Updated 2017 2022 PIP As Input To FY 2020 Budget Preparation Chapter 12 As of 12april19
Updated 2017 2022 PIP As Input To FY 2020 Budget Preparation Chapter 12 As of 12april19
Updated 2017 2022 PIP As Input To FY 2020 Budget Preparation Chapter 12 As of 12april19
2019)*
Chapter 12: Building Safe and Secure Communities**
Implementing Spatial Mode of Implementation INVESTMENT TARGETS
No. PIP Code Project Title Chapter Expected Outputs Region
Agency Coverage Implementation Period 2017 2018 2019 2020 2021 2022 TOTAL (2017-2022)
1 2020-35061-000024 Housing for AFAB Employees Authority of the 12 Housing facilities constructed. Region Region III LF 2020-2022 - - 2,000,000.00 118,850,000.00 75,000,000.00 - 195,850,000.00
Freeport Area of Specific
Bataan
2 2020-35061-000017 Housing for FAB Workers Authority of the 12 Housing facilities constructed: 8 economic Region Region III LF 2016-2022 - - - 105,000,000.00 90,000,000.00 90,000,000.00 285,000,000.00
Freeport Area of housing, 3 socialized-type housing, 3 dormitory Specific
Bataan buildings
3 2020-14001-000025 Capacitating LGUs on Housing Department of the 12 - Provide transitional resettlement assistance Interregional Region III, LF \ 355,693,000.00 - 152,288,850.00 504,171,703.00 397,556,000.00 397,556,000.00 1,807,265,553.00
and Resettlement Governance Interior and Local to LGUs to support the provision of basic NCR, Region
Government facilities and services in resettlement IVA
sites.
- Provide transitional support for LGU
operational activities.
- Provide capacity building assistance to LGUs
on resettlement concerns.
4 2020-35073-000001 Socialized Housing Loan National Home 12 From 2017 to 2022, the SHeLTeR Program Nationwide Others 2,556,700,000.00 1,850,000,000.00 2,330,000,000.00 2,320,000,000.00 2,830,000,000.00 3,360,000,000.00 15,246,700,000.00
TakeOut of Receivables Mortgage Finance aims to provide 31,600 socialized housing
(SHeLTeR) Program Corporation units to low-income families.
5 2020-35074-000004 Government Employees' National Housing 12 5,800 housing units to be started in 2020 Interregional Region I, Others 2020-2022 - - - 9,986,680,000.00 168,685,000.00 - 10,155,365,000.00
Housing Program Authority 180 housing units to be started in 2021 Region II,
Region III,
Region VII,
Region XI,
CAR, NCR,
Region IVA
6 2020-35074-000002 Regional Resettlement National Housing 12 Construction of 68,670 housing units to be Interregional Region I, LF 2020-2023 - - - 21,141,787,000.00 14,549,059,000.00 12,506,430,000.00 48,197,276,000.00
Program Authority started in 2020 Region II,
Construction of 57,991 housing units to be Region III,
started in 2021 Region V,
Construction of 53,382 housing units to be Region VI,
started in 2022 Region VII,
Region VIII,
Region IX,
Region X,
Region XI,
Region XII,
Region XIII,
ARMM, CAR,
Region IVA,
Region IVB
7 2020-35074-000001 Resettlement Program for ISFs National Housing 12 Construction of 19,091 housing units to be Interregional Region III, Others 2020-2024 - - - 7,511,331,000.00 3,002,000,000.00 3,552,000,000.00 14,065,331,000.00
Affected by Infrastructure Authority started in 2020 NCR, Region
Projects and Those Living Construction of 7,600 housing units to be IVA
along Danger Areas started in 2021
Construction of 6,000 housing units to be
started in 2022
8 2020-35074-000006 Resettlement Program for ISFs National Housing 12 Construction of 12,116 housing units to be Interregional Region III, Others 2020-2023 - - - 7,172,672,000.00 12,792,528,000.00 - 19,965,200,000.00
Affected by the Supreme Authority started in 2020 Region IVA
Court's Mandamus to Clean-up Construction of 21,609 housing units to be
the Manila Bay Area started in 2021
9 2020-35074-000003 Settlements Upgrading National Housing 12 747 lots to be surveyed/titled/upgraded in Interregional Region V, LF 2020-2023 - - - 45,630,000.00 834,892,000.00 - 880,522,000.00
Authority 2020 Region VII,
3,768 lots to be surveyed/titled/upgraded in NCR
2021
10 2020-35074-000005 Vertical Development National Housing 12 Construction of 3,769 housing units to be Region NCR LF 2020-2023 - - - 2,870,000,000.00 1,497,700,000.00 - 4,367,700,000.00
Authority started in 2020 Specific
Construction of 1,660 housing units to be
started in 2021
11 2020-35086-000001 Community Mortgage Program Social Housing 12 190,000 ISFs assisted with land acquisition, Nationwide LF 2018-2022 279,016,000.00 3,584,871,550.00 3,428,513,362.00 23,275,000,000.00 39,900,000,000.00 46,550,000,000.00 117,017,400,912.00
(CMP) Finance Corporation site development and house construction.
12 2020-35086-000002 High Density Housing Program Social Housing 12 26,640 ISFs assisted. Nationwide LF 2013-2019 2,843,961,145.00 1,168,836,386.00 3,428,513,362.00 - - - 7,441,310,893.00
(HDHP) Finance Corporation
13 2020-08008-000052 Housing Facilities for Formal University of the 12 With the newly designed master plan for the Region Region XI LF 2020-2022 - - - 95,000,000.00 95,000,000.00 95,000,000.00 285,000,000.00
Residents in the Campus (UP Philippines System whole campus, this facility shall have Specific
MINDANAO) approximately 100 units of single-detached
housing in an approximately 100 sqm land
area. They shall be asked to pay a minimal
monthly rental fee for the development cost of
the area. The site shall also have roads,
drainage/sewerage, lights and water
connections as well as an area for community
activities and communal farming.
* Based on the submission of the agencies and as validated by the NEDA Secretariat and confirmed by respective inter-agency bodies, including supplemental submissions as of April 12, 2019. The mode of implementation, investment targets and other PAP details may be updated in the course of project development, appraisal and implementation.