ESTIMATE FOR STAIR MODIFICATION

UNIT ITEM QUANTITY UNIT PRICE TOTAL


pcs 12mm steel bar 35 175 6125
pcs 10mm steel bar 7 125 875
pcs 2"x3" tubular @ 6m 2 616.8 1233.6
pcs 1"x2" tubular@ 6m 3 329.62 988.86
pcs 2"x2" tubular @ 6m 1 448.8 448.8
pcs 1"x1" tubular@6m 8 298.2 2385.6
pcs 1 1/2"x 1 1/2" tubular @6m 2 343.2 686.4
pcs 3/4 thk. Marine plywood 13 1170 15210
pcs 3/4 thk. Phenolic board 7 1058 7406
pcs Epoxy Primer @4L 2 729 1458
bags Cement @50kg 21 235 4935
cu.m. mixed gravel and sand 4.335 1000 4335
bags adhesive 12 250 3000
box welding rod 1 2340 2340
pcs 90mmx150mm wood tiles 20 50 1000
pcs 30mmx60mm ceramic tiles 40 100 4000
bags tile grout 4 70 280
bottles paint lacquer 10 45 450
Liters boysen quick drying enamel (black) @4L 3 480 1440
liters boysen quick drying enamel (white) @4L 2 683 1366
pairs sliding guide for drawers 7 200 1400
pairs concealed hinges 3 55 165
roll tie wire #16 2 1400 2800
pcs cabinet handle 10 85 850
pcs sand paper #220 15 18 270
pcs sand paper #120 15 18 270
Liters fula-tite lacquer type 8 230 1840
liters wood stain 2 465 930
kilos common wire nail #1 2 89 178
Sub-total 68666.26

LABOR for 2 weeks of workforce


Skilled 3 7500 22500
laborer 2 5250 10500
welder 1 7200 7200
carpinter 1 6000 6000
Sub-total 46200
TOTAL 114866.26