05 OR BMS MCQs
05 OR BMS MCQs
05 OR BMS MCQs
TM
OPERATIONS RESEARCH
(BMS Third Year : Sixth Semester)
(Core Courses – Compulsory)
NITIN KULKARNI
(1) Operations Research Models in which values of all variables and all
possible outcomes are known with certainty are called __________ models.
(a) Physical
(b) Symbolic
(c) Deterministic
(d) Probabilistic
(2) Operations Research Models in which some or all variables are random in
nature are called __________ models.
(a) Physical
(b) Symbolic
(c) Deterministic
(d) Probabilistic
(3) Mean, median and mode are measures of __________.
(a) Central tendency
(b) Dispersion
(c) Probability
(4) __________ and __________ are techniques applied in project management.
(a) CPM and PERT
(b) Assignment and Transportation
(c) Decision theory and Inventory models
(5) Operations Research techniques are __________ in nature.
(a) Qualitative
(b) Judgemental
TM Operations Research (BMS) by Nitin Kulkarni
TM
2 Operations Research (BMS) by Nitin Kulkarni
(c) Approximate
(d) Quantitative
[Ans.: (1 – Deterministic); (2 – Probabilistic); (3 – Central tendency);
(4 – CPM, PERT); (5 – Quantitative)]
(1) __________ are the entities whose values are to be determined from the
solution of the LPP.
(a) Objective function
(b) Decision Variables
(c) Constraints
(d) Opportunity costs
(2) __________ specifies the objective or goal of solving the LPP.
(a) Objective function
(b) Decision Variables
(c) Constraints
(d) Opportunity costs
(3) Objective function is expressed in terms of the __________.
(a) Numbers
(b) Symbols
(c) Decision Variables
(4) __________ are the restrictions or limitations imposed on the LPP.
(a) Variables
(b) Costs
(c) Profits
(d) Constraints
(5) The type of constraint which specifies maximum capacity of a resource is
‘__________ or equal to’ constraint.
(a) Less than
(b) Greater than
(c) Less than or greater than
(6) In linear programming ________ represents mathematical equation of the
limitations imposed by the problem. (April 19)
(a) Objective function
(b) Decision variable
(c) Redundancy
(d) Constraints
(1) The region of feasible solution in LPP graphical method is called ____.
(a) Infeasible region
(b) Unbounded region
(c) Infinite region
(d) Feasible region
(2) When it is not possible to find solution in LPP, it is called as case of
__________.
(a) Unknown solution
(b) Unbounded solution
(c) Infeasible solution
(d) Improper solution
(3) When the feasible region is such that the value of objective function can
extend to infinity, it is called a case of __________.
(a) Infeasible solution
(b) Alternate optimal
(c) Unbounded solution
(d) Unique solution
(4) When the constraints are a mix of ‘less than’ and ‘greater than’ it is a
problem having __________.
(a) Multiple constraints
(b) Infinite constraints
(c) Infeasible constraints
(d) Mixed constraints
(5) In case of an ‘________’ constraint, the feasible region is a straight line.
(a) less than or equal to
(b) greater than or equal to
(c) mixed
(d) equal to
(6) In linear programming, unbounded solution means ______. (April 19)
(a) Infeasible solution
(b) Degenerate solution
(c) Infinite solutions
(d) Unique solution
[Ans.: (1 – Feasible region); (2 – Infeasible solution); (3 – Unbounded
solution); (4 – Mixed constraints); (5 – equal to); (6 – Infinite solutions)]
TM Operations Research (BMS) by Nitin Kulkarni
TM
4 Operations Research (BMS) by Nitin Kulkarni
(b) penalty
(c) epsilon
(d) regret
(6) If M + N – 1 = Number of allocations in transportation, it means _________.
(Where ‘M’ is number of rows and ‘N’ is number of columns)
(a) There is no degeneracy
(b) Problem is unbalanced
(c) Problem is degenerate
(d) Solution is optimal
(7) Which of the following considers difference between two least costs for
each row and column while finding initial basic feasible solution in
transportation?
(a) North west corner rule
(b) Least cost method
(c) Vogel’s approximation method
(d) Row minima method
[Ans.: (1 – least cost); (2 – Vogel’s approximation); (3 – feasible);
(4 – non-degenerate); (5 – epsilon); (6 – There is no degeneracy); (7 – Vogel’s
approximation method)]
(1) If the number of rows and columns in an assignment problem are not equal
than it is called __________ problem.
(a) prohibited
(b) infeasible
(c) unbounded
(d) unbalanced
(2) The method of solution of assignment problems is called __________
method.
(a) NWCR
(b) VAM
(c) LCM
(d) Hungarian
(3) When a maximization assignment problem is converted in minimization
problem, the resulting matrix is called __________.
(a) Cost matrix
(b) Profit matrix
(c) Regret matrix
(d) Dummy matrix
TM Operations Research (BMS) by Nitin Kulkarni
Multiple Choice Questions (MCQs) for TYBMS 7
(4) The extra row or column which is added to balance an assignment problem
is called __________.
(a) regret
(b) epsilon
(c) dummy
(d) extra
(5) When a particular assignment in the given problem is not possible or
restricted as a condition, it is called a __________ problem.
(a) infeasible
(b) degenerate
(c) unbalanced
(d) prohibited
(6) If in an assignment problem, number of rows is not equal to number of
columns then __________.
(a) Problem is degenerate
(b) Problem is unbalanced
(c) It is a maximization problem
(d) Optimal solution is not possible
[Ans.: (1 – unbalanced); (2 – Hungarian); (3 – Regret matrix);
(4 – Dummy); (5 – Prohibited); (6 – Problem is unbalanced)]
(1) The longest path in the network diagram is called __________ path.
(a) best
(b) worst
(c) sub-critical
(d) critical
(2) The second longest path in the network diagram is called __________ path.
(a) alternate
(b) feasible
(c) sub-critical
(d) critical
(3) Forward pass calculations are done to find __________ occurrence times of
events.
(a) exact
(b) earliest
(c) latest
(d) approximate
(4) Backward pass calculations are done to find __________ occurrence times of
events.
(a) tentative
(b) definite
(c) latest
(d) earliest
(5) An activity whose start or end cannot be delayed without affecting total
project completion time is called __________ activity.
(a) dummy
(b) non-critical
(c) critical
(d) important
(6) Floats for critical activities will be always _________. (April 19)
(a) one
(b) zero
(c) highest
(d) same as duration of the activity
[Ans.: (1 – Critical); (2 – Sub-critical); (3 – earliest); (4 – latest);
(5 – critical); (6 – Zero)]
(1) The two types of costs involved in project crashing are __________ and
__________ costs.
(a) direct and indirect
(b) total and partial
(c) visible and invisible
(d) measurable and non-measurable
(2) In project crashing, rent and overheads are treated as __________ costs.
(a) significant
(b) insignificant
(c) direct
(d) indirect
(3) In project crashing, the costs associated with actual activities (e.g.
manpower, materials, machinery etc.) are called __________ costs.
(a) visible
(b) measurable
(c) direct
(d) indirect
(c) mean
(d) critical
(5) Fill in the blanks with ‘<’ or ‘>’ sign as applicable a m b
(a) <, >
(b) >, <
(c) >, >
(d) <, <
(6) The maximum time in which an activity will be completed assuming all
possible delays and postponements is termed as ___________.
(a) optimistic time
(b) most likely time
(c) pessimistic time
(d) expected time
[Ans.: (1 – optimistic); (2 – pessimistic); (3 – expected); (4 – mean);
(5 – <, <); (6 – pessimistic time)]
(1) The time required by each job on each machine is called __________ time.
(a) elapsed
(b) idle
(c) processing
(d) average
(2) The order in which machines are required for completing the jobs is called
__________.
(a) machines order
(b) working order
(c) processing order
(d) job order
(3) The time between the starting of the first job and completion of the last job
in sequencing problems is called __________.
(a) total time
(b) assignment time
(c) elapsed time
(d) idle time
(4) The time during which a machine remains waiting or vacant in sequencing
problem is called __________ time.
(a) processing
(b) waiting
TM Operations Research (BMS) by Nitin Kulkarni
Multiple Choice Questions (MCQs) for TYBMS 11
(c) idle
(d) free
(5) In sequencing problem, the order of completion of jobs is called
__________.
(a) completion sequence
(b) job sequence
(c) processing order
(d) job order
(6) The total time required to complete all the jobs in a job sequencing problem
is known as ___________.
(a) idle time
(b) processing time
(c) elapsed time
(d) processing order
[Ans.: (1 – processing); (2 – processing order); (3 – elapsed time); (4 – idle);
(5 – job sequence); (6 – elapsed time)]
(c) actions
(d) strategies
(5) A situation in a game where, in the payoff matrix, maximin of row is equal
to minimax of column is called __________.
(a) centre point
(b) main point
(c) saddle point
(d) equal point
(6) The various alternatives or courses of actions available to each player in a
game are called as __________.
(a) saddle points
(b) strategies
(c) pay-off
(d) ‘n’ player game
[Ans.: (1 – players); (2 – n-person); (3 – payoff); (4 – strategies); (5 – saddle
point); (6 – strategies)]