DS # 002625R1 (KH/MST/M/027 )
Provide details for the girder bridge and end trucks - their individual and assembled dimensions
1
and weights.
Provide details of shifting the girder bridge and the runway beams inside the building. List out
2 the preparations required outside the building and the machinery that would be used for their
shifting and lifting inside the buildings.
With chillers already located in their final position in B04 the space available inside the
building for assembling and maneuvering the individual part and the assembly is limited
therefore provide a sketch of the floor with chillers marked in their positions indicating the
3
location of assembling the unit and the movement of overhead crane components and the
machinery required for lifting and mounting the assembled unit and the runway beams on to the
corbels above.
Provide assembly and installation sequence of bridge girder, end trucks, hoist and trolley
raceway, runway, rails, conductor system, festoon cable and other components required to make
4
the crane assembly fully assembled and operational as per the specifications and other project
documents.
Confirm the length of the runway beams on both sides allows the girder bridge travel covering
5
the entire floor area of the equipment room.
Indicate in the drawings the total length of the runway beam and in case where the length of the
6 runway beam stops short of reaching the last corbel provide sectional details of installation of
the stopper. (See comments on the Drawing inside.)
Provide assembly sequence of the runway beam and indicate the sequence on a sketch of the
7
floor plans.
9 Provide details of the bolts to be used on gusset plates on the runway beams.
Embedment length and hole size required for the chemical anchors shall be as per the chemical
10
anchor manufacturer recommendations only.
Provide details of load test, trolley travel and girder bridge travel tests as per project
11
specifications.
All comments noted on the overhead cranes approved Material Submittals and Material
12
Receiving approvals through MIRs 685R2 and 744R1 shall be complied with
13 All comments noted on the Rev-00 of this Method Statement shall be complied with.
List out the statutory requirements if any of the civil defence and other relevant governing
14
bodies that shall be fulfilled prior to or post installation of the overhead cranes.
Page 1 of 1