Demystifying Earned Value Management
Demystifying Earned Value Management
Demystifying Earned Value Management
Earned value management (EVM) is a method to assess project performance. This is pretty simple
once you get a hang of it. First, spend some time trying to understand the following terms.
EVM develops and monitors the first three key dimensions (EV, AC and PV) for each work package
and control account.
On a time-cost graph these are typically an S-curve (refer to the image later in this lesson)
PMB – Total Planned Value is sometime referred to as Performance Measurement
Baseline. PMB is the time-phased budget plan for accomplishing work, against which contract
performance is measured. Note that this does NOT contain management reserve.
ES – Earned Schedule. An alternate way to measure schedule variance.
SV – Schedule Variance. It is the difference between how much of schedule for an activity
(or WBS component) is actually utilized versus how much of schedule should have been utilized,
at any given point in time.
CV – Cost Variance. It is the difference between how much of budget for an activity (or WBS
component) is actually utilized versus how much of budget should have been utilized, at any
given point in time.
SPI – Schedule Performance Index. It is a indication of schedule progress achieved on the
project as compared to the progress planned, at any given point in time. Ideal value for a project
is >= 1.0, which indicates that the project is ahead of schedule or on schedule.
CPI – Cost Performance Index. It is a indication of value of work completed as compared to
actual cost (or progress) made on the project, at any given point in time. Ideal value for a project
is >= 1.0, which indicates that the project’s expenditure is within the budget or just on it.
BAC – Budget At Completion. This is the total planned value for ALL activities (or WBS
components) over the entire project. In other words, this is the planned amount you will end up
spending on project work when the project ends. We say ‘planned’ because BAC is calculated
during planning period, which is much ahead of project completion time.
In reference to PMB, at the end of the project PMB terminates at BAC (refer to the image below).
Planned value is calculated by multiplying percentage of work planned to have completed and the
Budget At Completion.
Earned value is calculated by multiplying percentage of actual work completed and the Budget At
Completion.
If you discover a negative schedule variance, you need to think of possibilities of shortening duration
of few other tasks. Schedule compression techniques (discussed as part of Develop Schedule
process) will be useful.
Schedule Variance using Earned Schedule
This is an alternate way to measure schedule variance. ES is the Earned Schedule, and AT is the
actual time.
Thus, SV = ES – AT
This means that if earned schedule is more than the actual time spent to do the work at a given point
in time, then the project is ahead of schedule.
If you are calculating CV for the end of project, it will be the difference between Budget At Completion
and actual amount spent on project till then.
If there is a negative cost variance then that amount is gone; it cannot be recovered. So you can only
plan for corrective action by which you can save money on other tasks (if such a plan is possible).
Variance as Percentages
You can express cost variance and schedule variance in percentages, and here is how –
SPI = EV/PV
As you can see if planned value is less than earned value of the project, SPI will be > 1.
Hence if SPI >= 1, the project is ahead of schedule. This is a good thing!
Here’s an example –
John’s home construction project went into third quarter and his team completed bare bone structure
of first two floors and in terms of value this comes to $75,000. He had plans to complete even the
exteriors by this time which would have realized a value of $100,000. How is he doing on schedule?
Answer:
SPI = EV/PV;
This would be, 75,000/100,000 = 0.75
This is less than 1.0, which means that John is lagging in his schedule.
His schedule variance is EV – PV;
75,000-100,000=-25,000. He is falling short on producing $25,000 worth of work.
Using the Earned Schedule way,
Schedule performance index = Earned schedule / Actual time
SPI = ES/AT
CPI = EV/AC
As you can see if actual cost is less than earned value of the project, CPI will be > 1.
Hence if CPI >= 1, the project is well within the budget (or ‘cost underrun’). Again, this is a good thing!
An example –
From planning time to construction John had to pay 20% more for wood and steel due to price rise.
He ends up spending $110,000 in total into his third quarter. What do his cost numbers look like?
CPI = EV/AC;
This would be 75,000/110,000=0.6818
This is below the ideal number 1.0, this means John is falling short of budget too.
Cost Variance = EV – AC;
75,000-110,000=-35,000. John is falling short of $35,000 on budget.
It is time he goes to sponsor with EAC and ETC figures and asks for more budget.
If your project has CPI and SPI both >= 1.0, that project is ahead of schedule and has utilized less
than authorized budget, and is in good hands!
Any resultant changes to cost baseline are managed using Perform Integrated Change Control
process.
Controlling project costs involves a two-step process –
Apart from these the project manager has to monitor closely the expenditure with respect to cost
baseline, against work progress. In other words, if work is being done within defined schedule then
the risk of cost escalation is reduced.
If quality of the deliverables are maintained then external cost of quality can be avoided.
All this will naturally mean that control costs is not a one-time process to execute. Neither it is an
activity done in isolation. This is a regular, almost day-to-day activity for the project manager to keep
an eye on preventive measures that keeps the costs under control.
Acronyms
It would be useful at this stage to just understand important acronyms used in order to see how
project cost is controlled.
EV – Earned Value. Also referred to as Budgeted Cost of Work Performed (BCWP).
ES – Earned Schedule
AC – Actual Cost. Also referred to as Actual Cost of Work Performed (ACWP).
PV – Planned Value
PMB – Total PV is sometime referred to as Performance Measurement Baseline.
SV – Schedule Variance
CV – Cost Variance
SPI – Schedule Performance Index
CPI – Cost Performance Index
BAC – Budget At Completion
EAC – Estimate At Completion
ETC – Estimate To Complete
TCPI – To-Complete Performance Index
TAB – Total Allocated Budget
Exam tip: Understand the alternate acronyms used in the list above. Exam questions may refer to
any of them. For instance, instead of Actual Cost, the question may refer to Actual Cost of Work
Performed or just ACWP.
What do you need to control project costs?
You need to refer to Cost management plan, and the Cost baseline – which is the yardstick to
compare actual cost measurements against, so we know the variance and do something to fix it.
Project funding requirements is about figuring out amount and frequency of time at which budgeted
money should be released. This would depend on projected expenditure plan, which is made based
on when certain resources come into play during project execution.
For instance, for a new e-commerce product you may need an exhaustive security audit when version
1.0 of the product is released. You will need a funding release around this time.
Then you will need to know the state of project. Information such as which activities (or WBS
components) have been taken up, how many are completed, how many are delayed, what is the cost
incurred on the work performed, so on.
If your organization has certain cost control related policies, procedures, tools, reporting methods so
on, you need to know them as well.
Get help from experts. Just because the project manager is in charge of the project, it does not
mean that she needs to know the subject matter and do all the work herself. What are experts for,
right? They can help with one or more of the following.
Analyzing data.
Well, only then we know how things are going and what to do to fix those things that are broken,
right?
Some of the data analysis techniques are Earned value analysis, Alternatives analysis, Variance
analysis, Trend analysis, Reserve analysis and so on.
Forecasting
Forecasting is a means of identifying efforts required to meet project objectives based on the trend
shown by project progress so far.
Estimate at Completion (EAC)
Ideally this should be same as Budget at Completion (BAC), which is calculated first during initial
planning exercise. However, practically EAC will be different from BAC.
Since this assumes cost figures, EAC is also called Cost Estimate at Completion (CEAC).
How do you decide whether Budget at Completion is still valid for the project?
A good indication is if the value of CPIs you calculate for successive periods of time start getting
farther below 1.0. It is better to calculate EAC the moment you get a CPI < 1.0, to know what it takes
to complete the project work. In simpler words, if the project is over budget you need to calculate
EAC.
EAC can be calculated manually based on project management team’s knowledge of how project has
progressed, using bottom-up ETC.
There are few ways to calculate Estimate at Completion based on the data you already know.
Case 1: You know that remaining work will be performed at the planned rate (or ‘budgeted rate’)
This means that your project has carried out the work as per the schedule and cost planned for
activities, and will continue at the same rate.
Example 1:
John’s house construction project entered fourth quarter, his actual money spent is at $150,000, and
earned value is $153,000. For this much work he had planned approximately $155,000. During initial
planning period his total project budget was $300,000. What will be his Estimate at Completion?
Answer: $297,000
This is how it is calculated –
John’s SPI = EV/PV; 153,000/155,000 = 0.9871
CPI = EV/AC; 153,000/150,000 = 1.02
Both indicators are hovering around 1.0, which means John is ahead of schedule and good on
budget. He is reasonably confident of maintaining same rate going forward.
EAC = AC + (BAC – EV);
150,000 + (300,000 – 153,000) = $297,000
Note: you just need the last formula to calculate the answer. SPI and CPI are calculated just for cost
and schedule health check.
SPI, CPI and other EVM formulae are explained in the next lesson, you may want to go through them
before proceeding here.
Example 2:
John’s house construction project now entered fifth quarter, and he found his CPI that was
consistently around 1.0, this time at a much better 1.03. During initial planning period his total project
budget was found to be at $300,000. What will be his Estimate at Completion?
Answer: $291,262
John is quite happy to discover that his project is scheduled to complete within the initial Budget at
Completion!
This is how it is calculated –
EAC = BAC / CPI;
EAC = 300,000/1.03 = $291,262
Example 3:
John’s house project entered sixth quarter now and his earned value has come to $225,000, while his
actual spending is at $220,588. During initial planning period his total project budget was at $300,000.
Now his CPI is working out to 1.02 and SPI at 0.95, what will be his Estimate at Completion?
Answer: $297,987
John is proving to be a competent project manager. He is close to completing the project and his EAC
is still within initial BAC! He sure is happy to get his bonus once project is over!
This is how it is calculated –
EAC = AC + { [BAC – EV] / [CPI x SPI] };
EAC = 220,588 + { [300,000 – 225,000] / [1.02 x 0.95] } = $297,987
Estimate to Complete (ETC)
ETC is the estimate of work required to complete remaining activities on the project.
When EAC is known ETC is calculated as,
ETC = EAC – AC
This is because estimate to complete work is the difference between estimate at completion and
actual cost of work performed.
Now, if we are confident that future performance will go as per original plan, then ETC is calculated
as,
ETC = BAC – EV
Variance at Completion (VAC)
Based on the above, if you want to calculate variance at completion, you simply deduce EAC from
BAC!
Remaining Budget is calculated by deducting actual cost spent so far on the product from the Budget
at completion. This would be (BAC – AC) or (EAC – AC) – as the case may be. This makes two
distinct cases to calculate TCPI.
Case 1: If you find that project is under budget then you will use Budget at Completion –
TCPI = (BAC – EV) / (BAC – AC)
Case 2: If the project is over budget, you need to calculate Estimate at Completion (remember that
EAC should be approved through change control process) and use the following formula for TCPI –
TCPI = (BAC – EV) / (EAC – AC)
Consider an example –
John’s house construction project enters final phase and his CPI is < 1 (project is over budget).
Project has spent thus far $260,000 and earned value achieved is about $255,000. Total project
budget was planned to be $300,000. What is the TCPI to ensure that project completes within the
Budget At Completion?
Answer: 1.1
TCPI = remaining work/remaining budget;
TCPI = (BAC – EV) / (BAC – AC);
(300,000 – 255,000) / (300,000 – 260,000) = 1.1
PMIS (Project Management Information System) helps a great deal in automating many of these
calculations. This is useful especially in large scale projects.
Cost Forecasts – EAC (Estimate At Completion) calculated either manually (using bottom-up
approach) or using formulas is the forecast. These are shared with the stakeholders.
EAC becomes a formal figure only when change control board authorizes it. Authorization is given
after project manager or project management team takes EAC as a change request through
Integrated Change Control process and formalizes it.
Change requests – whenever some work is monitored it is bound to produce change requests as
deviations are discovered. EAC, among others, can be the single most prominent change request in
this process.
As we refer the plans and documents to control costs we may discover few issues with them, or the
change requests that we raise may necessitate changes to those plans and project documents. And
hence updating them would be a natural outcome of this process.
Summary
Control costs is one of those few project management activities that must be executed throughout the
project execution phase. If you are doing it for the first time, you may find it a bit tedious. However, the
advantage you get is the early warnings of whether the project is slipping. This may help you save
cost, effort, customer escalation, or may even save the day. You may find it almost a necessity to run
EVM calculations and TCPI every Monday (or whatever frequency you decide on) for your peace of
mind.