OR Assignment 1
OR Assignment 1
To be submitted before 5:30PM February 1, 2011 (Assignment will not accepted after this)
Q.1 The following maintenance job has to be performed periodically on the heat exchangers in a
refinery:
(a) Earliest Start time (b) Latest Start time (c) Earliest finish time
(d) Latest finish time (e) Total float (f) Free float
(g) Independent float (h) Interfering float (i) Project duration
Draw the updated network and find out its revised duration. Number 12 denotes activity 1 – 2 and
same is true for other activities.
Q.5 The activities involved in a certain project have been identified as follows:
Activity Preceding Duration No. of Men Activity Preceding Duration No. of Men
Activity (Weeks) required Activity (Weeks) required
A -- 4 1 E C 4 1
B -- 7 1 F B, E 4 2
C -- 8 2 G C 11 2
D A 5 3 H G, F 4 1
(a) For the above project draw the network. Determine the critical path and its duration.
(b) If there were only three men available at any one time, how long would the project take and
how would you allocate the men to the activities?
(c) If there were no restrictions on the amount of labour available, explain how you would
schedule the activities.