1.3 MSP Risk Tutorial - 2. Progress Wizard: Task Existence
1.3 MSP Risk Tutorial - 2. Progress Wizard: Task Existence
Task Existence
After "Strip off roof cover" we believe there is a 15% chance of finding rotten supports. Task Existence
can be used to model this uncertainty. During the risk analysis the "Rotten Supports" task will appear
15% of the time. When it appears it will have an impact on the project finish and cost.
Figure The value "15" indicates the % chance of the task occuring.
Costs
Each task has a remaining cost. This cost is used by Primavera Risk Analysis to model the cost
uncertainty. During the risk analysis the cost of a task is increased or reduced proportionally with its
duration. Probabilistic tasks will have a zero remaining cost for the iterations they do not exist.
Great. All the risk data has been entered. We will now look at the Progress Wizard.
We will use the Progress Wizard to identify this task and any others that may not be progressed in line
with the Status Date.
Click on the tool bar button to start the Wizard, or use the menu command Primavera Risk
Analysis | Progress Wizard.
Click OK to save any unsaved changes if prompted.
Click Next to move to Setting the Status Date .
Primavera Risk Analysis for MS Project | 5
Figure: Options for adjusting "Erect Scaffold" which is completed but it is ahead of the Status Date.
The task 'Erect Scaffold' has been completed so it should not be delaying any of the succeeding tasks that
are scheduled in the future after the Status Date. To correct this we will use the Move actual dates to
before status date to schedule the task behind the Status Date.
Select the option Move actual dates to before status date.
Click Next. This will find the next task. As there are no more progress problems the Wizard finishes:
Primavera Risk Analysis for MS Project | 6
Figure: Wizard finishes and displays the finish date difference and with the option to display the
changes made to each task.
Click Finish to complete the Wizard.
1.4 MSP Risk Tutorial - 3. Opening MS Project file in Primavera Risk Analysis
Our project has 3 point estimates for the durations and we have also included some additional information
to model probabilistic tasks and duration correlation.
We will now open the file in Primavera Risk Analysis ready for the risk analysis.
Click OK in the Microsoft Project Import Mappings dialog to accept the default mappings.
After file has opened in Primavera Risk Analysis click Save when prompted.
Click on the Gantt Chart tab.
The project should look something like this in Primavera Risk Analysis:
Primavera Risk Analysis for MS Project | 8
Notes
The Import Check tab displays Start Check and Finish Check columns that display any differences
between the MSP and Primavera Risk Analysis schedule. Check the columns for any differences - there
maybe differences of a day for milestones or zero duration activities - these will not affect the results.
On the MSP Import Check sheet the grey bars display the Start Check and Finish Check graphically.
The grey bars are the MSP schedule and the bars above them are the Primavera Risk Analysis
schedule.
After opening the MS Project project in Primavera Risk Analysis a risk analysis can be run.