PERT-CPM Sample
PERT-CPM Sample
DEPARTMENT OF AGRICULTURE
PHILIPPINE RURAL DEVELOPMENT PROGRAM
103(6) Pipe Culvert & Drain Excavation 1.04% 2,766.00 cu.m. 189.53 524,239.98
104 Embankment 5.70% 8,303.66 cu.m. 345.66 2,870,242.42
Prepared by:
MS. MA. LINA P. SANOGAL, MMPM, CES-E GOV. ALFREDO G. MARAÑON, JR.
PPMIU HEAD Governor
Name of Subproject: Rehabilitation of Brgy. Bug-ang to Sitio Vergara FMR
Location: Toboso, Negros Occidental
Breakdown of Subproject Cost
Labor
Item No Description Equipment Materials Direct Cost OCM
Skilled Unskilled Amount
100 Clearing & Grubbing 202,312.00 5,724.00 6,406.40 12,130.40 - 214,442.40 19,299.82
102(1) Surplus Common Excavation 1,575,952.00 17,690.88 19,801.60 37,492.48 - 1,613,444.48 145,210.00
103(1) Structure Excavation 35,072.00 1,040.64 1,164.80 2,205.44 - 37,277.44 3,354.97
103(6) Pipe Culvert Excavation 386,827.26 6,243.84 6,988.80 13,232.64 400,059.90 36,005.39
104 Embankment 810,466.56 10,926.72 12,230.40 23,157.12 1,356,679.49 2,190,303.17 197,127.28
105 Subgrade Preparation 496,552.00 7,284.48 8,153.60 15,438.08 511,990.08 46,079.11
201 Aggregate Base Course 893,081.92 25,545.92 35,380.80 60,926.72 6,089,422.50 7,043,431.14 633,908.80
311 PCCP 1,338,912.29 15,089.28 126,672.00 141,761.28 16,464,186.38 17,944,859.94 1,615,037.39
500(1) RCPC 188,971.20 19,104.00 26,208.00 45,312.00 703,277.57 937,560.77 84,380.47
505(5) GROUTED RIPRAP, CLASS A (Lined Canal) 166,071.68 218,982.40 385,054.08 2,753,355.00 3,138,409.08 282,456.82
506 Stone Masonry 20,800.00 19,200.00 40,000.00 852,554.00 892,554.00 80,329.86
603(3)a Concrete Barrier 1,463.04 7,641.60 6,988.80 14,630.40 15,000.00 31,093.44 2,798.41
Himuga-an River Overflow 122,278.40 74,711.36 288,288.00 362,999.36 2,054,135.00 2,539,412.76 228,547.15
Dalinson River Ford Slab 54,731.26 57,133.44 166,566.40 223,699.84 673,688.95 952,120.05 85,690.80
Total 6,106,619.94 435,007.84 943,032.00 1,378,039.84 30,962,298.88 38,446,958.65 3,460,226.28
Total Indirect
Estimated Direct Cost (EDC) Indirect Cost % for OCM & Profit Cost % for OCM
& Profit
Php OCM Profit
(% of EDC) (% of EDC)
Up to 5M 12 10 22
Above 5M up to 50M 9 8 17
Above 50M up to 150M 7 8 15
Above 150M 6 8 14
Contractor's
Taxes Total Cost
Profit
17,155.39 30,107.71 281,005.32
129,075.56 226,527.60 2,114,257.65
2,982.20 5,233.75 48,848.36
32,004.79 56,168.41 524,238.50
175,224.25 307,518.56 2,870,173.27
40,959.21 71,883.41 670,911.80
563,474.49 988,897.73 9,229,712.17
1,435,588.80 2,519,458.34 23,514,944.47
75,004.86 131,633.53 1,228,579.63
251,072.73 440,632.63 4,112,571.26
71,404.32 125,314.58 1,169,602.76
2,487.48 4,365.52 40,744.84
203,153.02 356,533.55 3,327,646.48
76,169.60 133,677.66 1,247,658.12
3,075,756.69 5,397,953.00 50,380,894.62
Name of Subproject: Rehabilitation of Brgy. Bug-ang to Sitio Vergara FMR
Location: Toboso, Negros Occidental
Project Implementation Schedule & S-Curve
No of Allow.
Days Bad
Item No Description Amount Unit Qty Unit Cost Per cent Relativ Det.EST. Weather No. of Wks Year
Month1 Month2
1 2 3 4 1 2
% 0.19% 0.19% 0.19%
100 Clearing and Grubbing 281,006.04 sq.m. 42,000 6.69 0.56% 11 4 3 P 100% 93668.68 93668.68 93668.68
A
% 95% 0.47% 0.47% 0.47%
102(2) Surplus Common Excavation 2,114,265.45 cu.m. 6,765.00 312.53 4.20% 34 10 9 P 234,918 234,918 234,918
A 90%
%
103(1) Structure Excavation 48,849.00 cu.m. 150.00 325.66 0.10% 2 1 1 P 85%
A
% 80%
103 (6) Pipe Culvert & Drain 524,239.98 cu.m. 2,766 189.53 1.04% 12 7 4 P
Excavation A 75%
%
104(1) Embankment 2,870,242.42 cu.m. 8,303.66 345.66 5.70% 30 10 8 P 70%
A
% 65%
105 Subgrade Preparation 671,144.04 sq.m. 32,564.00 20.61 1.33% 21 9 6 P
A 60%
%
201 Aggregate Base Course 9,229,747.80 cu.m. 8,610.00 1071.98 18.32% 31 9 8 P 55%
A
% 50%
311 Portland Cement Concrete 23,514,935.00 sq.m. 20,500.00 1147.07 46.67% 29 11 8 P
Pavement A 45%
%
500(1) Pipe Culvert 910mmØ 1,228,580.00 Lin.m. 235.00 5228.00 2.44% 15 9 5 P 40%
A
% 35%
505(5) Grouted Riprap & Class A 4,112,575.50 cu.m. 1,650 2492.47 8.16% 47 25 15 P
Canal Lining A 30%
%
506 Stone Masonry 1,169,603.30 cu.m. 370.00 3161.09 2.32% 16 10 6 P 25%
A
% 20%
603(3)a Metal Guardrail Including 40,744.75 lin.m. 25.00 1629.79 0.08% 6 4 2 P
Metal Post A 15%
%
Himuga-an River Overflow 3,327,646.48 lin.m. 70 47537.81 6.60% 63 35 20 P 10%
Rehabilitation A
% 5%
Dalinson River Ford Slab 1,247,658.12 lin.m. 30 41588.60 2.48% 23 15 8 P
Rehabilitation A 0%
50,381,237.88 1 2 3 4 5 6
0.71%
358780.3
0.33%
166382.32
7 8 9
1.87% 6.03%
2.89% 8.92%
939,673.53 3,040,324.04
1,455,597.96 4,495,922.00
0.00% 0.00%
0.00% 0.00%
- -
- -
Original Completion Date:
Scheduled Completion Date:
Project Duration: 224 Calendar Days
0.10%
48,849
0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54%
274171.7 274171.7 274171.7 274171.7 274171.7 274171.7 274171.7 274171.7 274171.7 274171.7 274171.7 274171.7 274171.7 274171.7 274171.7
0.04% 0.04%
20372.375 20372.375
0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33%
166382.32 166382.32 166382.32 166382.32 166382.32 166382.32 166382.32 166382.32 166382.32 166382.32 166382.32 166382.32 166382.32 166382.32 166382.32 166382.32 166382.32 166382.32 166382.32
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Equipment = 54,731.26
Materials = 673,688.95
per Lin.m.
PART - G. REHABILITATION OF EXISTING OVERFLOWS
ITEM NO.: B-2 UNIT: Cubic Meter
DESCRIPTION: TEMPORARY WATER DIVERSION STRUC QUANTITY: 75
122,278.40
Equipment =
74,711.36
Labor- Skilled = PROJECT DURATION:
288,288.00
- Unskilled = = 60 DAYS
2,054,135.00
Materials =
3,327,646.48
Total Project Cost =
47,537.81
Total Project Unit Cos =
per Lin.m.
PART - G. REHABILITATION OF EXISTING OVERFLOWS
Equipment Requirement
Boom Truck 1 26 10 3
DIRECT COST
Sub-Total 34,248.00
B. Labor:
Sub-Total 7,676.16
C. Materials:
C. Materials:
a. Sand Bag 3000 pcs. 8.00 24,000.00
b. Surplus Excavation 113 cu.m. -
Materials
Sub-Total 24,000.00
Materials Total -
Equipment Requirement
B. Labor:
C. Materials:
a. -
Materials Total -
Equipment Requirment
Type of No. of unit Quantites Equipment Activity
Equipment Required Output (m3/day) Duration (days)
Transit Mixer 2 4100.00 72 29
Pay Loader 1 4100.00 240 18
Water Truck 1 15
Conrete Vibrator 1 29
Concrete Screeder 2 29
Bar Cutter 1 2527.00 100 26
Conrete Saw 1 4100.00 272 16
Output
Item Description Equipment
Min.
100 Clearing and Grubbing Bulldozer 3200
Excavation Bulldozer
102
Compaction Road Roller 240
Embankment Payloader 240
104 Compaction Road Roller 240
Quarrying Bulldozer
Sub-grade Preparation Grader
105
Compaction Road Roller 240
Agg. Sub-Base Course Grader
200/201 Road Roller 240
Water Truck
Tractor-drawn cu.m./hr
Vibratory Rolling (6 passes – 2 cm lift) 240
Roller (1-D) cu.m./hr
Tander Roller Static Rolling 96 passes-20 cm lift) 24 cu.m./hr
5-T Dump truck Hauling Common Borrow 3.5 cu.m./hr
Hauling SEBC (Selected borrow,
basecourse) 5 cu.m./trip
TES
4000 sq.m./day
1600 sq.m./day
400 sq.m./day
200 sq.m./day
24 cu.m./day
2400 sq.m./day
400 cu.m./day
240 cu.m./day
280 cu.m./day
240 cu.m./day
360 cu.m./day
280 cu.m./day
192 cu.m./day
cu.m./day
1920
cu.m./day
192 cu.m./day
28 cu.m./day
24 cu.m./day
72 cu.m./day
8000 sq.m./day
240 cu.m./day
320 cu.m./day
100 kg./day
2009 ACEL RATES
(Minimum Operation = 8 hrs. per day)
11,628.16
6,052.16
15,931.76
17,724.16
10,148.16
13,196.16
16,716.16
11,388.16
9,564.16
5,027.20
7,852.16
Summary of Labor Rates
No. Designation Hourly Rate Daily Rate
1 Foreman 65.04 520.32
2 Highly Skilled Laborer 54.36 434.88
3 Skilled Laborer 47.08 376.64
4 Semi-Skilled Laborer 43.56 348.48
5 Part-time Safety Practitioner 75.00 600.00
6 First Aider 55.00 440.00
7 Unskilled Laborer 36.40 291.20
DPWH: PAY ITEM/MANPOWER REQUIREMENT
ITEM # DESCRIPTION UNIT
104a Embankment m3
Subgrade Preparation
Reinforcing Steel
404 kg.
(minor structure)
511a Gabions m3
511b Mattresses m3
Reflectorized Thermoplastic
612 m2
Pavement Marking
Danger/Warning Signs,
605(1) ea.
(60 cm. Triangle)
Danger/Warning Signs,
605(1) ea.
(90 cm. Triangle)
Regulatory Signs,
605(2) ea.
(60 cm. Triangle)
Regulatory Signs,
605(2) (90 cm. ea.
Triangle)
Regulatory Signs,
605(2) (60 cm. ea.
Octagon)
Regulatory Signs,
605(2) ea.
(90 cm. Octagon)
Informative Signs,
605(3) ea.
(12" x 24")
Informative Signs,
605(3) ea.
(12" x 48")
Informative Signs,
605(3) ea.
(12" x 48")
Informative Signs,
605(3) ea.
(18" x 24")
Informative Signs,
605(3) ea.
(18" x 48")
Reflectorized Thermoplastic
612(1) m²
Pavement Marking (white)
Reflectorized Thermoplastic
612(1) m²
Pavement Marking (white)
Reflectorized Thermoplastic
612(2) m²
Pavement Marking (yellow)
0.39 kgs - Reinforcing Steel Bars 4 - Transit Mixer (5 cu.m. cap.) 1 - Foreman
0.12 lit - Asphalt Sealant 1 - Batching Plant (30 cu.m. cap.) 12 - Unskilled
0.39 kgs - Reinforcing Steel Bars 1 - Batching Plant (50 cu.m./hr.) 1 - Foreman
8 - Unskilled
Minor Structure 9.5 1 - One Bagger Mixer 1 - Foreman
c,s,g = 9.50, 0.5, 1 1 - Concrete vibrator 4 - Skilled
Lumber = 45 bd.ft./cu.m. 0.10 - Water Truck 8 - Unskilled
Plywood = ½”x4’x8’ - 0.64 pc.
1 l.m. - RCPC (24" dia.) - 610 mm Minor Tools (10% of Labor) 4 - Laborer
1 l.m. - RCPC (30" dia.) - 760 mm Minor Tools (10% of Labor) 4 - Laborer
1 l.m. - RCPC (36" dia.) - 910 mm Minor Tools (10% of Labor) 4 - Laborer
500
60
80
20
50
300
50
50
50
50
0.30 m.t./hr.
0.30 m.t./hr.
171.30 sq.m./hr. or
20 m.t./hr.
171.30 sq.m./hr. or
20 m.t./hr.
70.00 sq.m./hr.
174
174
6 l.m./hr.
4 l.m./hr.
144 kgs./man-day
1.40 cu.m./hr.
18 l.m./day
16 l.m./day
14 l.m./day
12 l.m./day
10 l.m./day
8 l.m./day
1 cu.m./man-day
1.25 cu.m./man-day
0.15 cu.m./man-hour
10 l.m./hr.
2.0 cu.m./man-day
2.5 cu.m./man-day
25 sq.m./hr.
18.40 l.m./hr.
11.25 l.m./hr.
4.20 l.m./hr.
6.00 ea./hr.
1 - ea./hr.
1 - ea./hr.
1 - ea./hr.
1 - ea./hr.
1 - ea./hr.
1 - ea./hr.
1 - ea./hr.
1 - ea./hr.
1 - ea./hr.
1 - ea./hr.
1 - ea./hr.
1 - ea./hr.
1 - ea./hr.
10.00 m²/hr.
25.00 m²/hr.
25.00 m²/hr.
25.00 m²/hr.
1.00 pc./hr.
REQUIRED IN THE CALCULATION OF CYCLE TIME
PAVED 35 55
FLAT
UNPAVE
30 45
D
PAVED 30 40
ROLLING UNPAVE
25 30
D
PAVED 20 30
MOUNTAINOUS UNPAVE
15 25
D
LOADING TIME (min.) 3 Mins.
Unload and
= 2 minutes
Maneuver
Hauling
No. Description Unit Unit Price Total Price Remarks
Cost
1 Portland Cement bag 250.00 36.00 286.00
2 Sand cu.m. 1,200.00 602.00 1,802.00
3 Gravel cu.m. 1,800.00 602.00 2,402.00
4 Agg. Subbase Course cu.m. 400.00 100.00 500.00
5 Natural Gravel cu.m. 1,300.00 602.00 1,902.00
6 Granular Materials cu.m. 520.00 520.00
7 RSB, Grade 40 kg. 50.00 2.50 52.50
8 RSB, Grade 60 kg. 55.00 2.50 57.50
9 Tie Wire, #16 kg. 54.00 54.00
10 Boulders (Rock Class "A") cu.m. 1,300.00 970.00 2,270.00
11 PVC Pipe, 2" Ø l.m. 100.00 100.00
12 RCPC, 910mm Ø pc. 3,800.00 3,800.00
13 Steel Forms l.m. 200.00 200.00
14 Curing Compound liter 150.00 150.00
15 Asphalt Sealant liter 120.00 120.00
16 Form Lumber, Coco bd.ft. 20.00 20.00
17 Good Lumber, False Work bd.ft. 40.00 40.00
18 Yakal Lumber bd.ft. 50.00 50.00
19 Marine Plywood, 4'x8'x1/2" pc. 650.00 650.00
20 Ordinary Plywood, 4'x8'x1/2" pc. 580.00 580.00
21 CW Nails, Assorted kg. 70.00 70.00
22 Tarpauline (Printed), 4'x8' pc. 980.00 980.00
23 Embankment Matrls., Selctd Borrow cu.m. 350.00 350.00
24 Coco Trunk/Log l.m. 83.00 83.00
25 Pile Shoe pc. 2,200.00 2,200.00
26 Filter Cloth sq.m. 450.00 450.00
27 Precast RC Piles (450mx450m) l.m. 4,500.00 4,500.00
28 Steel Sheet Piles kg. 120.00 120.00
29 Premolded Expansion Joint Filler sq.m. 900.00 900.00
30 Welding Rod kg. 80.00 80.00
31 Structural Steel kg. 65.00 65.00