Prefab MCQ
Prefab MCQ
Q.NO Answers
1 B
2 True
3 C
4 False. Large panels used for both vertical (wall)and horizontal elements (slabs)
5 c.
Because of the early strength required for lifting the column in the factory, actual
characteristic strength are in the range 60-70 N/mm2
6 A
7 C
8 B
9 d
10 d
11 c
12 True
13 c
14 a
15 d
16 d
17 False.
It is not a isolated member,It is a part of the member which eliminate slow and
expensive form work.
18 b.
19 True. Shear walls are designed to take seismic and wind loads they are lateral or
Horizontal loads
20 d. Chalking is not defect it is sealing operation.
20.
a. Strut
b. Tie
c. Stub
d. None of the above
Q.NO Answers
1 d
2 c
3 d
4 c
5 b
6 a
7 c. bolt joint comes under hinged joint which allows rotation.
8 a.
9 b. It is hinged joint. It does not resist moment
10 a.
11 c
12 d.
13 b
14 a
15 d
16 b
17 False. Construction joints are required to accommodate the construction sequence for
placement of concrete in a cast in situ environment. But Prefabricated structures are
casted as an element does not require Construction joints.
18 True
19 c
20 c
UNIT III DESIGN PRINCIPLES
1. What demands for disuniting the prefabricated structures?
a)Less weight
b) quality
c) transportation and placing of structures
d) Design Constraints
11. The cross section design of wall panel depends on the requirements
a) Sandwich type wall panels
b) provide insulation
c) heavy weighted
d) smaller in section
INTRODUCTION
..........................is to the creation and use of guidelines for the production of uniform
interchangeable components especially for use in mass production
19. Certain geometric discipline using practical approaches which relate to setup
coordination and measurement of components and spaces in building design is
introduced in
a)Standardization
b)Modular coordination
c) Remoulding
d)Moulding
20. Prefabrication is a ......................... construction method
a)Automotive
b)Modern
c)established
d)Industrialised
Q.NO Answers
1 b
2 c
3 a
4 b
5 b
6 a
7 c
8 d
9 a
10 False
11 c
12 a
13 a
14 d
15 b
16 e
17 b
18 Standardization
19 b
20 d
UNIT V
1. ........................ is the factor by which the actual base shear force, that would be generated
if the structure were to remain elastic during its response to the Design Basis Earthquake.
a)Importance factor
b)Response reduction factor
c)All of the above
d)None of the above
2. ................... is the factor used to obtain the design seismic force depending on the
functional use of the structure, characterized by hazardous consequences of its failure, its
post-earthquake functional need, historic value, or economic importance.
a)Importance factor
b)Response reduction factor
c)All of the above
d)None of the above
3. The elastic rebound theory is an explanation for how ............. is spread during earthquakes
a)load
b)stress
c)energy
d)intensity of load
4. Damping is the energy dissipation properties of a material or system under ............ stress.
a)dynamic stress
b)static stress
c)non cyclic stress
d)cyclic stress
5. Damping is the effect of ..........................
i)enternal friction
ii) perfect elasticity of material
iii) slipping
iv) sliding
a)(i),(ii)
b)(ii),(iii)
c)(iii),(iv)
d)All of the above
e)none of the above
6. Choose the correct answer.
a)Converting static load into dynamic load is known as equivalent design loads.
b)Converting dynamic load into static load is known as equivalent design loads.
c) Both a & b
d) None of the above
7. Which of the following does not comes under progressive collapse?
a)local over loading
b)Service system (gas) explosion
c)vehicular and falling material impacts
d) planned localised fire
8. Which of the following defines intensity?
a)The severity of earthquake shaking is assessed using a descriptive scale
b)Quantitative measure of the size of the earthquake at its source
c)Both a & b
d)None of the Above
9. Which of the following defines Magnitude?
a)The severity of earthquake shaking is assessed using a descriptive scale
b)Quantitative measure of the size of the earthquake at its source
c)Both a & b
d)None of the Above
10. Degree of progressivity is the ratio of
i) total collapsed area by the triggering event.
ii) Affected region to the damaged by the triggering event
a) only (i)
b) only (ii)
c) both i & ii
d) none of i & ii
11. How many methods are generally used to avoid the disproportionate collapse in a building?
a)one
b)two
c)three
d)zero
12. Which is the are the approaches to avoid progressive collapse?
a)Redundancy or alternate load path.
b) Local resistance
c)Interconnection or continuity
d)all of the above
13. Choose the correct answer in terms of special requirements for building in High Seismic
Zones
a)The height of the building shall generally restricted to 5 stores in Zone IV
b)The height of the building shall generally restricted to 7 stores in Zone IV
c) The height of the building shall generally restricted to 8 stores in Zone IV
d)The height of the building shall generally restricted to 10 stores in Zone IV
14. Choose the correct answer in terms of special requirements for building in High Seismic
Zones
a)The height of the building shall generally restricted to 5 stores in Zone V
b)The height of the building shall generally restricted to 6 stores in Zone V
c)The height of the building shall generally restricted to 7 stores in Zone V
d)The height of the building shall generally restricted to 8 stores in Zone V
15. In a Prefabricated R C floors in a cyclone prone zone the Structural deck concrete of grade
not leaner than .............. should be provided over pre-cast components to act monolithic
with them.
a)M10
b)M15
c)M20
d)M25
16. Which of the following does not comes under the types of progressive collapse
a)Domino-type collapse
b)Section type collapse
c)Stability type collapse
d)Mixed-type collapse
17. Which type of failure follows the initiating event, separation of structural components,
release of potential energy and the occurrence of impact forces.
(a)Pancake-type collapse
(b)Zipper-type collapse
(c)Domino-type collapse
(d)Section type collapse
18. Which type of failure can be termed as “fast fracture” instead of progressive failure?
(a) Pancake-type collapse
(b)Zipper-type collapse
(c)Domino-type collapse
(d)Section type collapse
19. Structural integrity in a structure can be achieved by
(a)Connections between structural components should be ductile.
(b) Good plan layout
(c) Providing an integrated system of ties among the principal elements of the
structural system
(d) All of the above
20. What are the causes of failure during earthquake?
(i) Misconception of structural system which lacked lateral stability and strength
(ii)failure of connections
(iii)Inability of the system to undergo large deformation
a)(i),(ii)
b)(ii),(iii)
c)(iii),(i)
d)All of the above
e)none of the above
Q.NO Answers
1 b
2 a
3 c
4 d
5 c
6 b
7 d
8 A
9 b
10 a
11 c
12 d
13 d
14 a
15 c
16 c
17 a
18 d
19 d
20 d