Q&A Ballast Water Management Convention (BWMC) 2004
Q&A Ballast Water Management Convention (BWMC) 2004
Q&A Ballast Water Management Convention (BWMC) 2004
Introduction
Questions and Answers regarding various subjects of the BWMC 2004. This document
was written in response to recurring questions raised by the stakeholders, mainly ship
owners and classification societies. This Q&A is not meant to be exhaustive or static; it
will be updated according to experience gained. Q&A’s are listed roughly according to the
Convention articles.
Definitions
Application
Q2: Are there additional requirements for ships under Netherlands’ flag?
A2: There are no additional requirements for ships flying the Netherlands’ flag. The
equivalency under A-5 of the Convention has not been assessed by this Administration.
Q4: How can semi-submersible ships, heavy lift vessels and similar vessels comply with
the convention?
A4: The large volumes of water needed to carry out lifting operations are taken in and
discharged on the same location and thus not subject to the D-2 standard. Ideally, the
ballast system is split into a high capacity system for lifting operations and a regular
capacity system with a BWTS complying with the D-2 standard. The sediment
management for the “uncontrolled” tanks should be detailed in the BWMP and may
constitute regular tank inspections to assess the amount of sediment and a schedule for
flushing or cleaning.
Page 1
Exemptions
Q6: What are the possibilities for exemption for ships on a fixed route?
A6: The procedures according to G7 of the Convention should be followed. Any method
or combination of methods may be applied, like the OSPAR/HELCOM protocols or the SRA
concept.
Q7: What are the possibilities for exemption of ships on occasional voyages?
A7: Guidance is given in BWM.2-Circ.52, latest edition. Upon agreement of the States
involved, D-1 compliance may be sufficient.
Q10: What if the BWMP has not been approved before 8 September 2017?
A10: Class will issue a statement that the plan has been received, and will issue a
Certificate with a validity of three months. This will allow the vessel to continue trading
and provides Class with time to approve the plan.
Q12: What are the possibilities for external treatment of ballast water?
A12: External treatment of ballast water is allowed, provided the installation complies
with the relevant standards (type approval according to G8/G9). If external treatment is
used as an alternative method of compliance, in lieu of fitting a treatment system on
board, this needs to be included in the BWMP. Ballast operations conducted with external
treatment shall be recorded in the BWRB.
Q13: Upon selection and installation of a BWTS, what is to be taken into account?
A13: The choice of the treatment systems depends on a lot of factors, such as the
required capacity, the expected trading pattern of the vessel in relation to the ballast
water expected to be taken on board (fresh/salt, high/low turbidity), the expected
frequency and duration of operation etc. Most manufacturers recommend cleaning of the
ballast water tanks before commissioning. Upon installation of a BWTS, the BWMP is to
be revised and submitted for approval, the installation is to be surveyed to confirm
compliance with the type approval and a new IBWMC Certificate is to be issued indicating
“D-2” as the principal ballast water management method.
Page 2
Q14: How is BWM regulated at the repair yard?
A14: The discharge of ballast water in dock or at the repair yard is also subject to the
Convention. Discharges of water are the responsibility of the shipyard however and
subject to local regulations.
BW Exchange
Q15: Unmanned non-propelled barges cannot exchange ballast water. How shall these
barges comply with the Convention?
A15: It is acknowledged that unmanned vessels cannot exchange ballast water during
the voyage. Typically, the master will apply regulation B-4.4 on the basis of safety
issues. Therefore, during the interim period of ballast water exchange, unmanned vessels
are not required to exchange ballast water. This is also subject to acceptance of the Port
State concerned. When the D-2 standard becomes applicable to these vessels alternative
methods of treatment will need to be applied, like external treatment, the use of drinking
water or in-tank treatment.
Q16: When conducting BWE, how is regulation B-4.3 of the convention applied?
A16: According to the above regulation, ships shall not be required to deviate from their
intended voyage, or delay the voyage to perform ballast water exchange. This is also
reflected in the OSPAR/HELCOM document (BWM.2/Circ.56) on BWE where the North Sea
exchange area is designated. If any of these conditions cannot be met, only the tanks of
which can be exchanged completely need to be exchanged. For the remaining tanks,
BWE is not required and should not be carried out. This is of particular importance since
partial exchange may revive organisms in the ballast water and have an adverse effect.
When there are no opportunities for BWE during the complete voyage, no additional
measures need to be taken.
The reason for not conducting BWE shall be recorded in the BWRB.
Sediment management
Type approval
Q20: How can BWM be combined with sea trials / art 2 bis?
Page 3
A20: A vessels normally only proceeds with sea trials if all the quay trials are finished.
Testing and commissioning the BWTS should be part of these trials. Sea trials according
to art. 2 bis are not an international voyage however, and in that case the Convention is
not applicable.
Q21: Will the existing statement of compliance issued by the Classification Society be
replaced by a certificate?
A21: Since the Convention requires certification, existing statements of Compliance will
need to be replaced by a Certificate. Also see Q10 and Q12.
8-9- 8-9- 8-9- 8-9- 8-9- 8-9- 8-9- 8-9- 8-9- 8-9- 8-9- 8-9- 8-9-
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
D-2 Compliance
Vessels that have de-harmonised the IOPP certificate will likely have done so in the period from 8-
9-2016 ->8-9-2017. Installation of a system will then be required after the first IOPP renewal.
Undoing the de-harmonisation is not allowed because there is no legal basis to do so.
Page 4
A23: De-coupling is allowed but the new certificate may not be suspended, this means
that a maximum extension of five years is allowed.
Q24: What is the due date of application for vessels below 400GT?
A24: Smaller vessels may have a disadvantage with regards to implementation of the D-
2 standard since they hold no IOPP certificate. Therefore the due date for application is
8-9-2024, the maximum date allowed for all ships.
Q26: Which documents can be issued before the due date and when shall this be
replaced by a certificate?
A26: According to BWM.2-Circ.40 certificates can already be issued but should be
annotated that they will become valid on 8-9-2017. BWM plans written in accordance
with resolution A.868(20) remain valid until the installation of a BWTS.
Page 5
Q31: What is a representative sample?
A31: Representative sampling reflects the relative concentrations and composition of the
populations (organisms and/or chemicals) in the volume of interest. Samples should be
taken in accordance with the annex, part 1 and/or part 2 of the Guidelines on ballast
water sampling (G2). – BWM.2/Circ.42
Publication
Human Envirionment and Transport
ILT/Shipping
PB 16191| 2500 BD Den Haag
T 088 489 00 00
July 2017
Page 6