Sample X: Determination Engineer To Parties: Determination This Document Is Suitable For Use With The FIDIC Yellow and Red Book

The engineer provides a determination regarding Claim [number] related to Project [name]. The determination grants the Contractor [number] of days extension for completion of the project. The engineer reviewed statements from both parties and the Contractor's submitted particulars and evidence. The engineer found the Contractor gave timely notice of the relevant facts and was entitled to an extension according to the relevant sub-clauses because the event impacted a critical path activity.

Uploaded by

Vlatko Mihajlov
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
345 views1 page

Sample X: Determination Engineer To Parties: Determination This Document Is Suitable For Use With The FIDIC Yellow and Red Book

The engineer provides a determination regarding Claim [number] related to Project [name]. The determination grants the Contractor [number] of days extension for completion of the project. The engineer reviewed statements from both parties and the Contractor's submitted particulars and evidence. The engineer found the Contractor gave timely notice of the relevant facts and was entitled to an extension according to the relevant sub-clauses because the event impacted a critical path activity.

Uploaded by

Vlatko Mihajlov
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Sample X: Determination 427

Sample X: Determination
Engineer to Parties: Determination
This document is suitable for use with the FIDIC Yellow
and Red Book

Claim [insert number] related to project [insert project name]

Dear Sirs,

I hereby give notice of my determination as to claim no. [insert number]. With


regard to all relevant facts and circumstances I determine that the Contractor is
entitled to [. . .] days of extension of Time for Completion.
I have given my approval/disapproval with comments on [. . .].
I have consulted with the Parties who have submitted the following statements:
[insert details of statements]
The Contractor has submitted
l particulars
l supported by evidence,
l including contemporary records,
l which I have monitored.
The Contractor has given notice of [. . .] on [insert date]:
l This was in time because he became aware of the relevant facts on [. . .].
l This was not in time because became aware of the relevant facts on
[. . .].
In accordance with Sub-Clause [. . .] the Contractor is entitled to extension of Time
for Completion. In accordance with Sub-Clause 8.4 the relevant event must have an
impact on an activity which lies on the critical path. Both requirements are met:
[Insert reasons]

Yours faithfully

(Engineer)