Guide To Developing The Project Business Case
Guide To Developing The Project Business Case
Guide To Developing The Project Business Case
2018
GUIDE TO DEVELOPING THE
PROJECT BUSINESS CASE
2018
© Crown copyright 2018
This publication is licensed under the terms of the Open Government Licence
v3.0 except where otherwise stated. To view this licence, visit nationalarchives.
gov.uk/doc/open-government-licence/version/3 or write to the Information Policy
Team, The National Archives, Kew, London TW9 4DU, or
email: [email protected].
Where we have identified any third party copyright information you will need to
obtain permission from the copyright holders concerned.
ISBN 978-1-5286-0460-4
CCS0518648068-1
PU2145
Contents
Chapter 1. Introduction1
What is a project? 1
How does a project align with the strategic planning process? 1
What is the importance of the Project Business Case using the Five Case Model? 2
What are the advantages of the Project Business Case? 3
When should the Project Business Case be developed? 3
What is Project Assurance? 4
Chapter 2. An Overview of the Five Case Model 7
Introduction7
The Strategic Case 7
The Economic Case 8
The Commercial Case 9
The Financial Case 9
The Management Case 10
Chapter 3. The Business Case Development Process 11
Introduction11
The Business Case Development Framework 11
Stage 0 – Determining the strategic context and undertaking the Strategic
Assessment12
Stage 1 – Scoping the scheme and preparing the Strategic Outline Case (SOC) 13
Stage 2 – Planning the scheme and preparing the Outline Business Case (OBC) 13
Stage 3 – Procuring the solution and preparing the Full Business Case (FBC) 14
Stage 4 – Implementation and monitoring 15
Stage 5 – Evaluation and feedback 15
Other interested parties 15
Smaller Schemes and the Business Justification Case (BJC) 16
Responsibility for producing the business case 16
Business Case template 16
Chapter 4. Determining the Strategic Context and undertaking the Strategic
Assessment17
Introduction17
Step 1: Determining the Strategic Context 17
Chapter 5. Scoping the proposal and preparing the Strategic Outline Case (SOC) 19
Introduction19
Step 2: Making the case for change 19
Action 2: Agree strategic context 19
Organisation Overview 19
Alignment to existing policies and strategies 20
Action 3: Determine spending objectives, existing arrangements and business
needs20
Determining spending objectives 21
Determining existing arrangements 22
¨¨ Senior managers and executives responsible for designing, delivering and approving
projects, including Senior Responsible Owners (SROs), project directors, project managers
and business case practitioners and reviewers.
¨¨ directors of Finance, Planning and Procurement and others with responsibility for
operational aspects of the project.
What is a project?
A project is a temporary organisation that is needed to produce a unique and predefined
outcome or result at a pre-specified time using predetermined resources.
The Managing Successful Projects with PRINCE2 guidance defines a project as ‘a management
environment that is created for the purpose of delivering one or more business products
according to a specified business case’.
Programmes
Bring About
Organisations achieve their vision and mission through business strategies, policies,
initiatives and targets that are influenced and shaped by the political, economic, sociological,
technological and legal environment in which they operate.
Organisations’ implementation strategies consist of strategic portfolios that scope, define and
prioritise the programmes needed to deliver the agreed change, anticipated outcomes and
resultant benefits.
These programmes initiate, align and monitor the projects and related activities required to
deliver the agreed outputs. These outputs may consist of new products and services, new
processes and service capabilities, or changes to business operations. But it is not until the
projects deliver and implement the required outputs into business operations to achieve the
outcomes that the full benefits of the programme can be realised.
A continual process of alignment is required to ensure that the programme and its projects
remain linked to strategic objectives, because even as projects are in the process of
implementing changes and improvements to their target business operations, they may need to
respond to changes in strategies or accommodate new initiatives or policies.
A case study showing the relationship between strategy, programmes and projects is provided at
Annex A.
What is the importance of the Project Business Case using the Five
Case Model?
The Project Business Case is important because projects will only deliver their intended outputs
and benefits if they are properly scoped, planned and cost justified from the outset.
Preparing a Project Business Case using the five case model provides decision makers and
stakeholders with a proven framework for structured ‘thinking’ and assurance that the project:
¨¨ Will maximise public value to society through the selection of the optimal
combination of components, products and related activities.
This dimension of the five cases focuses on options appraisal and the identification of
the preferred option and is the ‘economic case’ section within the Project Business Case.
This dimension of the five cases focuses on the development and procurement of the
potential Deal and is the ‘commercial case’ section within the Project Business Case.
This dimension of the five cases focuses on the whole life costs of the proposed Deal and
is the ‘financial case’ section within the Project Business Case.
This dimension of the five cases focuses on the implementation arrangements for the
proposal and is the ‘management case’ section within the Project Business Case.
¨¨ enables the organisation and its key stakeholders to understand, influence and shape
the project’s scope and direction early on in the planning process
¨¨ assists decision makers to understand the key issues, the available evidence base and to
avoid committing resources to schemes that should not proceed
¨¨ provides the basis for management, monitoring and evaluation during and after
implementation.
The organisational strategy provides the context for the project and is important because
experience shows that a proposal begins most effectively when it is launched as part of a clear
organisational strategy.
The project mandate provides the trigger and context at the start of the project. The project
brief develops the concept for the scheme and provides an initial assessment of the viability and
achievability of the proposal, prior to formally developing the Project Business Case.
The project mandate and brief should be prepared in accordance with a recommended project
management methodology and are dependent upon the organisation’s top management
team having defined and agreed the policies and business strategies for the organisation,
including high level strategies for sourcing and service delivery and the prioritisation of new and
existing work.
The Project Business Case is a working document which must be developed and revisited over
the duration of the scheme.
Developing a Project Business Case applies to all types of projects and requires trained people
who have the capabilities and competencies to undertake the tasks involved.
Experience demonstrates that there is significantly added value in an organisation subjecting its
projects to rigorous assurance, since the effort and resources saved by refocusing or cancelling a
project that is no longer needed far outweighs its continued cost.
The review provides organisations early on in the planning process with assurance on how
well the practical service delivery issues are being addressed in preparing for change through
project delivery.
Working in collaboration with the project team, PARs provide assurance that the project’s
scoping and delivery options are being planned in line with national strategies and policies to
achieve optimal public value at affordable cost.
¨¨ property/construction developments
¨¨ Gateway 4 – ‘Readiness for Service’ prior to ‘going live’ and implementation of the
scheme.
This chapter provides an overview of the Five Case Model Methodology for the preparation of
business cases.
The Five Case Model is applicable to policies, strategies, programmes and projects and comprises
of five key dimensions:
Demonstrating that the scheme provides synergy and holistic fit with other projects and
programmes within the strategic portfolio requires an up-to-date organisational business
strategy that references all relevant local, regional and national policies and targets.
Making a robust case for change requires a clear understanding of the rationale, drivers and
objectives for the spending proposal, which must be made SMART – Specific, Measurable,
Achievable, Relevant and Time constrained – for the purposes of post-evaluation.
Key to making a compelling case for intervention is a clear understanding of the existing
arrangements: the Business As Usual (BAU), business needs (related problems and
opportunities), potential scope (the required organisational capabilities) and the potential
benefits, risks, constraints and dependencies associated with the proposal.
¨¨ to explain how further intervention and spend on key ‘inputs’ will deliver ‘outputs’
that improve the organisation’s capability to deliver better outcomes and benefits to
stakeholders and customers, while recognising the associated risks
¨¨ to ensure the organisation’s proposals focus on business needs that have been well
researched and are supported by service demand and capacity planning
Strategic Context
Organisational overview
Business strategy and aims
Other relevant strategies
Demonstrating public value requires a wide range of realistic options to be appraised (the
long-list), in terms of how well they meet the spending objectives and critical success factors for
the scheme; and then a reduced number of possible options (the short-list) to be examined in
further detail.
The short-list must include the BAU, a realistic and achievable ‘do minimum’ that meets
essential requirements, the preferred way forward (if this is different) and any other options
that have been carried forward. These options are subjected to cost benefit analysis (CBA) or
cost effectiveness analysis (CEA), where more appropriate, to identify the option that offers best
public value to society.
¨¨ to begin by selecting the ‘right’ options for scope, solution, service delivery, implementation
and funding, otherwise options will represent sub-optimal Value for Money (VfM) from
the outset
¨¨ to cost justify higher cost options in relation to BAU and the ‘do minimum’
Long-listed options
Preferred Way Forward
Shortlisted options (including the “Business As Usual (BAU)” and ‘do minimum’)
NPSC/NPSV findings
Benefits appraisal
Risk assessment
Sensitivity analysis
Preferred option
Putting in place a well-structured Deal requires a clear understanding of the services, outputs
and milestones required to be achieved and of how the potential risks in the Design, Build,
Funding and Operational (DBFO) phases of the scheme can best be allocated between the public
and private sectors and reflected in the charging mechanism and contractual arrangements.
The challenge for the public sector is to be an ‘intelligent customer’ and to anticipate from the
outset how best public value can continue to be secured in during the contract phase in the face
of inevitable changes to business, organisational and operational requirements.
Demonstrating the affordability and fundability of the preferred option requires a complete
understanding of the capital, revenue and whole life costs of the scheme and of how the Deal
will impact upon the balance sheet, income and expenditure and pricing arrangements (if any)
of the organisation.
The challenge is to identify and resolve any potential funding gaps during the lifespan of
the scheme.
Demonstrating that the preferred option can be successfully delivered requires evidencing that
the scheme is being managed in accordance with best practice, subjected to independent
assurance and that the necessary arrangements are in place for change and contract
management, benefits realisation and risk management.
¨¨ to manage the risks in the design, build, funding and operational phases of the scheme
and put in place contingency plans
¨¨ to deal with inevitable business and service change in a controlled environment, and
¨¨ to ensure that objectives are met, anticipated outcomes delivered and benefits evaluated.
This chapter provides an overview of the business case development process for large, medium
and small spending proposals using the Five Case Model.
It also explains how the business case development process aligns with the Cabinet Office
Gateway Review process for the assurance of programmes and projects.
The business case for significant spending proposals is developed in three key stages as follows:
Stage 1 – Scoping the scheme and preparing the Strategic Outline Case (SOC)
Stage 2 – Planning the scheme and preparing the Outline Business Case (OBC)
Stage 3 – Procuring the solution and preparing the Full Business Case (FBC)
The process is practical, because it is based on many years experience of successful delivery
across a wide range of public sector spending proposals.
The process is iterative, because as the business case develops earlier work is revisited to verify its
continued applicability.
The process is flexible, because the quality and quantity of supporting analysis can be tailored to
the size and complexity of the project under development.
The business case development stages and related Cabinet Office Gateway Review points are
as follows:
Stage 0 – Determining the strategic context and undertaking the Strategic Assessment
Step 1: determining the strategic context
Gateway 0: strategic assessment
Stage 1 – Scoping the scheme and preparing the Strategic Outline Case (SOC)
Step 2: making the case for change
Step 3: exploring the preferred way forward
Gateway 1: business justification
Stage 2 – Planning the scheme and preparing the Outline Business Case (OBC)
Step 4: determining potential Value for Money (VfM)
Step 5: preparing for the potential Deal
Step 6: ascertaining affordability and funding requirement
Step 7: planning for successful delivery
Gateway 2: delivery strategy
Stage 3 – Procuring the solution and preparing the Full Business Case (FBC)
Step 8: procuring the VfM solution
Step 9: contracting for the Deal
Step 10: ensuring successful delivery
Gateway 3: investment decision
The purpose of this stage is to assess the strategic context for the project and to demonstrate
how it provides synergy and holistic fit with other programmes and projects within the strategic
portfolio in support of the organisation’s business strategy.
This stage aligns with Cabinet Office Gate Review point 0 (strategic assessment) and comprises
of the following business case development activity:
Early indications that the project is still needed and approved in principle are:
¨¨ the successful completion of a Cabinet Office Project Validation Review for the scheme
¨¨ the existence of an approved Programme Business Case, where the project is not stand-
alone and forms part of the programme.
Consideration should be given to the preparation of a Programme Business Case (if this has not
been prepared for the programme) of which the project forms an integral part.
Stage 1 – Scoping the scheme and preparing the Strategic Outline Case
(SOC)
This is the scoping phase for the project, which results in the production of the Strategic Outline
Case (SOC).
The purpose of this stage is to reaffirm the strategic context for the project, because this may
have changed if some time has elapsed since the strategic assessment was undertaken; to make
the case for change and to determine ‘the preferred way forward’.
Identifying the preferred way forward is achieved in two stages: first, by appraising a wide range
of possible options (‘the long-list’”) against the spending objectives and critical success factors
for the project; and second, by calculating the indicative Net present social values of a reduced
number of possible options (‘the short-list’) on the basis of a preliminary analysis of their costs
and benefits, including optimism bias for uncertainty.
This stage aligns with the Cabinet Office Gateway Review point 1 (business justification) and
comprises of the following business case development activities:
At the conclusion of the SOC, senior management and stakeholders will have a good
understanding of the robustness of the proposal and the future direction of travel, and the
business case across the five dimensions of the Five Case Model will have been completed as
illustrated below.
Stage 2 – Planning the scheme and preparing the Outline Business Case
(OBC)
This is the planning phase for the project, which results in the production of the Outline Business
Case (OBC).
The purpose of this stage is to revisit the options identified in the SOC, to identify the option
which optimises public value (‘the preferred option’) following more detailed appraisal; and to
set out the possible Deal while confirming affordability and putting in place the management
arrangements for the successful delivery of the project.
This stage aligns with the Cabinet Office Gateway Review point 2 (delivery strategy) and
comprises of the following business case development activities:
The purpose of the FBC is to record the findings of the procurement phase and to identify the
option that offers the ‘most economically advantageous tender’ (MEAT) and best public value.
In addition, the FBC records the contractual arrangements, confirms affordability and puts in
place the agreed management arrangements for the delivery, monitoring and post-evaluation of
the project.
This stage aligns with the Cabinet Office Gateway Review point 3 (investment decision) and
comprises of the following business case development activities:
At conclusion of the FBC, the development of the business case across the five dimensions of the
Five Case Model will have been completed as illustrated below.
The stages for the development of the business case have now been completed. The business
case continues to play an important role as follows.
The management tools developed in support of the project business case should be used to
deliver and monitor progress and provide the basis for regular reports to the Project Board. This
includes use of the project implementation plan, and benefit and risk registers.
This stage of the project aligns with Cabinet Office Gateway Review point 4 (readiness
for service).
This stage of the project aligns with Cabinet Office Gateway Review point 5 (operations review
and benefits realisation).
External consultants provide invaluable assistance where the requisite skills and resources are
unavailable in- house, particularly with the facilitation of supporting workshops.
These may be found on the HM Treasury Green Book web pages at:
http://www.hm-treasury.gov.uk/d/greenbook- toolkittemplates170707.pdf.
In conclusion, the business case development process is a ‘thinking’ exercise which results in a
well scoped and planned project supported by a document that provides ‘the repository for the
evidence base’ in support of good decision making.
Preparing a business case must never be approached as a ‘writing’ exercise and a hurdle
to jump for approval purposes and its use should be considered regardless of the need for
external approval.
A project begins most effectively when it is launched in the context of a clear business strategy,
which explains:
¨¨ Where we want to be
All organisational strategies must be reviewed on a regular basis and in advance of a new
programme or project in order to verify continued fit and synergy with the organisation’s
overarching policies and other programmes and projects within the strategic portfolio.
¨¨ fits within the organisation’s business strategy and plans for the achievement of these
goals, and
¨¨ aligns with other projects and programmes in the organisation’s strategic portfolio.
Completing a strategic assessment provides the organisation and its key stakeholders with an
early opportunity to influence the direction, scope and content of the project and requires:
¨¨ a clear understanding of the critical path for the delivery of the programmes and projects
within the strategic portfolio: anticipated outcomes, outputs, milestones, timescales,
benefits and risks
¨¨ validating that the programmes and projects within the strategic portfolio are well
structured, organised and funded; and that the required governance, standards,
resources, competencies and capabilities are in place for successful delivery, and
¨¨ a detailed understanding of the business needs and service opportunities that the project
is seeking to address.
Related activities
Consideration should be given to the following activities at this stage:
¨¨ Undertaking a review of organisational policies and strategies and further research prior
to the commencement of the project, if this is required.
¨¨ The completion of a mandate and brief for the project, using a recognised project
management methodology.
¨¨ The completion of a Cabinet Office Risk Profile Assessment (RPA) for the intended project.
¨¨ A workshop for undertaking the strategic assessment, consisting of the senior responsible
owner (SRO), key stakeholders, members of the senior management team and other
personnel with the required business, technical and user input.
¨¨ The completion of a scoping document for the potential coverage and technical content
of the project business case - which can then be shared with the approving authority,
in order to make the most appropriate use of the guidance and assist early approval of
the programme.
The business case development process is scalable and the guidance should be used
proportionately.
Annex C provides a template for the Programme and Project Scoping Document
together with guidance on how the business case process may be tailored and
streamlined in certain circumstances.
There should now be a clear understanding of the strategic context for the project and how it fits with
other projects and programmes within the strategic portfolio to achieve organisational goals.
Senior management and key stakeholders should now have a high degree of confidence that the project
is required, deliverable and deserving of a supporting business case.
The purpose of the SOC is to establish the case for change and to provide a preferred way
forward for senior management’s approval prior to going onto the more detailed planning
stage.
Completing the strategic case section of the SOC requires the following:
Action 3 Determine the spending objectives, existing arrangements and business needs
Draw on the findings of the strategic assessment for completion of this section of the business
case.
Organisation Overview
Provide a brief overview of the organisation.
This summary introduces the organisation to the reader of the business case and can assist
post-evaluation of the project at a later stage, because public sector organisations are often
reorganised and renamed before their projects deliver all of their outcomes.
¨¨ The purpose of the organisation, including its vision and mission statements, strategic
goals, business aims and key stakeholders.
¨¨ The range of services presently being provided, including key customers, service levels,
current demand and annual turnover.
¨¨ The organisation’s existing financial position, including funding streams and levels of
spend.
This information may be gleaned from existing documents, including annual reports. These
should be briefly summarised or attached to the Project Business Case.
¨¨ all relevant international, national, regional, sector and local policies, initiatives and
targets, as required, and focus on those which are most relevant to the project
¨¨ how the organisation’s policies, strategies and work projects support these policies, as
required
¨¨ the relationship between the proposed project and other programmes and projects
within the organisation’s strategic portfolio, including relevant milestones and
timescales on the critical path for delivery.
Any linkages and interdependencies with another organisation’s projects and projects should be
explained, especially where the proposed project is intended to contribute to shared outcomes
across multiple organisations.
This information may be gleaned from existing documents, including organisational strategies
and business plans. These should be briefly summarised or attached to the Project Business Case.
¨¨ What is required to close the gap between where we are now (existing arrangements)
and where we need to be in the future (business needs).
Analysing a proposal in this way helps to establish a compelling case for change based on
business needs, rather than the contention it is ‘a good thing to do’.
Setting robust spending or investment objectives is essential in terms of making a coherent case
for change. They describe clearly what the organisation is seeking to achieve in terms of targeted
outcomes and provide the basis for post evaluation. So the key question to answer is ‘“why are
we undertaking this project?’.
¨¨ Aligned with the underlying policies, strategies and business plans of the organisation
and be bound by the strategic context for the project
¨¨ focused on the vital outcomes, since a single or large number of objectives can
undermine the clarity and focus of the project.
The setting of clear, concise and meaningful SMART spending objectives is an iterative process
and will depend upon the nature and focus of the project.
The project’s spending objectives will typically address one or more of the following five generic
drivers for intervention and spend. These are:
¨¨ To improve the quality of public services in terms of the delivery of agreed outcomes
(effectiveness). For example, by meeting new policy changes and operational targets.
¨¨ To reduce the cost of public services in terms of the required inputs (economy). For
example, through ‘invest to save’ schemes and spend on innovative technologies.
Procuring assets and infrastructure is rarely a spending objective in itself, because it is what the
organisation is seeking to achieve through the use of these resources in terms of identifiable and
measurable social, economic and environmental outcomes that constitute social value and Value
for Money for the related spend.
Providing a clear picture of the organisation’s current service model and existing arrangements
provides an evidential base against which to challenge current perceptions of what the
difficulties are, and the baseline from which to measure future improvements.
Any critique of the difficulties associated with existing arrangements should be provided in
conjunction with ‘business needs’ in order to avoid blurring the clarity of the evidential base.
This requires a clear understanding of the problems and difficulties associated with existing
arrangements and a clear understanding of the opportunities for bridging any existing or future
gaps in business operations and service provision.
Specifying the business needs and drivers for the project helps to identify the potential scope
for the project, and to ensure that it is predicated on operational needs rather than potential
benefits. This analysis should take service demand and capacity planning into consideration and
include:
¨¨ confirmation of the continued need for existing business operations with supporting
evidence
¨¨ projections of the nature and level of demand for future services, including customer
demographics and alternative sources of supply
A useful technique for framing this section of the project business case is to complete the
following template for each of the project’s spending objectives:
FIG:
Spending objective Outcome we are seeking to achieve
Existing arrangements Current situation
Business needs The opportunities and problems associated with the current situation – the service gap
Consider the range of business functions, areas and operations to be affected and the key
services required to improve organisational capability on a continuum of need, where:
¨¨ the ‘core’ coverage and services required represent the ‘essential’ changes without
which the project will not be judged a success
¨¨ the ‘desirable’ coverage and services required represent the ‘additional’ changes which
the project can potentially justify on a cost/benefit and thus Value for Money basis
¨¨ the ‘optional’ coverage and services required represent the ‘possible’ changes which
the project can potentially justify on a marginal low cost and affordability basis.
This will assist in avoiding ‘scope creep’ during the options appraisal stage of the project.
A table for the use of workshops and capturing this information is provided below.
Table:
Range Core Desirable Optional
Potential scope
Key service requirements
This assists with the early appraisal of the options for delivery of the project and the preparation
of supporting economic appraisals.
The approach to benefits identification and measurement should be prudent, proportionate and
appropriate.
At this stage in the development of the project business case, focus on the 20% of the benefits
which are likely to provide 80% of the project’s benefit value.
Consider the spending objectives for the project and linking targeted outcomes from the project
to the beneficiaries ; because understanding to whom the benefits will be of value is the key to
identifying benefits and not confusing them with outcomes.
Capture your supporting analysis and assumptions in the preliminary benefits register for the
project (to be made more detailed later).
In principle, all benefits are measurable and monetisable. The issue is the extent to which it is
practical and proportionate to do so given the evidence base and associated costs. This should
be agreed between the project and the approving authority prior to preparing the project
business case. The scoping document should be used for this purpose.
Risk is the possibility of a ‘negative’ event occurring, adversely impacting on the project. At this
stage in the development of the project business case, focus on the 20% of the risks which are
likely to provide 80% of the project’s risk values.
Identifying, mitigating and managing the key risks is crucial to successful delivery, since the key
risks are likely to be that the project will not deliver its intended outcomes and benefits within
the anticipated timescales and spend.
Consider the following key categories of risk in relation to the scope of the project:
The extent to which it is necessary and prudent to provide indicative values for these risks
depends on the nature of the project and should be agreed between the project and the
approving authority prior to the commencement of the business case. The scoping document
should be used for this purpose.
Adopt a prudent and evidence-based approach and capture supporting analysis and
assumptions in a preliminary risk register for the project (to be made more detailed later).
Constraints are the external conditions and agreed parameters within which the programme
must be delivered, over which the project has little or no control.
These can include policy decisions, ethical and legal considerations, rules and regulations, and
timescales within which the project must be delivered. Affordability constraints may include
agreed limits on capital and revenue spend.
Constraints on the project need to be managed from the outset, since they will constrain the
options that can be considered for project delivery.
These are the dependencies that are external to the project but are still within the perimeters of
the organisation’s project and project management environment, and most likely linked to the
scope of another project or project within the strategic portfolio.
These are the dependencies that extend beyond the boundaries of all the projects into
other parts of the organisation or even other organisations. These dependencies are outside
the control of the project management environment; potentially in business operations,
partnering organisations and include external dynamics, such as legislation, strategic decisions
and approvals.
A useful technique for completing the strategic case section of the project business case is to
build upon the earlier recommended template for each spending objective (Step 2, Action 3) as
follows:
Potential scope and services What we need to put in place to address our needs
Potential benefits The anticipated benefits as a result
Potential risks The risks that might arise
Potential constraints The limitations we face
Potential dependencies The things that must be in place and/or managed elsewhere
The purpose, objectives, key participants and outputs of this workshop are as follows:
¨¨ spending objectives
The strategic case section of the Strategic Outline Case (SOC) has been completed and must be kept
under review.
This is achieved in two steps: first, by identifying and appraising a wide range of realistic and
possible options (the long-list – Step 3); and second, by identifying and appraising a reduced
number of possible options in further detail (the short-list – Step 4).
It should be noted that the ‘preferred way forward’ for the project emerges from the appraisal
of the long-list (Step 3) and the ‘preferred option’ for the project from the appraisal of the
short-list (Step 4).
Completing the first stage of the economic case requires the following:
These are the attributes essential for successful delivery of the project, against which the
initial assessment of the options for the delivery of the project will be appraised, alongside the
spending objectives.
The critical success factors for the project must be crucial, not merely desirable, and not set at a
level that could exclude important options at an early stage of identification and appraisal.
Table: A starting point for identifying and agreeing the critical success factors based
on the Five Case Model.
Key Critical Success
Broad Description
Factors
Provide a full description of each option, together with an assessment of its Strengths,
Weaknesses, Opportunities and Threats (SWOT analysis) and a conclusion in terms of how well it
meets the spending objectives and critical success factors agreed for the project.
Identifying options
A wide range of realistic and possible options for the delivery of the project must be identified.
This is known as ‘the long-list’.
The long-list must include an option that provides the baseline for measuring improvement
and Value for Money. This option is known as ‘Business As Usual (BAU)’. It must also include
a realistic ‘do minimum’ based on the core functionality and essential requirements for the
project.
Options may be ruled out for ethical, legal, financial or political reasons. In such cases, it is
important to ensure that these constraints have not been imposed artificially.
¨¨ researching existing reports and consulting widely with practitioners and experts
to gather the set of data and information relevant to the objectives and scope of
the problem
¨¨ identifying best practice solutions from the research, including international examples,
if appropriate
¨¨ the full range of policy instruments or projects that may be used to meet the project’s
objectives. This may span different sorts or scales of intervention; regulatory (or
deregulatory) solutions may be compared with self-regulatory, spending or tax options
¨¨ radical options. These may not become part of the formal appraisal but can be helpful
to test the parameters of feasible solutions. Well-run brainstorming sessions can help
to generate such ideas
¨¨ use of the Options Framework in accordance with the HM Treasury Green Book.
This tool and technique has been used on a wide range of public sector schemes and has
proven useful in getting senior management, stakeholders and customers signed up to an
agreed preferred way forward early on in the scoping and planning stage in the development
of schemes.
The framework considers the creation of options as a series of choices to be made in sequence.
‘Why’ provides the rationale for intervention and the potential scope for change. Once the
potential scope for the scheme has been agreed, the next stage is to identify and appraise the
choices to be made in relation to the ‘what’, ‘where’, ‘how’, ‘who’, ‘when’ and ‘funding’.
The Options Framework identifies and filters these choices for the operational scope, service
solutions, service delivery vehicles, implementation timeframes and funding mechanism for
the project.
2. Confirm the spending objectives and potential scope for the project, as set
out in the strategic case section
4. Identify potential ‘scopes’ for the coverage of the project, ranging from business
as usual (BAU), through to the ‘do minimum’, and ‘do maximum’ and intermediate
options.
These options focus on the scale of potential change required. To avoid ‘scope
creep’, they must not exceed the potential scope for the project as defined within the
strategic case section: if they do, the ‘case for change’ requires revisiting and updating.
The ‘do minimum’ scope must be a realistic option that meets the ‘core’ scope and
essential business needs of the project. The do maximum is predicated on meeting
the full scope of the project and all needs. The intermediate options focus on key
differences in relation to the desirable and optional scopes for the project.
Be pragmatic: scoping options discounted for delivery in the short to medium terms
may be retained in the strategic portfolio for delivery in the longer term.
ii. Discount unrealistic options. Carry forward (C/F) possible options, including the
BAU and ‘do minimum’ scopes.
iii. Identify the preferred way forward (PWF) – the scope which is considered most
likely to optimise public value.
Project scopes that are more ambitious than the ‘do minimum’ must be justified on their
potential for optimising benefits in relation to costs.
A short case study has been prepared to illustrate the use of the Options Framework for filtering
choices – please note that this is not exhaustive.
Case study: for a highways project in a developing country where the spending objective is to
improve the road infrastructure in order to stimulate economic development and growth.
The workshop identified options for the potential scope and coverage of the project by the
number of major cities which could benefit and appraised them as follows:
1.Service scope 1.0 All Cities 1.1 Linking Cities 1.2. Linking Cities 1.3 Linking 1.4 Linking All
– as outlined in A and B A, B and C Cities A, B, C Cities, A, B, C,
strategic case and D D and E
Carried Carried forward Preferred Way Carried forward Discounted
forward Forward
5. Identify potential ‘solutions’ for delivering the project’s preferred way forward for
potential scope, ranging from the BAU through to the ‘do minimum’, ‘do maximum’
and intermediate options.
These options focus on the products, inputs and outputs, which make up the
final deliverable.
6. The ‘do minimum’ solution must be a realistic option that meets the ‘core’
requirements and essential business needs of the project. The ‘do maximum’ solution
must not exceed the agreed scope for the project as agreed within the strategic case
section (which must be revisited if it does). Limit intermediate options to those that
have key differences in relation to their desirable and optional outputs and activities.
Be innovative and think in terms of what other organisations have achieved, what is
likely to work, and what is available in the market place.
ii. Discount unrealistic options. Carry forward (C/F) possible options, including the
BAU and ‘do minimum’ scopes.
iii. Identify the preferred way forward (PWF) – the ‘solution’ which is considered
most likely to optimise public value.
Project ‘solutions’ that are more ambitious than the ‘do minimum’ must be justified on their
potential for delivering additional value.
Case study: the workshop identified options for improving the road network between three
major cities (the preferred scope) and appraised them as follows:
7. Identify potential options for ‘service delivery’ of the project’s preferred way
forward in relation to potential scope and service solution.
These options focus on the delivery of the outputs, activities and potential
projects required.
In this instance, the ‘do minimum’, intermediate, and ‘do maximum’ choices relate to
the varying levels and degrees of “ambition” for service delivery, so a ‘do maximum’ is
not necessarily required.
i. Subject each option for service delivery to SWOT analysis – noting advantages and
disadvantages and how well it meets the agreed spending objectives and CSFs.
ii. Discount unrealistic options. Carry forward (C/F) possible options, including the
BAU and ‘do minimum’ solutions.
iii. Identify the preferred way forward (PWF) – the method of ‘service delivery’ which
is likely to provide the optimal outcome in terms of project and operational
delivery.
Project solutions that are more ambitious than the ‘do minimum’ must be justified on their
potential for delivering additional value.
Case study: the workshop identified service delivery options for refurbishing, maintaining and
building new roads between three major cities and appraised them as follows:
These options focus on the sizing, sequencing and phasing of the potential
products required.
In this instance, the ‘do minimum’, intermediate, and ‘do maximum’ choices relate to
the varying levels and degrees of “ambition” for implementation, so a ‘do maximum’
does not necessarily apply.
–– Create work streams that provide synergies, holistic fit and sufficient critical mass
for delivering economies of scale and size accordingly.
–– Focus on the critical path for the modular delivery of the required products and
sequence accordingly.
–– Design the project to optimise benefits delivery whilst managing the risks and
phase accordingly.
i. Subject each implementation option for the sizing, sequencing and phasing of
the potential project to SWOT analysis – noting advantages and disadvantages
and how well it meets the agreed spending objectives and CSFs.
ii. Discount unrealistic options for implementation. Carry forward (C/F) possible
options, including the BAU and ‘do minimum’ options.
iii. Identify the preferred way forward (PWF) – the approach to the sizing, sequencing
and phasing of potential projects that is most likely to deliver successful outputs
and outcomes.
Case study: the workshop identified options for the implementing improvements to the road
network between three major cities using an international contractor and appraised them as
follows:
9. Identify possible ‘funding options’ for resourcing of the project’s preferred scope,
solution, method of service delivery and implementation.
In this instance, the ‘do minimum’, intermediate, and ‘do maximum’ choices relate to
the varying levels and degrees of ‘ambition’ for funding the service.
i. Subject each funding option for the delivery of the project to SWOT analysis –
noting advantages and disadvantages and how well it meets the agreed spending
objectives and CSFs.
ii. Discount unrealistic options for funding. Carry forward (C/F) possible options.
iii. Identify the preferred way forward (PWF) – the funding option that is most likely
to meet the requirements of the project, to optimise Value for Money and be
affordable.
Case study: the workshop identified a mix of options for a service improvement project where
potential projects and activities could be funded in their design, build and operational phases
through a number of sources.
The Options Framework is a useful tool, because in this simplified case study for a service
improvement project over twenty main options have been considered – for scope, solution,
service delivery, implementation and funding – and indirectly over a thousand possible
combinations of different options.
Use of the Options Framework also provides senior management with a single page summary of
the options that have been considered.
Heading Rationale
Description Full details of the option under consideration with reference to a category of choice
within the Options Framework.
Main advantages Strengths and opportunities in terms of the critical success factors
Main disadvantages Weaknesses and threats in terms of the critical success factors.
Conclusions Overall assessment of how well the option meets the project spending objectives and
critical success factors and whether it is the preferred way forward, should be carried
forward or discounted in respect of the short-list.
Note: the preferred way forward is NOT the preferred option at this stage. The preferred option
is identified from the appraisal of the shortlisted options.
Shortlisted options
The Project Business Case should identify a minimum of four shortlisted options for further
appraisal. These should include:
¨¨ ‘do minimum’ – a realistic way forward that also acts as a further benchmark for Value
for Money, in terms of cost justifying further intervention
¨¨ one or more other possible options based on realistic ‘more ambitious’ and ‘less
ambitious’ choices that were not discounted at the long-list stage
Care must be taken to avoid ‘rigging’ and ‘retro-fitting’ options that have been pre-determined.
The project should seek guidance from its reviewers if it finds itself in this position.
Case Study: the options workshop for the service improvement project generated the following
short-list of options on the basis of the summary of the long-list using the Options Framework
for further consideration and appraisal.
The box below uses the numbering in the case study box shown above “Summary Of The Long
List Using the Options Framework” to map option choices into a summary of the shortlist
identified in the case study.
The format used for drafting the long-list can be used for this purpose – see Action 7.
A summary of the shortlisted options can usefully be provided and colour coded as follows:
Indicative costs
Indicative costs and benefits for each of the above shortlisted options should be provided to test
the affordability of the project before more detailed appraisal takes place.
The costs should include some allowance for ‘optimism bias’ and the ‘cost of risk’, and
together with the benefits be discounted to provide indicative net present social values for the
shortlisted options.
Optimism bias
Within both the public and private sectors, there is a demonstrated and systematic tendency for
project appraisers to be optimistic. This is a worldwide phenomenon, whereby appraisers tend
to overstate benefits, and understate timings and costs, both capital and operational.
To redress this tendency, appraisers are now required to make explicit adjustments for this bias.
These will take the form of increasing estimates of the costs and decreasing and delaying the
receipt of estimated benefits. Sensitivity analysis should be used to test assumptions about
operating costs and expected benefits.
Adjusting for optimism provides a better estimate earlier on of key project parameters. Enforcing
these adjustments for optimism bias is designed to complement, rather than replace, existing
good practice in terms of calculating project specific risk. It is also designed to encourage more
accurate costing. Adjustments for optimism bias may be reduced accordingly as more reliable
estimates of relevant costs are built up and project specific risk work is undertaken.
Adjustments should be empirically based – for example, using data from past projects or similar
projects elsewhere, and adjusted for the unique characteristics of the project. Where sufficient
data are not available within the organisation, generic optimism values are available (see below)
and should be used in the absence of more specific evidence. Departmental guidance may also
be available and should be referred to at this stage.
¨¨ equipment and development projects – these are concerned with the provision
of equipment and/or development of software and systems (i.e. manufactured
equipment, information and communication technology development projects or
leading edge projects)
¨¨ outsourcing projects – these are concerned with the provision of hard and soft
facilities management services – for example, information and communication
technology services, facilities management and maintenance projects.
*
Optimism bias for outsourcing projects is measured for operating expenditure.
Recommended steps
Apply the steps set out below to derive the appropriate adjustment factor to use for their
projects:
A programme or project which includes several project types (for example, an element
of standard building, non-standard building, standard civil engineering, outsourcing
and equipment/development) should be considered as a ‘project’ with five ‘projects’
for assessment purposes.
Use the appropriate upper bound value for optimism bias (see above table) as the
starting value for calculating the level of optimism bias.
Reduce the upper bound level for optimism bias according to the extent to which the
contributory factors have been managed.
The extent to which these contributory factors are mitigated can be reflected in a
mitigation factor. The mitigation factor has a value between 0.0 and 1.0. Where 0.0
means that contributory factors are not mitigated at all, 1.0 means all contributory
factors in a particular area are fully mitigated and values between 0.0 and 1.0
represent partial mitigation.
Optimism bias should be reduced in proportion to the amount that each factor has
been mitigated. Ideally, the optimism bias for a project should be reduced to its lower
bound before contract award. This assumes that the cost of mitigation is less than the
cost of managing any residual risks.
The present value of the capital costs should be multiplied by the optimism bias
factor. The result should then be added to the total net present social cost (or NPSC)
to provide the base case. The base case, as defined in the Green Book, is the best
estimate of how much a proposal will cost in economic terms, allowing for risk and
optimism.
Clear and tangible evidence of the mitigation of contributory factors must be observed,
and should be verified independently, before reductions in optimism bias are made.
Procedures for this include the Gateway Review process.
Following this guidance will provide an optimism bias adjustment that can be used to provide a
better estimate of the base case.
The purpose, objectives, key participants and outputs of this workshop stage are as follows:
Commercial case:
¨¨ an assessment of the ability of the market place to provide the required goods and
services
¨¨ the attractiveness of any future Deal to potential service providers, including some
analysis of risk apportionment and supporting charging mechanisms
¨¨ reference to the commercial strategy of the organisation for maximising public value
through economies of scale and collaborative procurements.
Financial case:
¨¨ a statement of the organisation’s financial situation
¨¨ resources available for the project, including assessment of the resource holder’s ability
to provide support
Management case:
¨¨ who is involved in the project, both inside and outside of the organisation, including
users, commissioners and other key stakeholders
¨¨ achievability of the project, taking into account the organisation’s readiness and
resources
¨¨ a wide range of possible options (the long-list) that has been subjected to SWOT analysis
¨¨ a recommended shortlist of three to four options, including the BAU and ‘do minimum’ options,
with indicative present costs
¨¨ an overview of the financial, commercial and management cases for the scheme.
The SOC has now been completed for the approval of senior management and the approving authority.
A Gateway Review 1 (business justification) should be considered prior to formal submission. This will
provide assurance to senior management, stakeholders and the approving authority that the project can
be successfully delivered.
¨¨ approving the SOC and agreeing to the next stage: the development of the OBC
¨¨ postponing or abandoning the project, because it is considered either too high risk, too
expensive or too ambitious.
¨¨ identify the investment option which optimises Value for Money (VfM)
¨¨ put in place the necessary funding and management arrangements for the successful
delivery of the scheme.
Whilst bringing together a variety of information on costs, benefits and risks to aid decision
making, option appraisal should not be seen as unequivocally providing the ‘right’ answer. The
goal is ‘optimal’: we are seeking to identify the option which best balances the expected costs in
relation to the benefits and risks.
Action 9 Revisit the Strategic Outline Case (SOC) and confirm the short-list
¨¨ the case for change in the strategic case section of the SOC
¨¨ management approval of the SOC may have been conditional on some changes and
adjustments to the project
¨¨ the early opportunity for the organisation and its key stakeholders to consider the
project may have influenced its direction
¨¨ some time may have elapsed between SOC approval and commencement of the OBC
Confirm the case for change and record any material changes in the opening section to the
strategic case in the OBC.
Review and test the recommended short-list against the following ‘long-list to short-list’ criteria:
¨¨ Do any of the options fail to deliver the spending objectives and CSFs for the project?
¨¨ Do any of the options appear unlikely to deliver sufficient benefits, bearing in mind
that the intention is to deliver a positive Net Present Social Value (NPSV)?
¨¨ Are any options clearly impractical or unfeasible – for example, the technology or land
are unavailable?
¨¨ Is any option clearly inferior to another, because it has greater costs and lower
benefits?
¨¨ Do any of the options violate any of the constraints – for example, are any clearly
unaffordable?
¨¨ Are any of the options sufficiently similar to allow a single representative option to be
selected for detailed analysis?
This action will help to avoid wasted effort while preparing the economic appraisals in support
of short-listed options. It should be undertaken in a structured way with the results recorded
¨¨ the relevant costs and benefits to society of all the (shortlisted) options should be
valued and the net benefit and costs calculated. ‘Relevant’ in this instance means all
those costs and benefits that can be affected by the decision at hand
¨¨ costs and benefits should cover the useful lifetime of the assets; or the contractual
period for the purchase of the service outputs and outcomes
¨¨ the costs and benefits should be based on resource costs and reflect the best
alternative uses (the ‘opportunity cost’) that the goods, assets and services could be
put to
¨¨ the wider social and environmental costs – for which there is no market price – should
also be taken into account
¨¨ the sources and assumptions underlying each cost and benefit line in the economic
appraisals must be explained in full within an accompanying appendix
¨¨ the costs and benefits must be base year. The base year is defined as ‘year 0’ and must
be at real relative prices the same for all options .
Economic appraisals focus on public value from the perspective of society and take into account
all social, economic, environmental costs and all effects on public welfare. Financial appraisals
focus on affordability from the perspective of the public purse, often expressed in terms of the
public funding the project.
Focus: Focus:
¨¨ Net Present Social Value (NPSV) for money. ¨¨ Funding and affordability – cash flow and stock.
Coverage: Coverage:
¨¨ UK Society as a whole and distributional analysis ¨¨ Relevant public organisation(s) budget.
where relevant.
Analysis: Analysis:
¨¨ real (relative base year) prices ¨¨ current (nominal) prices
¨¨ use of opportunity costs ¨¨ benefits – cash releasing only
¨¨ includes quantifiable welfare costs and benefits to ¨¨ includes capital and revenue costs
society ¨¨ includes transfer payments (for example, VAT)
¨¨ includes environmental costs ¨¨ includes inflation.
¨¨ excludes Exchequer ‘transfer’ payments – for
example, VAT
¨¨ excludes general inflation
¨¨ excludes sunk costs
¨¨ excludes depreciation, impairment and capital
charges.
¨¨ Public Sector costs – those falling to the spending organisation (Direct Costs) and
those falling to other parts of the public sector (Indirect Costs).
¨¨ Wider Social costs – those other indirect costs falling to other sectors, including the
private sector.
The following provides an overview of the costs that should be included in the economic
appraisals. All are expressed in terms of real resource costs excluding VAT and any similar
tax effects:
¨¨ Capital costs. These include the opportunity cost of existing assets such as buildings
and land and can broadly be broken down into: land and property; construction and
refurbishment costs; professional fees; equipment (furniture, fittings, lighting and
wiring); technology and maintenance costs.
Assets may require replacement, refurbishment or upgrading over the lifetime of the
appraisal period. These ‘life-cycle’ costs should also be included as part of the whole
life costs. The assumed maintenance policy on which costs are based must be explicitly
and transparently set out and applied appropriately to all options.
¨¨ Revenue costs. These are the operational, running, management and overhead costs
that it should not be assumed will remain unchanged over time.
¨¨ Fixed, variable, semi-variable and step costs. These costs must be separately
identified within the economic appraisals and their relationships explained:
¡¡ fixed costs are constant over time; e.g. the overhead costs of fixed capital assets
¡¡ variable costs vary according to the volume of activity, e.g. training costs and
network usage
¡¡ semi-variable costs include both fixed and variable components, e.g. a combination
of fixed maintenance contract costs and variable call-out charges, and,
¡¡ step costs for a pre-determined level of activity that eventually rise by a given
amount – for example, the need for a new call centre after a certain volume of calls.
¨¨ Opportunity costs. These must be explored in full. In relation to land, buildings and
manpower, they should be assessed against the most valuable alternative use rather
than current use. Full Time Equivalents (FTE) costs should be used to estimate the costs
of employees’ time to the employer and must include all employment costs in addition
to basic pay – for example, pensions, national insurance and allowances etc.
¨¨ Sunk costs. These are amounts that have already been spent and cannot be
recovered. They should be noted in the case and excluded from the economic
appraisals.
¨¨ Full economic costs. The full costs (direct, indirect and attributable) of each option,
rather than its net cost in relation to a baseline must be shown. This means ‘bottom
up’ costing, which provides a better understanding of the cost differences between
options and is more transparent.
¨¨ Attributable costs. These include the opportunity cost of staff time spent in relation
to the implementation of the proposal. These costs are likely to be significant in
relation to business change and business re-engineering projects.
¨¨ Avoided costs. These should be included as a cost in the BAU option and not as a
benefit in the other options.
¨¨ Inflation. Some cash flows may be significantly out of line with general inflation. In
such cases, the differential should be reflected in the economic appraisals.
Every effort should be made to value the benefits of different options, building on the project
benefits identified earlier.
The benefits for the project must be appraised from the standpoint of UK society as follows:
All the benefits – cash releasing and non-cash releasing – should be accounted for in the
economic appraisals to derive the NPSV for the project.
Any costs associated with benefits delivery should be taken into account. A cost is a predictable
negative effect of the proposal and is the measurable reduction resulting from an outcome
perceived as negative by one or more stakeholders, which detracts from one or more
organisational objectives. For example, an electronic prescription service while allowing GPs to
print fewer prescription forms, might, in practice, require pharmacists to print more forms and
increase their costs.
The cost of mitigating significant risks should be identified to ascertain whether it is a price
worth paying.
¨¨ stated preference, which has two forms: willingness to pay and willingness to
accept (i.e. estimation of a price by means of carefully constructed questionnaires
and interviews to indicate how much people are prepared to pay for a thing or how
much they would pay to avoid it; for example, improved access to services or to avoid
undesirable outcomes), and
The HM Treasury Green Book provides guidance on the appraisal of public value. This includes
many values for costs and benefits that occur frequently in public spending proposals, such as
the value of energy savings and of greenhouse gas emissions
For example where particular prices are expected to increase at significantly higher rates (such
as land values) or at lower rates (such as computer processors) than average inflation, then the
relative price change should be calculated and factored into the economic appraisals.
There is, therefore, a need at both the long-list and short-list stages of options analysis to
consider whether significant gains or losses to any groups within society appear likely.
As with all analysis, this is subject to the principle of proportionality. Where such distributional
analysis is needed, it should be undertaken as a separate analytical process. The results of this
analysis should be shown separately from the UK public value figures, but should be included
within the consideration of total public welfare. This improves transparency and avoids the
possible swamping of these effects, which may be significant for a minority, but would be
overshadowed and lost within the overall total. It also allows uncertainty in the estimation of
welfare distribution to be reflected in the analysis.
The need to abide by ethical and legal standards and frameworks, such as legislation on
equalities, also requires consideration of distributional effects where they are significant, and this
is transparently supported by this approach.
A separate analysis of these local proposals should be carried out alongside the total UK analysis
and the results set out separately alongside the UK NPSV in order for the local benefit of the
proposal to be estimated and an appropriate option selection to be made.
This section is concerned with compiling the economic appraisals for the shortlisted options,
including BAU and the ‘do minimum’ options in their most basic format.
Discounting in the public sector – the Social Discount Rate and Time Preference
There is a universal human tendency to discount the future by giving more weight to current
values and events than to the future, which also applies to preference for current over
future welfare.
The social discount rate is an annual percentage reduction specified by the Treasury Green Book
that is applied to values in each year going forward that progressively reduces the current value
of future values.
This is because private finance provides service delivery as well as funding options:
¨¨ Potential options for service delivery may include: strategic partnerships, alliances, and
outsourcing arrangements.
¨¨ Potential options for funding may include: free-standing projects, joint ventures,
operating leases and services. All are fundamentally different approaches for the
delivery of services and infrastructure in partnership with the private sector.
When the use of private finance is carried forward as an option into the short- list of options
for the project, at least one of the other shortlisted options must be based on a comparable
provision by the public sector. This enables the partnership option to be appraised fairly against
a public sector comparator (PSC), as it is known, which should include the cost of the risks
retained by the public sector during the Design, Build, Funding and Operational (DBFO) phases
of the project. Similarly, if different partnership options are being taken forward, alternative
public sector comparators must be provided. The Green Book provides more detail on the
calculation of the public setor comparator.
The following criteria provide a useful starting point for assessing a service’s suitability for the
use of private funding against a number of favourable characteristics.
For technical guidance on the valuation of privately financed schemes see the Treasury
Green Book.
The main aim is to identify benefits that are quantifiable and can be expressed in monetary
equivalent terms and to avoid defining benefits that cannot be measured, assessed or evaluated
in any realistic way because there is no established evidence base.
Every reasonable attempt should be made to quantify benefits, even if they cannot be expressed
in monetary equivalent terms. For example, the benefit of an intervention that increases people’s
propensity to exercise might be quantifiable but not readily expressible in monetary terms.
Where quantification is particularly challenging, because the evidence base is spurious or the
research costs would be disproportionate to the expenditure, it may be acceptable to express a
benefit in qualitative terms; but even then it should be possible to provide evidence on the likely
order of the magnitude of the benefit.
In all cases, the appraisal of benefits that cannot be expressed in monetary equivalent terms
should be grounded in a review of the best available evidence. The evaluation of similar
interventions previously undertaken usually provides a particularly important source of evidence.
The quantifiable (non-monetised) and qualitative benefits must be recorded in the Benefits
Register with their sources and assumptions.
The HM Treasury Green Book requires public sector organisations to undertake a risk assessment
of the short-listed options. The project’s service risks should be estimated and quantified in
monetary terms, as equivalent likelihood values – that is the cost of mitigation multiplied by the
likelihood of occurrence.
Early on in the process an initial allowance was made for optimism bias. At this stage in
the process, service risks in the design, build and operational phases of the project must be
identified and their costs estimated and built into the project.
OB
Uncertainty Assessed Risk
over
MEASURED
UNCERTAINTY
OB
TIME
¨¨ accurate costing
The lower bound values of optimism bias represent the maximum optimism bias level to aim for
in projects with effective risk management by the time of contract award.
Case study
The capital costs of a non-standard civil engineering project within a major change programme are
estimated to be £50m NPSC. No detailed risk analysis work has taken place at this stage, although
significant costing work has been undertaken.
The project team reports to the project board and applies an optimism bias adjustment of 66% showing
that, for the scope of the work required, the total cost may increase by £33m to £83m in total. This is
based on consultants’ evidence and experience from comparable civil engineering projects at a similar
stage in the appraisal process.
As this potential cost is unaffordable, the chief executive requests reductions in the overall scope of the
project, and more detailed work. As the project progresses, more accurate costs and quantified risks
are identified. The adjustment for optimism bias is able to be reduced until there remains only a general
contingency of 6% for unspecified risks.
Without applying optimism bias adjustments, a false expectation would have been created that a larger
project could be delivered at a lower cost.
¨¨ By how much can we allow benefits to fall short of expectations, if the proposal is to
remain worthwhile? How likely is this?
¨¨ By how much can operating costs increase, if the proposal is to remain worthwhile?
How likely is this to happen?
A risk register should be developed from the beginning of the project (see management case),
updated and reviewed on a regular basis and used as the source for:
¨¨ identifying the main business and service risks (in the strategic case section)
¨¨ quantifying and appraising the business and service risks (in the economic case section)
¨¨ apportioning and transferring service risks (in the commercial case section)
¨¨ mitigating and managing risks over the entire life cycle of the scheme.
Risk identification
There are a number of techniques which may be used to identify the risks associated with
programmes and projects. Three commonly used methods are:
¨¨ structured review meetings – these involve the programme and project teams and
encourage participation and ownership of the risks by key personnel
¨¨ risk audit interviews – these are conducted by experienced managers and/or advisers,
with all those involved in the programme or project teams with responsibility for risk,
and
¨¨ risk workshops – these include all members of the programme and project teams and
encourage imaginative ideas for the mitigation and management of risk.
Business related risks remain with the public sector and can never be transferred. Service related
risks occur in the design, build, funding and operational phases of a project and may be shared
between the public and private sectors.
External, non-systematic and catastrophe risks affect all society and are unpredictable and
random in nature. They are dealt with as part of the social discount rate and do not need any
further separate treatment.
The generic types of risk that are likely to be encountered within these categories are set out in
broad terms below:
Risk quantification
It is good practice to quantify the cost of risk through a ‘risk cost’, which is added to the costs
of the options to provide the full expected value of the options. As the appraisal proceeds, more
specific risks will be identified, thus reducing the more general optimism bias.
An ‘expected value’ provides a single value for the expected impact of all risks. It is calculated
by multiplying the likelihood of the risk occurring (probability) by the cost of mitigation and
summing the results for all risks and outcomes.
It is estimated that a particular facility will cost £50m to build. The expected costs associated with
construction cost uncertainties have been calculated as follows:
Possible cost (£m) Difference from Estimated probability Risk value (£m)
estimated cost (£m) of the event occurring
45 -5 0.1 -0.5
50 0 0.6 0
55 +5 0.1 +0.5
60 +10 0.1 +1.0
65 +15 0.1 +1.5
The most likely outcome is that of no extra cost, as this outcome has the highest probability (60%).
However, the expected outcome – the sum of each possible outcome multiplied by its probability – is an
additional cost of £2.5 million. This needs to be calculated in NPSV terms, taking into account the time
period over which the risk occurs.
Decision trees
Decision trees can be useful ways of thinking about alternatives for the outcomes and so
can illustrate thinking about risk. They can be used to develop and show the key features of
alternative scenarios where key variables external to the proposal under consideration are likely.
In situations where there is a potential for learning over time to make better-informed decisions,
delay can also have a positive value which can be valued.
To help quantify such cases, decision trees have been developed into ‘real options analysis’.
These are graphical representations useful in assessing situations where the probabilities of
particular events occurring depend on previous events, and can be used to calculate expected
outcomes in more complex situations. For example, the likelihood of a particular volume
of traffic using a road in the future might depend on movements in the oil price. Different
scenarios can be analysed in this way.
Monte Carlo
There are a variety of packages available that take the analysis of risk a step further, using
computer simulation and probability distributions.
Monte Carlo analysis is a simulation technique that presents both the range as well as the
expected value of the collective impact of various risks. It is useful when there are many variables
with significant independent uncertainties. However, expert advice is required to ensure it is
applied properly, especially when risks may not be independent of each other. Sufficient data is
also needed on the key input variables and outputs to support a stable numerical model with
well estimated distribution functions.
The business case should present the information succinctly and clearly for each option to
support clear decision making. The following format provides a summary of the costs and
benefits by key category and class. While not all of the costs and benefits will apply to every
proposal, it should be considered as a starting point for the presentation of cost benefit
information, along with the required Green Book appraisal summary tables.
The values of costs, benefits and risks are not always comparable, because some benefits and
risks are non-quantifiable.
When an option has higher benefits, the decision needs to be made whether these benefits
justify a higher net present social cost. If the additional benefits are insufficient to justify the
additional costs and risks, a lower cost and risk option should be selected.
Often the choice will remain between high cost/high benefit options and low cost/low benefit
options. In these circumstances, a decision is required on the extent to which higher benefits
are worth paying for. Risk can also play a part in that a high cost/high benefit option may be
considered too risky to undertake, and an intermediate option might show a more optimal
balance of risk.
The final choice of the preferred option lies with senior management and their stakeholders,
drawing on professional advice.
Sensitivity analysis
An expected value is a useful starting point for undertaking the impact of risk between different
options. But however well risks are identified and analysed, the future is inherently uncertain; so
it is also essential to consider how future uncertainties can affect the options.
Sensitivity analysis may not change the preferred option. However, if small changes in the
assumptions alter the ranking, it is an indication that the investment process should proceed
cautiously, because it has non-robust elements in it. This means that a more detailed analysis
and testing of the costs, benefits and risks of some of the options should be considered.
¨¨ switching values
Switching values
This technique highlights the point at which the choice of the preferred option would switch to
another option due to any uncertain costs and/or benefits.
The calculation of switching values is carried out by showing other options in relation to
the preferred option using percentages (the preferred option is zero). This indicates by how
much a variable would have to fall (if it is a benefit) or rise (if it is a cost) to make it not worth
undertaking the preferred option. In other words how much variables would have to change
for the preferred option to be ‘dislodged’. This should be considered a crucial input to the
decision as to whether a proposal should proceed. It therefore needs to be a prominent part of
the appraisal.
Scenario analysis
Alternative scenarios are useful in considering how options may be affected by future
uncertainty and provide a valuable way of assessing risk, especially where there is a known risk
of significant variations in external conditions.
Scenarios should be chosen to draw attention to the major technical, economic and political
uncertainties on which the success of the proposal depends.
Careful consideration should be given before running the scenario analysis to the choice of
circumstances, as sensitivity analysis does not simply involve changing costs, benefits and risks
by an arbitrary 10 or 20%; but rather by the values that represent the most likely increases (or
decreases) in cost etc. for documented reasons.
Scenario analysis may take the form of asking simple ‘what if’ questions for small and medium
size investments and extend to creating detailed models of ‘future states of the world’ for major
projects and projects. The expected NPSV is then calculated for each scenario.
If the results for the scenario analysis are similar to the switching values, further work is required
on the options to determine their robustness. Where appropriate, the sensitivity analysis of the
economic appraisal findings should include the following:
More specifically, examples of variables that are likely to be both inherently uncertain and
fundamental to an appraisal are:
¨¨ forecast revenues
¨¨ demand
¨¨ prices
¨¨ risk values.
A prior understanding of how costs fall into fixed, step, variable and semi-variable categories can
help in understanding the sensitivity of the total costs of proposals.
Other factors may also affect the selection of the preferred option; in particular, any unvalued
costs, risks and non-monetised benefits. In these circumstances it is essential to involve
stakeholders in the decision-making process about whether any additional cost is a price
worth paying.
Overall ranking
The purpose, objectives, key participants and outputs of this workshop are as follows:
There should now be a clear understanding of the preferred option, which is evidenced from:
¨¨ the economic appraisals (NPSVs) for the short-listed options – risk adjusted and applying
optimism bias (£)
The economic case section of the outline business case is now complete and must be kept under review.
These arrangements need to be considered from the outset, in order to secure long-term public
value during the operational phase of the project.
Completing the commercial case requires undertaking the following actions for the preferred
option identified in the economic case.
This requires considering how the required services, supplies or works can best be procured
in accordance with established rules and regulations and the commercial strategy of the
organisation, which has been prepared in accordance with Government Commercial Operating
Standards.
¨¨ the choice of procurement method and the degree to which early consultation with
the supply side is required, and
Procurement rules
Public sector organisations must act in compliance with the appropriate procurement legislation.
Collaborative procurements
These strategic arrangements – at national, departmental, sector and local level – offer
significant flexibility and potential VfM, through economies of scale; and considerable reductions
in procurement costs, through pre-competition.
Refer to your departmental or local centre of excellence for procurement advice and assistance.
¨¨ Specifying the quality attributes of the services and outputs required, together with the
performance measures against which they will be assessed.
Consideration should be given to capturing the following details for the project:
¨¨ the required outputs, including: phases, performance measures and quality attributes
¨¨ the options for variation in the existing and future scope for services
A copy of the procurement notice for publication should be attached to the OBC.
The main aim is to ensure that specific risks should be allocated to the party best able to
manage it, subject to the risk premium. The intention is to optimise the allocation and sharing of
risk rather than to maximise the number of risks to be transferred to potential service providers
for delivery of the project.
Guiding principles
The following principles should be taken into account:
¨¨ the public sector should consider transferring risk to the private sector when the
service provider is better able to influence the outcome than the procuring authority
¨¨ the degree to which risks may be transferred depends on the specific proposal under
consideration
¨¨ the private sector should be encouraged to take the risks it can manage them
more effectively than the public sector; particularly where it has clear ownership,
responsibility and control
¨¨ the transfer of risks can generate incentives for the private sector to provide more
timely, cost-effective and innovative solutions.
Complete the following risk allocation for the project as required. Illustrate the amount of risk to
be shared by percentage point (%), if possible.
Consider how best to ‘incentivise’ the service provider(s) to provide Value for Money over the
lifespan of the project and its operational phase. This will assist the organisation to deal with the
inevitable need for ‘change’ to services and operations in the future and to embed risk transfer
and allocation within the charging mechanism for the project.
The charging mechanism is the formula against which payment for the contracted services will
be made. The underlying aim of the payment mechanism and pricing structure is to reflect the
optimum balance between risk and return in the contract. As a general principle, the approach
should be to relate the payment to the delivery of service outputs and the performance of the
service provider.
Properly constructed payment mechanisms incentivise the service provider to deliver services in
accordance with the business imperatives of the public sector in the following key phases of
the service:
¨¨ The operational phase – following acceptable delivery of the service up to the close of
the primary contractual period
Fixed price/costs
The service provider must be given an incentive to deliver services to time, specification and cost.
This element involves a fixed price for the delivery of ‘agreed outputs’ within a fixed timetable,
with appropriate remedies in place for delays and cost over-runs.
These payments may be staggered against the delivery of key outputs within the overall
implementation plan for the complete service. However, the guiding principle is that a revenue
stream to the service provider should only commence when an offsetting benefit stream is
realised on the part of the public sector.
Ultimately, a service that fails to perform could result in termination of all the payment streams
and, in extreme circumstances, pass the rights to the underpinning assets for the service to the
public sector.
Availability payment
This element links a proportion of the payment stream to the availability of the service. For
example, the contract could stipulate that the service must be available for a minimum of 95%
of the time between contracted hours.
In such instances, the procuring authority will need to negotiate service level agreements (SLAs),
which outline the availability criteria. In some cases, it may be appropriate to treat availability
as a threshold, which releases a payment stream based on a combination of other factors – for
example, performance or throughput of service.
Failure on the part of the service provider to meet the agreed availability criteria should lead to
reduced payments and, ultimately, to cessation of the service.
Performance payment
This element links a proportion of the payment mechanism to the performance of the service.
Linking payments to specified performance targets helps to ensure that the service provider
continues to deliver the agreed outputs throughout the lifespan of the service.
Transaction/volume payment
This element links a proportion of the payment mechanism to the achievement of business
benefit – for example, the number of transactions or volume of business provided.
Linking payment to the productivity or usage of the service in this way gives the service provider
the incentive to optimise the level of productivity and to invest further in the underlying
infrastructure, if increased levels of productivity are required.
Incentive payment
This element of the payment mechanism is linked to potential improvements in the overall
performance of the public sector’s business processes, and encourages the service provider to
deliver new ways of working and additional benefits that can be shared by both parties.
Cost of change
This element of the payment mechanism seeks to minimise the cost of change by encouraging
the service provider to build flexible and adaptable solutions in the first instance.
The cost of change represents a major risk to the public sector and should be mitigated through
the contractual obligation to benchmark and market test the contracted services at regular
intervals.
If it is not possible to agree exact prices for anticipated changes at some future time, the process
for agreeing the cost of change should be established at the outset.
The price for core services will be reduced and overall VfM improved, if the scope for these
potential revenue streams has been recognised and agreed, in principle, at the outset.
Two contractual devices can be employed to encourage the service provider to consistently
upgrade the core technology. First, various upgrades can be included in the initial price to ensure
that the infrastructure underpinning the service is kept up-to-date; and second, a proportion of
the service provider’s initial recoverable investment could be deferred – with agreement – until
the end of the contractual period.
Contract currencies
Contract currencies are the variable measures that make the payment mechanism meaningful
and effective in the service contract – for example, the number of complaints received; the
proportion of users of the service requiring assistance, time taken to answer the phone, number
of abandoned calls, etc.
The aim should be to choose contract currencies that demonstrate productivity and
performance. In other words, comparative measures which provide service providers with the
incentive to improve – a reduced payment for under performance and enhanced payments for
performing in excess of the minimum requirement specified in the contract.
Use of contract
State the form of contract to be used. In the case of a standard contract, state the title of
the model contract to be used. In the case of a bespoke contract, state why this is more
advantageous than using a standard contract.
Refer to your departmental or local centre of excellence for procurement for guidance.
¨¨ the service provider’s and procuring authority’s respective roles and responsibilities in
relation to the proposed Deal
¨¨ the organisation’s remedies in the event of failure on the part of the service provider to
deliver the contracted services – on time, to specification and price
¨¨ the operational and contract administration elements of the terms and conditions of
service
¨¨ arrangements for the resolution of disputes and disagreements between the parties
Accountancy treatment
Provide details of the intended accountancy treatment for the potential Deal by stating on
whose balance sheet – public or private sector, or both – the assets underpinning the service will
be accounted for; and the relevant accountancy standard(s).
A letter supporting the balance sheet conclusion should be provided by the Finance Director or
by an external auditor.
Personnel implications
Identify any personnel implications for the project.
Public sector organisations are obliged to involve their staff and their representatives in a process
of continuous dialogue during significant projects involving considerable internal change. This
also represents best practice in terms of human resources policies.
Consequently, the OBC should record any personnel implications to the scheme. In particular:
¨¨ details of any terms regarding subsequent transfers at market testing intervals (if these
apply)
¨¨ details of requirements for broadly comparable pensions for staff upon transfer (if
these apply)
¨¨ that codes of practice are in place for the well-being and management of staff.
The purpose, objectives, key participants and outputs of this workshop are as follows:
Workshop 4 Developing the commercial strategy and Deals for the project
Objectives ¨¨ To develop the service specification for the project.
¨¨ To apportion service risks and explore the underpinning payment mechanisms.
¨¨ To develop the contractual arrangements.
¨¨ To ensure that the Government Commercial Operating. Standards have been
adhered to.
Key participants ¨¨ External stakeholders or commissioners.
¨¨ Director of Finance.
¨¨ Commercial Director.
¨¨ Economic adviser.
¨¨ Customer and/or user representatives.
¨¨ Project manager.
¨¨ Facilitator.
Outputs ¨¨ Procurement and commercial strategies for the project
¨¨ Preliminary Risk Allocation Matrix (RAM) for the project
¨¨ Potential Deal for the project
¨¨ procurement strategy and routes in accordance with the appropriate procurement legislation
¨¨ the contract(s) to be used and the key contractual issues, including TUPE (if applicable)
¨¨ a procurement notice
The commercial case section of the Outline Business Case is now complete and must be kept under review.
This involves determining the funding and affordability of the proposed project on the
organisation’s income and expenditure account, balance sheet and prices for its services (if
applicable).
The costs and benefits appraised in the financial case reflect an accountancy-based perspective.
Consequently, both resource and non-resource costs and benefits are factored into the analysis;
so, for example, whereas VAT and depreciation are excluded from the economic appraisals,
these costs are included in the financial appraisals, because they have a direct bearing on the
affordability of the project.
The following financial statements are required for the project spend:
¨¨ a cash flow statement – which should show the cash which will be spent on the
lead option, if it goes ahead. The existing spend (if any) and the additional spend
should be shown separately
The above should include the contingencies (in £s) necessary to ensure that there is sufficient
financial cover for risks and uncertainties.
Financial modelling
For large, significant and complex projects, a financial model of the proposed expenditure needs
to be constructed.
The model will provide an informed ‘best guess’ of the likely impact and outcomes of the
proposed project in its early stage of development. However, the reliability and robustness of
the model will increase as it is kept under continuous review and updated to reflect the latest
information.
Building the model may require specialist advice from accountants and financial advisers from
outside of the organisation. In these circumstances, the organisation’s Director of Finance and
the Project’s Senior Responsible Owner must play a lead role in vetting and maintaining the
integrity of the model, since responsibility for its use as a decision making tool ultimately falls to
the organisation.
¨¨ agreeing and recording the underlying assumptions (for example, interest rates, inflation,
taxation, capital charges, depreciation etc.)
¨¨ preparing the inputs schedules (financial costs, cash-releasing benefits and risk contingencies)
¨¨ preparing supporting schedules – i.e. for loans, fixed assets, taxation, and payments.
¨¨ the capital and revenue consequences of the preferred option for the project over the lifespan
of the service and/or contract period
¨¨ how this compares with the original capital ceiling for the scheme (if any)
This statement should also indicate the capital sum being requested and, ideally, that the
organisation has sufficient income to meet the ongoing costs of the project. The minimum
requirement is as follows:
The impact on prices of capital charges must also be considered, if applicable. Capital charges
are significant when considering the affordability of a development and they must be included
in year-by-year financial projections, together with external financing limit (EFL) allocations,
running costs and contract income from any purchasers.
The benefits that the proposed Deal will deliver and the prices that the organisation will charge
as a result will have an impact on competitiveness. Organisations should, therefore, compare
and benchmark the prices and quality levels of similar services offered by other providers.
The effect on prices should be analysed in sufficient detail for purchasers to ascertain how the
scheme will impact them. This means considering the impact on:
Public sector investments are difficult to justify if they lead to an increase in prices for the
organisation’s services.
Where significant assets are an integral part of the investment, their accounting treatment will
need to be examined (see commercial case). This will require an independent opinion from the
organisation’s auditors.
Stakeholder(s)/commissioner(s) support
Affordability issues are one of the main reasons for delay at the point at which OBCs are
submitted for approval. The key principle here is that the source of funding, and the amount
over time, must be confirmed and the project shown to be affordable throughout its life.
An OBC will only be successful and approved if consultation has been held between the
organisation seeking spend for service improvement and its stakeholders/ commissioners/
purchasers, and other interested parties.
Agreement, in principle, must be obtained for the project from the funders of the scheme. This
should be in written form and included in an annex to the OBC.
¨¨ demonstrate that the main commissioner and other commissioners have been involved in
developing the project throughout the key stages
¨¨ confirm acceptance of the strategic aims and spending objectives of the project, including its
functional content, size and services
¨¨ confirm that the financial costs of the scheme can be contained within the agreed and available
budget and a willingness and ability to pay for the services at the specified price level
¨¨ demonstrate that suitable contingency arrangements are in place to work with the provider to
address any current or unforeseen affordability pressures
¨¨ be provided by the appropriate individual(s) within the organisation – usually the chief executive
officer.
Assessing affordability
Assessing affordability requires sound judgment of the organisation’s business and requires that:
1. the balance sheet has been correctly organised and properly accounts for current
assets, current liabilities, long-term liabilities and capital
There are a number of techniques available to the public sector for assessing affordability. Those
in common use within the private sector include:
An organisation should never run short of working capital or over-capitalise. This is a common
reason for business failure. A ratio of current assets to current liabilities of 2:1 is generally agreed
to be the minimum working capital ratio. The ratio is calculated as follows:
current assets
Working capital (ratio) = –––––––––––––––
current liabilities
Solvency – item 3
This means that the organisation can meet any debt obligation in the near future without
jeopardising the liquidity of the business.
Over-trading – item 4
This links in with over-capitalisation, where the organisation is running short of working
capital as a result of having acquired too many assets, leaving itself short of cash for
operational expenses.
In this situation attention must be paid to the organisation’s cash flow; but it is first necessary to
consider the return on capital employed and the return on capital invested.
The return on capital employed enables us to compare the receipts (or profits) earned with the
capital employed to earn them, and may be calculated as follows:
The return on capital invested calculates what the return was overall on the capital used and
takes into account the lost opportunity or ‘opportunity cost’ of the capital employed. As such it
is calculated as follows:
¨¨ budgeting for cash flow – a forecast which looks ahead and envisages the likely
income and expenditure
Risks – item 6
There are a number of risks that could affect the affordability of the project. The OBC should
summarise the results of the risk contingencies and sensitivity analysis which underpin the
financial case.
The risks and uncertainties will vary from project to project, but some key questions to
consider are:
¨¨ Would the project be affordable if capital costs were to be x% higher than expected?
Payback period
Finally, there is the payback period, which measures the rate at which the financial benefits from
the investment ‘pays back’ the initial investment costs. In general, projects with a short payback
period are preferable to those with long payback periods.
However, during the operational phase benefits can be expected to build up gradually, until they
reach the point where the net impact on operating costs and prices to purchasers is negative.
There are a number of remedies if the affordability analysis reveals the preferred option for the
project is unaffordable. These include the following:
¨¨ altering the scope of the preferred option – for example, its functional content and/or
the quantity and quality of the services offered
¨¨ considering different ways of financing the project – for example, private finance,
operating and financial leases
¨¨ finding other ways of reducing the costs and/or increasing cash releasing savings
¨¨ permitting service provider(s) to create additional revenue streams and new business,
and sharing in the resultant revenue streams.
¨¨ the impact on the income and expenditure account and the organisation’s charges for services
(if applicable)
¨¨ the impact on the budget, other sources of available funding and any shortfalls
There should also be written evidence of commissioner and stakeholder support (if required).
The financial case section of the Outline Business Case is now complete and must be kept under review.
Action 21 Plan change and contract management – strategy, framework and plans
Action 24 Plan project assurance and Post-Project Evaluation – strategy, framework and plans
Project framework
Summarise the following aspects and capture the key points in a diagram:
¨¨ structure
¨¨ reporting arrangements
¨¨ governance arrangements
PRINCE2 mandates that the senior responsible owner (SRO), project manager and business
change managers (BCMs) should be members of the project board. The project director should
also be included but this role is not a substitute for the SRO.
The individual who fulfils this role should be able to lead and champion the project and must be
empowered to direct the project and take decisions; for example, whether to delay or stop any
part of the project. The SRO must have sufficient seniority and authority to provide leadership to
the project and take on accountability for delivery.
The day-to-day leadership of the project may be undertaken by a project director, but this is not
an alternative to the SRO role.
Project Plan
The project plan is used to control and track the progress and delivery of the project and
resulting outcomes. It describes how, when and by whom a specific project, milestone or set of
targets will be achieved. It is the detailed analysis of how identified project targets, milestones,
deliverables and products will be delivered to timescales, costs and quality.
The most up-to-date version of the project plan should be summarised and attached to the OBC.
¨¨ the resources and time needed for all activities and any need for people with specific
capabilities and competencies
¨¨ the points at which progress will be monitored, controlled and reviewed, including
delivery and approval of the business case and undertaking Gateway Reviews/Health
Checks etc.
The requirement for special advisers usually falls into four key categories in the project plan:
financial, legal, technical and programme / project management. The OBC should indicate how
and when this advice will be used along with expected costs.
Special advisers should be used where an independent and impartial role is required to achieve
the best results. This includes facilitating workshops.
Care must be taken to ensure that ownership of the Business Case and responsibility for its
development is retained by the Project Board.
Projects are about delivering change. This can range from service improvement and business
process re-engineering (BPR) to a transformation in services and the way in which they are
delivered.
Even where change is not seen as the primary driver for investment, as in the case of a
replacement project, every effort should be taken to seize the opportunities for improving the
efficiency of the service and public value.
Change needs to be managed and embraced by individuals within the organisation, hence the
need for a change management strategy (linked to benefits realisation), a change management
framework (to manage anticipated and unexpected change) and a plan (to explain what will be
delivered by whom and when in terms of underlying activities).
There are various management strategies for implementing change. The choice of strategy will
depend upon the degree and pace of change required. The degree of service change can range
from increased automation and reconfiguration to the complete transformation of a business
function. The pace of change can range from ‘big bang’ to phased or incremental introduction
depending on the strategic driver and the ability of the organisation to cope with service
change.
The organisation’s choice of change management strategy should be set out in full, together
with its underpinning communication and development (training) strategies.
In the case of major societal change, the project may form only one part of a longer-term
strategy involving other projects and programmes, both current and future, within the strategic
portfolio. The associated and anticipated governance and reporting arrangements should be
clearly explained in these circumstances.
Benefits register
All projects must capture benefits within a benefits register. This register should also indicate
how those benefits are to be realised.
The benefits register should be updated and reviewed continuously throughout the course of
the project and capture the following information for each benefit:
Benefits Register
Benefits number (unique within the register)
Benefit category & class
Description (including enabling project or activity)
Service feature (what aspect of the project will give rise to the benefit – to facilitate
monitoring)
Potential costs (incurred during delivery)
Activities required (to secure benefit)
Responsible officer
Performance measure (key performance indicator)
Target improvement (expected level of change)
Full-year value
Timescale
All the benefits identified in the strategic case and economic case sections of the OBC must
be accounted for within the benefits register. This includes the economic appraisal for the
preferred option.
Action 23: Plan risk management – strategy, framework and outline plans
Put in place arrangements for managing and mitigating risks during the key phases of the
project.
Risk management is a structured approach to identifying, assessing and controlling risks that
emerge during the course of the project lifecycle. Its purpose is to support better decision-
making through understanding the risks inherent in a proposal and their likely impact.
Effective risk management supports the achievement of wider aims, such as:
¨¨ innovation.
¨¨ identifying possible risk in advance and putting mechanisms in place to minimise the
likelihood of them materialising with adverse effects
¨¨ the right balance of control to mitigate against the adverse consequences of the risks,
if they should materialise
Risk management strategies for individual projects should be adopted in a way that is
appropriate to their scale.
Risk mitigation
Recognised methods for the mitigation of risk throughout the lifespan of the project include:
¨¨ pilot studies – acquiring more information about risks affecting a project through pilot
studies allows steps to be taken to mitigate either the adverse consequences of bad
outcomes, or to increase the benefits of good outcomes
¨¨ design flexibility – where future demand and relative price are uncertain, it may be
worth choosing a flexible design adaptable to future changes, rather than a design
suited to only one particular outcome. Breaking a project into stages, with successive
review points at which the project could be stopped or changed, can also increase
flexibility
¨¨ precautionary action – where this can be taken to mitigate a perceived risk. The
precautionary principle states that because some outcomes are so bad, even though
they may be very unlikely, action is justified. In cases where such risks have been
identified, they should be drawn to the attention of senior management and expert
advice sought
¨¨ develop different options. Following the risk analysis, the appraiser may want to re-
instate options, or to develop alternative ones that are either less inherently risky or
deal with the risks more efficiently
¨¨ abandon the proposal. Finally, the proposal may be so risky that whatever mitigation is
considered, it has to be abandoned.
By reducing risks in these ways, the expected costs of a proposal are lowered or the expected
benefits increased. As can be seen, benefit and risk are simply two sides of the same coin and
successful delivery depends on the effective identification, management and mitigation of risk.
¨¨ establishing a risk management framework, within which risks are identified, mitigated
and managed
¨¨ embedding risk management fully into business processes and ensuring it is applied
consistently.
These actions should help establish an organisational culture that supports well thought out risk
taking and innovation.
The arrangements for the management of risk should be outlined, together with the respective
roles and responsibilities and reporting lines of the posts concerned. These should be made clear
in relation to the overall project management arrangements.
Risk register
All projects must capture risks within a risk register. This register should indicate how those risks
are to be mitigated and managed.
The risk register should be updated and reviewed continuously throughout the course of the
project and capture the following information for each risk:
Risk Register
Risk number (unique within the Register)
Risk type
Author (who raised it)
Date identified
Date last updated
Description (of risk)
Likelihood
Interdependencies (between risks)
Expected impact/value
Bearer of risk
Countermeasures
Risk status (action status)
All the risks identified in the strategic case and economic case sections of the OBC must
be accounted for within the risk register. This includes the economic appraisal for the
preferred option.
Additional information on risk management may be obtained from the National Audit Office
(NAO), HM Treasury and the Cabinet Office.
Project Assurance
Project assurance provides independent and impartial assessment that the project’s spending
objectives can be delivered successfully and improves the prospects of achieving intended
outcomes and benefits.
Other forms of assurance include: quality assurance; technical assurance; security assurance.
¨¨ to improve project delivery through lessons learnt during the project delivery phase.
This is often referred to as the ‘Project Implementation Review’ (PIR)
¨¨ to appraise whether the project has delivered its anticipated outcomes and benefits.
This is often referred to as the ‘Post Evaluation Review’ (PER).
This section of the OBC should set out the organisation’s strategy for both aspects of PPE explain
whether the PIR and PER are to be undertaken jointly or separately.
The PIR is linked to Gateway Review stage 5 (operations review and benefits realisation).
The purpose, objectives, key participants and outputs of this workshop are as follows:
¨¨ project plan
The management case section of the Outline Business Case is now complete and must be kept under
review.
The OBC has now been completed for the agreement of senior management and the approving
authority.
A Gateway Review 2 (delivery strategy) should be considered prior to formal submission. This will
provide assurance to senior management, stakeholders and the approving authority that the project
can be successfully delivered.
¨¨ approving the OBC and agreeing to the next stage: the development of the FBC, prior to
procurement
¨¨ postponing or abandoning the project, because it is considered either too expensive, too
ambitious or too high risk.
¨¨ identify the market place opportunity which offers optimum Value for Money (VfM)
¨¨ set out the commercial and contractual arrangements for the negotiated Deal
¨¨ put in place the detailed management arrangements for the successful delivery,
monitoring and evaluation of the scheme.
Much of the work involved in producing the FBC focuses upon revisiting and updating
the conclusions of the Outline Business Case (OBC) and documenting the outcomes of the
procurement.
Action 27 Detail procurement process and evaluation of Best And Final Offers (BAFOs)
Ensure the spending objectives have been made SMART for the purpose of post evaluation and
updated to reflect the latest information regarding the rationale, drivers, anticipated outcomes
and benefits for the project.
Attach further confirmation of the organisation’s commissioners and other key stakeholders, if
applicable.
The purpose of this action is evidence that the preferred option remains the same as that
identified at the OBC stage. Any new options must be clearly identified and any adjustments to
existing options explained.
The analysis from the OBC stage must be updated in the FBC because new information affecting
the ranking of the options may have become available since the approval of the OBC.
For example:
¨¨ the relative rankings may have changed as a result of supplier side offerings, prices and
other costs
¨¨ the expected benefits of the OBC preferred option may be lower, or the anticipated
benefits of another option higher, which may change the previous ranking of the
options
¨¨ the level of uncertainty in a high risk option may have reduced making it more
attractive
¨¨ operational changes may have led to significant changes in the preferred option.
If any of the key assumptions have altered, the FBC must demonstrate that the recommended
option continues to offer better public value than the other available options, including the ‘do
minimum’ (if applicable).
At the OBC stage, different methods of funding and procurement were examined. If the OBC
recommended that some form of private finance was deliverable and potentially offered better
VfM than conventional funding, a privately financed option may have been pursued. At the FBC
stage, any private finance offer must be appraised against the public sector comparator (PSC)
and ‘do minimum’ options outlined in the OBC to confirm VfM.
The principles of economic appraisal are the same as those used to identify the preferred option
at OBC stage.
Revisions to the PSC should avoid mimicking any design, engineering or operational attributes
offered by service providers during the procurement phase and focus on ensuring that scope of
the required outputs required remains consistent so as to enable meaningful comparisons to be
made.
It should not be necessary to adjust the ‘do minimum’ option at this stage.
Risk adjustment
Revisit the ‘cost of risk’ retained by the public sector, as calculated within the PSC outlined at the
OBC stage.
This is a minimum requirement that should also be undertaken for the risk values of the Business
As Usual (BAU) and ‘do minimum’ options, depending on which was carried forward as the
benchmark for VfM in the shortlisted options appraisal.
The main service risks in the design, build, funding and operational phases of the project
should be fully identified and quantified (£) at the FBC stage. The residual use of optimism bias
to measure continued uncertainties should be minimal and generally no more than 2% for a
standard capital scheme (Step 4, Action 13 refers to this).
Action 27: Detail the procurement process and the evaluation of Best And
Final Offers (BAFOs)
Update the economic case to provide a summary of the procurement process and how the Best
And Final Offers (BAFOs) were evaluated and the preferred bidder selected.
The purpose of this action is to evidence that the recommended service provider offers the ‘most
economically advantageous offer’ in relation to other service providers, and that the option is
offering best public value.
¨¨ who expressed interest at the pre-qualification and the reasons for any rejections
¨¨ who were taken forward into the ‘long-list’ and ‘short-list’ (Best and Final Offer
(BAFO)) stages of the procurement and the reasons for any rejections.
Record the preferred service provider(s) together with the reasons for their selection.
A copy of the procurement report may be attached to the FBC for this purpose.
The economic appraisals must account for the full cost of the scheme, including any
‘attributable’ costs falling to the organisation and other parts of the public and private sectors
over the contractual and expected lifespan of the service. This is required because different
service providers offer different levels of service provision, leading to different levels of cost,
including risk, and benefit falling to the public sector.
The recommended option should then be appraised against the BAU, ‘do minimum’ and PSC
and other in-house options, as required, taking into account any adjustments made as a result
of earlier Action 26 (revisit the OBC options), the further assessment of non-financial benefits
and risks and sensitivity analysis.
The option offering best public value should be the choice recommended for the approval,
subject to affordability.
¨¨ any changes to the strategic context and the case for change
¨¨ how the selection of the preferred service provider was made on the basis of an updated PSC (if
applicable) and the investment appraisals, including the benchmark for VfM, using HM Treasury
Green Book rules.
Output of Step 8
The strategic and economic cases have now been revisited, updated and completed in respect of the
FBC.
Action 28: Set out the negotiated Deal and contractual arrangements
Document the Deal that has been negotiated by the public sector organisation and its choice of
service provider.
The standard headings for the commercial case should be used to explain:
¨¨ the implementation timescales which have been agreed for their delivery
¨¨ the allocation of risk negotiated between the public sector and preferred service
provider
¨¨ the underpinning method of payment for these services and outputs, including the
premiums for risk transfer
¨¨ In the case of PPP (PFI) procurements, the contract form should be compliant with the
relevant Treasury and Cabinet Office standards
¨¨ the accountancy treatment of the negotiated Deal, with confirmation from the
organisation’s external auditors, as required.
¨¨ a detailed explanation of any personnel implications (for example, TUPE) and how they
are being managed.
The standard headings for the financial case should be used to explain:
¨¨ how the charges for the preferred service provider’s offer have been modelled,
including the resultant benefits
¨¨ the capital and revenue implications of the resultant Deal, including any financial costs
falling to the organisation
¨¨ the impact on the organisation’s income and expenditure account and balance sheet –
duly confirmed by the external auditor
¨¨ the overall affordability and funding arrangements for the Deal, including (written)
confirmation from the organisation’s commissioners and other key stakeholders and
any contingency arrangements for overspends.
There should now be a clear understanding of the financial implications of the proposed Deal, both
in terms of the organisation’s contractual obligations and associated spend in support of the required
services.
Output of Step 9
The commercial and financial cases have now been revisited, updated and completed in respect of
the FBC.
The existing framework (project structure, reporting lines, roles and responsibilities) should be
shown, together with named individuals, any vacancies and plans for any future changes.
The latest version of the project plan should be attached to the FBC. This must reflect the
implementation timescales agreed with the service provider for the delivery of the negotiated
services and be signed off by the stakeholders and customers (end users) for the services.
The existing framework (project structure, reporting lines, roles and responsibilities) should be
shown, together with named individuals, any vacancies and any plans for future changes.
The latest version of the change management plan should be attached to the FBC. This must
reflect the specific training and developmental needs of key groups of personnel and any
required communication arrangements. It should be signed off by the stakeholders for the
services and indicate customer (end user) involvement.
The strategy for the realisation of benefits during the key phases of the project should be
revisited and reaffirmed within the FBC.
The existing framework (project structure, reporting lines, roles and responsibilities) should be
shown, together with named individuals, any vacancies and any plans for future changes.
The ‘owner’ of the benefits register should be named and their reporting line identified to the
senior responsible owner (SRO), who is ultimately responsible for benefits delivery. It should be
confirmed that the benefits register will be reviewed regularly and form part of the standing
agenda for future project boards.
The strategy for the management of risks during the key phases of the project should be
revisited and reaffirmed within the FBC.
The existing framework (project structure, reporting lines, roles and responsibilities) should be
shown, together with named individuals, any vacancies and any plans for future changes.
The ‘owner’ of the risk register should be named and their reporting arrangements notified to
the senior responsible owner (SRO). It should also be confirmed that the risk register will be
reviewed regularly and form part of the standing agenda for future project board.
Contingency plan
The organisation should provide details of its contingency plan(s) in the event of the non-
delivery of the contracted services to the required level of performance and availability at some
unspecified future point in time.
Contract change
The more regular contract management arrangements will have been covered in the contract
and indicated in the commercial case (see contractual arrangements). These largely take care of
the day-to-day management of the service and cover subjects such as performance; availability;
minor changes; the escalation procedure for difficulties etc.
However, over the lifespan of the service contract it is likely that there will be some significant
changes given that it is in the nature of a successful organisation to anticipate and adapt to
meet changing circumstances.
In accordance with the ‘partnering’ principle, the organisation should consider its strategy
for managing future contractual change. Best practice suggests regular face-to-face meetings
between senior managers from both the customer and supplier organisations and dealing with
change in the context of a ‘shared vision’. This helps to manage expectations on both sides and
to reduce eventual cost.
The organisation should consider who will adopt this role over the lifespan of the contract and
plan accordingly. Any arrangements should be noted in the FBC.
¨¨ The arrangements for future Cabinet Office Gateway Reviews and organisational
Health Checks (if applicable) at Gateway Review 3 (investment decision); Gateway
Review 4 (readiness for service) and Gateway Review 5 (operational review and
benefits realisation).
Gateway 3 should take place prior to the formal submission of the FBC to the
approving authority
¨¨ The arrangements for post project evaluation. These reviews may be undertaken
separately or in conjunction with Gateway Review 5 (operational review and
benefits realisation).
The Post-Evaluation Review (PER) for reviewing how well the service is running and
delivering its anticipated benefits should typically take place within 6 to 12 months
after the commencement of service, and thereafter as required by the benefits
delivery plan.
The arrangements for Gateway Reviews / Health Checks and PPE should be included in the
project management plan.
¨¨ how the business and service risks will be mitigated and managed
¨¨ how major contract change will be handled over the longer term
Output of Step 10
The management case has now been revisited, updated and completed in respect of the FBC.
A Gateway Review 3 (investment decision) should now be considered for the project, prior to the formal
submission of the FBC to the approving authority.
All parties should now be content for the project to proceed to contract signature, providing the above
work has been completed satisfactorily and the resultant scheme is affordable.
The FBC must be re-submitted for approval if the costs, benefits or contract terms vary significantly
post-FBC approval. The approving authority should stipulate the relevant thresholds as a condition
of approval.
This chapter provides some basic criteria for the review of the business case at its key stages
of development: Strategic Outline Case (SOC), Outline Business Case (OBC) and Full Business
Case (FBC).
¨¨ evidence the most economically advantageous tender (MEAT) for the project
¨¨ establish that the management arrangements for successful delivery are in place.
1. Ensure the mandate and brief for the project have been completed.
4. Draft the Scoping Document for the Project Business Case and arrange a meeting with
the business case reviewer/ approver to agree the content, governance, reporting,
assurance and approval arrangements.
¡¡ Revisit the economic dimension of the case following Workshop 3 (Appraising the
short-list).
¡¡ Prepare the Financial dimension of the case with the Finance Directorate.
¡¡ Update the economic appraisals to reflect best and final offers (BAFOs).
14. Monitor project delivery and undertake a Cabinet Office Gateway Review 4 (Readiness
for Service) prior to going live.
15. Use the Full Business Case (FBC) to support post-evaluation and benefit realisation.
16. Undertake a Cabinet Office Gateway Review 5 (Operations Review and Benefits
Realisation). Items 14 and 15 may be combined where it makes sense to do so.
The above process and level of effort will vary depending on the nature of the organisation, the
decision being sought and the expectations agreed in the Scoping Document.
Organisation/Department
Proposal Title
Sponsor/Senior Responsible
Owner
The business case process is scalable and should be used proportionately. The purpose of this
document is to agree the nature, type and content of the business case required.
The anticipated coverage of the Business Case should be agreed between the Project (Business
Case Authors) and Approving Authority in order to calibrate the analysis required and assist the
business case review and approvals process.
Potential considerations
Strategic Case ¨¨ Mandate and brief for the project.
¨¨ Requirement for feasibility study.
¨¨ Priority within the strategic portfolio.
¨¨ Critical path for project delivery.
¨¨ Relationship to the programme and other projects (if applicable).
¨¨ Potential constraints and dependencies.
¨¨ Workshop 1 attendees.
Economic Case ¨¨ CBA or CEA.
¨¨ Use of optimism bias and risk measurement.
¨¨ Benefits identification.
¨¨ Workshop 2 and 3 attendees.
Commercial Case ¨¨ Compliance with Government Commercial Operating Standards.
¨¨ Commercial strategy for organisation.
¨¨ Commercial and procurement strategies for the project.
¨¨ Potential procurement route.
¨¨ Workshop 4 attendees.
Potential considerations
Financial Case ¨¨ Requirement for initial funding of the scheme.
¨¨ Available budget for the scheme.
¨¨ Likely balance sheet treatment.
Management Case ¨¨ Business case development plan.
¨¨ Risk profile assessment (RPA) score.
¨¨ Project management methodology (PRINCE2).
¨¨ Project assurance requirements (Cabinet Office Gateway, Quality, Technical,
Security etc.).
¨¨ Workshop 5 attendees.
Business Case
Development Plan
Completed by:
Programme/Project Representative: .................................................................................
Date: ..................................
This will be dependent upon the nature of the proposal and the anticipated level of spending
and the quality of the analysis already undertaken.
b. The iterative production of the Business Case (Strategic Outline Case (SOC), Outline
Business Case (OBC) and Full Business Case (FBC) should be considered for larger,
complex schemes requiring a competitive procurement.
c. Consideration may be given to combining the SOC and OBC where the case for change
has already been made and agreed as part of a Programme Business Case (PBC).
d. Consideration may be given to combining the OBC and FBC where the intended
procurement route has been pre-competed and firm prices are available in support of
the spending proposal.
e. A Business Justification Case (BJC) may be considered for smaller items of spend,
which are NOT novel or contentious; within the organisational limit agreed for the use
of single business cases (BJC); and can be procured from an existing pre-competed
arrangement.
The Cabinet Office Gateway Risk Profile Assessment (RPA) MUST be used to assess the ‘risks’
associated with the scheme. The table below provides an overview of some of the key
considerations:
Stage 1 – scoping Preparing the Strategic Outline Case (SOC) Strategic case
Step 2 Making the case for change
Action 2 Agree strategic context
Action 3 Determine spending objectives, existing arrangements and business
needs
Action 4 Determine potential business scope and service requirements
Action 5 Determine benefits, risks, constraints and dependencies
Base case The best estimate of how much a proposal option will cost in
economic terms, including an allowance for risk and optimism.
Business As Usual (BAU) The cost of BAU provides a benchmark for comparing proposal
option options for intervention.
Business Justification A single stage business case, using the Five Case Model, for the
Case (BJC) delivery of relatively low level spend for which firm prices are
available.
Cost Benefit Analysis Analysis which quantifies in monetary terms as many of the costs
(CBA) of a proposal as feasible (financials), including items for which the
market does not provide a satisfactory measure of economic value
(non-financials).
Cost Effectiveness Analysis that compares the cost of alternative ways of producing
Analysis (CEA) the same or similar outputs.
Discounted Cash Flow A technique for appraising investments. It reflects the principle
(DCF) that the value to an investor of a sum of money depends on when
it is received.
Discount rate The annual percentage rate at which the present value of a £, or
other unit of account, is assumed to fall away through time.
Do minimum option An option where the public sector takes the minimum amount of
action necessary.
Expected value The weighted average of all possible values of a variable, where
the weights are the probabilities (in %s).
Five case model A systematic framework for the development and presentation
of the business case, comprising of the strategic, economic,
commercial, financial and management dimensions of the Case.
Full Business Case (FBC) The completed business case and third stage in the development
of a business case for a significant project, which identifies the
most economically advantageous offer following procurement,
confirms affordability and puts in place the detailed arrangements
for successful delivery.
Net Present Social Cost The discounted value of a stream of future costs.
(NPSC)
Net Present Social Value The discounted value of a stream of future costs and benefits. The
(NPSV) NPSV provides the present values of the sum of a future costs and
benefits.
Opportunity cost The value of the most valuable alternative uses of an asset or the
cost of something in terms of an opportunity forgone.
Options Framework filter A systematic framework for the generation of a wide range of
possible options (the ‘long-list’) and the filtering of a few possible
options for CBA/CEA (the ‘short-list’) and identification of the
preferred option (Flanagan, JC (2006).
Outline Business Case The ‘intermediate’ business case and second stage in the
(OBC) development of a business case for a significant project, which
identifies the option offering best public value for spend, confirms
the Deal and affordability, and puts in place the arrangements for
successful delivery.
Public Sector The best viable alternative option for direct public provision
Comparator (PSC) comparable to a PPP (PFI) option.
Required rate of return A target average rate of return for a public sector trading body,
usually expressed as a return on the current cost value of total
capital employed.
Spending objectives The ‘targeted’ outcomes for the scheme, which reflect the
rationale for the intervention and must be made SMART for the
purposes of evaluation. Occasionally referred to as the investment
objectives for the scheme.
Strategic Outline Case The ‘early’ business case and first stage in the development of a
(SOC) business case for a significant project, which makes the case for
change and appraises the available options.
Strategy The strategic context for the project, which demonstrates how the
project aligns with other projects within the strategic portfolio to
deliver the mission and vision of the organisation in the longer
term.
Switching values The point at which the choice of the preferred option would
switch to another option due to any uncertain costs and/or
benefits.
Transfer payment A payment for which no goods or services are received in return.
Uncertainty A scenario within which probabilities have not been identified for
a range of possible outcomes.
The Author:
Joe Flanagan is the architect of the Five Case Model Methodology and the author of this
series of international and national guides for the development of programme and project
business cases.
Joe retired in 2017, following 45 years of public service, but still supports the Better Business
Case Programme as joint Chief Examiner for the accreditation training scheme.
Prior to his retirement, Joe was the Director of Investment Policy and Appraisal for NHS Wales,
where he assisted Health Boards and Welsh Government with the development and appraisal of
their schemes.
Joe joined HM Treasury in 1972. In his last posting as Head of the Investment Proposal Service,
Central Computer and Telecommunication Agency and Cabinet Office, he assisted some
30 Government departments with the development of their IT schemes and HM Treasury
expenditure divisions with their appraisal, before moving on to become Commercial Director
for NHS Information Authority with responsibility for the national IT contract in NHS England
and Wales.
The Editor:
Since 2006 Joseph Lowe has been Head of Economics Branch in the spending side of
HM Treasury, where he is responsible for the Treasury’s Green Book and its supplements on
the appraisal of spending and investment. He is the editor of the Green Book, a new edition
of which was published in March 2018 and is author of several papers, published as Treasury
guidance, that apply economics to questions of public finance. He also looks after the guidance
on the ‘Treasury Spending Approvals Process’, known as TAPs, and is executive editor of the
Treasury guidance on development of business cases working with the originating author of the
five case model, Joe Flanagan, on the Treasury Better Business Cases accreditation and training
programme launched in May 2014.
He is a London University Graduate in Economics with Maths and Statistics and is a Chartered
Statistician. Before joining the civil service in 2003 he was a senior consulting director working
with companies in the energy, telecommunications, IT and financial services industries.
HM Treasury Green Book: Central Government Guidance on Appraisal and Evaluation 2018
Projects