Technip used Acumen software to analyze a subsea EPCI project schedule that was experiencing delays. They loaded monthly schedule updates into Acumen as separate projects to graphically compare float, critical activities, and earned value over time. This identified client review cycles as causing increased float and schedule variance. Exporting data to Excel allowed further analysis, supporting Technip's change order for cost impacts due to engineering and equipment delivery delays.

Uploaded by

anaattia
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
137 views20 pages

Technip Subsea Case Study Using Acumen: 11-Sept-13 Presenters: Cesar Ramos & Pat Smith

Technip used Acumen software to analyze a subsea EPCI project schedule that was experiencing delays. They loaded monthly schedule updates into Acumen as separate projects to graphically compare float, critical activities, and earned value over time. This identified client review cycles as causing increased float and schedule variance. Exporting data to Excel allowed further analysis, supporting Technip's change order for cost impacts due to engineering and equipment delivery delays.

Uploaded by

anaattia
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 20

Technip Subsea Case Study

using Acumen

11-Sept-13
Presenters: Cesar Ramos & Pat Smith

1 Acumen Technip SS Case Studies - 11-Sept-13


Agenda
 Presenters intro
 Technip at a Glance
 Technip & Acumen
 Presentation of Case Study
 Live Demonstration of Acumen software (open floor
for questions & comments)

2 Acumen Technip SS Case Studies - 11-Sept-13


Presenters
 Cesar Ramos
 Technip’s North American Subject Matter Expert for Planning/Scheduling &
Earned Value. He has a dual role as the Technip North American Onshore
Business Unit Leader. Has experience in Offshore & Subsea as well.

 Pat Smith
 Technip’s North American P6 Administrator. Also has a dual role as the
Technip North American Subsea Business Unit Leader. Has Onshore &
Offshore experience as well.

3 Acumen Technip SS Case Studies - 11-Sept-13


Technip at a Glance
Technip is a world leader in project management,
engineering and construction for the energy industry.
From the deepest Subsea oil & gas developments to the
largest and most complex Offshore and Onshore
infrastructures, our 38,000 people are constantly offering
the best solutions and most innovative technologies to meet
the world’s energy challenges.
Present in 48 countries, Technip has state-of-the-art
industrial assets on all continents and operates a fleet of
specialized vessels for pipeline installation and subsea
construction.
Technip shares are listed on the NYSE Euronext Paris
exchange and traded in the USA on the OTCQX
marketplace (OTCQX: TKPPY).
Quick Facts
Technip is active in three business segments: Subsea, Offshore and
Onshore
38,000 people in 48 countries
Industrial assets on five continents
A fleet of 28 vessels in operation and 8 more under construction
2012 operating income from recurring activities: €821.7 million
2012 revenues of more than €8.2 billion
Technip is listed on Euronext Paris (EURONEXT: FR0000131708)

4 Acumen Technip SS Case Studies - 11-Sept-13


Technip & Acumen History
 Technip started using Acumen Fuse in 2009.
 Acumen was officially incorporated into Technip
North America’s Schedule Review Procedure in
2010.
 Technip Schedule Review Procedure consists of
the following:
o Compliance with Technip standards of EPC schedule
development
o Compliance with PMBOK & AACE.
o Technip follows Acumen Metrics [250] which include; PMI,
AACE, DCMA, & others
 Technip has acquired the full Acumen Suite
which has Acumen Risk.
 After a Technip/Acumen presentation in a
conference in Brazil 2013, Technip Corporation
has acquired over 25+ Acumen Licenses
Globally.

5 Acumen Technip SS Case Studies - 11-Sept-13


TECHNIP SUBSEA EPCI
SCHEDULE ANALYSIS
An innovated way of analyzing using
Acumen was needed. Acumen Analyzed
11-Oct-12; 4:14pm (total 2hrs 20min)

6 Acumen Technip SS Case Studies - 11-Sept-13


Recognizing the Need for Analysis
A full Subsea EPCI contract was awarded. As the project progressed,
delays started occurring to the project which delayed Engineering
Deliverables & began to impact Offshore Mobilization Date & Critical
Equipment Delivery.
 Engineering Delays required forensic analysis of all possible impacts to these delays.
 Initial analysis provided belief that the client had impact to these delays.
 Upon further research the evidence was clear.
 In order to support a change order, to prove the impact, the business unit required
supporting details and analysis.
 The initial attempt was to review the depletion of float, that was caused by the client.

7 Acumen Technip SS Case Studies - 11-Sept-13


Analyzing with Acumen
Once the need was recognized, a small peer group to explore the
limitations of Acumen. Gathering all files, the business unit had to
compare all project files to see how we could prove this.
 Acumen Phase Analyzer does not produce overlapping graphs over a timeline. This was
confirmed by Acumen.
 Acumen recommendation was to export to Excel for further graph modifications
 The planner had saved all monthly updates as baselines. So as it was suggested that we
take every baseline and compare as snapshots.
 With this we were able to emulate the graph functions out of Acumen as a timeline.
 See example below Float Ribbon Analyzer [count per time]

8 Acumen Technip SS Case Studies - 11-Sept-13


Implementing the Concept of Analysis
A concept of loading each updated schedule as a snapshot seemed to be a
feasible solution. The difference from a normal snapshot comparison is
we knew the snapshots represented an updated cycle. By renaming the
file name as a time stamp, the graph looked like time analyzed graph.
In order to emulate this function we had to do the following:
 Imported 14 XER files to Acumen
 To our benefit, Pat Smith [assigned planner] had backed up every month XER.
 This allowed us to “act” as if each XER is a time stamp
 We renamed each XER to reflect the month
 Then produced a comparison of multi files named as months.
 Acumen naturally compares projects but in this instance each project
represented a month, allowing a graph that looks like a time scale.
 For future notice; if other projects follow similar scrutiny and do not backup or
copy files periodically (monthly? Wkly?), this emulation of a timeline can not be
reproduced within Acumen. Of course using Excel will allow modifications.

9 Acumen Technip SS Case Studies - 11-Sept-13


TECHNIP SUBSEA EPCI
FLOAT ANALYSIS
Phase I of Analysis
Utilizing the graphical impacts in
Acumen we were able to begin
researching detail impacts.

10 Acumen Technip SS Case Studies - 11-Sept-13


Critical Float [count of activities]
Our immediate place to compare was the Float depletion & behavior.
 As you can see in the example, there was a substantial jump in critical float count.
 This allowed us to further investigate.

11 Acumen Technip SS Case Studies - 11-Sept-13


0 to 20 Days Float
[count of activities]
Our next place to compare was further Float depletion & behavior.
We looked at Non-Critical and didn’t find alarming behaviors so we moved on to 0 to 20 Days Float [count
of activities]. This also pulled up anomalies.

12 Acumen Technip SS Case Studies - 11-Sept-13


Ribbon & Trace Logic
Ribbon & Trace Logic allowed us to dissect indicators.
 Tracing the peak critical, then started looking at the IFC drawings.

13 Acumen Technip SS Case Studies - 11-Sept-13


Trace Logic Backwards Analysis
Trace Logic allowed us to dissect indicators.
 Here is where the indicator of Client Review cycles extended beyond contractual agreements.

14 Acumen Technip SS Case Studies - 11-Sept-13


Trace Logic Export to Excel
Trace Logic export to Excel allows for further analysis.
 Using Excel with combinations of Filters, Sorts, & Conditional Formatting allows us to find exact details.

15 Acumen Technip SS Case Studies - 11-Sept-13


TECHNIP SUBSEA EPCI
EARNED VALUE WORK
ANALYSIS
Phase II of Analysis
Utilizing the graphical impacts in
Acumen we were able to begin
researching detail impacts.

16 Acumen Technip SS Case Studies - 11-Sept-13


Earned Value Work
Schedule Variance [EV-PV]
Schedule Variance provides a comparison of “where we planned to be” vs “where we really are”.
Schedule Variance is using P6 values and is calculated as Earned minus Planned.
This variance shows a disparity of slipping on planned dates and is used to calculate a recovery index.

17 Acumen Technip SS Case Studies - 11-Sept-13


Earned Value Work
Estimate at Complete [EAC]
Estimate at Completion provides necessary forecasting.
Estimate at Completion has 5 different calculations. However the most common is using the “Remaining
to Earn + Actual Costs”. Acumen brings in the P6 calculation of EAC.
Since the project is still in progression and has almost halfway remaining to complete, it is important to use
current performance to provide a valid means of forecasting.
This EAC can be used to forecast cost impacts where engineering delays, manufacturer delays due to held
up specs & data sheets as well as the impact of delaying the Pipe Lay Vessel and what that equates to
dollars.

18 Acumen Technip SS Case Studies - 11-Sept-13


Conclusion
As the results of the Float Analysis, Trace Logic Analysis, & Earned
Value Work, we were able to determine a cost impact to these delays.
These cost impacts to support the change order was submitted up to
contracts management for approval & submit to the client.
The analysis proven to be extremely useful & favorable.

The results still pending & confidential.

19 Acumen Technip SS Case Studies - 11-Sept-13


QUESTIONS?
FEEL FREE TO ASK QUESTIONS
OR COMMENTS

Cesar Ramos Pat Smith


Technip USA Technip USA
SME/ Earned Value Specialist & P6 Administrator &
Onshore Business Unit Leader Subsea Business Unit Leader
[email protected] [email protected]

20 Acumen Technip SS Case Studies - 11-Sept-13

You might also like