Sub-Section 4.1. RW No.1 - Expert's Witness Report - Claim No.117-Rev01
Sub-Section 4.1. RW No.1 - Expert's Witness Report - Claim No.117-Rev01
Sub-Section 4.1. RW No.1 - Expert's Witness Report - Claim No.117-Rev01
September 2020
Supervision of Design and Works
Nadzor nad Projektovanjem i Izgradnjom
Revision 01
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
Revision History
SIGNATURE
1
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
LIST OF CONTENTS
1. INTRODUCTION / UVOD................................................................................................................................3
2. CLAIM EVENT / DOGAĐAJ POTRAŽIVANJA.......................................................................................... 3
3. TECHNICAL REVIEW OF CONTRACTOR’S DOCUMENTATION / TEHNIČKI PREGLED
DOKUMENTACIJE IZVOĐAČA RADOVA .....................................................................................................6
3.1. GENERAL COMMENTS / OPŠTI KOMENTARI..........................................................................................6
3.2. TECHNICAL COMMENTS / TEHNIČKI KOMENTARI........................................................................... 13
3.3. TECHNICAL CONCLUSION / TEHNIČKI ZAKLJUČAK .................................................................. 15
4. GENERAL DESCRIPTION / OPŠTI OPIS.................................................................................................. 17
5. PRELIMINARY DESIGN / IDEJNI PROJEKAT....................................................................................... 21
6. CONCLUSION ON PRELIMINARY DESIGN / ZAKLJUČAK O IDEJNOM PROJEKTU................ 31
7. CONTRACTOR’S CLAIM ANALIZY / ANALIZA POTRAŽIVANJA IZVOĐAČA RADOVA...........33
8. FINAL CONCLUSION / KONAČAN ZAKLJUČAK................................................................................. 38
2
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
1. INTRODUCTION 1. UVOD
Background Pozadina
“On construction Site of 4.1 subsection, the „Na gradilištu podeskcije 4.1 Izvođač se susreo
Contractor encounter a change in the geological sa promjenom geoloških uslova na dijelu
conditions at the part of open route, so THE otvorene trase, pa se pristupilo izmjeni
Main Design for Gravity retaining wall 1 and Glavnog projekta gravitaciono potpornog zida
slope has been modified. 1 i kosine.
The Contractor considers theses adverse Izvođač smatra da su ovi nepovoljni fizički
physical conditions to have been Unforeseeable, uslovi Nepredvidivi, stoga, u skladu sa PK 4.12
therefore in accordance with SC 4.12 of the Ugovora o projektovanju i izgradnji Autoputa
Design and Build Contract for Bar-Boljare Bar-Boljare, Izvođač je obavijestio Inženjera
Highway, the Contractor informed the Engineer dopisom RB-BBH/ 23/CD-P3 datiranim
that we encountered unforeseeable physical 07.01.2019. godine (Prilog 2) da smo se susreli
conditions on the construction site via letter RB- sa nepredvidivim fizičkim uslovima na
BBH/ 23/CD dated on 07.01.2019 (Enclosure 2). gradilištu.
Having in mind that theses changed geological Imajući u vidu da su ovi promijenjeni geološki
conditions led to a variation of the scope of uslovi doveli do varijacije obima Radova, stoga
Works, therefore pursuant to the Sub-clause 13.9 je u skladu sa Podklauzulom 13.9 Nepredvidivi
Unforeseeable Works, the Contractor asked the radovi, Izvođač je zatražio od Inženjera da
Engineer to apply the required Variation primijeni neophodnu Proceduru o varijaciji u
procedure in accordance with Contract Sub- skladu sa Potklauzulama 13.1 i 13.3 Ugovora.
clauses 13.1 and 13.3.
Gorenavedeni Nepredvidivi fizički uslovi - su
The abovementioned Unforeseeable Physical evidentirani u sljedećim dokumentima:
Conditions - are all recorded in the following Izmjena Glavnog projekta zbog promjene u
documents: geološkim uslovima (prilog 4)
Main Design change due to changes in Građevinski Dnevnik (priolog 5)
3
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
Design change
No. Items unit unit
quantity total price
price
Excavation for wall foundations into the
1 m3 49101.00 8.67 425,705.67
ground Ⅲ-Ⅳ category
Deformed steel bar B500B for retaining 790665.8
2 Kg 1.30 1,027,865.66
walls. As per specification. 9
Protection of slopes by hanging steel wire
3 nets.Systematic anchorage with 12m long m2 9945.00 141.16 1,403,836.20
IBO anchors in raster 2x2 m
4 Prestressing anchors, L=23m Pcs 42.00 1668.95 70,095.90
5 Prestressing anchors, L=28m Pcs 37.00 1939.84 71,774.08
Concreting of underlayer for the beam of
6 m3 66.46 350.24 23,276.95
pile cap,MB20
Concreting of piles, L=16m to L=26m,
7 m3 4488.86 400.36 1,797,159.99
D=1.8m,MB30
8 Concreting for the beam of pile cap,MB30 m3 1195.32 380.05 454,281.37
9 Concreting of dithes, MB30 m3 616.00 219.78 135,384.48
Concreting of underlayer for
10 m3 343.00 219.78 75,384.54
ditches,MB15
11 Protous concrete between piles m3 120.00 284.71 34,165.20
12 Geotextile m3 600.00 11.82 7,092.00
13 Water stop M 670.00 14.78 9,902.60
14 Shotcreting m3 57.00 248.80 14,181.60
15 Concreting of retaining wall in-between m3 120.00 284.71 34,165.20
4
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
piles
16 Installation of wiremesh for ditches,Q188 m2 4511.48 64.05 288,960.29
Installation of drainage pile for the
17 M 606.00 82.17 49,795.02
seepage ditch, DN400
18 Land acquisition m2 9900.00 4.00 39,600.00
19 Top soil removal and cutting trees m2 9900.00 3.00 29,700.00
10% of management cost 599.232.67
Total 6.591.559,42
5
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
attached, which would indicate the fact that the činjenicu da geološka struktura terena ne
geological structure of the terrain does not odgovara predviđenoj u sklopu Idejnog, a
correspond to the one envisaged within the kasnije i Glavnog projekta.
Preliminary and later the Main Design.
Stoga, u nastavku donosimo detalje iz
Therefore, below are the details from the Geološkog izvještaja za Usjek otvorene trase
Geological Report for the Cut of the Open (LK 31+685 – LK 31+835), izrađenog
Route (LK 31 + 685 - LK 31 + 835), prepared 28.11.2017.; koji se odnosi na drugi nivo
on 28.11.2017; which refers to the second level kosine od stacionaže LK 31+706,33 –
of the slope from the chainage LK 31 + 706.33 - 31+828,03.
31 + 828.03.
The Geological Report states:
U Geološkom izvještaju navedeno je:
“With engineering-geological mapping of the
„Inženjersko-geološkim kartiranjem II etaže
II level, open route LK 31 + 706.33 - 31 +
otvorene trase LK 31+706,33 – 31+828,03
828.03, it is ascertained that geological
konstatovano je da geološka građa i
material and engineering-geological
inženjersko-geološki uslovi iskopa odgovaraju
conditions of the excavation correspond to the
prikazanom u Geotehničkom elaboratu za
Geotechnical Study for the open route 4.1…
otvorenu trasu 4.1...
…This slope is built from quaternary
...Data kosina izgrađena je od kvartarnih
sediments that are very widespread and
sedimenata koji su veoma rasprostranjeni i
developed in the form of deluvial slope
razvijeni u vidu deluvijalnog padinskog
material, basically it is a gravel woth
materijala, u osnovi to je zaglinjena drobina
fragments od flysch decay, consisting a
sa komadima flišne raspadine, koju čine
medium to large pieces of sandstone,
srednji do krupni komadi pješčara, alevrolita i
alevrolite, claystone with interlayers of clay
glinaca sa proslojcima gline debljine i do
with thickness up to several cm, the
nekoliko cm, učešće drobine je promjenjivo.
participation of the fragments is variable. The
Debljina deluvijalnog nanosa je različita i
thickness of the dilluvial coating is different
kreće se od 2-4 m.Ispod površinskog
and ranges from 2-4 m. Beneath the surface
padinskog materijala primjećuje se eluvijalna
slope, the elluvial decay of flysch sediments,
raspadina flišnih sedimenata, kredno-
cretaceous-paleogenic age are observed, and
paleogene starosti, a predstavljena je paketom
it is presented wth a package of claystone,
glinaca, alevrolita i pješčara izmješanih sa
alevrolite and sandstone mixed with clay,
glinom, tektonski srednje do jače degradirani
tectonically medium to heavily degraded and
i oštećeni....
damaged…
...Elemente zaštite kosine izvesti kao u
…Slope protection elements should be
Glavnom projektu.“
performed as in the Main Design.”
Inženjer je odobrio ovaj Izvještaj uz pisani
The Engineer approved this Report with
komentar: „Podsjećamo Izvođača da pomno
comment: “We are reminding the Contractor
prati kosinu i u slučaju bilo kakve lokalne
to closely monitor the slope and in case of
(globalne) nestabilnosti obavijesti
any local (global) instability inform a
Projektanta i preprojektuje te primijeni
Designer and re-design and apply additional
dodatne mjere zaštite kosine.
slope support measures.
Takođe, Izvođač bi trebao ponovno
Also, Contractor should re-consider hydro
razmotriti hidro sjetvu kako bi izbjegao
seeding in order to avoid errosion (ASAP – in
6
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
7
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
In chapter 3.4 Landslide stated: “Flysch U poglavlju 3.4 Prikaz klizišta navedeno je:
sediments this Highway section will be passing „Flišni sedimenti kroz koje prolazi ovaj dio
through are "eligible" for formation of autoputa predstavljaju vrlo »pogodne« terene
landslides. Of course this is, and will be, most za formiranje klizišta. Naravno ovo je, i biće
pronounced in open-route zones, as is the najviše izraženo u zonama otvorenih trasa kao
case, as well as portals of the tunnel. što je ovaj slučaj kao i portalnim djelovima
tunela.
The Quaternary cover (deluvial-eluvial
material)is sliding over the base rock, however Uglavnom kliza kvartarni pokrivač
it is not rarely that the landslide also affects (deluvijalnoeluvijalni materijal) preko
the strong alteration and degradation zone of osnovne stijene dok nije rijedak slučaj da
the base rock (F category). Likewise, sliding klizištem bude zahvaćena i zona jake
may take place through the sound rock mass in alteracije i degradacije osnovne stijene (F
the case of unfavorably - oriented plicative kategorija). Isto tako može doći do klizanja
formation of rock. kroz zdraviju stijensku masu u slučaju
nepovoljno orijentisanog plikativnog sklopa
After reviewing the data regarding the subject
stijene.
landslide, it could be said that the Quaternary
as well as very degraded parts of the base rock Na osnovu analize podataka za predmetno
have been in motion. klizište se može reći da je došlo do pokretanja
kvartarnih i jako degradiranih dijelova
Certainly, in the stage of the Main civil design
8
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
9
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
incorporated into this category of rock mass so terena u kome dominira F kategorija stijenske
the function of this security measure is mase. Njih nije moguće adekvatno ugraditi u
questionable. There is no data on possible ovu kategoriju stijenske mase tako da je
pull-out tests. upitna funkcija ove mjere osiguranja.
Podataka o eventualnom testiranju ankera na
The state of boundary equilibrium is
čupanje nema.
considered to occur at the first greater inflow
of storm water and even groundwater. Major Smatra se da je stanje granične ravnoteže pri
deformations occurred in the winter period prvom velikom prilivu atmosferskih a samim
2017-2018. tim i podzemnih voda. Glavne deformacije su
se i dogodile u zimskom periodu 2017-2018
There was a surface drainage channel (depths
godine.
up to 1 m) at the top of the slope, not far from
the top of the vice, but it itself had no function Na vrhu kosine je postojao površinski
in eliminating the adverse groundwater but drenažni kanal (dubine do 1 m), nedaleko od
only eliminating the surface water washing the vrha škarpe, ali on sam po sebi nema funkciju
face of the slope during higher precipitation. u eliminsanju nepovoljnih podzemnih voda
već samo eliminisanje površinskih voda koje
It would be more important that waters
spiraju lice kosine prilikom većih padavina.
occurring in a ravine at the frontal groove had
been removed. The frontal groove practically Ono što bi bilo bitnije da su se eliminisale
formed in one part on the ravine (Figure 32). vode koje se javljaju u vododerini na uz čeoni
This ravine has a southwest-northeast ožiljak. Čeoni ožiljak je praktično formiran
direction and gravitates toward a transversal jednim dijelom po vododerini (slika 32). Ova
large ravine at the northern end of the slope. vododerina ima pravac jugozapad-
sjeveroistok i gravitira ka poprečnoj velikoj
It formed at higher parts of the terrain, and
jaruz na sjevernom kraju kosine.
following the ravine uphill (Figure 33) it is
obvious that the water head is not low and that Formira se na višim djelovima terena i prateći
there is plenty of water in the rainy season. jarugu uz brdo (slika 33) vidi se da energija
vode nije mala i da u kišnom periodu ima
This means that besides the groundwater in the
dosta vode.
rainy season there is also smooth inflow of
surface water in the body of landslides directly To znači da pored podzemnih voda u kišnom
from the occasional flow. periodu postoji i nesmetan uliv površinske
vode u tijelo klizišta direktno iz povremenog
All the above, together with EG composition of
toka.
the slope presented in the previous chapters,
results in landsliding. Sve gore navedeno, uz nepovoljnu IG građu
padine, što je prikazano u prethodnim
poglavljima, rezultuje klizištem.
10
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
Picture 1: Main Design – Landslide on left slope of open route on km LK 31+705 – LK 31+820 - EG map
with positions of the designed exploratory works; DWG No. 1; Design code: BBC122TR***GL03
Slika 1: Glavni projekt – Klizište na lijevoj kosini otvorene trase na km LK 31+705 – LK 31+820 – IG
karta sa položajem projektovanih istražnih radova; Crtež br. 1; Šifra projekta: BBC122TR***GL03
11
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
Picture 2: Landslide on left slope of open route on km LK 31+705 – LK 31+820 - EG section 1-1ʹ; DWG
No. 2.1; Design code: BBC122TR***GL03
Slika 2: Glavni projekt – Klizište na lijevoj kosini otvorene trase na km LK 31+705 – LK 31+820 – IG
presjek1-1ʹ; Crtež br. 2.1; Šifra projekta: BBC122TR***GL03
12
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
13
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
14
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
15
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
16
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
17
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
includes: sandy clay of variable plasticity, do 7.5 m. U sastavu ove jedinice učestvuje:
brown-reddish color; sand medium-grained to pjeskovita glina promjenljive plastičnosti,
fine-grained, brown in color; and debriss of braon-crvenkaste boje; pijesak srednjezrn do
marlstones, sandstones, marly limestones, and sitnozrn, smeđe boje; i drobina od laporaca,
sandy marlstones. The size of the fragments pješčara, laporovitih krečnjaka i pjeskovitih
ranges from 0.5 to 10 cm. Due to the variable laporaca. Veličina odlomaka kreće se u rasponu
mineralogical-petrological and granulometric od 0.5 do 10 cm. Zbog promjenljivog
composition, the physical-mechanical properties mineraloško-petrološkog i granulometrijskog
of the environment are also variable. The sastava, promjenljiva su i fizičko-mehanička
compressibility is very high to medium. Steeper svojstva sredine. Stišljivost je vrlo velika do
parts of the environment are subject to erosion srednja. Strmiji djelovi sredine podložni su
and sliding. spiranju i kliženju.
Cretaceous-Paleogene "Durmitor flysch"
Kredno-paleogeni „Durmitorski fliš“
The two flysch facies are different in terms of
engineering geological properties.
Dvije facije fliša su različite u pogledi
Sandstones, siltstones, marlstones, claystones inženjerskogeoloških svojstava.
and subordinate limestone breccias (PS, LC,
Pješčari, alevroliti, laporci, glinci i podređeno
GC); represent a sandy-marly flysch facies. They
krečnjačke breče (PŠ,LC,GC); predstavljaju
are located in the base of Quaternary sediments,
pjeskovito-laporovito faciju fliša. Nalaze se u
ie the entire terrain. The general dip of the strata
podlozi kvartarnih sedimenata, odnosno
is to the north and northeast at angles of 30 to
cjelokupnog terena. Genaralni pad slojeva je
500. The strata mostly fall into the hill. Cracks
prema sjeveru i sjeveroistoku pod uglovima od
generally occur in two systems, mutually
30 do 500. Slojevi uglavnom padaju u brdo.
perpendicular and perpendicular to the layers.
Pukotine se generalno javljaju u dva sistema,
Numerous decomposition cracks of different
međusobno upravne i upravne na slojeve. U
orientations also occur in the surface zone. With
površinskoj zoni javljaju se i brojne pukotine
interlayer cracks they divide the rock mass into
raspadanja, različite orjentacije. Sa
blocks usually cm to dm in size. The thickness of
međuslojnim pukotinama dijele stijensku masu
the zone of physical and chemical change ranges
na blokove obično cm do dm dimenzija.
from 15 to 20 m.
Debljina zone fizičko-hemijske izmjene kreće
The dominant representation in the series are se od 15 do 20 m.
sandstones and siltstones, followed by
Dominantnu zastupljenost u seriji imaju
marlstones and claystones, so they generally
pješčari i alevroliti, zatim laporci i glinci, pa
conditioning the engineering geological
oni generalno uslovljavaju inženjerskogeološke
characteristics of this environment.
karakteristike ove sredine.
Sandstones appear in the series as laminar and
Pješčari se u seriji javljaju kao pločast i slojevi,
layered, rarely banked, 3-5-10 to 70 cm thick.
ređe bankoviti, debljine 3-5-10 do 70 cm. Boja
Their color is yellow and gray. They are fine-
im je žuta i siva. Sitnozrni su do srednjezrni.
grained to medium-grained. They cracked
Ispucali su po sistemu subvertikalnih pukotina,
according to the system of subvertical cracks,
upravnih na slojeve, hrapavih zidova, obloženih
perpendicular to the layers, rough walls, lined
limonitom, a neke su ispunjene kalcitom.
with limonite, and some were filled with calcite.
Marlstones are gray, black and green. They are
18
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
layered, thin-layered, exfoliated and strongly Laporci su sive, crne i zelene boje. Slojeviti su,
shaly. In the surface part, they underwent a tankoslojeviti, listasti i jako uškriljeni. U
physico-chemical change, so they decomposed površinskom dijelu pretrpjeli su fizičko-
into small clay debris, exfolias and flakes. hemijsku promjenu pa su raspadanjem
Therefore, they are prone to intense erosion. pretvoreni u sitnu glinovitu drobinu, listiće i
They cracked on the systems of subvertical, ljuspice. Zbog toga skloni su intezivnom
subhorizontal (interlayer) and oblique cracks. spiranju. Ispucali su po sistemima
Compressed cracks appear and those with a gap subvertikalnih, subhorizontalnih (međuslojnih)
of 1 to 3 mm. The distance between the cracks is i kosih pukotina. Javljaju se stisnute pukotine i
1-3-5 to 10-30-50 cm. Vitoper cracks in the one sa zijevom od 1 do 3 mm. Rastojanje
rough walls also occur. The filling of the cracks između pukotina je 1-3-5 do 10-30-50 cm.
consists of calcite wires 2 to 3 mm wide and Javljaju se i vitoperne pukotine grubih zidova.
limonite. Limonite scraps are secreted between Ispunu pukotina čine žice kalcita širine 2 do 3
the stratification surfaces. They are dilapidated mm i limonit. Između površina slojevitosti
(especially in the overlying parts), they easily izlučene su skrame limonita. Trošni su (naročito
split on the layers. With depth, the strength u povlatnim djelovima), lako se cijepaju po
increases. površinama slojevitosti. Sa dubinom povećava
se čvrstoća.
Claystones appear as interlayers, in marlstones, 5
to 50 cm thick. They are dilapidated, shiny,
easily split on shale surfaces and represent
Glinci se javljaju kao proslojci, u laporcima,
weakened zones and zones in which larger
debljne 5 do 50 cm. Trošni su, uškriljeni, lako
amounts of water can flow.
se cijepaju po površinama škriljavosti i
Modern geodynamic processes and predstavljaju oslabljene zone i zone u kojima je
phenomena moguć dotok većih količina vode.
From modern geodynamic processes and Savremeni geodinamički procesi i pojave
phenomena in the road corridor appear:
Od savremenih geodinamičkih procesa i pojava
- planar erosion of the terrain u koridoru puta javljaju se:
- line erosion of watercourses - planarno spiranje terena
- sliding and falling - linijska erozija vodotoka
Planar erosion is characteristic of a surface cover - kliženje i odronjavanje
composed mainly of deluvial deposits. It is
Planarno spiranje je karakteristično za
especially pronounced on bare terrains and
površinski pokrivač sastavljen pretežno od
terrains with a higher steep of the slope.
deluvijalnih naslaga. Posebno je izraženo na
Line erosion is very pronounced in the entire ogoljenim terenima i terenima sa većim
research area. The ravines are numerous, of nagibom.
different lengths and depths. In them, the surface
Linijska erozija je jako izražena na kompletnom
cover and exposed shoots are usually taken away
području istraživanja. Jaruge su brojne,
in the upper part, while the deluvial-proluvial
različitih dužina i dubina. U njima je obično u
material in the form of cones and fans has
gornjem dijelu odnesen površinski pokrivač i
accumulated in the lower part. In addition to
otkriveni izdanci, dok je u donjem akumiliran
dredging as a product of line erosion, the
deluvijalno-proluvijalni materijal u vidu konusa
abrasion of the Tara river bank as well as the
i lepeza. Osim jaružanja kao produkti linijske
migration of the riverbed in a relatively short
erozije značajni su i abrazija obale rijeka Tare
19
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
period of time are also significant. Migration and kao i migracija korita rijeke u relativno kratkom
is particularly pronounced in the lower reaches vremenskom periodu. Migracija je posebno
of the Tara river. The Tara riverbed has been izražena u donjem dijelu toka rijeke Tare.
changed in several places over a period of Korito Tare je na više mjesta promijenjeno u
several years. After the flow shifts, old troughs periodu od nekoliko godina. Nakon pomjeranja
remain, partially flooded with water, and dead toka ostaju stara korita, djelimično zaplavljena
ends are most often formed. vodom i najčešće se formiraju mrtvaje.
Landslides are mostly shallow and involve the
deluvial cover and the crumbling part of the
Klizišta su uglavnom plitka i zahvataju
bedrock. Deeper landslides also occur in some
deluvijalni pokrivač i raspadnuti dio osnovne
places.
stijene. Na nekim mjestima se javljaju i dublja
klizišta.
Landslides are also present, and occur from steep
cliffs. A larger landslide in combination with
Odronjavanje je takođe prisutno, a javlja se sa
landslides and landslides is present at the
strmih litica. Veći odron u kombinaciji sa
location of Lazi Radevića.
kliženjem i osipanjem masa je prisutan na
lokaciji Lazi Radevića.
20
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
21
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
have a clayey and laminar silicate cementation. listasti do pločasti. Listasti alevroliti imaju
glinovito, a pločasti silikatno vezivo.
The ratio in the mutual representation of
sandstones and siltstones ranges from 80-20% in Odnos u međusobnoj zastupljenosti pješčara i
favor of sandstones, with the most common ratio alevrolita se kreće od 80-20% u korist
being 60: 40%. Sandstones and siltstones have a pješčara, sa najčešćim odnosom 60:40%.
relatively slight dip (225 / 15,250 / 15,280 / 25), Pješčari i alevroliti imaju relativno blag pad
with no noticeable creases. They are (225/15,250/15,280/25), bez zapaženih
characterized by 3 systems of cracks at cm- nabornih oblika. Karakterišu ih 3 sistema
distance mutually perpendicular. The size of the pukotina na cm-rastojanju međusobno
crack distance is dictated by the stiffness of the upravnih. Veličina rastojanja pukotina
engineering geological unit and the thickness of diktirana je krutošću inžinjerskogeološke
the layers. jedinice i debljinom slojeva.
Siltstones represent a weaker engineering
geological unit subject to faster surface
Alevroliti predstavljaju slabiju
degradation, and dominantly determine the
inžinjerskogeološku jedinicu podložnu bržoj
conditions for performing engineering works in
površinskoj degradaciji, te dominantno
the surface part of the terrain. The terrain
određuju uslove izvođenja inžinjerskih radova
surface itself is covered with a shallow surface
u površinskom dijelu terena. Sama površina
decay 0.3-0.5 m thick, while the surface impacts
terena je prekrivena plitkom površinskom
are estimated at about 10.0 m.
raspadinom debljine 0,3-0,5m, dok se
Within the Quaternary sediments, we distinguish površinski uticaji procjenju na oko 10,0m.
the following engineering geological
U okviru kvartarnih sedimenata razlikujemo
environments:
sledeće inžinjerskogeološke sredine:
Deluvial sediments (DR, P, G) d;
Deluvial-proluvial sediments (DR, P, G) dpr;
Deluvijalne sedimente (DR,P,G)d;
Terrace sediments (Š, P, G) t1 i
Deluvijalno - proluvijalne sedimente
Alluvial sediments (W, L) al (DR,P,G)dpr;
Terasne sedimente (Š,P,G)t1 i
The engineering geological environment of Aluvijalne sedimente (Š,P)al
-Deluvial sediments (DR, P, G) d has been
Inžinjerskogeološka sredina -Deluvijalnih
isolated in a thickness of over 2.0 m. It occurs
sedimenta (DR,P,G)d je izdvojena u debljini
locally on the slopes of the terrain built of
preko 2.0m. Javlja se lokalno na padinama
carbonate-marly flysch facies, which is
terena izgrađenog od karbontno-laporovite
characterized by a greater thickness of surface
facije fliša, koja se karakteriše većom
decay.
debljinom površinske raspadine.
In a narrow area of research, it was found in the
Na uskom području istraživanja je
vicinity of chainage from Ch 3+080-3+160, ie
konstatovana u okolini stacionaža od st.
3+060-3+150, and 14+100-14+190. The
3+080-3+160, tj 3+060-3+150, i 14+100-
composition of this environment includes: sandy
14+190. U sastavu ove sredine učestvuje:
clay of variable plasticity, brown-reddish color;
pjeskovita glina promjenljive plastičnosti,
sand medium-grained to fine-grained, brown in
braon-crvenkaste boje; pijesak srednjezrn do
color; and debris of marlstones, sandstones,
sitnozrn, smeđe boje; i drobina od laporaca,
22
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
marly limestones, and sandy marlstones. The pješčara, laporovitih krečnjaka i pjeskovitih
size of the fragments ranges from 0.5 to 10 cm. laporaca. Veličina odlomaka kreće se u
Due to the variable mineralogical-petrological rasponu od 0.5 do 10 cm. Zbog promjenljivog
and granulometric composition, the physical- mineraloško-petrološkog i granulometrijskog
mechanical properties of the environment are sastava, promjenljiva su i fizičko-mehanička
also variable. The compressibility is very high to svojstva sredine. Stišljivost je vrlo velika do
medium. The environment is water saturated. srednja. Sredina je vodozasićena. Strmiji
Steeper parts of the environment are subject to djelovi sredine podložni su spiranju i kliženju.
erosion and sliding.
Deluvijalni sedimenti koji nisu izdvojeni kao
Deluvial sediments that have not been singled posebna inžinjerskogeološka sredina su manje
out as a special engineering geological debljine od pomenute i prosječno se kreće oko
environment are smaller in thickness than 1.0m. Sobzirom na njenu malu debljinu,
mentioned and average around 1.0m. Due to its povratno se zaključuje, a što je i kartiranjem
small thickness, it can be concluded, and what utvrđeno, da je ona jače prašinasta, te niže
was determined by mapping, that it is dustier plastičnosti, a navedene niže vrijednosti težina
and lower plasticity, and the lower weight values su posljedica nemogućnosti adekvatnog
are due to the inability to adequately take a soil uzimanja uzorka tla, koji u sebi sadrži
sample, which contains an increased amount of povećanu količinu drobinskog materijala.
debris material.
Deluvijalno - proluvijalni sedimenti
Deluvial - proluvial sediments (DR, P, G)dpr; (DR,P,G)dpr; granulometrijski sastav
the granulometric composition of the proluvial- proluvijalno-deluvijalnog nanosa čini: drobina,
deluvial sediment consists of: debris, sand and pijesak i prašina sa varijatetima ovih jedinica.
dust with varieties of these units. The clay U poodređenom odnosu učestvuje glinovita
component participates in a certain relationship. komponenta. Debljina sredine u okolini
The thickness of the environment around the projektovane trase se kreće do 6m.
designed route is up to 6 m.
U neposrednoj okolini trase, na mjestu
In the immediate vicinity of the route, on the site projektovanih vijadukata lijeve i desne trake
of the designed viaducts of the left and right st.km. 5+900, 6+219 i 6+349 debljina sredine
lanes ch.km. 5+900, 6+219 and 6+349, the se kreće do 4m, kao i u predjelu Jasenovačkog
thickness of the environment is up to 4 m, as well potoka, gdje je projektovana otvorena trasa.
as in the area of Jasenovački potok, where an
open route is projectedesigned.
U granulometrijskom sastavu učestvuje:
The granulometric composition includes: debris
drobina (pješčara, laporaca, glinaca,
(sandstone, marlstone, claystone, limestone,
krečnjaka, breča) veličine od 0.5 do preko 10
breccia), size from 0.5 to over 10 cm; fine-
cm; pijesak sitnozrn do grubozrn, smeđe i
grained to coarse-grained sand, brown and
zelenkaste boje; i glina smeđebraon boje, jače
greenish in color; and brown clay, more sandy.
pjeskovita. Promjenljiv mineraloško-petrološki
The variable mineralogical-petrological and
i granulometrijski sastav uslovljava
granulometric composition conditions the
promjenljiva fizičko-mehanička svojstva
variable physical-mechanical properties of the
sredine, a koja su generalno posmatrano
environment, which are generally considered
povoljna. Sredina je dobro konsolidovana, vrlo
favorable. The environment is well consolidated,
do srednje stišljiva.“
very to medium compressible. "
U potpoglavlju 7.1.2.7.4-2 GEOTEHNIČKO
In sub-chapter 7.1.2.7.4-2 GEOTECHNICAL
ZONIRANJE TERENA navedeno je
ZONING OF THE TERRAIN states the
23
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
following: slijedeće:
The engineering-geological composition and Inžinjerskogeološki sastav i svojstva terena u
properties of the terrain in cooperation with the sadejstvu sa planiranim inžinjerskim zahvatima
planned engineering interventions predetermine predodređuju geotehničko zoniranje, tj
the geotechnical zoning, ie terrain modeling. modeliranje terena.
Considering the engineering geological
composition, general geotechnical models have
S obzirom na inžinjerskogeološki sastav,
been separated, which sporadically have
izdvojeni su opšteni geotehnički modeli, koji
subvariants depending on the narrow local
sporadično imaju podvarijante u zavisnosti od
properties of the terrain and the specifically
uskih lokalnih svojstava terena i konkretno
planned engineering intervention.
planiranog inžinjerskog zahvata.
Within flysch sediments, engineering geological
U okviru flišnih sedimenata,
environments of sandstones and siltstones (Pš) is
inžinjerskogeološke sredine pješčara i
singled out:
alevrolita (Pš) izdvojen je:
GEOTECHNICAL MODEL 1 (GTM-1); it
consists of four geotechnical environments.
Geotechnical environments are separated within GEOTEHNIČKI MODEL 1 (GTM-1); čine ga
sandstones and siltstones, and the fourth is četiri geotehničke sredine. Geotehničke sredine
represented by deluvial or proluvial sediments su izdvojene u okviru pješčara i alevrolita, a
with a max-thickness of 0.5 m, as shown in četvrta sredina je predstavljena deluvijalnim ili
Figure 1. proluvijalnim sedimentima max-debljine 0,5m,
kao što je prikazano na skici 1.
Geotechnical environments "A, B, C" within
sandstones and siltstones (Pš), were isolated on
the basis of physicochemical degradation. Poor
wrinkled and tectonic fracture of sediments, as Geotehničke sredine „A,B,C“ u okviru pješčara
well as the dominant participation of i alevrolita (Pš), izdvojene su na osnovu
sandstones, determined the isolation of this fizičkohemijske degradacije. Slaba ubranost i
geotechnical model. It is characterized by a GSI- tektonska polomljenost sedimenata, kao i
geological strength index of 15-37, according to dominantno učešće pješčara, odredili su
the Hoek-Brown classification. izdvajnje ovog geotehničkog modela.
Karakteriše ga GSI-geološki indeks čvrstoće od
In chapter C. 7.1.2.8. ANALYSIS OF 15-37, po Hoek-Brown klasifikaciji.
INVESTIGATION RESULTS AND
DETERMINATION (SUCCESSFUL
FORECAST) OF GEOTECHNICAL U poglavlju C. 7.1.2.8. ANALIZA
CONDITIONS FOR THE CONSTRUCTION REZULTATA ISTRAŽIVANJA I
OF THE BAR-BOLJARI HIGHWAY UTVRĐIVANJE (USPJEŠNA PROGNOZA)
SECTION: UVAČ - MATEŠEVO; within the GEOTEHNIČKIH USLOVA IZGRADNJE
Separate for the Open Route it is stated: AUTO-PUTA BAR-BOLJARI DIONICA:
Geotechnical terrain modelling UVAČ – MATEŠEVO; u okviru Separata za
otvorenu trasu navedeno je:
"Engineering-geological composition and
properties of the terrain in cooperation with the Geotehničko modeliranje terena
planned engineering interventions predetermine „Inžinjerskogeološki sastav i svojstva terena u
geotechnical zoning, ie terrain modeling. sadejstvu sa planiranim inžinjerskim zahvatima
24
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
25
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
small sliding. As the stratification and bankiness lokalnih šumskih puteva). Osipanje sitnih
of sandstones is rare, with an estimated komada je iz sredine „C“, a ređa odronjavanja
probability of occurrence of 15%, the possibility većih komada duž kosina gdje su pješčari
of landslides of larger pieces is reduced to the slojeviti do bankoviti (fotografija br.8.).
lowest possibility. Sredinu „B“ prati sitno osipanje. Kako je
slojevitost i bankovitost pješčara rijetka, sa
In technogenic surface interventions, the Terrain
procijenjenom vjerovatnoćom javljanja od
Model (GTM-3; environments C2, B2, A2)
15%, to se i mogućnost odronjavanja većih
represents a conditionally stable to unstable
komada smanjuje na najnižu mogućnost.
terrain. Stability, in addition to falling, is
endangered by sliding. Sliding most often occurs
due to inadequate engineering interventions, by
Pri tehnogenim površinskim zahvatima Model
cutting the foot of the slope covered with
terena(GTM-3; sredine C2,B2,A2), predstavlja
deluvial sediments (thickness 2.3 and more m.).
uslovno stabilan do nestabilan teren. Stabilnost
In that case, the environment "E" (deluvial
je pored osipanja i odronjavanja, ugrožena
deposits), often water-saturated, slides along the
kliženjem. Kliženje se najčešće javlja uslijed
environment "C2". Such an example of sliding
neadekvatnih inžinjerskih zahvata,
was found to the left of the entrance portal of the
podsijecanjem nožice padine koja je prekrivena
left tunnel axis of tunnel No. 3, where a
deluvijalnim sedimentima (debljine 2,3 i više
deluvium up to 1.5 thick slid towards the road.
m.). U tom slučaju sredina „E“ (deluvijalne
Remark: Tunnel No. 3 – Cestogaz – not existing naslage), često vodozasićena klizi po sredini
in the Main Design „C2“. Takav primjer kliženja je konstatovan
lijevo od ulaznog portala lijeve tunelske ose
In technogenic surface interventions, this terrain
tunela br.3., gdje je deluvijum debljine do 1,5
model (GTM-2; environments C1, B1, A1)
klizao prema putu.
represents conditionally stable to unstable
terrain. Stability is, in addition to falling and Napomena: Tunel br. 3 – Čestogaz – ne postoji
landslides, endangered by possible sliding of the u Glavnom projektu
environment "E" in the conditions of inadequate
Pri tehnogenim površinskim zahvatima, ovaj
cutting of slopes, and in the way already
model terena (GTM-2; sredine C1,B1,A1),
described in tunnel no.4. The presence of small
predstavlja uslovno stabilne do nestabilne
debris scattering and less frequent erosion of
terene. Stabilnost je pored osipanja i
larger pieces is present along the notches in the
odronjavanja, ugrožena mogućim kliženjem
environment C1 and B1.
sredine „E“ u uslovima neadekvatnog
In any case, for these mountainous areas, it is podsijecanja padina, a na način kako je već
a general statement that instabilities along the opisano kod tunela br.4. Prisustvo osipanja
subvertical to vertical slopes of the cut in the sitne drobine i ređe odronjavanje krupnijih
form of sliding, shedding and subordinate komada je prisutno duž zasjeka u sredinama C1
landslides are present, which must be taken i B1.
into account when designing the highway
U svakom slučaju za ove planinske predjele
section. Also, due to the easy movement of the
opšta je konstatacija da su nestabilnosti duž
deluvial debris (thickness over 2 m), the
izvedenih subvertikalnih do vertikalnih kosina
inclination of the executed slope (max. 1: 0.5)
zasjeka u vidu kliženja, osipanja i podređeno
and its protection must be taken into account.
odronjavanja prisutna o čemu se mora voditi
The chapter Geotechnical conditions for the računa prilikom projektovanja dionice
construction of cuts and walls states: autoputa. Takođe se zbog lakog pokretanja
deluvijalne drobine (debljine i preko 2m) mora
26
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
"Until the chainage km 2+312.00, the cuts are in voditi računa o nagibu izvedene kosine (max
the environment, which is built by sandstones 1:0,5) i njenom osiguranju.
and siltstones, and subordinately by claystones
U poglavlju Geotehnički uslovi izgradnje
and sandy limestones. The coating is a deluvial
usjeka, zasjeka i zidova navedeno je:
material of small thickness (0.5-0.7 m). There
are calculated parameters according to the „Do stacionaže km 2+312.00 zasecanja su u
geotechnical model GTM-1. sredini koju grade pješčari i alevroliti i
podređeno glinci i pjeskoviti krečnjaci. U
Remark: mentioned chainages are related to the
povlati je deluvijalni materijal male debljine
Section Uvac – Matesevo from the Preliminary
(0.5-0.7m). Tu su računski parametri po
Design and corresponds to location of
geotehničkom modelu GTM-1.
Contractor’s Claim No. 117.
Napomena: navedene stacionaže odnose se na
The remaining part of the open route is in the
dionicu Uvač – Mateševo iz Idejnog projekta i
environment formed by the marly-carbonate
korespondiraju lokaciji Izvođačevog
flysch facies, which is characterized by
Potraživanja br. 117.
increased thickness of surface decay and
increased thickness of deluvial and deluvial-
proluvial (2-3m) sediments. The calculated
parameters are according to the geotechnical Preostali dio otvorene trase je u sredini koju
models GTM-2 and GTM-3. gradi laporovito-karbonatna facija fliša, koju
karakteriše povećena debljina površinske
Cutting is mostly in a zone that is significantly raspadine i povećana debljina deluvijalnih i
physico-chemically altered. The thickness of this deluvijalno-proluvijalnih (2-3m) sedimenata.
zone ranges from 10m (geotechnical Računski parametri su po geotehničkim
environments B + C in the GTM-1 model) to modlima GTM-2 i GTM-3.
over 18m (geotechnical environments B2 + C2
in the GTM-3 model). Layer orientation is Zasjecanje je najvećim dijelom u zoni koja je
generally favorable in all zones (mostly falling značajnije fizičko-hemijski izmijenjena.
uphill). The joints are steeply sloping, Debljina ove zone se kreće od 10m
perpendicular to the layers. (geotehničke sredine B+C u modelu GTM-1) do
preko 18m (geotehničke sredine B2+C2 u
In general, it can be accepted that according to modelu GTM-3) . Orjentacija slojeva generalno
the geotechnical model GTM-1, the slopes are je povoljna na svim zonama (uglavnom padaju
made in the inclination 1.5: 1 to 2: 1 in the u brdo). Pukotine su strmog pada, upravne na
geotechnical environment B and 2: 1 to 3: 1 in slojeve.
the geotechnical environment A. In the surface
part in the geotechnical environment C in the
slope 1 : 1 to 1: 1.5.
Generalno se može prihvatiti da po
The general inclination of the cut slopes geotehničkom modelu GTM-1, kosine izvesti u
according to the geotechnical model GTM-2 and nagibu 1.5:1 do 2:1 u geotehničkoj sredini B i
GTM-3, execute in the inclination of 2:1 2:1 do 3:1 u geotehničkoj sredini A. U
geotechnical environment B1 / B2 and 3:1 površinskom dijelu u geotehničkoj sredini C u
geotechnical environment A1 / A2. In the surface nagibu 1:1 do 1:1.5.
part in the geotechnical environment C1 / C2 in
the inclination 1:1 and in the environment E
with the inclination 1:1.5. Generalni nagib kosina zaseka po
geotehničkom modelu GTM-2 i GTM-3, izvesti
On parts of the cuts where a satisfactory u nagibu 2:1 geotehnička sredina B1/B2 i 3:1
27
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
28
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
Picture 3: Elaborate of detailed geotechnical Investigations for the preparation of the Preliminary Design;
Section: Uvač-Mateševo - Separate for the Open route; Enclosure C4.1 – Engineering-geological map CH
km from 0+000-0+483,50 – right axe; 0+000 to 0+515 – left axe
Slika 3: Elaborat detaljnih geotehničkih istraživanja za izradu Idejnog projekta; Dionica: Uvač-Mateševo
– Separat za otvorenu trasu; Prilog C4.1 - Inženjerskogeološku karta st. km od 0+000-0+483,50 – desna
os; 0+000 do 0+515 – lijeva os
29
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
Picture 4: Elaborate of detailed geotechnical Investigations for the preparation of the Preliminary Design;
Section: Uvač-Mateševo; Enclosure C4.1.1I – Forecasted engineering-geological longitudinal profile open
route CH km from 0+000 to 0+515 – left axe
Slika 4: Elaborat detaljnih geotehničkih istraživanja za izradu Idejnog projekta; Dionica: Uvač-Mateševo;
Prilog C4.1.1I - Prognozni inženjerskogeološki presjek terena otvorena trasa st. km 0+000 do 0+515 –
lijeva os
30
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
Taking into account the main purpose of the Uzimajući u obzir glavnu svrhu Idejnog
Preliminary Design to provide input data for the projekta da obezbijedi ulazne podatke za
Design and Built Contractor; by relatively low, izvođača radova na projektovanju i izgradnji;
but sufficient level of geotechnical relativno niskim, ali dovoljnim nivoom
investigations, the appearance of a geotechnical geotehničkih istraživanja, pojave geotehničkog
model defined as GEOTECHNICAL MODEL 1 modela definisanog kao GEOTEHNIČKI
(GTM-1), and is represented along the section MODEL 1 (GTM-1), a zastupljen je duž
from ch.km.0 + 000 to ch.km.2 + 130 (on the dionice od st.km.0+000 do st.km.2+130 (po
right axis), or 2 + 312 (on the left axis), are desnoj osi), odnosno 2+312 (po lijevoj osi),
described in the Geotechnical Study. opisane su u Geotehničkom elaboratu.
GEOTECHNICAL MODEL 1 (GTM-1); GEOTEHNIČKI MODEL 1 (GTM-1); čine
consists of four geotechnical environments. četiri geotehničke sredine. Geotehničke sredine
Geotechnical environments are separated within su izdvojene u okviru pješčara i alevrolita, a
sandstones and siltstones, and the fourth one is četvrta sredina je predstavljena deluvijalnim ili
represented by deluvial or proluvial sediments proluvijalnim sedimentima max-debljine 0,5m.
with a max-thickness of 0.5 m.
Napomena: navedene stacionaže odnose se na
Remark: mentioned chainages are related to the dionicu Uvač – Mateševo iz Idejnog projekta i
Section Uvac – Matesevo from the Preliminary korespondiraju lokaciji Izvođačevog
Design and corresponds to location of Potraživanja br. 117.
Contractor’s Claim No. 117.
Also, as part of the Report, the following is
Takođe, u sklopu Elaborata navedeno je
stated: " In any case, for these mountainous
slijedeće: „U svakom slučaju za ove planinske
areas, it is a general statement that instabilities
predjele opšta je konstatacija da su
along the subvertical to vertical slopes of the cut
nestabilnosti duž izvedenih subvertikalnih do
in the form of sliding, shedding and subordinate
vertikalnih kosina zasjeka u vidu kliženja,
landslides are present, which must be taken into
osipanja i podređeno odronjavanja prisutna o
account when designing the highway section.
čemu se mora voditi računa prilikom
Also, due to the easy movement of the deluvial
projektovanja dionice autoputa. Takođe se zbog
debris (thickness over 2 m), the inclination of the
lakog pokretanja deluvijalne drobine (debljine i
executed slope (max. 1: 0.5) and its protection
preko 2m) mora voditi računa o nagibu
must be taken into account. "
izvedene kosine (max 1:0,5) i njenom
The mentioned Geotechnical Study is an integral osiguranju.“
part of the Preliminary Design and was available
Navedeni Geotehnički elaborat je sastavni dio
to the Contractor in the tender phase of the
Idejnog projekta i bio je dostupan Izvođaču u
Project.
tenderskoj fazi Projekta.
We also refer to the statement of the Designer of
Takođe, pozivamo se na navod Projektanta
the ELABORATION ON DETAILED
ELABORATA O DETALJNIM
GEOTECHNICAL CONDITIONS FOR
GEOTEHNIČKIM ISTRAŽIVANJIMA ZA
REHABILITATION AND MONITORING
POTREBE SANACIJE I MONITORINGA
OF LEFT SLOPE AT KM LK 31+705 TO
LIJEVE KOSINE NA KM LK 31+705 DO
LK 31+820 first stage where he stated the
LK 31+820 prva faza gdje je konstatovao
following: “Certainly, in the stage of the Main
slijedeće: „Svakako da u fazi glavnog projekta
civil design it is impossible to review each slope
autoputa nije moguće razmatrati svaku padinu
planned for side-cut as a potential landslide, so
u kojoj se planira zasjek kao potencijalno
as to design greater number of surveys at that
klizište, da bi se u toj fazi projektovao veći broj
stage and have a better insight into EG
31
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
structure.” If this is not possible in the Main istraživanja i samim tim imao bolji uvid u IG
Design phase, even less consideration is given in građu terena.“ Ukoliko to nije moguće izvesti
the Preliminary Design phase. u fazi Glavnog projekta, jož je manje
razmatranje istog u fazi Idejnog projekta.
Expected reaction of the world-renowned
Contractor, taking into account the data available Očekivana reakcija svjetski priznatog
at the time of the Bid on the existence of a Izvođača, uzevši u obzir podatak dostupan u
geotechnical environment in which flysch vrijeme Ponude o postojanju geotehničke
sediments are covered with deluvial cover (note sredine u kojoj su flišni sedimenti prekriveni
that no exploratory boreholes were not drilled at deluvijalnim pokrivačem (napominjemo da na
the site – the data were given by geological navedenoj lokaciji nisu rađene istražne bušotine
mapping of the terrain, what is usually, having in u okviru Idejnog projekta – podaci su dobijeni
mind the Design level - Preliminary Design) and geološkim kartiranjem terena, što je uobičajeno,
the complexity of the designed structure (gravity imajući na umu nivo Projekta – Idejni projekt) i
retaining wall with high and prety steep slopes kompleksnosti projektovane konstrukcije
above) would be a more detailed investigation in (gravitacioni potporni zid sa visokim i prilično
order to obtain confirmation of the Main Design. strmim kosinama iznad) bila bi detaljnije
However, although there were two inclinometer istraživanje u svrhu dobivanja potvrde Glavnog
structures on the said slope, the main role of projekta. Međutim, iako su na navedenoj kosini
which was to analyze the depth displacement in postojale dvije inklinometarske konstrukcije,
order to confirm the potential landslide, the čija je glavna uloga analiza pomjeranja po
Contractor by his decision stopped the dubini u svrhu potvrđivanja potencijalnog
monitoring. This is the main purpose of klizišta, Izvođač je samoinicijativno prekinuo
geotechnical investigations for the level of the sa monitoringom. To i je glavni smisao
Main Design, which does not necessarily end geotehničkih istraživanja za nivo Glavnog
with the approval of the Main Design. projekta, koja nužno ne završavaju odobrenjem
Glavnog projekta.
Bearing in mind all the above, as well as the fact
that the above information is considered Imajući na umu sve gore navedeno, kao i
sufficient for the level of Preliminary Design, as činjenicu da se pomenute informacije smatraju
well as the fact that the Contractor is an dovoljnim za nivo Idejnog projekta, kao i
experienced and world-renowned Contractor, činjenicu da je Izvođač radova na projektovanju
with prior knowledge of similar works in a i izgradnji iskusan i svjetski priznat Izvođač, sa
similar environment, the Engineer’s opinion is prethodnim poznavanjem sličnih radova u
that the mentioned geological conditions cannot sličnom okruženju, mišljenje Nadzornog organa
be treated as unforeseeable geological je da se pomenuti geološki uslovi ne mogu
conditions. tretirati kao nepredvidivi geološki uslovi.
32
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
33
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
34
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
levels in some parts) without successive ovim terenima (slika 31). Takođe je
anchoring and security is unacceptable in these neprihvaljivo da kosine ostanu ne osigurane
terrains (Figure 31). It is also unreasonable for duži vremenski period.
the slopes to remain unsecured for a longer
Ankeri koji su korišćeni na ovoj kosini su SN
period of time.
ankeri. Ovi ankeri su neprihvatljivi za ovaj tip
Anchors used for this slope are SN anchors. terena u kome dominira F kategorija stijenske
These anchors are unacceptable for this type of mase. Njih nije moguće adekvatno ugraditi u
terrain that is dominated by the F category of ovu kategoriju stijenske mase tako da je upitna
rock mass. They can not be adequately funkcija ove mjere osiguranja.
incorporated into this category of rock mass so
Na vrhu kosine je postojao površinski drenažni
the function of this security measure is
kanal (dubine do 1 m), nedaleko od vrha
questionable.
škarpe, ali on sam po sebi nema funkciju u
There was a surface drainage channel (depths eliminsanju nepovoljnih podzemnih voda već
up to 1 m) at the top of the slope, not far from samo eliminisanje površinskih voda koje
the top of the vice, but it itself had no function in spiraju lice kosine prilikom većih padavina.
eliminating the adverse groundwater but only
eliminating the surface water washing the face
of the slope during higher precipitation. Sve gore navedeno, uz nepovoljnu IG građu
padine, što je prikazano u prethodnim
All the above, together with EG composition of
poglavljima, rezultuje klizištem.“
the slope presented in the previous chapters,
results in landsliding.” Tokom izvođenja radova i Inženjer je aktivno
upozoravao Izvođača o mogućim negativnim
During the execution of the works, the
posljedicama u vidu lokalnih i globalnih
Engineer actively warned the Contractor about
nestabilnosti, pa se pozivamo na pisani
possible negative consequences in the form of
komentar Inženjera na Geološkom izvještaju,
local and global instabilities, so we refer to the
nakon pojave prvih lokalnih nestabilnosti:
written Engineer’s comment on the Geological
„Podsjećamo Izvođača da pomno prati
Report, after the first local instabilities were
kosinu i u slučaju bilo kakve lokalne
observed: “We are reminding the Contractor
(globalne) nestabilnosti obavijesti
to closely monitor the slope and in case of
Projektanta i preprojektuje te primijeni
any local (global) instability inform a
dodatne mjere zaštite kosine.
Designer and re-design and apply additional
slope support measures. Takođe, Izvođač bi trebao ponovno razmotriti
hidro sjetvu kako bi izbjegao eroziju (HITNO
Also, Contractor should re-consider hydro
- s obzirom na vremenske uslove)!“
seeding in order to avoid errosion (ASAP – in
respect to weather conditions)!“ Sve gore navedeno dovodi do zaključka da se
ovo klizište može posmatrati prema Podklauzuli
All of the above mentioned leads to the
7.1 Način izvođenja Uslova Ugovora u kojoj je
conclusion that this landslide can be observed
definisano: - Izvođač se obavezuje da
according to Subclause 7.1 Manner of
proizvede Postrojenje, proizvede i izradi
Execution where defines as: The Contractor
materijale i izvede sve ostale Radove:
shall carry out the manufacture of Plant, the
production and manufacture of Materials, (a) na način predviđen Ugovorom (ako
and all other execution of the Works: je predviđen),
(a) in the manner (if any) specified in the (b) stručno i pažljivo, u skladu sa
Contract, priznatom dobrom praksom, i
35
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
36
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
37
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
Contractor's description of this Claim event is: U obrazloženju ovog događaja potraživanja
“On construction Site of 4.1 subsection, the Izvođač navodi: “„Na gradilištu podeskcije 4.1
Contractor encounter a change in the geological Izvođač se susreo sa promjenom geoloških
conditions at the part of open route, so THE uslova na dijelu otvorene trase, pa se
Main Design for Gravity retaining wall 1 and pristupilo izmjeni Glavnog projekta
slope has been modified. gravitaciono potpornog zida 1 i kosine.
The Contractor considers theses adverse Izvođač smatra da su ovi nepovoljni fizički
physical conditions to have been Unforeseeable, uslovi Nepredvidivi, stoga, u skladu sa PK 4.12
therefore in accordance with SC 4.12 of the Ugovora o projektovanju i izgradnji Autoputa
Design and Build Contract for Bar-Boljare Bar-Boljare, Izvođač je obavijestio Inženjera
Highway, the Contractor informed the Engineer dopisom RB-BBH/ 23/CD-P3 datiranim
that we encountered unforeseeable physical 07.01.2019. godine (Prilog 2) da smo se susreli
conditions on the construction site via letter RB- sa nepredvidivim fizičkim uslovima na
BBH/ 23/CD dated on 07.01.2019 (Enclosure gradilištu.”
2).”
We are reffering to the STUDY ON
Pozivamo se na ELABORAT O
DETAILED GEOTECHNICAL
DETALJNIM GEOTEHNIČKIM
INVESTIGATIONS (BASIS FOR THE
ISTRAŽIVANJIMA (PODLOGE ZA NIVO
LEVEL OF THE PRELIMINARY
IDEJNOG GRAĐEVINSKOG PROJEKTA)
CONSTRUCTION DESIGN) HIGHWAY
AUTO PUT „BAR – BOLJARI“ DIONICA:
"BAR - BOLJARI" SECTION: "UVAČ -
„UVAČ – MATEŠEVO“ – Separat za
MATEŠEVO" - Separate for open route.;
otvorenu trasu; Prilog C4.1 -
Enclosure C4.1 – Engineering-geological map
Inženjerskogeološku karta st. km od 0+000-
CH km from 0+000-0+483,50 – right axe;
0+483,50 – desna os; 0+000 do 0+515 – lijeva
0+000 to 0+515 – left axe, as well as Enclosure
os (slika 3), kao i Prilog C4.1.1I - Prognozni
C4.1.1I – Forecasted engineering-geological
inženjerskogeološki presjek terena otvorena
longitudinal profile open route CH km from
trasa st. km 0+000 do 0+515 – lijeva os (slika
0+000 to 0+515 – left axe (Figure 4).
4).
Also, in the textual part of the study, an
Takođe, u tekstualnom dijelu elaborata dat je
unambiguous description of the geotechnical
nedvosmisleni opis geotehničkog modela 1
38
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
model 1 (GTM 1) located on the part of the open (GTM 1) lociranog na dijelu otvorene trase na
route to which this Contractor's Claim refers is koji se odnosi ovo Potraživanje Izvođača. Uz
given. Along with the description of the model, opis modela nedvosmisleno je navedeno da se
it is unequivocally stated that in these flysch u ovim flišnim formacijama sa kvartarnim
formations with a Quaternary cover built of pokrivačem izgrađenim od deluvijalnog nanosa
deluvial sediment, sliding of material can be može očekivati klizanje materijala, a kao
expected, and anthropogenic influences are osnovni uzrok navedeni su antropogeni uticaji:
stated as the main cause: Sliding most often „Kliženje se najčešće javlja uslijed
occurs due to inadequate engineering neadekvatnih inžinjerskih zahvata,
interventions, by cutting the foot of the slope podsijecanjem nožice padine koja je
covered with deluvial sediments (thickness 2, 3 prekrivena deluvijalnim sedimentima (debljine
and more m)." 2,3 i više m.).“
Uzevši u obzir navedene dijelove
ELABORATA O DETALJNIM
By taking into consideration mentioned parts of
GEOTEHNIČKIM ISTRAŽIVANJIMA
the STUDY ON DETAILED
(PODLOGE ZA NIVO IDEJNOG
GEOTECHNICAL INVESTIGATIONS
GRAĐEVINSKOG PROJEKTA) AUTO
(BASIS FOR THE LEVEL OF THE
PUT „BAR – BOLJARI“ DIONICA:
PRELIMINARY CONSTRUCTION
„UVAČ – MATEŠEVO“ – Separat za
DESIGN) HIGHWAY "BAR - BOLJARI"
otvorenu trasu; zaključak Inženjera je da je
SECTION: "UVAČ - MATEŠEVO" -
dostavljeni Idejni projekt u fazi Tendera, na
Separate for open route, the Engineer’s
osnovu kojeg je pripremljena ponuda pruža
conclusion is that delivered Preliminary
Izvođaču dovoljnu informaciju na osnovu
Design in the Tender phase, base for the
koje je mogao predvidjeti stvarne geološke
Offer preparation, providing enough
uslove.
information to the Contractor to forseen
exact geological conditions. Takođe, nejasnan je razlog iz kojeg se Izvođač
odlučio na prekid monitoringa inklinometarskih
Also, the reason why the Contractor decided to
konstrukcija nakon završetka geotehničkih
stop monitoring inclinometer structures after the
istraživanja u svrhu pripreme Glavnog projekta,
completion of geotechnical investigations for the
iako je uobičajena praksa da se navedeni
preparation of the Main Design is unclear,
monitoring nastavlja tokom faze izgradnje, kao
although it is common practice to continue this
i tokom operativne faze autoputa – naravno, sa
monitoring during the construction phase and
drugačijom frekvencijom očitanja. Na taj način
during the operational phase of the highway - of
onemogućen je uvid u pomjeranja u dubini, a
course with a different frequency of readings. In
posredno je onemogućeno uočavanje klizišta
this way, the insight into the displacements in
prije početka izvođenja građevinskih radova.
depth is disabled, and indirectly the detection of
landslides before the start of construction works
is disabled.
Prema našem mišljenju, smisao kontinuiranog
In our opinion, the purpose of continuous geotehničkog monitoringa ja dobivanje
geotechnical monitoring is to obtain measurable mjerljivih podataka o pomjeranjima, a samim
data on displacements, and thus control the time i kontrola pretpostavki Glavnog projekta, a
assumptions of the Main Design, which was not što ovdje nije bio slučaj.
the case here.
Mišljenje Inženjera je da se dogodio propust u
The opinion of the Engineer is that there was an Načinu izvođenja - stručno i pažljivo, u
omission in the Manner of Execution - in a skladu sa priznatom dobrom praksom, a što
39
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
proper workmanlike and careful manner, in dokazuju upozorenja u sklopu Idejnog projekta
accordance with recognised good practice, as i navodi iz ELABORATA O DETALJNIM
evidenced by the warnings within the GEOTEHNIČKIM ISTRAŽIVANJIMA ZA
Preliminary Design and statements from the POTREBE SANACIJE I MONITORINGA
ELABORATION ON DETAILED LIJEVE KOSINE NA KM LK 31+705 DO
GEOTECHNICAL CONDITIONS FOR LK 31+820 prva faza, koji je konstatovao
REHABILITATION AND MONITORING slijedeće:
OF LEFT SLOPE AT KM LK 31+705 TO
„Kao i obično, na formiranje klizišta uticalo je
LK 31+820 first stage, which stated the
dosta faktora od čega je potrebno izdvojiti
following: “As usual, formation of landslides
glavni uzrok klizanja a to je antropogeni uticaj
has been influenced by many factors, and the
tj. izgradnja dijela usjeka i neadekvatno
main cause of the sliding is anthropogenic
osiguranje istog.
influence, i.e. construction of through-cut and
inadequate security of the slope. Pored toga iskop cijele etaže (a u pojedinim
djelovima i dvije etaže) bez sukcesivnog
In addition, excavating the entire level (even two
ankerisanja i osiguranja je neprihvatljivo u
levels in some parts) without successive
ovim terenima (slika 31). Takođe je
anchoring and security is unacceptable in these
neprihvaljivo da kosine ostanu ne osigurane
terrains (Figure 31). It is also unreasonable for
duži vremenski period.“
the slopes to remain unsecured for a longer
period of time. Mišljenje je Inženjera da je do propusta došlo
izvođenjem radova u kojima nije praćen
The Engineer’s opinion is that the omission
propisani redoslijed radova. Iskop kosina u
occurred due to the execution of works in which
geotehničkim sredinama potvrđenim na lokaciji
the prescribed sequence of works was not
potrebno je voditi horizontalno i vertikalno na
followed. The excavation of slopes in
način da se iskopani dio kosine može zaštititi
geotechnical environments confirmed on the site
odgovarajućim elementima zaštite kosina u
should be conducted horizontally and vertically
jednom danu.
in such a way that the excavated part of the slope
can be protected by appropriate elements of Odmah nakon iskopa potrebno je ugraditi
slope protection in one day. odgovarajuće elemente zaštite kosina, čije je
parametre potrebno potvrditi propisanim
Immediately after the excavation, it is necessary
ispitivanjima što je prije moguće.
to install the appropriate slope protection
Napominjemo da su na kosini ugrađivana SN
elements, the parameters of which must be
sidra za koja je propisano ispitivanje nosivosti
confirmed by the prescribed tests as soon as
čupanjem sidara, a isto ispitivanje nije
possible. Please note that SN anchors were
izvršeno prije pojave klizišta. Pozivamo se na
installed on the slope, for which the load-bearing
pisani komentar Inženjera u sklopu
capacity test by pull-out the anchors was
odobravanja (uz komentare) Izvođačevog
prescribed, and the same test was not performed
Geološkog izvještaja: „Podsjećamo Izvođača
before the landslide occurred. We refer to the
da pomno prati kosinu i u slučaju bilo kakve
written comment of the Engineer as part of the
lokalne (globalne) nestabilnosti obavijesti
approval (with comments) of the Contractor's
Projektanta i preprojektuje te primijeni
Geological Report: “We are reminding the
dodatne mjere zaštite kosine.
Contractor to closely monitor the slope and in
case of any local (global) instability inform a Takođe, Izvođač bi trebao ponovno razmotriti
Designer and re-design and apply additional hidro sjetvu kako bi izbjegao eroziju (HITNO
slope support measures. - s obzirom na vremenske uslove)!“
Also, Contractor should re-consider hydro
40
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
41
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo
42