Weekly Report - 4 PDF

The weekly progress report summarizes construction of the Daraz store in Mahalaxmisthan, Lalitpur. Key updates include: the truss structure is on schedule to be completed as planned; rebar work for the first floor slab is finished in Lalitpur; wall work is ongoing in Hub using diagonal struts for strength; and steel staircase, toilet truss, drain works, and wall plastering are all in progress. Recommendations are provided to address seepage in walls and add gutters and water resistant plastering.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
49 views10 pages

Weekly Report - 4 PDF

The weekly progress report summarizes construction of the Daraz store in Mahalaxmisthan, Lalitpur. Key updates include: the truss structure is on schedule to be completed as planned; rebar work for the first floor slab is finished in Lalitpur; wall work is ongoing in Hub using diagonal struts for strength; and steel staircase, toilet truss, drain works, and wall plastering are all in progress. Recommendations are provided to address seepage in walls and add gutters and water resistant plastering.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

Weekly Progress Report :

Name of project : Daraz store construction


Site Visit : 20th ,22nd and 23rd and 25th September
Location : Mahalaxmisthan, Lalitpur
Report Prepared By : Interface Engineering

This Progress report includes weekly construction progress as well as status of


individual tasks and the work performed in the construction project site.

PROJECT OVERVIEW :
The construction of the truss structure is expected to end as per scheduled
date,subject to changes in plan.
The construction works are continuously working as per the plan.
CONSTRUCTION PROJECT SCHEDULE:

Lalitpur slab reinforcement going on.


Hub Wall work going on.
Diagonal strut used in wall .
Good for strength of truss structure
Base P.P.C completed

sheet work and truss work completed.

Fig : First Floor rebar work done.Ready for concrete work


Fig :Wall work done with diagonal strut

Fig :Wall work


Wall Works : Laying of wall being performed
STAIRCASE WORK :

Steel staircase Work being done


Toilet Work :

Truss part for toilet beside Lalitpur Hub.


Truss Part completed.
Laying of wall in the toilet behind the load bearing building.
Drain Works

Recommendation and suggestion:


 Seepage seen in the wall .
 Gutter required in the truss structure.
 Plaster with water resistant material on both sides of wall required.
Main store structure :

Colouring of wall is on the process .(Wall putty)


Double coat required for better finishing
Wall work around the truss structure is complected.
Coloring works going on.
Shutter Works going on .