Required Detail Against Commissioned Lines FY 19-20

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 4

Project South Spread

TRANSMISSION LINES COMMISSIONED DURING F.Y. 2019-20

Dia. Commissining
Sr. # Type Kms Job Number Description of Line Commissioning Date
(Inch) Length (Kms)

1 93.00 24 18/70/00-0987 Loopline from A8 To Punjab Power Plant Jhang 92.77 20.09.2019 & 21.09.2019

2 24.00 16 19/60/00-0992 Gas Feeder Line of Pakarab Fertilizer Limited 23.40 30.11.2019

12
3 1.40 19/60/00-0992 Gas Feeder Line of Pakarab Fertilizer Limited 1.28 07.02.2020
(10mm)

4 50.70 10 13/70/00-0933 Transmission Line From Rep. Stn. F3 Daud Khel to Mianwali 50.70 07.05.2020

SALES METERING STATIONS (SMSs) COMMISSIONED DURING FY 2019-20

Sr. # Job Number Capacity Description of SMS Commissioning Date


(MMCFD)

1 12/70/230919 5 SMS ROJHAN 03.10.2019

2 18/70/25-0987 200 SMS Cum CMS Punjab Power Plant Jhang 16.10.2019

3 17/74/60-0855 5 SMS Mandi Yazman 30.06.2020

4 10/70/23-0881 1 SMS Shahwali 30.06.2020


South Spread

Satatus of Completion Reports Status Contractor Payment (FPC) Booked in Accrual Other Pending Payment Included in Accrual

5223344
(CIVIL 1107475)

(CIVIL756320, (CP 413419)


3318415

6806084

Satatus of Completion Reports Status Contractor Payment (FPC) Booked in Accrual Other Pending Payment Included in Accrual
Project South Spread

Material Contractor Payment (FPC) Booked in


Sr. # MNA / MPA Job# Year Description / Name of Locality / Village Commissioning Date Region Remarks Satatus of Completion Reports Status Accrual Other Pending Payment Included in Accrual
MS/PE

1 NA-142 17/33/019440 17 Supply Mian from Village Kot Umar Din to Ghuman Kalan MS 2-Jul-19 LHR Commissioned on 02.07.2019 Sent through memo No. F/EIC/PSS/19-20 (272) dated 14.05.2020 Sent

Supply Main For M/S Dream Avenue Housing Society


2 COST JOB 18/33/022140 18 Lahore MS 18-Jul-19 LHR Commissioned on 18.07.2019. Pending

Operational Phase from School Chowk to Neeli Kothi,


3 OPS 19/58/062412 19 MS 19-Sep-19 MUL Commissioned on 19.09.2019. Sent through memo No. F/EIC/PSS/19-20 (237) dated 15.03.2020 Sent 82719
A&B Block, Shah Rukne Alam Colony, Multan NO
Operational Phase from T-Chowk Shah Rukn-e-Alam to
4 OPS 19/58/061312 19 Noon Chowk, New Multan MS 19-Sep-19 MUL Commissioned on 19.09.2109. Sent through memo No. F/EIC/PSS/19-20 (237) dated 15.03.2020 Sent
NO
Supply Main for Rakh Mundaky, Kot Mehtab Khan, Chak
5 NA-141 17/33/019240 17 MS 28-Sep-19 LHR Commissioned on 28.09.2019. Sent through memo No. F/EIC/PSS/20-21 (07) dated 15.07.2020 Sent
No.18, Chak No.15 & Chak No.17 of NA-141 Distt. Kasur

6 OPS 18/33/014012 18 Operational Phase from SMS Abdul Hakim to Mummy MS 17-Oct-19 MUL Commissioned on 17.10.2019. Partially completion report Sent through memo No. F/EIC/PSS/19-20 (237) Partial
Shopping Goods Center, Abdul Hakim dated 15.03.2020 69779
Segments Partially Commissioned out OF 2" Dia 8165 & 13/04/2018 Partially commissioned on 13.04.2018 &
7 NA-129 18/35/044740 18 1-1/4" Dia 13423 Meters PE Gas Mains for Various PE LHR Pending
Localities of Lahore 17/10/2019 17.10.2019

Operational Phase for new Galgasht Nawabpur Road Partially completion report Sent through memo No. F/EIC/PSS/19-20 (237)
8 OPS 17/33/013012 17 Chah Nainwala and Adjacent Localities MS 23-Oct-19 MUL Commissioned on 23.10.2019 dated 15.03.2020 Partial
NO

●1st Segment 0.86 Km (2830')


9 COST 19/53/002512 19 Supply Main for Shifting/Re-routing of Network due to MS 24/10/2019 MUL commissioned on 24.10.2019. Sent through memo No. F/EIC/PSS/20-21 (14) dated 21.07.2020 Sent
Dualization of Taunsa Urban Area 25/10/2019 ●2nd Segment 0.56 Km (1843')
commissioned on 25.10.2019.
NO
10 GOVT 12/33/111213 12 Supply Main for Rojhan Mazari, Rajanpur (NA-195) MS 25-Oct-19 BWP Commissioned on 25.10.2019. Sent through memo No.F/EIC/PSS/20-21 (01) dated 06.07.2020 Sent
NO
Operational Phase Siddiqui Mobile Old Shujaabad Road to
11 OPS 18/33/013612 18 MS 2-Nov-19 MUL Commissioned on 02.11.2019 Sent through memo No. F/EIC/PSS/19-20 (296) dated 22.06.2020 Sent 82719
Fashion Glamour, Farooqpura Road, Multan NO

12 OPS 18/33/004513 18 Operational Phase for Low Gas Pressure in Sadiqabad City MS 5-Nov-19 BWP Commissioned on 05.11.2019. Pending
NO
RLNG Based Industrial (Captive Power) Gas Connection to
13 COST 19/32/891221 19 M/S Roomi Food Pvt. Limited 04-Km Multan road, MS 13-Nov-19 MUL Commissioned on 13.11.2019. Sent through memo No. F/EIC/PSS/19-20 (296) dated 22.06.2020 Sent
Molapur Kabirwala
39617
Operational Phase from Sui Gas Road to PTCL Exchange Partially completion report Sent through memo No. F/EIC/PSS/19-20 (237)
14 OPS 18/33/014312 18 Shah Shams Road, Multan MS 14-Nov-19 MUL Commissioned on 14.11.2019. dated 15.03.2020 Partial
NO

Segments Partially Commissioned out OF 8" Dia 11500


26/11/2019 8inch dia partially commissioned on
15 COST JOB 18/53/019040 18 Meters & 6" DIA 100 Meters Supply Main Relocation MS 21/01/2020 LHR 26.11.2019 & 21.01.2020 and 6inch dia Pending
from Hudiara Drain Bridge, Multan Road to Thokar Niaz
Baig Interchange, Lahore 26/11/2019 partially commissioned on 26.11.2019.

Operational Phase from SMS Khanpur Nawakot Road to


16 OPS 19/58/060213 19 existing TBS Punjmori Bago, Bahar Road Khanpur MS 27-Nov-19 BWP Commissioned on 27.11.2019. Pending
NO

17 NA-142 17/33/017340 17 Supply Main for Chak No. 32 and Chak No. 33 District MS 3-Dec-19 LHR Commissioned on 03.12.2019. Sent through memo No. F/EIC/PSS/20-21 (07) dated 15.07.2020 Sent
Kasur NA-140 (Old NA-142)

Supply Main from Jamber Kalan to Village Bho-e- Asal,


18 NA-142 17/33/017440 17 MS 3-Dec-19 LHR Commissioned on 03.12.2019. Sent through memo No. F/EIC/PSS/20-21 (07) dated 15.07.2020 Sent
NA-140 (Old NA-142) Distt. Kasur

Supply Main for RLNG Based Industrial Gas Connection to


M/S Dream Garden Phase-I & II Housing Scheme, Izhar
19 COST JOB 18/33/022540 18 MS 26-Dec-19 LHR Commissioned on 26.12.2019 Sent through memo No. F/EIC/PSS/20-21 (07) dated 15.07.2020 Sent
Monnoo Developers,1.5 Km Deffence Road, Opposite
COMSATS University, Lahore

Supply Main for Chak No.88/DB Mandi Yazman, Distt. Partially completion report Sent through memo No. F/EIC/PSS/19-20 (237)
20 GOVT 17/33/004013 17 MS 7-Jan-20 BWP Commissioned on 07.01.2020 Partial
Bahawalpur dated 15.03.2020 1188375

21 GOVT 17/33/004113 17 Supply Main for Chak No. 103/DB & Chak No. 106/DB, MS 7-Jan-20 BWP Commissioned on 07.01.2020 Partially completion report Sent through memo No. F/EIC/PSS/19-20 (237) Partial
Mandi Yazman dated 15.03.2020 NO
MS Gas Mains from Cement Point Shop, Maulana Shuja
22 OP. PHS 18/58/006540 18 Ali Road to Ali Muhammad General Store, Bahar Colony MS 8-Jan-20 LHR Commissioned on 08.01.2020. Sent through memo No. F/EIC/PSS/20-21 (24) dated 13.08.2020 Sent
Lahore

Operational Phase from Uniliver Bridge to Tibbi Laran, Partially completion report Sent through memo No. F/EIC/PSS/19-20 (237)
23 OPS 19/58/060113 19 MS 12-Jan-20 BWP Commissioned on 12.01.2020. Partial
Rahim Yar Khan dated 15.03.2020 (WORK ODER AMOUNT2419041)
Supply Main form Village Kot Umer Din to Village Halla
24 NA-142 17/33/019440 17 MS 12-Jan-20 LHR Commissioned on 12.01.2020. Sent through memo No. F/EIC/PSS/19-20 (296) dated 22.06.2020 Sent
NA-140 (Old NA-142)

25 NA-129 18/35/044740 18 PE Gas Mains for Various Localities of Lahore PE 17-Jan-19 LHR Commissioning completed on 17.01.2019 Pending

26 NA-129 18/58/007140 18 PE Gas Mains for Old Kahna of NA-129 Lahore PE 23-Jan-20 LHR Commissioning completed on 23.01.2020 Pending

Operational Phase from Residence Officers Commanding Partially completion report Sent through memo No. F/EIC/PSS/19-20 (237)
27 OPS 19/58/061912 19 Army to Main Gate, DHQ Hospital Vehari MS 28-Jan-20 MUL Commissioned on 28.01.2020. dated 15.03.2020 Partial
NO

28 NA-129 18/35/044940 18 PE Gas Mains for Various Localities of Lahore PE 1-Feb-20 LHR Commissioning completed on 01.02.2020 Pending

29 OPS 19/58/061413 19 Operational Phase from Bhatta Chowk, Ahmedpur Road MS 15-Feb-20 BWP Commissioned on 15.02.2020. Sent through memo No.F/EIC/PSS/20-21 (01) dated 06.07.2020 Sent
to City Chowk, Multan Road, Bahawalpur 2737177
RLNG Based Commercial Gas Connection from Khanewal
30 COST 19/32/901220 19 Road to M/s Hafiz Ikhlas Ahmad, Rewari Sweets Khushhal MS 17-Feb-20 MUL Commissioned on 17.02.2020 Pending
Colony, Multan 44057

31 NA-129 18/35/045240 18 PE Gas Mains for Various Localities of Lahore PE 26-Feb-20 LHR Coomiissioning completed on 26.02.2020 Pending

32 OPS 20/58/065212 20 Additional Pipeline for commissioning of SMS MS 27-Feb-20 MUL Commissioned on 27.02.2020 Sent through memo No. F/EIC/PSS/19-20 (296) dated 22.06.2020 Sent
Jahangirabad (Multan Region) NO
Supply Main for RLNG Based Gas Connection at M/S
33 COST JOB 19/31/062740 19 Indus Hospital Block - B, Jubilee Town, Defence Road, MS 29-Feb-20 LHR Commissioned on 29.02.2020 Pending
Lahore
Supply Main for RLNG Based Gas Commercial Gas
34 COST 19/31/065412 19 Connection at Tariq Aziz S/O Mushtaq Ahmad (Al-Aziz MS 9-Mar-20 MUL Commissioned on 09.03.2020. Pending
Wire Knitting) Multan NO
Operational Phase from SMS Shadani Sharif to Al-Madina
35 OPS 19/58/062013 19 MS 29-Mar-20 BWP Commissioned on 29.03.2020. Pending
Cold Corner, KLP Road, Khan Bela (WORK ODER AMOUNT 2121524)

Supply Main for Enhancement of Load Special Domestic


36 COST JOB 19/31/064240 19 Gas Connection at Medical Superintendent Mayo MS 26-Apr-20 LHR Commissioned on 26.04.2020. Pending
Hospital, Surgical Tower Mayo Hospital, Lahore

37 NA-142 17/33/016940 17 Supply Main for Kanwan Mallian Mathra Das, Kanwan MS 16-May-20 LHR Commissioned on 16.05.2020. Pending
Balaka Singh District Kasur NA-140 (Old NA-142)

Feeder Main from F-3 Daud Khel to Main Gate of Housing


38 GOVT 19/58/062732 19 Colony Iskanderabad, Distt. Mianwali MS 19-May-20 SGD Commissioned on 19.05.2020. Pending
NO

39 NA-129 18/35/045140 18 PE Gas Mains for Various Localities of Lahore PE 6-Jun-20 LHR Commissioned on 03.06.2020. Pending

12” Ø 300 Mtr M.S Gas Line Approved as Pilot Project for
40 COST JOB 19/59/050140 19 Replacement of Larger Diameter Lines (Manga Raiwind MS 15-Jun-20 LHR Commissioned on 15.06.2020 Pending
Road) in Lahore East.

41 NA-138 15/33/013640 15 Supply Main for Various Villages of NA-138 Distt. Kasur MS 16-Jun-20 LHR Commissioned on 16.06.2020. Pending 1365345

Supply Main for External Network of Provision of New


42 COST 19/31/063813 19 RLNG Based Gas Connection to M/s Model City Housing MS 17-Jun-20 BWP Commissioned on 17.06.2020 Pending
Scheme Sadiqabad
NO
Supply Main for Internal Network of Provision of New
43 COST 19/31/063913 19 RLNG Based Gas Connection to M/s Model City Housing MS 17-Jun-20 BWP Commissioned on 17.06.2020 Pending
Scheme Sadiqabad NO
26-04-2018
17.04.2018
Segments Partially Commissioned out of 4" Dia 1340 26.04.2018
44 NA-129 18/35/044840 18 Meters, 2" Dia 3770 Meters & 1-14" Dia 4295 Meters PE PE 14.05.2018 LHR Partially commissioned completed. Pending
Gas Mains for Various Localities of Lahore 13.05.2018
16.05.2018

45 NA-129 18/35/045340 18 PE Gas Mains for Various Localities of Lahore PE 23-Jun-20 LHR Commissioning completed on 23.06.2020. Pending

(16.0 Kms. (approx.) out of 20.74 Kms. from STARTING


46 GOVT 15/33/012512 15 POINT to U/S of Khadir Brach) Supply of Gas from MS 6/30/2020 MUL Partially commissioned on 30.06.2020 Pending
Bahawal Nagar to Qabula Sharif NA-165
(WORK ODER AMOUNT 1783628)

Summary of Completion Reports


Sent to HO 15
Partially sent to HO 7
Pending 24