100% found this document useful (10 votes)
4K views2 pages

Ethiopian Roads Authority Routine Road Maintenance Bill of Quantity

This document is a bill of quantities for routine road maintenance work on the Debre Tabor section of the Gondar Road Network in Ethiopia. It lists various maintenance activities like spot repair of gravel roads, culvert cleaning, ditch cleaning, asphalt patching, blading of gravel roads, and bridge repairs. The quantities, unit rates, and total amounts are provided for each activity. The subtotal for all activities is listed as 5,705,884.7 ETB with additional amounts for contingency, VAT, and a grand total of 7,217,944.20 ETB.

Uploaded by

Natinael Wolde
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (10 votes)
4K views2 pages

Ethiopian Roads Authority Routine Road Maintenance Bill of Quantity

This document is a bill of quantities for routine road maintenance work on the Debre Tabor section of the Gondar Road Network in Ethiopia. It lists various maintenance activities like spot repair of gravel roads, culvert cleaning, ditch cleaning, asphalt patching, blading of gravel roads, and bridge repairs. The quantities, unit rates, and total amounts are provided for each activity. The subtotal for all activities is listed as 5,705,884.7 ETB with additional amounts for contingency, VAT, and a grand total of 7,217,944.20 ETB.

Uploaded by

Natinael Wolde
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

4.4 4.

1 BILL OF QUANTITIES
Ethiopian Roads Authority
Routine Road Maintenance Bill of Quantity
RNMD: Gondar Road Network & Safety Management Branch Directorate
Maintenance Type: Routine Maintenance
Project Name: Debre Tabor section
Intervention Area: Area 1
Act No Activity Name Unit Quantity Unit price Amount
(ETB)
110 Spot Repair Gravel Road (Nat. ) m3 118.00 173.74 20,501.32
111 Spot Repair Gravel Road (C.A ) m3 - 938.92 -
121 Culvert cleaning m3 382.59 193.20 73,915.62
122 Ditch cleaning (Manual) m 4,107.37 15.91 65,348.19
123 Repair erosion damage (Selected fill) m3 56.65 224.84 12,736.96
124 Repair erosion damage (Rock fill) m3 - 306.60 -
125 Mortared Masonry Repair m3 519.69 1,226.40 637,351.50
3
126 Dry Masonry Repair m - 678.62 -
3
127 Gabion structure m 149.42 1,214.97 181,543.25
131 Brush Clearing m2 - 1.13 -
2
210 Asphalt Patching (Seal coat) m - 83.46 -
2
211 Asphalt Patching (SST) m - 91.34 -
212 Asphalt Patching (DST) m2 2,873.50 176.91 508,350.89
3
213 Asphalt Patching (Cold - Mix) m - 6,234.20 -
3
214 Asphalt Patching (Hot Mini - Mix) m - 6,887.34 -
215 Asphalt Patching (Individual cracks) ml - 51.50 -
216 Pothole Reinstatement (D S T) m2 - 165.78 -
217 Pothole Reinstatement (Cold Mix) m3 - 6,726.07 -
218 Pothole Reinstatement (Hot Mini - m3 - 6,954.91 -
Mix)
219 Pothole Reinstatement (Base failure) m3 - 793.34 -
220 Blading gravel road (light) km - 3,200.80 -
221 Blading gravel road (Heavy) km 41.05 12,496.11 512,965.32
222 Gravel Provision-Selected Material m3 15,114.50 141.23 2,134,620.84
223 Gravel Provision-Crushed Agg. m3 - 883.82 -
230 Ditch cleaning (Machine) km 28.74 7,899.04 226,978.91
240 Shoulder Blading km - 1,624.62 -
241 Shoulder rehabilitation m3 - 224.84 -
251 Concrete Construction (Class1) m3 - 5,110.00 -
252 Concrete Construction (Class2) m3 - 3,427.87 -
253 Steel reinforcement Kg - 51.11 -
15.01(a) Detour Construction (not including Km - 431,583.2 -
Culvert) 5
15.01(b) Detour Maintenance (not including Km - 114,000.0 -
Culvert) 0
BRIDGE REPAIR - -
2
1-CWL-1 Water linkage on Deck slab m - 1,035.66 -
10-FSCO-3 Abutment and Wingwall scour m2 49.26 2,067.00 101,820.42
2
1-CHE-2 Honeycomb on deck slab m - 1,476.75 -
10-MHR-1 missing of curb and railing ea - 9,839.31 -
1-CPO-1 Abutment and Wingwall peel off m2 - 1,841.10 -
1-CRE-2 Rebar exposed on Pier and foundation m2 - 1,990.58 -
2
10-FSCO-3 River bed scour m - 2,246.59 -
2
5-RER-1 Riprap erosion m - 615.79 -
10-FSCO-3 Crack (deck slab) ml - 1,169.64 -
DAYWORKS 1,229,751.55
Sub Total 5,705,884.7
contingency (10%) 570,588.5
15% VAT 941,470.98
Total 7,217,944.20