&L, need to further assess
the potential to accommodate light rail, structurally, geometrically, and from an asset management
perspective (differing service life criteria, responsibilities, etc.). Accommodation of light rail may impact
structure type decisions and the grade/profile decisions.
• Maritime User Impacts The CBA focused on land-based mobility impacts, specifically those on motor
vehicle users and neighborhoods seeing increases in traffic. We recommend that future studies delve further
into the project’s impacts on the maritime community, including river mobility, industry use, and maritime
recreation. It is also imperative for the local economy that the project minimize impacts on the Port of
Seattle’s operations, and we recommend further coordination with the Port to achieve this.
• Railroad Impacts The CBA focused on land-based mobility impacts, specifically those on motor vehicle
users and neighborhoods seeing increases in traffic. We recommend that future studies further examine
potential impacts to railroad traffic from the WSHB closure. Discussions and coordination with railroad
operators such as BNSF and UPRR could be helpful.
• Tribal Coordination Because of its limited scope and duration, the CBA was not able to capture impacts
to tribal fishing rights or examine the details of the treaties with local tribes. However, this coordination
will be critical to project success. The City of Seattle recognizes all tribal treaties and so it is important that
this perspective be incorporated into design and construction means and methods.
Page 70
ACKNOWLEDGEMENTS
This report would not have been possible without the support of the Mayor of Seattle, the Seattle City Council, the
Technical Advisory Panel, and the Community Task Force. In addition, we would like to recognize in particular the
contributions of the indefatigable Seattle Department of Transportation team, and most of all, we would like to
acknowledge the people of Seattle. The West Seattle Bridge belongs to them, and this project is dedicated to them.
Page 71
REFERENCES
Page 72
APPENDIX