Construction Guidelines - SMGS
Construction Guidelines - SMGS
Construction Guidelines - SMGS
MANAGEMENT CORP.
____________________________________________________________________
TOC1
Part 1
Pre - Construction
Architectural
Electrical
Mechanical (aircon, sprinkler, exhaust)
Details of signage
Structural load computation (if any)
Plumbing/sanitary (if any )
2. Once plans are approved, LESSEE must obtain the following and submit
to the MALL ADMINISTRATION OFFICE:
A. Building Permit from Building Official, City Hall submitting:
Five (5) sets of SM - EDD approved plans
Five (5) sets of duly completed application form
Five (5) sets of specifications writing and detailed bill of materials.
Electrical Wiring Permit
Sanitary / Plumbing Permit (for water connection)
Water sub-meter with MWSS certificate of calibration.
Meter can be purchased from MWSS or hardware store.
1-1
Part 1: Pre - Construction
A . BASIC PERMIT TO CONSTRUCT shall only be issued by SCMC
REQUIREMENTS ADMINISTRATION upon submission of ALL requirements.
TO BE SUBMITTED,
continued
1-2
Part 1: Pre - Construction
C. POST 7. LESSEE shall request in writing to SCMC ADMINISTRATION for FINAL
CONSTRUCTION / INSPECTION of the construction which should be scheduled at least three (3)
PRE - OPERATION, days before the intended store opening.
continued
8. LESSOR has the right to restrain store opening depending upon the
degree of deficiencies stipulated in the final inspection report.
D. PHYSICAL 1. Floor - concrete floor designed to carry a maximum load of 60 lbs./sq ft.
CONDITION OF with rough cement finish.
LEASED PREMISES
2. Wall Partition and Ceiling - must be fitted with double wall board partition
made of non-combustible materials. (Examples are Gypsum Board, Viroc Board
and FiCem). For restaurants, LESSEE shall be required to put CHB from floor
to slab soffits and fire bricks For all surrounding walls of cooking area.
4. Storefront - none
1-3
Part 1: Pre - Construction
Part 2
Drawing Submission & Approval
INTRODUCTION LESSOR’s approval of Design and Working Drawing is required before LESSEE
can start construction. It is understood that all comments, corrections and
notations made by LESSOR on Working Drawings are deemed acceptable,
approved, and have to be
implemented by the LESSEE.
A. DESIGN DRAWINGS 1. LESSEE shall submit to Mall Administration eight (8) sets of Design and
Working Drawings for review and approval.
2. LESSOR shall return to LESSEE two (2) sets of APPROVED plans. One copy
to be kept at job site.
B. WORKING LESSEES are required to visit actual site and take actual measurements
DRAWINGS (Scale PRIOR to preparation of plans.
1:50 m at 20 “ x 30 “)
2-1
Part 2 : Drawing Submission & Approval
Part 3
Construction
INTRODUCTION LESSEE shall improve the leased premises following the latest trends in
shopping center development , using the most modern facilities that
will give the feeling of elegance and spaciousness to the consumers. This
will serve as an integration of various sections into a unified concept while
at the same time, each space maintaining its own character and Identity.
GENERAL PROVISIONS 1. All works shall be in accordance with the latest government regulations,
Building Code, Fire Code, Electrical and Mechanical Codes, and other codes
being implemented by other approving bodies.
2. All corrections and additional notations on the plans shall be followed. Any
deviation from the approved plan shall have special approval by the
Administration office/SM EDD.
3. During construction and before the store can open, Administration office
shall inspect the construction works of the lessee. All deviations from the
approved shall be asked to redo.
4. Damages done but not limited to existing utilities, viroc wall partitions,
neutral piers, aircon fascia, and common area, by the lessee, whether
accidental of intentional, shall be repaired by Administration office and
corresponding expenses shall be charged to lessee.
5. Hangers and supports of lessee’s ceiling and utilities (pipes, ducts, etc.)
shall not be attached or anchored to the mall’s existing utilities and
concrete beams or columns. Lessee shall attach their hangers only to
concrete slab soffits.
6. Do not cover or block the return air passages and grills of aircon system.
8. All approved plans shall be present at the work site at all times.
BASIC REQUIREMENTS All works shall be in accordance with the latest government regulations,
Building Code, Fire Code, Electrical and Mechanical Codes, and other codes
being implemented by other approving bodies.
All corrections and additional notations on the plans shall be followed. Any
deviation from the approved plan shall have special approval by the Admin -
istration office/SM EDD.
During construction and before the store can open, Administration office
shall inspect the construction works of the lessee. All deviations from the
approved shall be asked to redo.
Damages done but not limited to existing utilities, viroc wall partitions,
neutral piers, aircon fascia, and common area, by the lessee, whether
accidental of intentional, shall be repaired by Administration office and
corresponding expenses shall be charged to lessee.
Hangers and supports of lessee’s ceiling and utilities (pipes, ducts, etc.)
shall not be attached or anchored to the mall’s existing utilities and
concrete beams or columns. Lessee shall attach their hangers only to
concrete slab soffits.
Do not cover or block the return air passages and grills of aircon system.
All approved plans shall be present at the work site at all times.
LESSEES are required to visit actual site and take actual measurements PRIOR
to preparation of plans.
4-1
Part 4 : Aircondition Guidelines
Air Conditioning Plan
Main duct
REFLECTED CEILING Plan showing coordination of supply air diffusers and return air.
4-2
Part 4 : Aircondition Guidelines
CONTROL SCHEMATIC For all fan coil units, complete with specification of all major components.
Indicate sizing information (C V) for all control valves.
COOLING LOAD ESTIMA- For each air conditioned area submit a completed “Cooling Load Estimation
TION DATA Data” form.
4-3
Part 4 : Aircondition Guidelines
Facilities Connection
4-4
Part 4 : Aircondition Guidelines
Air Conditioning Design Criteria
FOR TENANTS WITH Tap only to the side of the nearest branch provision, bottom tapping is
AIRCON DUCT not allowed. Do not tap to duct elbows and duct reducers.
PROVISION
Tapping to the main ducts shall be at 45° takeoff and properly sealed.
All duct works must be provided with complete insulation and G.I. corner
beads.
Install duct hanger fro every duct bend, drop collar, and for every two(2)
meters run of duct. Install trapeze type of duct hanger made of 10mm
dia, round bar and 25mm x 25mm x 5mm angular bar catch support.
Provide mechanical clips or plastic straps for every meter run of ducts.
All flexible duct shall be installed in strict compliance with SMACNA guide-
lines and suspended to prevent kinks and air blockage.
Where flexible duct is used to connect to supply air diffusers , the connec-
tion shall be made to a hard sheet-metal colar to prevent kinking.
4-5
Part 4 : Aircondition Guidelines
FOR TENANTS WITH All branch ducts (and taps to existing main ducts) shall be properly sealed
AIRCON DUCT to prevent air leakage in excess of that required by SMACNA Leakage
PROVISION, Class C with CL=24 CFM/100FT2 at 1.0 INWG.
continued
All branch ducts shall be adequately insulated to prevent condensation and
water damage to the spaces through which they pass. All insulation used
shall conform to local code requirements for flame spread and smoke
density but shall not exceed a Flame Spread Index of 25 or a smoke
density of 50 when tested as a composite installation including
insulation, facing materials, tapes and adhesives as applied.
FOR TENANTS WITH Taps for chilled water (supply and return) branch lines shall be provided
CHILLED WATER with isolation valves located at the connection point.
PROVISION
FCU installed above ceiling or concealed type shall be provided with air
return plenum ducts with ceiling type grills.
FCU should not be installed near exhaust system or directly above the
kitchen cooking area.
Provide condense drain pipe to all FCU with minimum size of 25mm,
with p-traps and shall be terminated in condense drain stub out through
an indirect connection (air gap) and with insulation.
All chilled water (supply and return) branch lines shall be adequately
insulated to prevent condensation and water damage to the spaces
through which they pass (same flame spread index and smoke density
limitations as item #10 above).
All Fan Coil Units (FCU) shall be installed with 2-way control valves
properly sized for the C V corresponding to the flow they serve and a wide
open pressure drop of 10FTWG.
Chilled water strainers and maximum flow limiting valves are not required
and not encouraged
4-6
Part 4 : Aircondition Guidelines
FOR TENANTS WITH Condensers and other heat emitting equipment shall be installed
SPLIT TYPE AIR CON outside the building on an approved location by SM.
SYSTEM
Piping layout should be tightly sealed with rubber insulation and
wrapped with blue polyethylene tape. Boring of holes for the piping layout
shall be approved by SM.
NOTE The Lessee will provide an exhaust air system for all comfort rooms.
Exhaust air quantities shall be in accordance with local codes but shall not
be less than 50 CFM per water closet or urinal.
All Food, Medical Clinic, Petshops, Internet Cafes, Spa and Wellness
Centers, and Hair Salon Tenants shall supply and install its own fan Coil
Unit (FCU). The Lessor shall provide the chilled water line stub-out .
4-7
Part 4 : Aircondition Guidelines
Testing & Commissioning
INTRODUCTION Upon completion of the work, and before acceptance by SM, Lessee’s
Mechanical contractor will submit a “Certificate of Commissioning” for
all air conditioning systems. Lessor shall have the right to witness any or all of
the final measurements shown in the certificate of commissioning. The certifi-
cate of commissioning shall include at least the following items (‘Final” readings
after all balancing adjustments have been made)
SMOKE TESTING Conduct smoke test of ductworks prior to tapping to main duct and installation
of insulation
AIR CONDITIONING Static and total air pressure in the Lessee’s ductwork for each point connection
FROM THE CENTRAL AIR to the AC supply air main ducts.
SYSTEM Measured air flow at each supply diffuser (Air Balancing)
AIR CONDITIONING BY Chilled water pressure entering and leaving each fan coil unit
FAN COILS SERVED BY
THE CHILLED WATER Chilled water temperature entering and leaving each fan coil unit
SYSTEM
Temperature of supply air leaving each fan coil unit
For ducted systems- measured air flow at each supply air diffuser and static
and total air pressure at the discharge of the fan coil unit
For free blow systems – measured air flow at each fan coil unit
4-8
Part 4 : Aircondition Guidelines
Part 5
Architectural Guidelines
BASIC REQUIREMENTS All works shall be in accordance with the latest government regulations,
Building Code, Fire Code, Electrical and Mechanical Codes, and other codes
being implemented by other approving bodies.
All corrections and additional notations on the plans shall be followed. Any
deviation from the approved plan shall have special approval by the
Administration office/SM EDD.
During construction and before the store can open, Administration office
shall inspect the construction works of the lessee. All deviations from the
approved shall be asked to redo.
Damages done but not limited to existing utilities, viroc wall partitions,
neutral piers, aircon fascia, and common area, by the lessee, whether
accidental of intentional, shall be repaired by Administration office and
corresponding expenses shall be charged to lessee.
Hangers and supports of lessee’s ceiling and utilities (pipes, ducts, etc.)
shall not be attached or anchored to the mall’s existing utilities and
concrete beams or columns. Lessee shall attach their hangers only to
concrete slab soffits.
Do not cover or block the return air passages and grills of aircon system.
All approved plans shall be present at the work site at all times.
LESSEES are required to visit actual site and take actual measurements
PRIOR to preparation of plans.
5-1
Part 5 : Architectural Guidelines
Architectural & Structural Plans
ARCHITECTURAL Key plan showing perspective of storefront, location of premises within the
DRAWINGS Shopping Center.
Floor Plan
Note: Food Tenants with dining area and with a leased area of at least 80 sq.
m. should provide rest room for their customers’ use.
5-2
Part 5 : Architectural Guidelines
Architectural Design Criteria
SIGNAGE A. GENERAL
Text of main signage shall be limited to store’s trade name. Additional
wordings must be behind glass panels.
B. SIGNAGES
Signage width should not exceed 50% of shop front and can be of any
dimension and location within the store front. FULL-WIDTH SIGNAGE
BAND is not allowed.
D. PROHIBITED SIGNAGES
5-3
Part 5 : Architectural Guidelines
FOR ENTRANCE DOOR The tenant has the option to the determine their shop front entrance
AND GLASS PANELS width. Minimum - 1.00m, maximum = 50% of the shop front width.
Lessee using roll-up doors shall have a minimum height opening of 3.00
meters.
SM reserves the right to approve the design and construction of all shops.
5-4
Part 5 : Architectural Guidelines
FOR CEILING Ceiling should have a minimum of 3.00m clear for all floors, except for
Cyberzone area (Refer to Cyberzone design criteria). The retail ceiling
must be conceived as a three dimensional component of the shop design,
not just a flat surface.
If the tenant wish to expose the ceiling structure within their leased space,
written approval must be obtained and all visible elements must be
painted.
Install firebricks on the kitchen walls from floor line to ceiling line.
FOR WALLS Do not make any attachment to existing viroc wall partitions. Construct
double wall
Install firebricks on the kitchen walls from floor line to ceiling line.
5-5
Part 5 : Architectural Guidelines
FOR FLOORING Use natural stone terrazo, commercial quality ceramic tiles, reconstituted
stone finishes, wood parquet, laminated flooring, carpet or marble flooring
and all materials indicated, specified or necessary for a complete and finish
installation.
The store’s flooring shall be of the same level as that of the mall’s flooring.
Provide 3 to 5 mm aluminum strip at mall tile and shop front tile
termination.
Chipping on floor slab is not allowed. Pipes shall not be embedded in the
floor slab.
For drainage outlets, use drills to bore a hole. Uses of hammers exceeding
8lbs. are not allowed.
For mall drainage stubouts or cleanouts that are located inside a tenant’s
premises, said drainage cleanouts & stub outs shall not be sealed or
covered with tiles or floor finish. The removable cover of the
stubouts/cleanouts shall be exposed.
Install gauge 10 or bigger steel matting at storefront above the ceiling for
security reasons.
5-6
Part 5 : Architectural Guidelines
Part 6
Electrical Guidelines
BASIC REQUIREMENTS All works shall be in accordance with the latest government regulations,
Building Code, Fire Code, Electrical and Mechanical Codes, and other codes
being implemented by other approving bodies.
All corrections and additional notations on the plans shall be followed. Any
deviation from the approved plan shall have special approval by the
Administration office/SM EDD.
During construction and before the store can open, Administration office
shall inspect the construction works of the lessee. All deviations from the
approved shall be asked to redo.
Damages done but not limited to existing utilities, viroc wall partitions,
neutral piers, aircon fascia, and common area, by the lessee, whether
accidental of intentional, shall be repaired by Administration office and
corresponding expenses shall be charged to lessee.
Hangers and supports of lessee’s ceiling and utilities (pipes, ducts, etc.)
shall not be attached or anchored to the mall’s existing utilities and
concrete beams or columns. Lessee shall attach their hangers only to
concrete slab soffits.
The return air passages and grills of air-con system shall not be covered or
blocked (for Non-food tenants).
The stubouts (cleanouts, water source, exhaust, sewer, drainage, etc) shall
be accessible and free from obstructions.
All approved plans shall be present at the work site at all times.
6-1
Part 6 : Electrical Guidelines
Electrical Drawings
Schedule of load
Power layout
Lighting layout
Specifications
Legend
The main power supply to the tenant space tapped to temporary wirings
ELECTRICAL GUIDELINES shall be 3.5mm2 THHN stranded. Tapping shall be supervised by
FOR TEMPORARY POWER engineering personnel.
OF MALL TENANTS
Sizes of the main power shall be determined by the following:
1. If the tenant contractor shall only utilize lighting and portable
electrical equipment (excluding welding machine), the main power
supply of temporary power shall be 3.5 mm2 THHN stranded with
grounding and protected with 30 AT,1-pole,1-phase Circuit Breaker.
2. If the tenant contractor shall be using welding machine, the main
power supply shall be 14 mm2 THHN stranded protected with 30
AT,1-pole,1-phase Circuit Breaker.
The Lessor shall provide a temporary calibrated kWHR meter with seal .
The main power supply connections for temporary power shall be removed
upon completion of the project or if the permanent power supply will be
made available and properly metered.
6-2
Part 6 : Electrical Guidelines
Electrical Load Requirement for ( 400 / 230 volts Electrical System)
A. Plan Submittal
REQUIREMENTS Plan Submittal (Complete with):
Facilities Connection
REQUIREMENTS SM (Lessor) will provide Main breaker & kWHR meter for
basic electrical feeder line provision from main tapping point
upto the pullbox in the Tenant (Lessee) area.
6-3
Part 6 : Electrical Guidelines
Electrical Design Criteria
CONNECTED LOAD Actual load should not exceed 80% of the rating of the over current
device and ampacity of the cable.
Use high temperature rating THHN wire and shall be in RSC, IMC or
CONDUCTORS / WIRES EMT conduit.*
& CONDUIT Minimum size of wire shall be 3.5 mm2 THHN stranded.
Installation of Flat cord, BX wire and PVC conduit shall not be permitted.**
Cover all junction boxes and pull boxes. Complete pipe fittings : locknut
bushings among others shall be provided on junction boxes and pull boxes.
For Kiosk and Carts, individual electrical branch circuits – 30AT, 1 Phase
shall be provided. Minimum size of wire shall be 5.5 mm2 THHN
stranded.
For Tenant below the escalators, electrical branch circuit – 60AT, 1 Phase
shall be provided. Minimum size of wire shall be 14 mm2 THHN
stranded.
Notes:
*flexible conduit with maximum length of 300 mm shall be permitted.
** PVC shall be used for communication installation.
PANEL BOARD Should be bolt-on type.
Number of overcurrent device should not exceed more than 42-poles and
construction shall conform to code standards.
Bus bar shall be sized and cut based on standard ampacity. Crimping of
bus bar shall not be permitted.
Breakers with ground fault circuit interrupter (GFCI) shall be used for
branch circuits serving power outlets for comfort rooms, cooking equipment
and outdoor electrical loads and signages.
6-4
Part 6 : Electrical Guidelines
Wiring Details (1 Phase Load)
WIRING DETAILS For lighting & power - use 230V,60hz lie neutral + ground.
MOTOR CONTROL Use magnetic starter or solid state soft starter. For magnetic starter, use
110V coil voltage contactors w/ a 380V /110V control transformer.
DEVICES All sockets & convenience outlet shall be 3-prong ( for hot, neutral &
ground Wire).
Use wall outlet with ground fault circuit interrupter (GFCI) in lieu of branch
circuit with no GFCI .
All lighting fixtures should be provided with ground wire. Branch circuit
should be protected with GFCI.
SWITCH/ All convenience outlet shall be 3-prong ( for line, neutral & ground).
CONVENIENCE OUTLETS
Use wall outlet with ground fault circuit interrupter (GFCI) - for Comfort
Rooms ,cooking equipment, outdoor load & signages.
LIGHTING FIXTURES Wiring of lighting fixtures shall be line to neutral with ground wire.
Fluorescent Lamp shall have high power factor ballast and shall be in a
metal box enclosure.
Enclosure shall be properly grounded.
The LESEE shall provide at least one (1) low wattage light (night lighting)
with a dedicated branch circuit. This shall be switched-on after mall
operation and normally off during mall operation.
6-5
Part 6 : Electrical Guidelines
NIGHT/PILOT LIGHT Provide at least one (1) low wattage light with a dedicated branch circuit .
GROUNDING Provide an isolated neutral bus in each panel for connection of circuit
neutral conductors.
Provide a separate ground bus marked with green stripe along its front
and bonded to steel for connecting grounding conductors.
FILLING UP OF RETAIL Tenant must provide the necessary electrical requirements by answering
DESIGN MANAGEMENT The Retail Design Management Questionnaire (please refer to 6-7 to 6-8)
QUESTIONNAIRE for SM to make the necessary appropriation.
6-6
Part 6 : Electrical Guidelines
SHOPPING CENTER
MANAGEMENT CORP.
Kindly complete the following questionnaire and return it with your FINAL Drawing submission.
SCMC shall provide each Non Food tenant the following basic feeder line:
SCMC shall provide each Food tenant the following basic feeder line:
100 AT, (3) Phase, 400 V, 60 Hz 5-wires (3-line, neutral & ground)
1. Power Supply
Please check the appropriate answer:
___ We require additional power supply at: ___ Amps
___ Single Phase
___ Three Phase
___ We accept the power supply to be provided for our shop.
2. Lighting Load
6-7
Part 6 : Electrical Guidelines
3. Electrical Heat Load
Submitted by:
________________________________________ _________________________________________
Tenant Representative Designation
Pls print and sign
6-8
Part 6 : Electrical Guidelines
Testing & Commissioning
BALANCING OF LOAD
NOTE All electrical works shall be under the direct supervision of duly Registered
Master Electrician (RME) or Registered Electrical Engineer (REE).
Engineering Personnel, who will interpret and evaluate the drawings and
specifications, shall have the power to reject any work and material which
in their judgment are not in full accordance therewith.
6-9
Part 6 : Electrical Guidelines
Part 7
Kitchen & LPG Guidelines
BASIC REQUIREMENTS All works shall be in accordance with the latest government regulations,
Building Code, Fire Code, Electrical and Mechanical Codes, and other codes
being implemented by other approving bodies.
All corrections and additional notations on the plans shall be followed. Any
deviation from the approved plan shall have special approval by the
Administration office/SM EDD.
During construction and before the store can open, Administration office
shall inspect the construction works of the lessee. All deviations from the
approved shall be asked to redo.
Damages done but not limited to existing utilities, viroc wall partitions,
neutral piers, aircon fascia, and common area, by the lessee, whether
accidental of intentional, shall be repaired by Administration office and
corresponding expenses shall be charged to lessee.
Hangers and supports of lessee’s ceiling and utilities (pipes, ducts, etc.)
shall not be attached or anchored to the mall’s existing utilities and
concrete beams or columns. Lessee shall attach their hangers only to
concrete slab soffits.
Do not cover or block the return air passages and grills of aircon system.
All approved plans shall be present at the work site at all times.
LESSEES are required to visit actual site and take actual measurements
PRIOR to preparation of plans.
7-1
Part 7 : Kitchen & LPG Guidelines
Kitchen General Guidelines
REQUIREMENTS Provide CHB and fire bricks / fire insulation (from floor to slab) of all
surrounding walls of cooking equipment.
7-2
Part 7 : Kitchen & LPG Guidelines
Centralized Gas System Facilities Connection
REQUIREMENTS A centralized gas system is installed by the LESSOR. All food LESSEE who
will use gas for their cooking shall tap to the system through a stubout
provided by the LESSOR.
LESSOR shall provide the gas meter through the mall’s gas contractor. Gas
meter shall be installed simultaneously with the tapping of LESSEE’s
system to the mall’s. Coordinate with SCMC Administration Office on the
schedule of Tapping.
7-3
Part 7 : Kitchen & LPG Guidelines
Centralized Gas System Design Criteria
REQUIREMENTS All pipeline joints shall be full welded except for thread and flange connec -
tions such as ball valves meters, regulators, etc.
Provide rigid supports for every pipe bend and for every meter run of pipe.
Brackets shall be installed with a minimum distance of 3 meters or as per
required.
Do not use rubber hose for connection to cooking equipment. Use heavy-
duty hose or metal braided hose rated at 300 psi.
Branch outlets shall be not lower than 60 cm from the floor finish.
Gas hoses or flexible connectors shall not sag more than 10 cm.
Painting of gas line - QDE Paint – two (2) coats. Lemon Yellow on
Pipes,Black on Pipe Support, PRIMER – Two (2) coats.
7-4
Part 7 : Kitchen & LPG Guidelines
Testing & Commissioning
st
Leak test pipeline before 1 regulator manifold at 150 psig for a minimum
st
period of 12 hrs. and 100 psig after 1 stage regulator manifold for a
minimum period of 2 hrs. using nitrogen. Submit certificate of leak testing
from LPG pipeline contractor/installer.
LESSEE shall not be allowed to open without their gas system undergoing
leak testing and a certificate submitted to SCMC Administration Office.
7-5
Part 7 : Kitchen & LPG Guidelines
Part 8
Sanitary & Plumbing Guidelines
BASIC REQUIREMENTS All works shall be in accordance with the latest government regulations,
Building Code, Fire Code, Electrical and Mechanical Codes, and other codes
being implemented by other approving bodies.
All corrections and additional notations on the plans shall be followed. Any
deviation from the approved plan shall have special approval by the
Administration office/SM EDD.
During construction and before the store can open, Administration office
shall inspect the construction works of the lessee. All deviations from the
approved shall be asked to redo.
Damages done but not limited to existing utilities, viroc wall partitions,
neutral piers, aircon fascia, and common area, by the lessee, whether
accidental of intentional, shall be repaired by Administration office and
corresponding expenses shall be charged to lessee.
Hangers and supports of lessee’s ceiling and utilities (pipes, ducts, etc.)
shall not be attached or anchored to the mall’s existing utilities and
concrete beams or columns. Lessee shall attach their hangers only to
concrete slab soffits.
Do not cover or block the return air passages and grills of aircon system.
All approved plans shall be present at the work site at all times.
LESSEES are required to visit actual site and take actual measurements
PRIOR to preparation of plans.
8-1
Part 8 : Sanitary & Plumbing Guidelines
Plumbing Plan
PLAN VIEW (SHOWING) Design that includes Length of Pipe and specifications.
Legend
8-2
Part 8 : Sanitary & Plumbing Guidelines
Plumbing / Sanitary Design Criteria
REQUIREMENTS Lessee’s sanitary system, vent and domestic water piping should conform
to all local requirements and code standards.
Check stub-out provisions (potable water line, vent, kitchen waste and
domestic waste ) on-site before preparation of drawing plans.
Use G.I. Schedule 40 pipe or Zero leak fusion type pipe for cold water
line. Indicate on the plan location of water meter.
Provide Grease Traps for every sinks with the following specs:
A) The grease trap shall be made of stainless steel materials with the
following specifications:
22 gauge stainless steel for partition, partition guide, and perforated collec-
tion basket;
3/8” diameter stainless steel shafting for cover handle and strainer handle;
8-3
Part 8 : Sanitary & Plumbing Guidelines
Testing & Commissioning
For food tenants including cafeterias/canteens, a minimum of 15 gpm of
grease trap per sink shall be installed with the dimension of (500mm)
19.69” L X (350mm) 13.78” W X (325mm) 12.80” H;
For non-food tenants, like lavatory for hand washing , medical clinics and
hair salons, developing films and other forms of sanitary fit-out which
involve grease, oils and chemicals. A minimum of 5-gpm grease trap shall
be installed with the dimension of (350mm) 13.78” L X (250mm) 9.34”
W X (300mm) 11.81” H;
For food carts/kiosks with sink which tapped to the kitchen waste line, a
minimum of 5-gpm grease trap shall be installed with the dimension of
(350mm) 13.78” L X (250mm) 9.34” W X (300mm) 11.81” H;
To check the accuracy of the grease trap size, the following formula shall
be used: dimension of the sink in term of inches (L X W X H) X 0.003;
and
Cylindrical grease traps/strainer with at least 4-chambers and 3- partition
shall be applied for those non-food tenants with sink of less than 5-gpm
based on the formula under item “d”.
LAY OUT:
Conduct hydrostatic leak test of piping works prior to tapping to the main
stub-out
8-4
Part 8 : Sanitary & Plumbing Guidelines
Part 9
Sprinkler Guidelines
BASIC REQUIREMENTS All works shall be in accordance with the latest government regulations,
Building Code, Fire Code, Electrical and Mechanical Codes, and other codes
being implemented by other approving bodies.
All corrections and additional notations on the plans shall be followed. Any
deviation from the approved plan shall have special approval by the
Administration office/SM EDD.
During construction and before the store can open, Administration office
shall inspect the construction works of the lessee. All deviations from the
approved shall be asked to redo.
Damages done but not limited to existing utilities, viroc wall partitions,
neutral piers, aircon fascia, and common area, by the lessee, whether
accidental of intentional, shall be repaired by Administration office and
corresponding expenses shall be charged to lessee.
Hangers and supports of lessee’s ceiling and utilities (pipes, ducts, etc.)
shall not be attached or anchored to the mall’s existing utilities and
concrete beams or columns. Lessee shall attach their hangers only to
concrete slab soffits.
Do not cover or block the return air passages and grills of aircon system.
All approved plans shall be present at the work site at all times.
LESSEES are required to visit actual site and take actual measurements
PRIOR to preparation of plans.
9-1
Part 9 : Sprinkler Guidelines
Sprinkler Plan
PLAN VIEW (SHOWING) Design (indicate distance between sprinkler heads, and between sprinkler
head and lease line) & specifications.
Isometric drawing
Legend
9-2
Part 9 : Sprinkler Guidelines
Sprinkler System Facilities Connection
9-3
Part 9 : Sprinkler Guidelines
Sprinkler System Design Criteria
Use upright sprinkler head for tenant with open ceiling and pendent sprin -
kler head for tenant with ceiling.
Sprinkler pipe should be Schedule 40 and painted red. G.I. pipe is not
allowed.
9-4
Part 9 : Sprinkler Guidelines
Testing & Commissioning
9-5
Part 9 : Sprinkler Guidelines
Part 10
Ventilation Guidelines
BASIC REQUIREMENTS All works shall be in accordance with the latest government regulations,
Building Code, Fire Code, Electrical and Mechanical Codes, and other codes
being implemented by other approving bodies.
All corrections and additional notations on the plans shall be followed. Any
deviation from the approved plan shall have special approval by the
Administration office/SM EDD.
During construction and before the store can open, Administration office
shall inspect the construction works of the lessee. All deviations from the
approved shall be asked to redo.
Damages done but not limited to existing utilities, viroc wall partitions,
neutral piers, aircon fascia, and common area, by the lessee, whether
accidental of intentional, shall be repaired by Administration office and
corresponding expenses shall be charged to lessee.
Hangers and supports of lessee’s ceiling and utilities (pipes, ducts, etc.)
shall not be attached or anchored to the mall’s existing utilities and
concrete beams or columns. Lessee shall attach their hangers only to
concrete slab soffits.
Do not cover or block the return air passages and grills of aircon system.
All approved plans shall be present at the work site at all times.
LESSEES are required to visit actual site and take actual measurements
PRIOR to preparation of plans.
10-1
Part 10 : Ventilation Guidelines
Mechanical / Vent / Exhaust Plan
EQUIPEMENT (WITH Kitchen hoods – indicating dimensions and which sides are open for air
UNIQUE MARK FOR EACH Flow
ITEM OF EQUIPMENT)
Exhaust and fresh air fans
EXHAUST DUCT Detail plans and elevations showing connection of exhaust branch duct to
CONNECTION TO MAIN exhaust main.
EQUIPEMNT SCHEDULES With complete specification for all exhaust and fresh air fan
KITCHEN HOOD DATA For each kitchen hood submit a completed “Kitchen Hood Data” form
10-2
Part 10 : Ventilation Guidelines
COOKING EQUIPMENT BTU load per Burner and Total BTU load.
DATA
10-3
Part 10 : Ventilation Guidelines
General Criteria
REQUIREMENTS All steam, vapors, heat, odors and moisture producing areas and
high-heat producing equipment must be exhausted by special mechanical
exhaust systems.
TYPE 1 - designed to collect and remove all types of cooking effluent from
the exhausted air.
TYPE 2 - designed to collect and remove only steam, vapors, heat and
odors.
10-4
Part 10 : Ventilation Guidelines
Ventilation Design Criteria
REQUIREMENTS Connection to main exhaust duct shall be angled by 45° towards the
direction of air flow.
All fans used in exhaust duct systems and fresh-air duct system must be
adjustable type that permits adjustments to capacity during final testing
and balancing. Rigid ceiling manhole and catwalk along the exhaust
duct blower should be provided.
Any portion of the ducting that is inaccessible from the duct entry or
discharge shall be provided with clean out openings.
The vertical distance between the lower lip of the hood and the cooking
equipment surface shall not exceed 4-feet.
Exhaust fan motor shall be located outside the exhaust airstream and
provided with vibration isolators.
10-5
Part 10 : Ventilation Guidelines
(Refer to attach drawing of SS Exhaust Hood Canopy w/ F.A at the Last Page.)
All hood filters should be baffle type and shall be installed at an angle
not less than 45O from the horizontal and shall be equipped with a drip
side gutter and oil collector tray.
Pop rivets, metal screws , or other similar exposed fasteners shall not be
used on the internal surfaces of the hood.
Lighting fixtures installed inside exhaust hoods shall be marked, “For use
within commercial cooking hoods”, or equivalent explosion proof
fixture.
Provide duct hanger for every duct bend, drop collar, machine connec-
tion and for every Two (2) meters run of duct.
Provide 40mm thick aluminum foil coated acoustic duct insulation around
the duct with the use of non combustible adhesive to paste the insulation.
10-6
Part 10 : Ventilation Guidelines
Commercial Kitchen Hood Design Criteria
WHERE REQUIRED Hoods shall installed at or above all commercial food heat-processing equip-
ment. Included are deep fat fryers; broilers; fry grills;steam-jacketed kettles;
hot-top ranges; ovens; barbecues; rotisseries; dishwashing machines and similar
equipment. For the purpose of this section, a food-processing establishment
shall include any building or a portion thereof used for the processing of food.
Solid fuel. Type I hood for use over solid fuel-burning cooking equip-
ment shall discharge to an exhaust system is dependent of other exhaust
systems.
FUEL BURNING Where vented fuel-burning appliances are located in the same room or space
APPLIANCES as the hood provisions shall be made to prevent the hood system from interfer-
ing with normal operation of the appliance vent.
10-7
Part 10 : Ventilation Guidelines
MATERIALS Type I and II hoods shall be constructed of materials conforming D.1 or
D.2 or other approved material.
JOINTS AND SEAMS External joints and seams shall be welded liquid tight.
CLEANING AND GREASE A hood shall be designed to provide for through cleaning of the entire
GUTTERS hood.
CLEARANCES FOR TYPE I Type I hood shall be installed with a clearance to combustibles of not less
HOOD than 18 inches (457 mm), or not less than 3 inches (76 mm) where the
combustible material is protected with noncombustible materials having a
minimum 1-hour fire-resistance rating on the hood side.
Hoods located less than 12 inches (305 mm) from ceiling or wall shall be
flashed solidly with materials specified in D.1 & D.2 or noncombustible
materials having a minimum 1-hour fire-resistance rating.
HOODS PENETRATING A Type I hoods or portions thereof penetrating a ceiling, wall or furred space
CEILING shall comply with all the requirements.
10-8
Part 10 : Ventilation Guidelines
GREASE FILTERS Type I hoods shall be equipped with approved grease filters designed for the
specific purpose. Grease-collecting equipment shall be accessible for cleaning.
The lowest edge of a grease filter located above the cooking surface shall be
not less than the height specified.
Minimum Distance between the Lowest Edge of a Grease Filter and the
Cooking Surface or the Heating Surface.
Criteria: Filters shall be of such size, type and arrangement as will permit
the required quantity of air to pass through such units at rates not exceeding
those for which the filter or unit was designed or approved. Filter units shall be
installed in frames or holders so as to be readily removable without the use of
separate tools,unless designed and installed to be cleaned in place and the
system is equipped for such cleaning in place. Removable filter units shall be
of a size that will allow them to be cleaned in an dishwashing machine or pot
sink. Filter units shall be arranged in place or provided with drip-intercepting
devices to prevent grease or other condensate from dripping into food or on
food preparation surfaces.
NON CANOPY SIZE AND Non canopy-type hoods shall be located a maximum of 3 feet (914 mm)
LOCATION above the cooking surface. The edge of the hood shall be set back a
maximum of 1 foot (305 mm) from the edge of the cooking surface.
10-9
Part 10 : Ventilation Guidelines
CAPACITY OF HOODS Canopy-type commercial cooking hoods shall exhaust a minimum quantity of
air, where:
A = the horizontal surface area of the hood, in square feet (m2).
D = distance in feet (mm) between the lower lip of the hood
and the cooking surface
P = that part of the perimeter of the hood that is open, in feet
(mm).
Q = quantity of air, in cubic feet per minute (L/s).
Solid fuel - burning cooking equipment. The minimum airflow for exhaust
systems used for solid fuel-burning cooking equipment, grease-burning
charbroilers and similar equipment shall be:
High temperature - The minimum airflow for Type I hoods used for high-
temperature appliances such as deep-fat fryers shall be determined as follows:
10-10
Part 10 : Ventilation Guidelines
Testing & Commissioning
SMOKE TESTING Conduct smoke test of ductworks prior to tapping to main duct and instal-
lation of insulation
AIR FLOW MEASUREMENT Measured air flow at each kitchen hood and fresh air delivery point
MEASUREMENT OF: Static and total air pressure at inlet and discharge of each fan
/blowerOperating RPM of each fan/ blower
Static and total air pressure in the Lessee’s ductwork at the point of
connection to the exhaust / fresh air main ducts.
10-11
Part 10 : Ventilation Guidelines
Design Schematic of Self Compensating Hood
10-12
Part 10 : Ventilation Guidelines
Part 11
House Rules & Regulations
It is understood that the following House Rules shall form an integral part of the Contract of Lease.
General Responsibilities
USE OF THE LEASED All LESSEES are advised to strictly adhere to the conditions and privileges
PREMISES of their respective Lease Contract regarding the use of the premises and
the specified items and merchandise to be carried.
OFFICIAL BUSINESS Shops must be opened for business from during regular mall hours daily.
HOURS However, on All Saints Day and Election Day, store hours shall be from
12:00 noon - 9:00 p.m.
The LESSEE shall secure the written approval of the LESSOR at least three
(3) days in advance if it intends to close the Premises. Use this same
procedure for any time deviation.
UTILITIES AND SERVICE All LESSEES are advised to pay their individual air-condition charges, if
CHARGES applicable and their share of common area maintenance service charges
on or before the due date indicated in the billing. After which period, a
service of disconnection order shall be issued if no payment is received. Any
delay in the issuance of such disconnection order may not be construed as
a waiver of the LESSOR.
UNIFORM OF SHOP To enhance the appearance of each shop and develop better image for
PERSONNEL the MALL, shop owners are strongly urged to have their personnel wear
properly coordinated uniforms that blend with the total concept of the
shop, complete with identification tags.
IDENTIFICATION CARDS LESSEES shall furnish the LESSOR names of their employees assigned at
the MALL with their respective position and 1” x 1” color photo in white
background at least five (5) days before their store opening for the
necessary issuance of SCMC ID.
11-1
Part 11 : House Rules & Regulations
IDENTIFICATION CARDS, Likewise, in cases where your employees resign, are transferred or
continued terminated, the IDs shall be surrendered to SCMC ADMINISTRATION.
The policy of “NO ID, NO ENTRY” shall be strictly followed by the MALL
SECURITY. Employees shall use only designated employees entrance
before regular operating hours.
All store employees are required to wear their SCMC ID during store
hours.
SHOP DISPLAY AND It shall be the responsibility of the LESSEE to see that their stocks are
STOCKING replenished to assure shoppers of variety of choice. This will ensure the
continuous patronage of shops at the MALL.
LESSEES are prohibited from selling untaxed imported goods which are
deemed to be a violation of law.
LESSEE shall, in order to maintain the prestige and standard of the MALL,
adopt pricing mechanisms which assure that goods for sale are reasonably
and competitively priced.
REPORTING AND LESSEES are requested to report immediately the outbreak of fire in their
COMBATING FIRE area and to apply necessary measures within their disposal to extinguish
the blaze.
For this purpose, LESSEES and their staff are required to familiarize
themselves with fire-fighting procedures by attending fire-fighting
orientation and participating in fire drills which SCMC ADMINISTRATION
may periodically call from time to time.
11-2
Part 11 : House Rules & Regulations
NIGHT LIGHT Shops must be provided with night lights when not open for business and
after store hours for security reasons and to provide continuous viewing of
the merchandise on display.
11-3
Part 11 : House Rules & Regulations
Maintenance of Leased Premises
GUIDELINES LESSEE shall warehouse, store and/or stock in the premises only such
goods, wares and merchandise as LESSEE intends to offer for sale in the
premises. This shall not preclude bonafide transfers of merchandise
between LESSEE’s other stores in the metropolitan area.
LESSEE must at all times keep the premises clean and in sanitary
condition. SCMC ADMINISTRATION or its representative reserves the
right to enter any of the leased premises, particularly the kitchen and
comfort rooms of food establishments to look into the sanitary condition of
the same.
LESSEE must attend immediately to any repair the shop needs, which
shall be undertaken at his own expense. LESSEE shall first secure approval
from SCMC ADMINISTRATION at least three (3) days before any
repair/renovation is to be done.
LESSEE shall provide receptacles and sufficient containers for trash and
agrees that the disposal of same shall be done at such time, place and
manner as may be fixed by LESSOR.
11-4
Part 11 : House Rules & Regulations
Prohibitions
Except for food establishments, cooking of any kind and by any means is
strictly prohibited within the leased premises. Eating within the leased
premises, however, will be permitted provided strict sanitation is observed
and should not be in full view of the customers.
LESSEE shall not use or permit the use of any portion of the premises as
sleeping or living quarters or use the same for illegal purposes.
Shops with piped-in music are advised to play the same at regulated
and moderate volume. The SCMC ADMINISTRATION reserves the right to
regulate the volume which interferes with its own activities in the MALL.
LESSEE shall not use or employ any audio-visual services, such as but not
limited to loud speakers, mechanical or moving display devices, unusually
bright and flashing lights and similar devices, the effect of which may be
seen or heard outside the leased premises.
Entries, passages, mall, hallway and corridors of the building shall not be
used by LESSEE or his store personnel for any other purpose other than
ingress or egress.
LESSEE shall not paint, drive nails, screws or abutments on the walls
or frames, nor post any indecent, immoral or objectionable inscription, nor
make alterations, improvements or changes in any part of the leased
premises, including electrical installation, plumbing and other fixtures
without prior written approval from the LESSOR.
11-5
Part 11 : House Rules & Regulations
LESSEE shall not use or store in the leased premises inflammable or
explosive materials or gas-fueled appliances in any form or quantity. In
addition thereto, RESTAURANTS shall provide and install within the leased
premises adequate safety devices such as fire extinguishers, LPG safety
device and smoke and fire alarms to minimize and avoid fire hazards. The
LESSEE shall permit regular inspection by the LESSOR or its agents of its
appliances, and shall immediately furnish such reasonable safety devices
when required by the LESSOR or its agents. In all cases, LESSEE shall not
perform any act or thing which may expose the leased premises to fire or
increase the volume of fire hazard or change to insurance rate of the
building, it being understood that should LESSEE do so, he shall be
responsible for all the damages which such violation may cause the
LESSOR and/or its other LESSEES aside from LESSEE’S other liabilities
under the lease contract.
11-6
Part 11 : House Rules & Regulations
Movements of Merchandise, Machinery, Furniture, & Equipment
INTRODUCTION Delivery of merchandise, supplies and other materials shall be from 6:00 A.M.
to 3:00 P.M. for food tenants, and from 6:00 A.M. to 12:00 noon for nonfood
tenants daily without need of a gate pass, subject to the following guidelines.
Delivery carts must have rubber rollers. Items should not be allowed to be
dragged damaging the flooring.
Deliveries that would stain and mess the mall and hallways are not
allowed. Wet deliveries should be placed in tightly sealed plastic sanitary
bags or styro containers.
Tenants can use the basement service elevator for deliveries not
exceeding 1,000 lbs. at any given time. Basement services area can only
be used for loading and unloading of merchandise of not more than 15
minutes.
Deliveries shall be subject to proper safety and security policy of the MALL.
11-7
Part 11 : House Rules & Regulations
Advertising
THE SM LOGO All LESSEES are required to use the symbolic SM logo of which standard
design is readily available at the SCMC ADMINISTRATION, for use in all
communications, promotions, advertising material forms. Said logo must be
used in all materials adjacent to, immediately above or below your store’s
name in newspaper advertisements, circulars, mailers, or any other print
media advertising of your products or services.
SALE SIGNS AND Except for the duly authorized store sign, no other signs and posters shall
POSTERS be installed on the facade of each shop without any prior approval or
clearance from SCMC ADMINISTRATION. The Administration reserves the
right to review the nature and preparation of the sales campaign materials
and other proposed signs and posters.
GUIDELINES ON THE Only tenants are allowed to distribute flyers to promote their stores/outlets
DISTRIBUTION OF at the MALL.
LEAFLETS/FLYERS
Tenants should secure approval from SCMC ADMINISTRATION on the
following:
- Contents of the flyer
- Dates of distribution
Time of distribution shall be from 11:00 a.m. - 2:00 p.m. for food tenants
and from 3:00 - 5:00 p.m. for nonfood tenants.
11-8
Part 11 : House Rules & Regulations
GUIDELINES ON THE Distribution shall be in a manner by which it would not obstruct the flow of
DISTRIBUTION OF customers inside the mall.
LEAFLETS/FLYERS,
continued
11-9
Part 11 : House Rules & Regulations
Payment Guidelines
GUIDELINES Per our Contract of Lease, payment of rental and other charges shall be
made within the first fifteen (15) calendar days after the end of every
calendar month to which the rental statement of account corresponds.
If full payment is not made at the end of the month, a cashier will be
posted in your area on the first day of the following month. The cashier
shall monitor all sales transactions and collect forty (40%) percent of the
total daily cash and credit sales. The daily rate of the cashier in your
premises shall be reflected in your account. The cashier posting shall cease
only upon full payment of your rental arrears.
If full payment is still not made after twenty five (25) days of cashier
posting, the lease contract shall be subject to termination.
11-10
Part 11 : House Rules & Regulations
GUIDELINES, continued The LESSEE undertakes to remit to the Bureau of Internal Revenue (BIR)
all taxes withheld from his payments on or before the tenth (10th) of the
month. The LESSEE shall likewise submit to the SCMC ADMINISTRATION
three (3) copies of the Certificate of Creditable Income Tax Withheld at
Source (BIR Form 2307) for the quarter within fifteen (15) days after the
end of each quarter.
(on or before...)
January - March April 15
April - June July 15
July - September October 15
October - December January 15
Failure to submit said Certificate shall be construed as non remittance to
BIR, as such, tax withheld shall be billed accordingly. In addition, interest at
3% per month shall be charged correspondingly for the equivalent amount
of tax withheld not supported with withholding tax certificate, which shall
be computed from the month the tax was withheld from payments.
For the convenience of the LESSEE, payments may be made at any of the
following venues:
- Any Banco De Oro branch nearest to the Lessee (Bring the Payment Slip
attached in your Statement Of Account)
11-11
Part 11 : House Rules & Regulations
Sales Reporting (For Non-Fixed Tenants)
GUIDELINES LESSEE should submit a daily sales report thru the Lotus Notes Sales
Reporting System on or before 10:00 a.m. of the following day. LESSEE
should submit a certified monthly sales report within the first three (3)
days after the end of each calendar month.
The sales report should state the total gross sales made during each
preceding month. All sales transactions and sales related transactions,
which include but not limited to approved/unapproved discounts, inventory
losses charged to employees, employees meals, and sales from inventory
pull-out, must be reported/ shown in the certified monthly sales report.
Credit/charge sales should be treated as a sale for the full price at the
same time of the transaction, regardless of the time of payment or when
title passes. Credit/charge sales are to be punched in to your POS
machine(s) / Cash Register Machine(s).
11-12
Part 11 : House Rules & Regulations
Submission of Fire Insurance & Comprehensive General Liability
Insurance Coverage
GUIDELINES LESSEE shall furnish the LESSOR a photocopy of the insurance coverage of
your improvements, merchandise, and all other properties inside your
leased premises. The insurance shall be against fire and/or lightning and/or
other perils, and an adequate comprehensive general liability insurance
coverage.
11-13
Part 11 : House Rules & Regulations
General Services
INTRODUCTION One of our prime objectives is to provide assistance to our tenants, specifically
in relation to work that would require EMERGENCY repairs of existing
plumbing, electrical, and air-conditioning facilities.
GUIDELINES Please inform our office of the needed services and fill up a SERVICE
REQUEST form.
Only emergency and minor repairs not to exceed one hour’s work shall be
attended to by our maintenance group. A minimum service fee per call will
be charged. Materials to be supplied by LESSEE.
11-14
Part 11 : House Rules & Regulations
Trash Collections & Disposal Guidelines
INTRODUCTION In line with our continuing maintenance program, garbage collection for
NON-FOOD ESTABLISHMENTS will be done by collectors assigned at the
Mall.
Place all trash in properly sealed sanitary bags, separating wet from dry.
Garbage should be brought out only when the collector arrives at your
outlet.
11-15
Part 11 : House Rules & Regulations
Pest Control Program (Spraying / Misting / Fogging / Rat & Mice
Control)
11-16
Part 11 : House Rules & Regulations
Fire Extinguishers
Institute periodic inspection of all units to ensure that contents have not
expired.
11-17
Part 11 : House Rules & Regulations
Sprinkler System
GUIDELINES For our mutual benefit, everyone is enjoined to observe and strictly follow the
safety guidelines, to wit:
Sprinkler heads and pipes should always be free from any obstruction.
Improper utilization of the pipes, hanging of merchandise is strictly
prohibited.
Immediately report any leak found and/or misalignment that you may
notice.
Practices other than the above guidelines may prove detrimental to your
operation, as it may result in malfunctioning in cases of fire and premature
water spray, causing water damage.
11-18
Part 11 : House Rules & Regulations
Exhaust Duct Cleaning & Safety Measures (For Food
Establishments)
INTRODUCTION To safeguard our lives and valuable property, fire prevention measures as
embodied in our Lease Contract should be strictly observed.
11-19
Part 11 : House Rules & Regulations
Guidelines on Emergency Power Operations
Always maintain the lever of the double throw switch upward (normal
power).
Failure to comply with any of the above conditions would mean forfeiture of
the LESSEE’s privilege of using emergency power.
11-20
Part 11 : House Rules & Regulations
LPG Safety
LPG cylinders and piping system should be free and away from any
spark producing objects, convenience outlet or switches. (If applicable)
11-21
Part 11 : House Rules & Regulations
Delivery Parking
GUIDELINES The delivery parking area is open for tenants delivery services, using the freight
elevators under the following guidelines:
Delivery vehicles with gross weight of more than 5000 kg. must
secure entry pass from SCMC ADMINISTRATION.
Delivery area shall only be used for loading and unloading of supplies and
materials, not to exceed 15 minutes.
11-22
Part 11 : House Rules & Regulations
Emergency Telephone Numbers
11-23
Part 11 : House Rules & Regulations
Customer Relations Service
GUIDELINES The Security Force of the MALL, in addition to its primary function of
securing the physical building facilities, is charged with the responsibility of
reporting violations of the MALL’S HOUSE RULES. They shall see to it that
the following rules are strictly enforced and implemented to the letter.
In the event that LESSEE decides to hire, solicit and engage the
services of a private security guard or watchman’s agency for his own
purposes, he shall only hire and engage the services of reputable security
agencies acceptable to and subject to the prior written approval of
LESSOR; provided, that LESSOR shall not, in any manner be responsible
for any losses and/or damages sustained by LESSEE relative to the choice
and approval of any particular security agency; and provided further that
LESSOR reserves the right to formulate such supplementary rules and
regulations for the proper observance of the parties for the coordination of
the private security system in the entire center.
The security guard should submit his individual Mayor’s Permit, copy of
license, bio-data and 1 x 1 ID picture.
11-24
Part 11 : House Rules & Regulations
Parking
GUIDELINES The parking areas are open to the general public. As such the SCMC
ADMINISTRATION thru its security services, cannot be held accountable
for damages or losses incurred even when drivers or owners have
specifically informed the roving guard on duty of its presence. The guard’s
responsibility lies primarily in the enforcement of the regulations of SCMC
ADMINISTRATION regarding traffic, parking, and molestations from
unauthorized people.
Loading and unloading zones shall be properly identified for this purpose.
Customer Relations Service Office shall see to it that the security guards
on duty direct the delivery of construction materials and the like through
the designated entrances.
Security guards must see to it that traffic flows smoothly within the
MALL and must politely request car owners/drivers to park properly in
designated parking areas.
11-25
Part 11 : House Rules & Regulations
Sanitation
GUIDELINES The janitorial service engaged by the Mall is charged with the same
responsibility in the enforcement of the House Rules involving sanitation,
particularly enumerated as follows:
Calling the attention of the Customer Relations Service Office and the
SCMC ADMINISTRATION to any violation of the House Rules that
come to its attention.
11-26
Part 11 : House Rules & Regulations