Draft Specification For Execution of Work PDF
Draft Specification For Execution of Work PDF
STANDARD SPECIFICATIONS
FOR
EXECUTION OF BUILDING WORKS
Updated: March 2006
DRAFT
T A B L E O F C O N T E N T S
SPECIFICATION FOR
EXECUTION OF BUILDING WORKS
PAGE
SECTION DESCRIPTION
NO.
25 CARRIAGE OF MATERIAL 223
26 STEEL WINDOWS/DOORS 225
27 EARTH WORK 258
27-1 GENERAL 258
27-2 EXCAVATION 261
27-3 EARTH FILLING 268
28 TERMITE TREATMENT 270
28-1 PRE-CONSTRUCTION TREATMENT 270
28-2 ANTI TERMITE TREATMENT OF 272
EXISTING BUILDINGS
29 DISMANTLING 274
29-1 SCREENS 274
29-2 UNDER-PINNING 277
29-3 SHORING 279
30 CEMENT CONCRETE 280
30-1 GENERAL 280
30-2 CLASSES OF CONCRETE 338
30-3 MATERIALS 340
30-4 PROPORTIONING OF CONCRETE 342
30-5 MANUFACTURE OF CONCRETE 345
30-6 PROTECTION OF CONCRETE FROM 349
ENVIRONMENTAL CONDITIONS
30-7 FORM WORK 352
30-8 HANDLING AND PLACING CONCRETE 354
30-9 COVER OVER REINFORCEMENT 359
30-10 CONSTRUCTION JOINTS 360
30-11 EXPANSION AND CONSTRUCTION JOINTS 362
30-12 FINISHING PLASTIC CONCRETE 366
30-13 CURING CONCRETE 370
30-14 FINISHING FORMED CONCRETE SURFACES 373
30-15 PRE-CAST CONCRETE MEMBERS 376
30-16 MOULDED CEMENT CONCRETE ARTICLES 379
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
PAGE
SECTION DESCRIPTION
NO.
30-17 MORTAR AND GROUT 382
30-18 APPLICATION OF LOADS 384
30-19 MEASUREMENT AND PAYMENT 385
31 REINFORCING STEEL 386
32 BRICK WORK 390
32-1 GENERAL 390
32-2 BRICK WORK 1ST CLASS 398
32-3 BRICK WORK 2ND CLASS 399
32-4 BRICK WORK IN ARCHES 400
32-5 CORBELLING 403
32-6 COPING 404
32-7 WINDOW SILLS 405
32-8 CORNICES 406
32-9 STRING COURSES 407
32-10 EAVE BRICK WORK 408
32-11 DRIP COURSE 409
32-12 BRICK WORK IN REIMBURSEMENT TO DRAIN 410
32-13 BRICK WORK IN TEGA TO DRAIN 412
33 STONE 413
33-1 STONE MASONRY (GENERAL) 413
33-2 DIMENSION STONE (DRESSING AND CUTTING) 426
33-3 ASHLAR MASONRY 428
33-3(A) ASHLAR FINE 428
33-3(B) ROUGH TOOLED OR BASTARD ASHLAR 430
33-3(C) ROCK RUSTIC OR QUARRY FACED 431
ASHLAR MASONRY
33-4 ASHLAR FACING 432
33-5 ASHLAR BLOCK IN COURSE MASONRY 434
33-6 ASHLAR BLOCK IN COURSE FACING 436
33-7 COPING, CORNICES AND COLUMNS 438
33-8 COURSE RUBBLE MASONRY (1ST CLASS) 440
33-9 COURSE RUBBLE MASONRY (2ND CLASS) 442
33-10 RANDOM RUBBLE MASONRY 444
33-11 DRY RUBBLE MASONRY 446
33-12 STONE MASONRY IN ARCHES 448
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
PAGE
SECTION DESCRIPTION
NO.
34 ROOFING 451
34-1 FIRST CLASS TILES ROOFING 455
34-2 SECOND CLASS TILES ROOFING 459
34-3 JACK ARCH ROOFING 460
34-4 JACK ARCH ROOFING 464
(SPRUNG FROM TOP OF BEAMS)
34-5 JACK ARCH ROOFING 465
(FOR CARING FLOORING OF THE ROOM)
34-6 GALVANIZED CORRUGATED STEEL 466
SHEET ROOFING
34-7 CORRUGATED ASBESTOS CEMENT 469
SHEET ROOFING
34-8 “KHURRAS” “PERNALAS” AND SPOUTS 472
34-9 GUTTERS AND FLASHINGS 474
34-10 TREATMENT OF ROOF SLAB 476
34-11 THERMAL INSULATION OF R.C.C. ROOF 478
35 FLOORING 488
35-1 MUD FLOORING 491
35-2 BASE FOR FLOORING 492
35-3 BRICK OR TILE FLOORING 494
35-4 FLAGSTONE FLOORING 497
35-5 MARBLE FLOORING 500
35-6 GLAZED TILE FLOORING 503
35-7 MOSAIC TILE FLOORING 506
35-8 CONGLOMERATE FLOORING 509
(CEMENT CONCRETE SINGLE COAT)
35-9 CONGLOMERATE FLOORING (TWO COAT) 511
35-10 TERRAZO FLOORING 513
35-11 DRY BRICK PAVING 516
35-12 WOODEN FLOORING 517
36 SURFACE RENDERING 526
36-1 GENERAL DEFECTS IN PLASTER AND 526
THEIR REMEDIES
36-2 CEMENT-SAND PLASTERING 529
36-3 LIME-CEMENT-SAND PLASTERING 532
36-4 COLOURED CEMENT-SAND PLASTERING 534
36-5 COLOURED LIME PLASTERING 536
36-6 MUD PLASTER 538
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
PAGE
SECTION DESCRIPTION
NO.
36-7 GYPSUM PLASTER 540
36-8 POINTING 551
36-9 WHITEWASHING 555
36-10 CEMENT WASH 557
36-11 COLOUR WASHING 559
36-12 VINYL EMULSION 561
36-13 PLASTIC EMULSION 563
37 WOOD WORK 567
37-1 GENERAL 567
37-2 DOORS AND WINDOWS (GENERAL) 581
37-3 PANELLED AND GLAZED DOORS AND WINDOWS 586
37-4 FRAMED AND BRACED DOORS AND WINDOWS 589
37-5 LEDGED AND BRACED DOORS AND WINDOWS 591
37-6 LEDGED DOORS AND WINDOWS 593
37-7 CLERESTORY WINDOWS 595
37-8 WIRE GAUZED DOORS 597
37-9 WIRE GAUZED WINDOWS 599
37-10 WIRE GAUZED CLERESTORY WINDOWS 600
37-11 FIXED WIRE GAUZED 601
37-12 GLAZING 602
38 PAINTING AND VARNISHING 623
38-1 GENERAL 623
38-2 PAINTING NEW WOOD WORK 633
38-3 REPAINTING WOOD WORK 636
38-4 VARNISHING 639
38-5 WAX POLISHING 641
38-6 FRENCH POLISHING 644
38-7 PAINTING WOOD WORK WITH SOLIGNUM 646
OR CREOSOTE ON COAL TAR
38-8 PAINTING IRON WORK ABOVE WATER 648
38-9 PAINTING IRON WORK WHICH REMAINS 650
UNDER WATER
39 CLADDING 652
39-1 BRICK CLADDING 652
39-2 WASH TERRAZZO 654
39-3 PORCELAIN/CERAMIC TILE CLADDING 656
39-4 CAST STONE CLADDING 658
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
PAGE
SECTION DESCRIPTION
NO.
40 FALSE CEILING 659
40-1 GENERAL 659
40-2 FALSE CEILING WITH THERMOPORE SHEET 661
40-3 FALSE CEILING WITH GYPSUM BOARD 663
40-4 FALSE CEILING WITH PLASTER OF PARIS 664
40-5 FALSE CEILING WITH M.D.F. BOARD 665
41 DAMP PROOF COURSE (D.P.C.) 666
41-1 CEMENT CONCRETE DPC 666
41-2 DPC OF CEMENT SAND PLASTER 668
41-3 MARBLE DPC 670
41-4 JUTOID (JUTE BASED) DPC 672
42 ALUMINUM ALLOY WINDOWS 673
43 WALLCOVERING/ARCHITECTURE COATING 678
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–25
CARRIAGE OF MATERIALS
25-1 DESCRIPTION
Unless otherwise specified or directed in writing by the Engineer In-
charge, carriage of all materials between stations connected by rail
shall be done only by the railway goods train and all rules and
regulations in force in the Railway Department in this regard, shall
hold good. Other means of transport shall be allowed only when:
(i) The goods train is not available within the stipulated period. In
this case a certificate shall have to be recorded by the Engineer
in-charge.
(ii) The railway track is not in order for a certain reason and is
expected to take a considerable time before it is put in order.
(iii) The material to be transported is perishable, and the goods train
takes a considerably longer time than the road transport, and
thus does not ensure a safe transportation.
(iv) Any other unforeseen calamity, which in the opinion of the
Engineer in-charge is so pressing as to make carriage by road
essential.
25-3 STOCKING
The material carted shall be properly stacked at the specified site to the
satisfaction of the Engineer in-charge or his authorized subordinate.
223
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
25-5 MEASUREMENT
Carriage shall be contracted for by weight or by volume at a mileage,
kilometre or chainage rate or a fixed rate between specified places. In
the former case the distance shall be measured by the nearest
practicable route, and the miles kilometres and chains measured shall
be statute miles kilometres/chains.
25-6 RATE
(i) The unit rate shall include loading of material within one chain,
carriage to a specified site, unloading and stacking, as per
above specifications, within a distance of one chain from the
site of unloading.
(ii) If the lead for loading, unloading and stacking exceeds one
chain the payment for additional carriage shall be made whole
of the distance and not starting from the second chain.
(iii) In case of works where item rates include the handling of
material up to three chains distance, any extra carriage involved
beyond this distance of three chains shall be payable for whole
of the distance and not for the 4th and subsequent chains only.
This does not alter the procedure of carriage at the carriage
rates for subsequent miles beyond prescribed limits.
224
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–26
STEEL WINDOWS/DOORS
26-1 DESCRIPTION
This section of specifications covers materials, construction, sizes,
finishes and hardware for steel windows and doors for buildings.
26-2 GLOSSARY
Accessory An essential fixing or glazing component or material or
weather bar, not attached at the factory.
Casement A window, or that part of a window, which open on
hinges or pivots. A casement door is hinged at the side.
Composite An assembly two or more units coupled together by
one or more mullions or transoms.
Coordinating A plane by reference to which a building component or
plan assembly is coordinated with another.
Coordinating A space bounded by coordinating plans allocated to a
space building component or assembly, including allowance
for joints and tolerances.
Coordinating 1. A dimension of a coordinating space.
dimension 2. A dimension which is common to two or more
building components to permit their assembly.
Coordinating The size of a coordinating dimension (length or height
size of a coordinating space).
Basic space A space bounded by reference plans assigned to
received a building component or assembly, including
allowance for joints and tolerances.
Work size The size of a building component specified for its
manufacture, to which its actual size should conform
within specified permissible deviations.
Manufacturing A size within the specified permissible deviations from
size a work size.
Tolerance The difference between the limits within which a size
or position should lie.
Deviation The difference between a size or position (actual, limit,
etc) and a specified size or position.
Margin The distance between the joints face of a building
component and the joint reference plane.
Mullion A vertical bar for coupling units side by side.
Transom A horizontal bar for coupling units one above the other.
Unit A four-sided frame which may be a fixed light or a
casement or a combination of both. Each unit in this
standard has an individual code reference.
225
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
26-3 GENERAL
26-3.1 Windows and doors shall comply with the elevations and sizes shown
in Figs.3 to 6 (page 235 to 238). All shall have glazing rebates 12.7mm
deep for outside glazing. Lungs and/or screws necessary for fixing
shall be provided.
26-3.2 Casements and doors shall open outwards except for bottom-hung
casements and the upper halves of reversible casements which shall
open inwards.
26-3.3 Casements shall be supplied complete with the hinges and fittings
attached as specified in 26-9, 26-10 and 26-11. Casements shall be
fitted to their frame so as to provide face contact all round allowing for
the thickness of normal site painting. The fittings shall be properly
checked and adjusted by the manufacturer so that the casements can be
operated correctly. Casements and doors shall be secured in the closed
position before dispatch.
26-5 CONSTRUCTION
26-5.1 Windows and doors (and their constituent parts) covered by this British
Standard shall be made solely of steel except where other materials are
stated in this specification. Typical elevations and details of windows
and doors, both single and composite, are shown in Fig. 7 to 11 (page
239 to 248).
26-5.2 Windows and doors shall be constructed of bars which have been cut
to length and mitred. All corners shall be welded solid to form right
angles and all frames shall be square and flat. Subject to manufacturing
tolerances.
26-5.3 Internal bars shall be tenoned and riveted to the outer frames and to
each other.
26-5.4 Windows and doors may have holes in the webs of the bars other than
those required in manufacture and for fixing.
26-5.5 Handle plates, stay pegs, brackets and stay rests shall be of steel.
26-5.6 Windows and doors shall have glazing rebates 12.7mm deep for
outside glazing. Lugs and/or screws necessary for fixing shall be
provided.
26-5.7 Casements and doors shall open outwards except for bottom-hung
casements and the upper halves of reversible casements which shall
open inwards.
226
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
26-5.8 Casements shall be supplied complete with the hinges and fittings
attached as specified in 7,8 and 9. Casements shall be fitted to their
frame so as to provide face contact all round allowing for the thickness
of normal site painting. The fittings shall be properly checked and
adjusted by the manufacturer so that the casements can be operated
correctly. Casements and doors shall be secured in the closed position
before dispatch.
26-6.4 TOLERANCES
The tolerance upon a work size shall be 3 mm.
26-6.5 DEVIATIONS
The maximum permissible manufacturing deviation shall be + 1.5mm.
26-7 COMPOSITES
26-7.1 GENERAL
26-7.1.1 Coupling
Coupling to form composites shall be by screws and nuts through the
fixing holes of the units and corresponding holes in the mullions and
transoms see Fig. 15 (page 254, 255). Minimum fixings shall be in
accordance with the positions. Mastic, screws and nuts sufficient for
these purposes shall be supplied by the window manufacturer.
26-7.1.2 Transport
At the discretion of the manufacturer, composites or parts of
composites may be assembled in the works before dispatch. In any
such assembly there shall be:
(a) No single item assembled with a coordinating size greater than
2400 mm x 1800 mm or 2700 mm x 1200 mm.
(b) Not more than two mullions spanning the full height nor more
than two transoms spanning the full length.
227
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
26-7.3 TRANSOMS
26-7.3.1 Transom section are shown in Fig: 16 (page 256, 257). Generally the
transom bar shall be of section K12. The mullion section K11 may be
supplied as a transom above a fixed light not exceeding 1200 mm long.
26-7.3.2 In composite up to a maximum coordinating size of 2400 mm long
where both mullions K11 and transoms K12 occur, the transom section
K12 shall be continuous across the full length of the assembly.
228
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
229
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
230
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Each door shall be provided with one lock, one pair of lever handles
and two face-operated bolts or turn buckles. Double doors shall also
have two concealed bolts. Each leaf shall be provided with a concealed
head stay to limit opening to 90o, except where friction hinges are
fitted.
26-11.2 LOCKS
26-11.2.1 Each single door and the first opening leaf (the left hand leaf looking
from the outside) of each double door, shall be fitted with a mortice
lock which can be locked by a loose key from both the inside and
outside. The lock shall be housed inside the steel panel.\
26-11.2.2 Each lock shall have nylon bushes, brass bolts and at least four brass
levers and phosphor bronze springs. The lock bolts shall have a
minimum throw of 12 mm. Key holes shall be covered by escutcheons.
The forend and the striking plate shall be of zinc alloy complying with
BS 1004-A. The locks shall be made with 150 differs arranged on the
levers without the use of wards, so that skeleton keys cannot be
produced to operate more than one differ. Lock spindles shall be of
steel, zinc plated complying with BS 1706 Classification No. Zn10 and
passivated.
26-11.2.3 Two steel keys, nickel-plated complying with BS:1224 Classification
No. Fe/Ni 10b (or p or d) shall be supplied for each lock.
231
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
26-13.4 PRE-TREATMENT
Manufacturers shall indicate if windows and doors are prepared for site
painting by any treatment at works after galvanizing.
232
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
26-16 GLAZING
All frames to receive glass shall have holes for spring wire glazing
clips or glazing cleats in accordance with the requirements of CP 152.
Cleats shall be supplied by the window manufacturer if specified, but
spring wire glazing clips, setting blocks and distance pieces shall be
supplied by the glazing contractor. To obviate the use of excessive
putty in certain bar sections, the manufacturer shall securely fix a
blocking piece of inert of insert material in these section as shon at (6)
in Fig.7 (page 239 to 241). Glass sizes are listed in British Standard BS
990:Part-2:1972 Appendix B.
26-17 WEATHER-STRIPPING
26-17.1 Reversible horizontally pivoted casements shall be weatherstripped
with chloroprene rubber (CR) to comply with BS 4255, Part 1, class C.
26-17.2 Side-hung, top-hung and bottom-hung casements shall be supplied
weatherstripped if so ordered. For this weatherstripping the
manufacturer may use either CR, or polyvinyl chloride (PVC) to
comply with BS 2571.
26-17.3 Weatherstripping shall be securely fixed by the manufacturer to
provide a continuous contact between the opening casement and the
fixed frame.
Note. It is recommended that weatherstripping should not be painted.
26-18 MEASUREMENT
Payment for doors and windows will be made by measuring clear
opening area in brickwork or concrete in square feet/meters.
26-19 RATE
Rates for all the items under this Section shall cover the cost of
furnishing all the materials, labour, scaffoldings and performing all
operations in connection with their installation in accordance with
instructions. It is particularly mentioned that the rates for fixing doors
and windows etc. shall include fixing of all finished hardware iron
mongery fittings such as locks, peg stays, handles, push plates, kicking
plates, door-closers, glazing, flexible compounds, rubber lining and
appliances at site and performing all operations in accordance with the
drawings and specifications.
233
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
234
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
235
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
236
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
237
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
238
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
239
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
240
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
241
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
242
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
243
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
244
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
245
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
246
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
247
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
248
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
249
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
250
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
251
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
252
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
253
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
254
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
255
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
256
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
257
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–27
EARTHWORK
27-1 GENERAL
27-1.1 DESCRIPTION
All excavations and earthwork shall be performed and executed in
accordance with stipulations (specifications) and requirements set forth
here which shall apply except when they are specifically modified in
writing by the Engineer-in-charge for any particular item. The method
of carrying out earthwork shall be subject to the approval of the
Engineer in-charge in writing.
27-1.2 GLOSSARY
Borrow-pits A wall provided at the downstream and/or up stream
extremity of a sluice or regulator to prevent the
undermining of the sub-soil by scour, piping, or
floatation.
Cover The minimum thickness or height of earth required
anywhere over a specified level or line measured
vertically or horizontally, as the case may be. The
cover over hydraulic gradient line or saturation line
is measured vertically.
Embankment The earth work above natural ground by deposition
of specified materials.
Lead The shortest possible horizontal route between the
Horizontal centre of gravity of the material excavated and the
centre of gravity of the material finally placed in the
building.
Lead-Total The horizontal lead as defined above plus the lift
converted into horizontal lead, if any.
Lead-Vertical The vertical difference between the centre of gravity
of the earth excavated and the centre of gravity of the
earth placed in the building.
Soil Sediments, or other unconsolidated accumulation of
solid particles produced by the physical and chemical
disintegration of rocks, and which may or may not
contain organic matter.
258
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
grades and levels shown on the approved drawings. If they are not
indicated on the drawing, they shall be carried out to the profile agreed
to by the Engineer in-charge in writing before the commencement of
work.
27-1.5 DATUM
Any bench mark, which is to be used for the work, shall be correctly
related to the datum specified on the approved drawing or fixed by the
Engineer in-charge and the contractor shall make and maintain at his
own cost all such permanent bench marks required for the proper
execution of works in the vicinity thereof, in perfect order to the
satisfaction of the engineer-in-charge.
259
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
wide and 6 inches deep and pegs shall be fixed at every centre line. In
the case of the excavation of foundation, the centre, longitudinal or
face line and at least one main cross line, shall be marked by means of
masonry pillars built clear of the point to which the slopes of the
excavation shall extend. On each pillar, there shall be an accurate mark
to enable a surveying instrument to be set up over it for setting out
purposes.
260
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
27-2 EXCAVATION
27-2.1 DESCRIPTION
All excavations shall be done in accordance with the provisions of this
section and to the lines and grades shown on the approved drawings or
as directed in writing by the Engineer in-charge. During the progress of
work, if it is considered necessary or desirable by the Engineer in-
charge to vary the dimensions of the excavation from those shown on
the drawings or specified, he shall get the dimensions revised by the
competent authority and communicate the change in writing to the
contractor. The contractor shall perform the work and make
excavations according to the revised dimensions as communicated by
the Engineer in-charge.
261
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
262
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
263
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
27-2.7 CLASSIFICATION OF
EXCAVATED MATERIAL
Excavation shall be classified under the following heads for recording
measurement and making payment:
(a) Soft soil. It includes all cutting in sand, silt and those soils,
which offer no resistance to excavation and sometimes require
shoring when foundation (of buildings etc) of exact dimensions
is required to be excavated since they have small angle of
repose.
(b) Ordinary soil. It includes all cutting in earth which can be
ploughed, irrespective of the fact whether picks or “phawarahs”
have been used in the actual excavation. Usually it includes:-
i) Spoil or rubbish of every description.
ii) Earth and sandy loam.
iii) Any other formation into which a spade can be entered
and can be easily excavated by the application of kassi,
pick or shovel.
(c) Hard soil. There are the following two types of hard soil:
i) It includes stiff and heavy clay soil having specific
gravity of 1.5 and above, which can be dug with
repeated blows of kassi or pick axe.
ii) Soil having small percentage, say up to 15% of
kankar or boulders which can be easily dug and
removed along with the soil.
(d) Very hard soil. The following types of soil fall under this
definition:
i) It includes hard moorum with high percentage of kankar
(more than 15%) or boulder (less than 20%), which can
be individually lifted by hand.
ii) Mud concrete.
iii) Conglomerate formation, shale lime concrete,
brickwork in lime and stone masonry in lime.
iv) Metalled surface of the road (tarred or untarred).
v) Hard core under floor and road bottoming.
264
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
265
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
27-2.8 MEASUREMENT
27-2.8.1 QUANTITY OF WORK
Excavation shall be done as per authorized outlines mentioned in
Section 27-1.3 of these specifications. The exact quantum of earthwork
shall be ascertained by taking measurements of excavation from which
the material has been taken out and not of the resultant spoil and
converted to solid measurement by multiplying it with factors
mentioned below for soil and rocks. The unit of measurement shall be
100 cubic feet.
27-2.9 RATE
The unit rate shall be full compensation for all costs to comply the
provision of above specifications. A special rate shall be settled and
paid for the following items of works:
(a) For cutting down, removing and digging out roots of all trees
(not shrubs, grass etc) of 2 feet girth. Measurement of girth
shall be taken 5 feet above ground level. Rate shall be fixed for
each tree. Trees shall be counted and marked before removal.
This work may be done departmentally if thought necessary by
the engineer-in-charge.
(b) Special material such as sand, or selected earth, brought from
the other source than retrieved from the excavation.
266
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Table No. 1
Conversion
In the case of earthwork measurement where extra lead is to be paid
for lift the method will be as follows: The lift will be measured from
the centre of gravity of the excavated earth to that of placed earth. This
will constitute the mean lift. The equivalent leads for various mean lifts
are given below:
Equivalent Horizontal
Lift in feet Conversion factor
lead in feet
1 1' lift 8' lead 8
2 1' lift 8' lead 16
3 1' lift 8' lead 24
4 1' lift 8' lead 32
5 1' lift 10' lead 50
6 1' lift 10' lead 60
7 1' lift 10' lead 70
8 1' lift 10' lead 80
9 1' lift 11' lead 99
10 1' lift 12' lead 120
11 1' lift 13' lead 143
12 1' lift 14' lead 168
13 1' lift 15' lead 195
14 1' lift 16' lead 224
15 1' lift 17' lead 255
16 1' lift 18' lead 288
17 1' lift 19' lead 323
18 1' lift 20' lead 360
19 1' lift 21' lead 399
20 1' lift 22' lead 440
21 1' lift 23' lead 483
22 1' lift 24' lead 528
23 1' lift 25' lead 575
24 1' lift 26' lead 624
25 1' lift 27' lead 675
26 1' lift 27' lead 702
27 1' lift 27' lead 729
28 1’ lift 27’ lead 756
29 1' lift 27' lead 783
30 1' lift 27' lead 810
These conversion factors also incorporate allowance for extra lead due
to cross lead with a view to ensuring a uniform system. The equivalent
lead will be added to the horizontal lead to get the total lead to be paid
for. The exact site or R.Ds between which extra lead is to be given
must be recorded in the first column of detailed measurements in the
measurement book.
267
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
27-3.1 DESCRIPTION
This work shall consist of filling earth in accordance with these
specifications and in conformity with the level and dimensions shown
on the Drawings or as directed by the Engineer Incharge.
268
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
27-3.3.1.5 Filling material that does not contain sufficient moisture to obtain the
required compaction shall be given additional moisture by means of
approved sprinklers and mixing. Material containing more than the
amount of moisture necessary to obtain the required compaction may
not, without written approval of the Engineer Incharge be incorporated
in the filling until it has been sufficiently dried out.
27-3.3.1.6 When materials of widely divergent characteristics, such as clay and
chalk or sand, drawn from different source are to be used in the filling,
these shall be deposited in different layers (with individual layer of the
same material) and sequence of material to be laid as approved by the
Engineer Incharge. Lumps of clay or other similar material shall be
broken down, and no accumulation of lumps or boulders in the filling
with be permitted.
27-3.4 MEASUREMENT
The quantities to be paid for shall be the number of cubic meters or
thousands of cubic feet in the volume of filling compacted to desired
densities in place, accepted by the engineer incharge made with
material resulting from:
1. Borrow Area
2. Structural Excavation.
Material from Structural Excavation, as defined in section 27-2 which
is placed in the Filling and accepted by the Engineer Incharge will be
paid for under pay item No. 27-3.6.3 or 27-3.6.4 as the case may be,
and such payments will be deemed to include all costs in connection
with this material in constructing the embankment.
27-3.5 RATE
The unit rate shall be full compensation for all costs of complying with
the provisions of this section regarding filling, in accordance with
Drawings and as directed in writing by the Engineer-in-charge.
269
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–28
TERMITE CONTROL
28-1.1 DESCRIPTION
The work shall consist of pre-construction termite treatment through
treatment of soil beneath the building and around the foundation with
termicides in accordance to these specifications.
28-1.2 MATERIALS
28-1.2.1 TERMICIDES
Termicides shall conform to specifications as approved by the
Departmental Committee for already working for enlistment and pre-
qualification of manufacturer for building components, fixtures,
fittings and other allied services.
28-1.2.2 WATER
It shall conform to Section 1 of these specifications.
28-1.3 TREATMENT
28-1.3.1 TREATMENT OF FOUNDATION
Bottom surface and sides of the excavation shall be treated with the
termicide solution through uniform spray with power sprayer at the
rate of 4-litre per m2/10.76 ft2. The preparation of solution i.e. ratio of
termicide and water shall as recommended by the manufacturers of
termicide.
270
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
28-1.3.4 PRECAUTIONS
28-1.3.4.1 Laying of lean concrete should start when the termicide solution is
absorbed by the soil and surface is quite dry.
28-1.3.4.2 Treatment shall not be carried out when it is raining or when the soil is
wet with rain or sub-soil water.
28-1.3.4.3 Once formed, treated soil barrier should not be disturbed.
28-1.4 MEASUREMENT
The work shall be measured as surface area treated separately in the
following stages.
a) Foundation stage.
Treated surface area shall be worked out by multiplying the
sectional perimeter of excavation made for foundation with the
length of excavation.
b) Floor area of the building.
c) Out side barrier.
External perimeter of the building multiplied by 5 ft.
28-1.5 RATE
28-1.5.1 LABOUR RATE
This shall include.
a) Preparation of solution of termicide and water.
b) Application of solution with power spray machine which also
includes, operation charges of spray machine i.e. Hire charges
POL lubricant and crew.
c) Drilling of hole for outside barrier.
d) Injection of termicide solution in the holes.
e) Tempting of earth after creation of outside barrier.
271
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
28-2.1 DESCRIPTION
This work consist of treatment of buildings to control subterranean
termite attack in accordance to these specifications.
28-2.2 MATERIALS
28-2.2.1 TERMICIDES
It shall conform to Section 28-1.2.1 of these specifications.
28-2.2.2 WATER
It shall conform to Section 1 of these specifications.
272
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
exposing the sides of the column and plinth beams up to a depth of 300
mm, or up to the bottom of the plinth beams, if this level is less than
300 mm. The Termicide solution should be sprayed on the backfill
earth, as it is refilled into the trench, directing the spray against the
concrete surface of the beam or column as the case may be. If there is a
concrete or masonry apron around the building, approximately 12 mm
diameter holes are drilled to the plinth wall about 300 mm apart, deep
enough to reach the soil below and the chemical emulsion pumped into
these holes to soak the soil below and the chemical emulsion pumped
into theses holes to soak the soil below at a rate of 2.25 liter/linear
meter. 12 to 15 mm diameter hole shall be drilled at the junctions of
floors and walls at 300 mm interval to depth of 375 mm to reach the
soil underneath the floor.
28-2.3.4 Termicide solution should be injected in to the holes using power
operated pressure pump at the rate 4 liter/hole. Holes should then be
sealed with matching coloured cement. The movement of termite
through masonry walls should be restricted by drilling holes in the
masonry walls at the plinth level. The holes should be drilled at a
downward angle of 45 degree preferably on both side of plinth wall
approximately at 300 mm intervals. The Termicide solution should be
injected, holes to holes in the masonry using a pressure pump. The
holes should also be drilled at critical points such as wall corners and
the points where door and windows are erected. The Termicide
solution should be injected to the holes till refusal or to maximum of 1
liter/hole. The treated holes then be sealed.
28-2.3.5 All existing woodwork in the building in contact with the floor and
walls and which is invested by termite should be treated at the points
of contact with adjoining masonry, with the Termicide solution. The
holes of 6 mm diameter should be drilled downward angle 45 degree at
the junction of woodwork and masonry. Termicide solution should be
ejected into these holes upto a ½ liter per hole. The treated hole should
then be sealed. If the wood work is not already painted/varnished two
coats of temicide should be given on all surface and crevices adjoining
the masonry. Cover of the electrical switch boxes should be removed
and inside of such boxes should be treated with termicides dist.
Refixing of switch boxes covers should be done after termide treatment
of switch boxes.
28-2.4 MEASUREMENT
It shall be measured as plinth area of the building treated. Its unit shall
be Sft.
28-2.5 RATE
The rate shall include for full compensation for the cost of the
termicide dirlling, pumping/injection of termicides sealing the treated
holes with cement sand slurry of matching colour, cleaning the floor to
the satisfaction of Engineer-in-charges.
273
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–29
DISMANTLING
29-1 SCREENS
29-1.1 SCREENS
If specified or directed by the Engineer-in charge, the contractor shall
provide, erect and remove screens of canvas or other suitable material
to minimize the nuisance from dust and shall provide for watering as
the work of demolition proceeds.
29-1.4 DAMAGE
(i) The contractor shall be responsible for carrying out dismantling
operations strictly in accordance with the specifications or
directions of the Engineer-in-charge, with appropriate tools and
in such a manner as to avoid unnecessary damage or injury to
other adjoining work, and those parts of work which are to be
retained, and to render unserviceable as little of the material as
possible.
(ii) The contractor shall, if specified or directed by the Engineer-in-
charge, make good any damage to work caused during
demolition and shall protect as far as possible all trees, shrubs,
etc., near the work.
274
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
29-1.7 LOWERING
Trusses, R. S. beams, battens, purlins, sheets, tiles, boards, wooden
frames, water supply and electric fittings and all material liable to be
damaged by dropping from a height, shall be lowered down to the
ground by means of rope or another approved appliance. If any
serviceable article is damaged or broken on account of the negligence
of the contractor he shall have to pay to the department the current
market rates for the acticle.
275
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
29-1.10 MEASUREMENT
Dismantling (Demolition) shall be measured by bulk, surface area or
linear dimensions depending upon the article to be dismantled. The
units of measurement shall be 100 cu.ft/cu.m, 100 sq.ft./sq.m or 1 Rft.
29-1.11 RATE
(i) The unit rate for demolition shall include dismantling of
material, its careful lowering to the ground, sorting out and
stacking within 300 feet of the site of demolition, in accordance
with the above specifications.
(ii) The rates for dismantling roofs or upper storey floors include
the dismantling of all materials, except roof supports such as
beams and trusses.
276
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
29-2 UNDER-PINNING
29-2.1 LENGTHS
Unless otherwise specified or directed by the Engineer-in-charge, the
underpinning shall be executed in lengths not exceeding 5 feet at a
time and all operations shall be carried out to the satisfaction of the
Engineer-in-charge. No under-pinning shall be done simultaneously at
a distance less than 6 feet apart.
29-2.5 WEDGING
Unless otherwise specified or directed by the engineer-in-charge, the
top of new underpinning shall be wedged and pinned up to the under
side of old concrete foundations, when required, with cement sand
mortar 1:3 mixed fairly dry and well-rammed.
277
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
29-2.8 MEASUREMENTS
Measurement shall be made of each operation involved in under-
pinning according to the relevant items of work. The unit of
measurement shall be the same as of the relevant items.
29-2.9 RATE
The unit rate shall include underpinning as per above specifications
and carriage of materials to the site of work as in case of relevant items
of work.
278
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
29-3 SHORING
29-3.1 USE
Unless otherwise specified or directed by the engineer-in-charge, all
walls, floors, roofs, partitions of building on the site or adjoining the
works shall be secured by means of shoring to the entire satisfaction of
the Engineer-in-charge, and on completion of the work or when
directed by the Engineer-in-charge or his authorized representative the
shoring shall be removed and the area left in good order.
29-3.2 REQUIREMENTS
Unless otherwise specified, the shoring shall generally consist of dogs
hoop iron, hooks, shores or rakers, sloe pieces, wall pieces or plates,
braces, struts, needles, cleat, wedges and posts. The wooden
components when used shall be of properly seasoned Shisham, except
for rakers and struts which shall be of Sal, free from defects, unless
otherwise specified.
279
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–30
CEMENT CONCRETE
30-1 GENERAL
30-1.1 DESCRIPTION
This work shall consist of furnishing placing, finishing and curing
concrete in structures in accordance with these specifications and
conforming to the lines, grades, and dimensions shown on the plans.
The work includes elements of structures constructed by cast-in-place
and precast methods using either plain (unreinforced), reinforced, or
prestressed concrete or any combination thereof.
30-1.2 GLOSSARY
The following definitions apply to cement & concrete:
Abrasion Wearing away of a surface by rubbing and friction.
damage
Abrasion Ability of a surface to resist being worn away by
resistance rubbing and friction.
Absolute Ratio of the mass of a given volume of a solid or liquid
specific gravity at a stated temperature to the mass of an equal volume
of gas-free distilled water at a stated temperature.
Absolute In the case of solids, the displacement volume of
volume particles themselves, including their permeable and
impermeable voids, but excluding space between
particles; in the case of fluids, their volume.
Absorbed Moisture that has entered a solid by absorption and has
moisture physical properties not substantially different from
ordinary water at the same temperature and pressure.
Absorption The process by which a liquid is drawn into and tends
to fill permeable pores in a porous solid; also the
increase in mass of a porous solid resulting from the
penetration of a liquid into its permeable pores.
Accelerator A substance which, when added to concrete, mortar, or
grout, increases the rate of hydration of the hydraulic
cement, shortens the time of setting, or increases the
rate of hardening, strength development, or both.
Adhesion The state in which two surfaces are held together by
interfacial effects which may consist of molecular
forces, interlock action, or both.
Adhesives The group of materials used to join or bond similar or
dissimilar materials; for example, in concrete work, the
epoxy resins.
280
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
281
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
282
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
283
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
284
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
285
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
286
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
287
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
288
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
289
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
bags.
Cement, low- A Portland cement that produces limited generation of
heat heat during setting.
Cement, A hydraulic cement produced by pulverizing Portland-
Portland cement clinker and usually containing calcium sulfate.
Cement, A hydraulic cement consisting of an intimately
Portland blast- interground mixture of Portland-cement clinker and
furnace slag granulated blast-furnace slag or an intimate and
uniform blend of Portland cement and fine granulated
blast-furnace slag in which the amount of the slag
constituent is within specified limits.
Cement, A hydraulic cement consisting of an intimate and
Portland- uniform blend of Portland cement or Portland blast-
pozzolan furnace slag cement and fine pozzolan produced by
intergrinding Portland-cement clinker and pozzolan, by
blending Portland cement or Portland blast-furnace slag
cement and finely divided pozzolan, or a combination
of intergrinding and blending, in which the pozzolan
constituent is within specified limit.
Cement, slag A hydraulic cement consisting mostly of an intimate
and uniform blend of granulated blast-furnace slag and
hydrated lime in which the slag constituent is more
than a specified minimum percentage.
Cement, Portland cement, low in tricalcium aluminate, to reduce
sulfate- susceptibility of concrete to attack by dissolved sulfates
resistant in water or soils.
Cement, Super A hydraulic cement made by intimately grinding a
sulphated mixture of granulated blast-furnace slag, calcium
sulfate and a small amount of lime, cement, or cement
clinker, so named because the equivalent content of
sulfate exceeds that for Portland blast-furnace slag
cement.
Cement, white Portland cement which hydrates to a white paste; made
from raw materials of low iron content the clinker for
which is fired by a reducing flame.
Cement- The ratio of cement to total aggregate, either by mass
aggregate ratio or volume.
Cement Quantity of cement contained in a unit volume of
content concrete or mortar, preferably expressed as weight.
Cement gel The colloidal material that makes up the major portion
of the porous mass of which mature hydrated cement
paste is composed.
Cement gun A machine for pneumatic placement of mortar or small
aggregate concrete; in the “Dry Gun”, water from a
separate hose meets the dry material at the nozzle of
the gun; with the “Wet Gun”, the delivery hose
conveys the premixed mortar or concrete.
Cement paint A paint consisting generally of white Portland cement
and water, pigments, hydrated lime, water repellents, or
hygroscopic salts.
290
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
291
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
292
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
293
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
green
Concrete, heat- Any concrete that will not disintegrate when exposed to
resistant constant or cyclic heating at any temperature below
which a ceramic bond is formed.
Concrete, Concrete of substantially higher density than that made
heavyweight using normal-weight aggregates, usually obtained by
use of heavyweight aggregates and used especially for
radiation shielding.
Concrete, Concrete, which, through the use of high-early-strength
high-early- cement or admixtures, attains a given level of strength
strength earlier than normal concrete.
Concrete, Concrete that has a specified compressive strength for
high-strength design of 6000 psi (41 MPa) or greater.
Concrete, in- Concrete that is deposited and allowed to harden in the
situ place where it is required to be in the completed
structure, as opposed to precast concrete.
Concrete, Concrete having low thermal conductivity; used as
insulating thermal insulation.
Concrete, lean Concrete of low cement content.
Concrete, Concrete of substantially lower density than that made
lightweight using aggregate of normal density
Concrete, mass Any volume of concrete with dimensions large enough
to require that measures be taken to cope with
generation of heat from hydration of the cement and
attendant volume change to minimize cracking.
Concrete, Concrete cast with no joints other than construction
monolithic joints.
Concrete, Concrete having a unit weight of approximately 150 lb
normalweight per cu ft (2400 kg/cu m) made with normalweight
aggregates.
Concrete, plain Concrete without reinforcement; reinforced concrete
that does not conform to the definition of reinforced
concrete; also used loosely to designate concrete
containing no admixture and prepared without special
treatment.
Concrete, Concrete in which an organic polymer serves as the
polymer binder; also known as resin concrete; sometimes
erroneously employed to designate hydraulic cement
mortars or concrete in which part or all of the mixing
water is replaced by an aqueous dispersion of a
thermoplastic copolymer.
Concrete, A mixture of water, hydraulic cement, aggregate, and a
polymer- monomer or polymer; polymerised in place when a
cement monomer is used.
Concrete, Concrete cast elsewhere than its final position.
precast
Concrete (1) Concrete that has been mixed for a short period in a
(mortar, stationary mixer before being transferred to a transit
grout), mixer. (2) grout, mortar, or concrete that has been
preshrunk mixed 1 to 3 hr before placing in order to reduce
294
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
295
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
296
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
297
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
298
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
299
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
300
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
301
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Effective width That part of the width of a slab taken into account
of slab when designing T- of L-beams.
Efflorescence A deposit of salts, usually white, formed on a surface,
the substance having emerged in solution from within
either concrete or masonry and subsequently been
precipitated by evaporation.
Elastic design A method of analysis in which the design of a member
is based on a linear stress-strain relationship and
corresponding limiting elastic properties of the
material.
Elastic limit The limit of stress beyond which the stain is not wholly
recoverable.
Elastic loss In prestressed concrete, the reduction in prestressing
load resulting from the elastic shortening of the
member.
Elasticity That property of a material by virtue of which it tends
to recover its original size and shape after deformation.
Elongation Increase in length.
Embedment The length of embedded reinforcement provided
length beyond a critical section.
Embedment- The length of embedded reinforcement which can
length develop the same stress as that which can be developed
equivalent by a hook or mechanical anchorage.
Enclosure wall A nonload-bearing wall intended only to enclose space.
Erosion Progressive disintegration of a solid by the abrasive or
cavitation action of gases, fluids, or solids in motion.
Evaporable Water in set cement paste present in capillaries or held
water by surface forces; measured as that removable by
drying under specified conditions.
Evaporation A long-chain organic material such as cetyl alcohol
retardant which when spread on a water film on the surface of
concrete retards the evaporation of bleed water.
Expanded- A metal network, often used as reinforcement in
metal lath concrete or mortar construction, formed by suitably
stamping or cutting sheet metal and stretching it to
form open meshes, usually of diamond shape.
Expansion Increase in either length or volume.
Expansion (1) A separation provided between adjoining parts of
joint structure to allow movement where expansion is likely
to exceed contraction. (2) A separation between
pavement slabs on grade, filled with a compressible
filler material. (3) An isolation joint intended to allow
independent movement adjoining parts.
Exterior panel In a flat slab, a panel having at least one edge which is
not in common with another panel.
Factored load Load, multiplied by appropriate load factors, used to
proportion members by the strength design method.
Falsework The temporary structure erected to support work in the
process of construction; composed of shoring or
vertical posting, formwork for beams and slabs, and
302
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
lateral bracing.
Fascia A flat member or band at the surface of a building or
the edge beam of a bridge; also exposed eave of a
building
Fatigue The weakening of a material caused by repeated or
alternating loads.
Fatigue failure The phenomenon of rupture of material, when
subjected to repeated ladings, at a stress substantially
less than the static strength.
Fatigue The greatest stress which can be sustained for a given
strength number of stress cycles without failure.
Faulting Differential vertical displacement of a slab or other
member adjacent to a joint or crack.
Field-cured Test cylinders that are left at the job-site for curing as
cylinders nearly as practicable in the same manner as the
concrete in the structure to indicate when supporting
forms may be removed, additional construction loads
may be imposed, or the structure may be placed in
service.
Fillet A concave junction formed where two surfaces meet.
Fin A narrow linear projection on a formed concrete
surface, resulting from mortar flowing into spaces in
the formwork; also a type of blade in a concrete mixer
drum.
Final set A degree of stiffening of a mixture of cement and water
greater than initial set, generally stated as an empirical
value indicating the time in hours and minutes required
for a cement paste to stiffen sufficiently to resist to an
established degree, the penetration of a weighted test
needle; also applicable to concrete and mortar mixture
with use of suitable test procedures.
Final setting The time required for a freshly mixed cement paste,
time mortar, or concrete to achieve final set.
Final stress In prestressed concrete, the stress which exists after
substantially all losses have occurred.
Fineness A factor obtained by adding the total percentage of
modulus material in the sample that are coarser than each of the
following sieve (cumulative percentages retained), and
dividing the sum by 100:150-µm (No.100), 300-µm
(No.50), 600-µm (No.30), 1.18mm (No.16), 2.36mm
(No.8), 4.75mm (No.4), 9.5mm (3/8-in.), 19.0mm (¾
in.), 37.5mm (1½ in.), 75mm (3 in.), 150mm (6 in.).
Finish The texture of a surface after consolidating and
finishing operations have been performed.
Finish grinding The final grinding of clinker into cement, with calcium
sulfate in the form of gypsum or anhydrite generally
being added; the final grinding operation required for a
finished concrete surface, e.g. bump cutting of
pavement, fin removal from structural concrete,
terrazzo floor grinding.
303
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
304
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
305
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
306
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
307
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
308
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
309
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
310
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
311
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
312
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
313
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
314
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
315
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Permanent Any form that remains in place after the concrete has
form developed its design strength; it may or may not
become an integral part of the structure.
Permanent set Inelastic elongation or shortening.
Permeability to The rate of discharge of water under laminar flow
water, condition through a unit cross-sectional area of a
coefficient of porous medium under a unit hydraulic gradient and
standard temperature condition, usually 20C.
Petrography The branch of petrology dealing with description and
systematic classification of rocks aside from their
geologic relations, mainly by laboratory methods,
largely chemical and microscopical; also, loosely
petrology or lithology.
Phi (Ø) factor Capacity reduction factor (in structural design); a
number less than 1.0 (usually 0.65-0.90) by which the
strength of a structural member or element (in terms of
load, moment, shear, or stress) is required to be
multiplied in order to determine design strength or
capacity; the magnitude of the factor is stipulated in
applicable codes and construction specifications for
respective types of members and cross sections.
Pigment A colouring matter, usually in the form of an insoluble
fine powder.
Pile A slender timber, concrete, or steel structural element,
driven, jetted, or otherwise embedded on end in the
ground for the purpose of supporting a load or of
compacting the soil.
Pile bent Two or more piles driven in a row transverse to the
long dimension of the structure and fastened together
by capping and (sometimes) bracing.
Pile cap (1) A structural member that is placed on top of a
group of piles and used to transmit loads from the
structure through the pile group into the soil; the piles
may be connected to the cap with reinforcement to
resist uplift or with reinforcement to resist moment so
as to form a bent; also known as a rider cap or girder;
also a masonry, timber, or concrete footing resting on a
group of piles. (2) A metal cap or helmet temporarily
fitted over the head of a precast pile to protect it during
driving; some form of shock-absorbing material is
often incorporated.
Pipe column Column made of steel pipe; often filled with concrete.
Pipe pile A steel cylinder, usually between 10 and 24 inch (250
and 600mm) in diameter, generally driven with open
ends to firm bearing and then excavated and filled with
concrete, this pile may consist of several sections from
5 to 40 feet (1.5 to 8m) long joined by special fitting
such as cast steel sleeves and is sometimes used with
its lower end closed by a conical steel shoe.
Pitting Development of relatively small cavities in a surface;
316
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
317
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
318
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
319
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
320
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
321
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
322
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
323
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
324
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
325
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
326
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
327
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
328
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
329
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
330
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
331
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
332
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
333
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
334
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
strength design
Unbonded A prestressed concrete member post-tensioned with
Member tendons that are not bonded to the concrete between the
end anchorages after stressing.
Unbonded post Post tensioning in which the tendons are not grouted
tensioning after stressing.
Unbonded A tendon that is permanently prevented from bonding
tendon to the concrete after stressing.
Unbraced Distance between lateral support.
length of
column
Undersize. Particles of aggregate passing a designated sieve.
Unit water The quantity of water per unit volume of freshly mixed
content concrete, often expressed as pounds or gallons per
cubic yard; the quantity of water on which the water-
cement ratio is based, not including water absorbed by
the aggregate.
Unsound. Not firmly made, placed or fixed, subject to
deterioration or disintegration during service exposure.
Volume Either an increase or decrease in volume due to any
change. cause.
Volume Change in volume produced by continued hydration of
change, cement, exclusive of effects of applied load and change
autogenous. in either thermal condition or moisture content.
Wall A vertical element used primarily to enclose or separate
spaces.
Warping A deviation of a slab or wall surface from its original
shape, usually caused by either temperature or moisture
differentials or both within the slab or wall.
Warping joint A joint with the sole function of permitting warping of
pavement slabs when moisture and temperature
differentials occur between the top and bottom of the
slabs. I.e. longitudinal or transverse joints with bonded
steel or tie bars passing through them.
Water cement The ratio of the amount of water, exclusive only of that
ratio absorbed by the aggregate, to the amount of a cement
in a concrete, mortar, grout , or cement paste mixture,
preferably stated as a decimal by mass and abbreviated
w/c.
Water proof Impervious to water in a either liquid or vapor state.
(Since nothing can be completely “impervious “to
water under infinite pressure over infinite time, this
term should not be used).
Water Property of a surface that resist wetting (by matter in
repellant. either liquid or vapor state) but permits passage of
water when hydrostatic pressure occurs.
Water tight. Impermeable to water except when under hydrostatic
pressure sufficient to produce structural discontinuity
by rupture.
Water void. Void along the underside of an aggregate particle or
335
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
336
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
337
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-2.1 GENERAL
The classes of concrete to be used in each part of the structure shall be
as specified or shown on the plans. If not shown or specified the
Engineer will designate the class of concrete to be used.
338
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Table 1
339
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-3 MATERIALS
30-3.1 CEMENT
Portland cements shall conform to the requirements of Section 4 of
these specifications.
30-3.2 WATER
Water for concrete shall conform to the requirement of Section 1 of
these specifications.
340
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-3.8 STEEL
Materials and installation of reinforcing and prestressing steel shall
conform to the requirements of Section 15 & 31 of these specifications.
341
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-4.1.3 APPROVAL
All mix designs, and any modifications thereto shall be approved by
the Engineer prior to use. Mix design data provided to the Engineer for
342
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
each class of concrete required shall include the name, source, type ,
and brand of each of the materials proposed for use and the quantity to
be used per cubic meter of concrete.
Table 2
When Type F or G high range water reducing admixtures are used, the
above listed slump limits may be exceeded as permitted by the
Engineer. When the consistency of the concrete is found to exceed the
nominal slump, the mixture of subsequent batches shall be adjusted to
reduce the slump to a value within the nominal range. Batches of
concrete with a slump exceeding the maximum specified shall not be
used in the work. If concrete of adequate workability cannot be
obtained by the use of the minimum cement content allowed, the
cement and water content shall be increased without exceeding the
specified water/cement ratio, or an approved admixture shall be used.
343
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
344
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
345
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-3.4.2 MIXING
30-3.4.2.1 The concrete shall be mixed only in the quantity required for
immediate use. Mixing shall be sufficient to thoroughly intermingle all
mix ingredients into a uniform mixture. Concrete that has developed an
initial set shall not be used. Retempering concrete by adding water will
not be permitted. For other than transit mixed concrete, the first batch
of concrete materials placed in the mixer shall contain a sufficient
excess of cement, sand, and water to coat the inside of the drum
without reducing the required mortar content of the mix. When mixer
performance tests, as described in AASHTO M 157, are not made, the
required mixing time for stationary mixers shall be not less than 90
seconds nor more than 5 minutes. The minimum drum revolutions for
transit mixers at the mixing speed recommended by the manufacturer
shall not be less than 70 and not less than that recommended by the
manufacturer.
30-3.4.2.2 The timing device on stationary mixers shall be equipped with a bell or
other suitable warning device adjusted to give a clearly audible signal
each time the lock is released. In case of failure of the timing device,
the Contractor will be permitted to operate while it is being repaired,
provided he furnishes an approved timepiece equipped with minute
and second hands. If the timing device is not placed in good working
order within 24 hours, further use of the mixer will be prohibited until
repairs are made.
30-3.4.2.3 For small quantities of concrete needed in emergencies or for small
noncritical elements of the work, concrete my be hand-mixed using
methods approved by the Engineer. Between uses, any mortar coating
inside of mixing equipment which sets or dries shall be cleaned from
the mixer before use is resumed.
30-3.5 DELIVERY
The organization supplying concrete shall have sufficient plant
capacity and transporting apparatus to ensure continuous delivery at
the rate required. The rate of delivery of concrete during concreting
operations shall be such as to provide for the proper handling, placing,
346
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
and finishing of the concrete. The rate shall be such that the interval
between batches shall not exceed 20 minutes and shall be sufficient to
prevent joints within a monolithic pour caused by placing fresh
concrete against concrete in which initial set has occurred. The
methods of delivering and handling the concrete shall be such as will
facilitate placing with the minimum of rehandling and without damage
to the structure or the concrete.
347
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
348
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-4.1 GENERAL
Precautions shall be taken as needed to protect concrete from damage
due to weather or other environmental conditions during placing and
curing operations. Concrete that has been frozen or otherwise damaged
by weather conditions shall be either repaired to an acceptable
condition or removed and replaced. The temperature of the concrete
mixture immediately before placement shall be between 50 F and 90 F,
except as otherwise provided herein.
349
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
detailing the methods and equipment which will be used to assure that
the required concrete temperatures are maintained. The concrete shall
be maintained at a temperature of not less than 45 F for the first six
days after placement except that when pozzolan cement or fly ash
cement is used, this period shall be as follows:
350
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
351
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
352
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
353
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-6.1 GENERAL
30-6.1.1 Concrete shall be handled, placed, and consolidated by methods that
will not cause segregation of the mix and will result in a dense
homogeneous concrete which is free of voids and rock pockets. The
methods used shall not cause displacement of reinforcing steel or other
materials to be embedded in the concrete. Concrete shall be placed and
consolidated prior to initial set and in no case more than 1 ½ hours
after cement was added to the mix. Retempering the concrete by
adding water to the mix shall not be done.
30-6.1.2 Concrete shall not be placed until the forms, all materials to be
embedded and, for spread footings the adequacy of the foundation
material have been inspected and approved by the Engineer. All mortar
from previous placements, debris, and foreign material shall be
removed from the forms and steel prior to commencing placement. The
forms and subgrade shall be thoroughly moistened with water
immediately before concrete is placed against them. Temporary form
spreader devices may be left in place until concrete placement
precludes their need, after which they shall be removed.
30-6.1.3 Placement of concrete for each section of the structure shall be done
continuously without interruption between planned construction or
expansion joints. The delivery rate, placing sequence and methods
shall be such that fresh concrete is always placed and consolidated
against previously placed concrete before initial set has occurred in the
previously placed concrete.
30-6.1.4 During and after placement of concrete, care shall be taken not to
injure the concrete or break the bond with reinforcing steel. Workmen
shall not walk in fresh concrete. Platforms for workmen and equipment
shall not be supported directly on any reinforcing steel. Once the
concrete is set, forces shall not be applied to the forms or to reinforcing
bars, which project from the concrete, until the concrete is of sufficient
strength to resist damage.
354
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-6.2.2 SUPERSTRUCTURES
30-6.2.2.1 Unless otherwise permitted, no concrete shall be placed in the
superstructure until substructure forms have been stripped sufficiently
to determine the character of the supporting substructure concrete.
30-6.2.2.2 Concrete for T_beam or deck girder spans whose depth is less than 4
feet may be placed in one continuous operation or may be placed in
two separate operations; first, to the top of the girder stems, and
second, to completion. For T-beam or deck girder spans whose depth is
4 feet or more and, unless the false work is nonyielding, such concrete
shall be placed in two operations and at least 5 days shall elapse after
placement of stems before the top deck slab is placed.
30-6.2.2.3 Concrete for box girders may be placed in two or three separate
operations consisting of bottom slab, girder stems and top slab. In
either case the bottom slab shall be placed first and, unless otherwise
permitted by the Engineer, the top slab shall not be placed until the
girder stems have been in place for at least 5 days.
30-6.2.3 ARCHES
The concrete in arch rings shall be placed in such a manner as to load
the centering uniformly and symmetrically. Arch rings shall be cast in
transverse sections of such size that each section can be cast in a
continuous operation. The arrangement of the sections and the
sequence of placing shall be as approved and shall be such as to avoid
the creation of initial stress in the reinforcement. The sections shall be
bonded together by suitable keys or dowels. Arch barrels for culverts
and unless prohibited by the special provisions, other arches may be
cast in a single continuous operation.
355
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-6.3.2 EQUIPMENT
30-6.3.2.1 All equipment used to place concrete shall be of adequate capacity and
designed and operated so as to prevent segregation of the mix or loss
of mortar. Such equipment shall not cause vibrations that might
damage the freshly placed concrete. No equipment shall have
aluminum parts which come in contact with the concrete. Between
uses, the mortar coating inside of placing equipment which sets or
dries out shall be cleaned from the equipment before use is resumed.
30-6.3.2.2 Chutes shall be lined with smooth watertight material and, when steep
slopes are involved, shall be equipped with baffles or reverses.
30-6.3.2.3 Concrete pumps shall be operated such that a continuous stream of
concrete without air pockets is produced. When pumping is completed,
the concrete remaining in the pipeline, if it is to be used, shall be
ejected in such a manner that there will be no contamination of the
concrete or separation of the ingredients.
30-6.3.2.4 Conveyor belt systems shall not exceed a total length of 550 lineal feet,
measured from end to end of the total assembly. The belt assembly
shall be so arranged that each section discharges into a vertical hopper
arrangement to the next section. To keep segregation to a minimum,
scrapers shall be situated over the hopper of each section so as to
remove mortar adhering to the belt and to deposit it into the hopper.
The discharge end of the conveyor belt system shall be equipped with a
hopper, and a chute or suitable deflectors to cause the concrete to drop
vertically to the deposit area.
30-6.4 CONSOLIDATION
30-6.4.1 All concrete, except concrete placed under water and concrete
otherwise exempt, shall be consolidated by mechanical vibration
immediately after placement. The vibration shall be internal except that
external form vibrators may be used for thin sections when the forms
have been designed for external vibration.
30-6.4.2 Vibrators shall be of approved type and design and of a size
appropriate for the work. They shall be capable of transmitting
356
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
357
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
large pours, more than one tremie or pump shall be used to ensure
compliance with this requirement.
30-6.5.2 EQUIPMENT
30-6.5.2.1 A tremie shall consist of a watertight tube having a diameter of not less
than 10 inches and fitted with a hopper at the top. The tremies shall be
supported so as to permit free movement of the discharge end over the
entire top surface of the work and so as to permit rapid lowering when
necessary to retard or stop the flow of concrete. The discharge end
shall be sealed closed at the start of work so as to prevent water from
entering the tube before the tube is filled with concrete. After
placement has started the tremie tube shall be kept full of concrete to
the bottom of the hopper. If water enters the tube after placement is
started, the tremie shall be withdrawn, the discharge end resealed, and
the placement restarted. When a batch is dumped into the hopper, the
flow of concrete shall be induced by slightly raising the discharge end,
always keeping it in the deposited concrete. The flow shall be
continuous until the work is completed. When cofferdam struts prevent
lateral movement of tremies, one tremie shall be used in each bay.
30-6.5.2.2 Concrete pumps used to place concrete under water shall include a
device at the end of the discharge tube to seal out water while the tube
is first being filled with concrete. Once the flow of concrete is started,
the end of the discharge tube shall be kept full of concrete and below
the surface of the deposited concrete until placement is completed.
30-6.5.3 CLEANUP
Dewatering may proceed after test specimens cured under similar
conditions indicate that the concrete has sufficient strength to resist the
expected loads. All laitance or other unsatisfactory materials shall be
removed from the exposed surface by scraping, chipping, or other
means which will not injure the surface of the concrete before placing
foundation concrete.
358
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
359
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-8.1 GENERAL
Construction joints shall be made only where located on plans, or
shown in the pouring schedule, unless otherwise approved. All planned
reinforcing steel shall extend uninterrupted through joints. In the case
of emergency, construction joints shall be placed as directed by the
Engineer and , if directed, additional reinforcing steel dowels shall be
placed across the joint. Such additional steel shall be furnished and
placed at the Contractor’s expense.
30-8.2 BONDING
30-8.2.1 Unless otherwise shown on the plans, horizontal joints may be made
without keys and vertical joints shall be constructed with shear keys.
Surfaces of fresh concrete at horizontal construction joints shall be
rough floated sufficiently to thoroughly consolidate the surface and
intentionally left in a roughened condition. Shear keys shall consist of
formed depressions in the surface covering approximately one-third of
the contact surface. The forms for keys shall be beveled so that
removal will not damage the concrete.
30-8.2.2 All construction joints shall be cleaned of surface laitance, curing
compound and other foreign materials before fresh concrete is placed
against the surface of the joint. Abrasive blast or other approved
methods shall be used to clean horizontal construction joints to the
extent that clean aggregate is exposed. All construction joints shall be
flushed with water and allowed to dry to a surface dry condition
immediately prior to placing concrete.
360
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
361
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-9.1 GENERAL
Expansion and contraction joints shall be constructed at the locations
and in accordance with the details shown on the plans. Such joints
include open joints, filled joints, joints sealed with sealants or
waterstops, joints reinforced with steel armor plates or shapes and
joints with combinations of these features.
30-9.2 MATERIAL
30-9.2.1 PREMOLDED EXPANSION JOINT FILLERS
Premolded fillers shall conform to one of the following specifications:
30-9.2.1.1 Specification for Preformed Expansion Joint Fillers for Concrete
Paving and structural Construction, ASTM-1751 Specification for
Preformed Sponge Rubber and Cork Expansion Joint Fillers for
Concrete Paving and Structural Construction, ASTM D-1752), Type II
(cork) shall not be used when resiliency is required.
30-9.2.1.2 Specification for Preformed Expansion Joint Filler for Concrete,
ASTM D- 994.
362
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
suitable for retaining the liquid sealant at the proper elevation in the
joint while hardening.
30-9.2.6 WATERSTOPS
Waterstops shall be of the type, size and shape shown on the plans.
They shall be dense, homogeneous, and without holes or other defects.
363
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-9.3 INSTALLATION
30-9.3.1 OPEN JOINTS
Open joints shall be constructed by the insertion and subsequent
removal of a wood strip, metal plate or other approved material. The
insertion and removal of the template shall be accomplished without
chipping or breaking the corners of the concrete. When not protected
by metal armor, open joints in decks and sidewalks shall be finished
with an edging tool. Upon completion of concrete finishing work, all
mortar and other debris shall be removed from open joints.
364
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
the sealant and isolate it from the filler material. The sealant materials
shall then be mixed and installed in accordance with the
manufacturer’s directions. Any material that fails to bond to the sides
of the joint within 24 hours after placement shall be removed and
replaced.
30-9.3.4 WATERSTOPS
Adequate waterstops of metal, rubber, or plastic shall be placed as
shown on the plans. Where movement at the joint is provided for,
waterstops shall be of a type permitting such movement without injury.
They shall be spliced welded, or soldered, to form continuous
watertight joints. Precautions shall be taken so that the waterstops shall
be neither displaced nor damaged by construction operations or other
means. All surfaces of the waterstops shall be kept free from oil,
grease, dried mortar, or any other foreign matter while the waterstop is
being embedded in concrete. Means shall be used to insure that all
portions of the waterstop designed for embedment shall be tightly
enclosed by dense concrete.
365
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-10.1 GENERAL
Unless otherwise specified, after concrete has been consolidated and
prior to the application of cure, all surfaces of concrete which are not
placed against forms shall be struck off to the planned elevation or
slope and the surface finished by floating with a wooden float
sufficiently to seal the surface. While the concrete is still in a workable
state, all construction and expansion joints shall be carefully tooled
with an edger. Joint filler shall be left exposed.
366
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-10.2.3 TEXTURING
The surface shall be given a skid-resistant texture by either burlap or
carpet dragging, brooming, tining, or by a combination of these
methods. The method employed shall be as specified or as approved by
the Engineer. Surfaces that are to be covered with a waterproofing
membrane deck seal shall not be coarse textured. They shall be
finished to a smooth surface free of mortar ridges and other
projections. This operation shall be done after floating and at such time
367
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
and in such manner that the desired texture will be achieved while
minimizing displacement of the larger aggregate particles.
30-10.2.3.1 Dragged
If the surface texture is to be a drag finish, the surface shall be finished
by dragging a seamless strip of damp burlap over the full width of the
surface. The burlap drag shall consist of sufficient layers of burlap and
have sufficient length in contact with the concrete to slightly groove
the surface and shall be moved forward with a minimum bow of the
lead edge. The drag shall be kept damp, clean, and free of particles of
hardened concrete. As an alternative to burlap, the Engineer may
approve or direct that carpet or artificial turf of approved type and size
be substituted.
30-10.2.3.2 Broomed
If the surface texture is to be a broom finish, the surface shall be
broomed when the concrete has hardened sufficiently. The broom shall
be of an approved type. The strokes shall be square across the slab,
from edge to edge, with adjacent strokes slightly overlapped, and shall
be made by drawing the broom without tearing the concrete, but so as
to produce regular corrugations not over 1/8 of an inch in depth. The
surface as thus finished shall be free from porous spots, irregularities,
depressions, and small pockets or rough spots such as may be caused
by the accidental disturbing of particles of coarse aggregate embedded
near the surface during the final brooming operation.
30-10.2.3.3 Tined
If the surface is to be tined, the tining shall be in a transverse direction
using a wire broom, comb or finned float having a single row of tines
or fins. The tining grooves shall be between 1/16 inch and 3/16 inch
wide and between 1/8 inch and 3/16 inch deep, spaced ½ to ¾ inch on
centers. Tining shall be discontinued 12 inches from the curb line on
bridge decks. The area adjacent to the curbs shall be given a light
broom finish longitudinally. As an alternative, tining may be achieved
using an approved machine designed specifically for tining or grooving
concrete pavements.
368
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
369
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-11.1 GENERAL
30-11.1.1 All newly placed concrete shall be cured so as to prevent loss of water
by use of one or more of the methods specified herein. Curing shall
commence immediately after the free water has left the surface and
finishing operations are completed. If the surface of the concrete
begins to dry before the selected cure method can be applied, the
surface of the concrete shall be kept moist by a fog spray applied so as
not to damage the surface.
30-11.1.2 Curing by other than steam or radiant heat methods shall continue
uninterrupted for 7 days except that when pozzolans in excess of 10%
by weight, of the Portland cement are used in the mix. When such
pozzolans are used, the curing period shall be 10 days. For other than
top slabs of structures serving as finished pavements, the above curing
periods may be reduced and curing terminated when test cylinders
cured under the same conditions, as the structure indicate that concrete
strengths of at least 70% of that specified have been reached.
30-11.1.3 When deemed necessary by the Engineer during periods of hot
weather, water shall be applied to concrete surfaces being cured by the
liquid membrane method or by the forms-in-place method, until the
Engineer determines that a cooling effect is no longer required. Such
application of water will be paid for as extra work.
30-11.2 MATERIALS
30-11.2.1 WATER
Water shall conform to Section 30-3.2 of these specifications.
30-11.3 METHODS
30-11.3.1 FORMS-IN-PLACE METHOD
Formed surfaces of concrete may be cured by retaining the forms in
place without loosening for the required time.
370
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
371
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
372
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-12.1 GENERAL
30-12.1.1 Surface finishes for formed concrete surfaces shall be classified as
follows:
Class 1 Ordinary Surface Finish
Class 2 Rubbed Finish
Class 3 Tooled Finish
Class 4 Sandblast Finish
Class 5 Wire Brush, or Scrubbed Finish
30-12.1.2 All concrete shall be given a class 1, Ordinary Surface Finish, and in
addition if further finishing is required, such other type of finish as is
specified.
30-12.1.3 If not otherwise specified, exposed surfaces except the soffits of
superstructures and the interior faces and bottoms of concrete girders
shall also be given a class 2, Rubbed Finish.
30-12.1.4 Class 3, 4, or 5 type surface finishes shall be applied only where shown
on the plans or specified.
373
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-12.2.4 The resulting surfaces shall be true and uniform. Repaired surfaces the
appearance of which is not satisfactory, shall be “rubbed” as specified
under Class 2, Rubbed Finish.
374
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
375
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-13.1 GENERAL
30-13.1.1 Precast concrete members shall be constructed and placed in the work
in conformance with the details shown on the plans, specified or shown
on the approved working drawings.
30-13.1.2 If approved by the Engineer, the use of precasting methods may be
used for elements of the work which are otherwise indicated to be
constructed by the cast-in-place method. When such precasting is
proposed, the Contractor shall submit working drawings showing
construction joint details and any other information required by the
Engineer.
376
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-13.4 CURING
Unless otherwise permitted, precast members shall be cured by either
the water method or the steam or radiant heat method.
377
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-13.6 ERECTION
30-13.6.1 The Contractor shall be responsible for the safety of precast members
during all stages of construction. Lifting devices shall be used in a
manner that does not cause damaging bending or torsional force. After
a member has been erected and until it is secured to the structure,
temporary braces shall be provided as necessary to resist wind or other
loads.
30-13.6.2 Precast deck form panels shall be erected and placed so that the fit of
mating surfaces shall be such that excessive grout leakage will not
occur. If such fit is not provided, joints shall be dry-packed or sealed
with an acceptable caulking compound prior to placing the cast-in-
place concrete. End panels for skewed structures may be sawed to fit
the skew.
378
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-14.1 GENERAL
All coping landing, steps, slabs, ashlar, cobber stone, kerb stone and
other similar things specified or shown on the drawings to be moulded
concrete shall consist of well-graded aggregate. The proportions of
Portland cement shall be as specified. Concrete shall be cast in strongly
proportioned moulds fitted with all requisites for the formation of
chamfers, radii, V-grooves, recesses, lewis holes, etc, to produce
blocks perfect in shape, true to dimensions, having smooth and true
faces and clearly defined chamfers, radii and sharp arises on all
exposed edges.
30-14.2 MOULDING
Concrete shall be deposited slowly in layers, and shall be thoroughly
worked in and packed so as to dispel all air and fill the moulds
perfectly. The moulds shall not be slackened off or removed till a
period of 36 hours has elapsed since the blocks were made.
Immediately after the removal of moulds, the back and side joints of
the blocks against which concrete-in-mass or mortar will abut shall be
thoroughly roughened whilst the concrete is still green. No plastering
of any exposed face or surface shall be allowed. All moulded concrete
shall be kept continuously watered for a period of at least 28 days after
the moulding.
379
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
380
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
381
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-15.1 GENERAL
This work consists of the making and placing of mortar and grout for
use in concrete structures other than in prestressing ducts. Such uses
include mortar for filling under masonry plates and for filling keyways
between precast members where shown on the plans, mortar used to
fill voids and repair surface defects, grout used to fill sleeves for
anchor bolts, and mortar and grout for other such uses where required
or approved.
382
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
383
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-16.1 GENERAL
Loads shall not be applied to concrete structures until the concrete has
attained sufficient strength and, when applicable, sufficient
prestressing has been completed, so that damage will not occur.
384
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
30-17.1 MEASUREMENT
30-17.1.1 Except for concrete in components of the work for which payment is
made under other bid items, all concrete for structures will be
measured by ether the cubic foot or cubic meter for each class of
concrete included in the schedule of bid items or by the unit for each
type of precast concrete member listed in the schedule of bid items.
30-17.1.1.1 When measured by the cubic foot or cubic meter, the quantity of
concrete will be computed from the dimensions shown on the plans or
authorized in writing by the Engineer with the following exceptions.
30-17.1.1.2 The quantity of concrete involved in fillets, scorings and chamfers I
square inch or less in cross-sectional area will not be included or
deducted. Deductions for embedded materials as reinforcing, structural
and prestressing steel, expansion joint filter material, waterstops and
deck drains will not be made.
30-17.1.1.3 When there is a bid item for concrete to be used as a seal course in
cofferdams, the quantity of such concrete to be paid for shall include
the actual volume of concrete seal course in place, but in no case shall
the total volume to be paid for exceed the cubical contents contained
between the vertical surfaces 1 foot outside the neat lines of the seal
course as shown on the plans. The thickness of seal course to be paid
or shall be thickness shown on the plans or ordered in writing by the
Engineer.
30-17.1.2 The number of precast concrete members of each type listed in the
schedule of bid items will be the number of acceptable members of
each type furnished and installed in the work.
30-17.1.2.1 Whenever an alternative or option is shown on the plans or permitted
by the specifications, the quantities of concrete will be computed on
the basis of the dimensions shown on the plans and no change in
quantities measured for payment will be made because of the use by
the Contractor of such alternatives or options.
30-17.1.3 The number of moulded concrete articles of each type listed in the bid
items will be number of acceptable numbers of each type furnished.
30-17.2 RATE
The unit rates for various types of Portland cement concrete listed in
table 1 (page 339) shall be full compensation for all the work specified
in this section including testing of concrete and shall also include all
forms, false work, weep holes, drain setting anchor bolts and dowels,
surface finish and cleaning up as shown on the drawings or ordered by
the Engineer-in-charge.
385
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–31
REINFORCING STEEL
31-1.1 DESCRIPTION
This work shall consist of furnishing and placing reinforcing steel in
accordance with these Specifications and in conformity with the plans.
31-1.2 MATERIALS
Reinforcing plain or deformed billet steel bars of specified grade shall
conform to Section 15 of these specifications.
31-1.4 FABRICATION
31-1.4.1 BENDING
Bar reinforcement shall be cut and bent to the shapes shown on the
plans. All bars shall be bent cold, unless otherwise permitted. Bars
partially embedded in concrete shall not be field bent except as shown
on the plans or specifically permitted.
386
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
387
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
31-1.8 SUBSTITUTIONS
Substitution of different size reinforcing bars will be permitted only
when authorized by the Engineer. The substituted bars shall have an
area equivalent to the design area, or larger.
31-1.9 MEASUREMENTS
Steel reinforcement incorporated in the concrete will be measured in
pounds / Kg on the total computed weight for the sizes and lengths of
bars. The weight of bars will be computed using the following weights.
Weight lbs. per lin
Bar Size
feet
No.3 0.376
No.4 0.668
No.5 1.043
No.6 1.502
No.7 2.044
No.8 2.670
No.9 3.400
No.10 4.303
No.11 5.313
No.14 7.65
No.18 13.60
388
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
No allowance will be made for clips, wire, separators, wire chairs, and
other material used in fastening the reinforcement in place, If bars are
substituted upon the Contractor’s request and as a result more
reinforcing steel is used than specified, only the amount specified will
be included. The additional reinforcing steel required for splices that
are not shown on the plans but are authorized as provided herein, will
not be included.
31-1.10 RATE
The unit rate for the quantity of reinforcement determined under
measurement for each class of reinforcing steel shown in the bid
schedule will be made at the contract price per pound / Kg.
Reinforcement steel to be full compensation for furnishing, fabricating,
splicing, and placing of the reinforcing steel including all incidental
work and materials required as per above specifications specially
included in the contract.
389
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–32
BRICKWORK
32-1 GENERAL
32-1.1 DESCRIPTION
Unless otherwise specified, all brickwork shall be finished in a
workmanlike manner, true to dimensions and grades shown on the
drawings to the following specification.
32-1.2 GLOSSARY
Frog Indentation formed on the bedding surface of a
brick manufactured by moulding or pressing.
The indentation may be shallow (not exceeding
3/8" (9.5mm). The frog face is to be kept
upward in brickwork.
Course Row of bricks between tow consecutive bed
joints. Its thickness is taken as one brick plus
one mortar joint.
Bed Joints Joints normal to the pressure.
Quoins External corners of walls. The term is
sometimes used for bricks or stones which
from the quoins e.g. quoin brick, quoin stone.
Prepends Vertical joints of the face of the wall. In plain
walling it is necessary for good bond that these
joints should, in alternate coursed, be vertically
one above the other.
Stretchers Bricks laid with their lengths on the face of
wall or parallel to the face of wall.
Headers Bricks laid with their widths on the face of wall
or parallel to the face of wall.
Bats Pieces of bricks and are usually known as ½ or
¾ bat according to the fraction of a whole
brick.
Lap Horizontal distance between the vertical joints
in two consecutive. Queen Closers Bricks made
with the same length and thickness but with
half the width of a brick. They are usually
placed next to the quoin header to obtain the
lap. They are usually made economically by
cutting the broken bricks.
King Closer Bricks which are cut in such a way that one end
is half the width of the brick. They are used in
390
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
391
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
course.
Coping Covering course of brickwork at the lightest to
form the water-proof top for preventing the
interior of the wall from wetting. Copings are
commonly throated.
Drip Course Drip course throws off water clear of walls. It
has a throated under surface and is usually done
over arches, doors and window sills and
parapets.
String Courses Horizontal projections of brickwork often
constructed below windows.
Flush joint Joint formed by slicing surplus surface mortar
on the face of brickwork.
Raked joint Joint formed by raking the mortar about ¼ inch
or 3/8 inch so that the joint is in shade. It is
effective when the perpends are flush.
Weathered joint Joint formed by drawing the point of trowel at
a slight angle along the course. It is the best
joint for reducing the ingress of water.
Mason’s V joint Where it is desired to produce the even looking
joints, mason’s V joint is formed.
32-1.3 CLASSIFICATION
Unless otherwise specified, brickwork shall be of the following 2
classes.
(a) Brickwork 1st Class
(b) Brickwork 2nd Class
32-1.4 MATERIALS
32-1.4.1 BRICKS
Bricks shall conform to Section 6-1 of the specifications for Clay
Bricks, unless otherwise specified. No bats shall be used, except where
absolutely necessary for obtaining the dimensions of different courses
or the specified bond.
32-1.4.2 MORTAR
Mortar shall be contained in bill of quantities. It shall be prepared in
accordance with he relevant provisions set forth in Section 16 of these
specifications for the specified Mortar.
32-1.4.3 WATER
Water in brickwork shall conform to Section 1 of these specifications.
392
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-1.5 TOOLS
All equipment used for mixing mortar, transporting it and for laying
bricks shall be clean and free from set mortar, dirt, or other injurious
foreign substances. It shall be thoroughly cleaned at the end of each
day’s work.
32-1.7 BOND
Unless otherwise specified, all brickwork shall be laid in English Bond
with facing frogs upwards.
32-1.9 JOINTS
Horizontal joints shall be parallel and truly level, vertical joints in
alternate course shall come directly over one another. Thickness of
joints, unless otherwise specified, shall not be less than ¼ of an inch
and shall not be more than 3/8 of an inch. The height of 4 courses and
3 joints as laid shall not exceed more than 1 inch the height of 4 bricks
as piled dry one upon the other.
32-1.10 CORNER
At all corners alternate courses of bricks shall be laid header-wise and
stretcher-wise so as to bond the two walls well together.
393
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-1.18 FIXTURES
Holdfasts and similar fixtures shall be built in with the surrounding
brickwork in their correct position in specified mortar. They shall be
394
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
built in as the work progresses and not inserted later on into space left
for them.
32-1.19 PROGRESS
Brickwork shall be carried up in a uniform manner. No portion shall be
raised more than 3 feet above another at the same time. Temporary
spaces left during construction shall be racked and not toothed.
Straight edges supplied to bricklayers shall have courses marked on
them with saw cut or measuring rod shall be provided and the height of
course shall be checked all over the building from time to time so as to
keep all courses level.
395
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
contractor shall use metal mortar board equipped with oil torches. No
anti-freez liquid, salt or other substance shall be used in mortar, except
when specified or permitted by the Engineer-in-charge.
32-1.21.7 ENCLOSURES AND ARTIFICIAL HEAT
All work under construction shall be protected from freezing for a
period of 48 hours by means of enclosures, artificial heat or by other
suitable methods duly approved by the Engineer-in-charge.
32-1.22 OPENING
Door and window openings shall have flat or relieving arches or lintels
spanning across them as shown on the drawing or as specified.
32-1.23 CENTRING
Centrings for all openings shall be strong enough to support the lintels
or arches spanning the openings and shall remain in position till the
brickwork has set. No additional payment will be made to the
contractor for this item of work.
32-1.24 SCAFFOLDING
The contractor shall provide all scaffolding, staging, ladders, etc.
necessary for the work. All walls or other brickwork shall be securely
braced and protected against damages by wind and storms during the
construction period. No extra rate shall be paid for this item.
32-1.25 PUTLOGS
Only headers shall be left out to allow a putlog to be inserted and not
more than one brick shall be left out for each putlog. Under no
circumstances shall putlogs be made immediately under or next to the
impost or skew back of arches.
32-1.27 MEASUREMENT
Brickwork shall be measured by volume. The unit of measurement
shall be 100 cubic feet. No deduction shall be made for openings
having a superficial area of one square foot or less.
396
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-1.28 RATE
32-1.28.1 LABOUR RATE
The unit rate (on labour rate basis) for brickwork shall include cost of
carrying out brickwork, cutting bricks wherever required, curing and
protecting as per above specifications specially included in the
contract. It shall further include the cost of providing, using and
removing scaffolding, shuttering, centering, staging, ladders, supports
and other tools and plants required for carrying out brickwork as per
above specifications.
32-1.28.2 COMPOSITE RATE
The unit rate shall include the cost of bricks, mortar and any other
material required, in addition to the labour rate detailed in Section
32-1.28.1.
397
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-2.1 DESCRIPTION
The brickwork shall be executed in accordance with section 32-1 of
these specifications using the specified mortar.
32-2.2 MATERIALS
32-2.2.1 BRICKS
Bricks shall conform to section 6-3.1 of these specifications. Their size
shall be as specified.
32-2.2.2 MORTAR
Mortars shall conform to Section 16-2 of these specifications as
specified.
32-2.4 MEASUREMENT
Brickwork shall be measured by volume. The unit of measurement
shall be 100 cubic feet. No deduction shall be made for openings
having a superficial area of one square foot or less.
32-2.5 RATE
32-2.5.1 LABOUR RATE
The unit rate (on labour rate basis) for brickwork shall include cost of
carrying out brickwork, cutting bricks wherever required, curing and
protecting as per above specifications specially included in the
contract. It shall further include the cost of providing, using and
removing scaffolding, shuttering, centering, staging, ladders, supports
and other tools and plants required for carrying out brickwork as per
above specifications.
32-2.5.2 COMPOSITE RATE
The unit rate shall include the cost of bricks, mortar and any other
material required, in addition to the labour rate detailed in Section
32-2.5.1.
398
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-3.1 DESCRIPTION
The work covers brickwork 2nd class in accordance with Section 32-1
of these specifications using the specified mortar.
32-3.2 MATERIALS
32-3.2.1 BRICKS
Bricks shall conform to section 6-3 of these specifications. Their size
shall be as specified.
32-3.2.2 MORTAR
It shall conform to section 16 of these specifications as specified.
32-3.4 MEASUREMENT
Brickwork shall be measured by volume. The unit of measurement
shall be 100 cubic feet. No deduction shall be made for openings
having a superficial area of one square foot or less.
32-3.5 RATE
32-2.5.3 LABOUR RATE
The unit rate (on labour rate basis) for brickwork shall include cost of
carrying out brickwork, cutting bricks wherever required, curing and
protecting as per above specifications specially included in the
contract. It shall further include the cost of providing, using and
removing scaffolding, shuttering, centering, staging, ladders, supports
and other tools and plants required for carrying out brickwork as per
above specifications.
32-2.5.4 COMPOSITE RATE
The unit rate shall include the cost of bricks, mortar and any other
material required, in addition to the labour rate detailed in Section
32-3.5.1.
399
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-4.1 DESCRIPTION
The work covers brickwork in Arches.
32-4.2 MATERIAL
32-4.2.1 BRICKS
1st class bricks shall conform to section 6-3 of these specifications.
32-4.2.2 MORTAR
Mortar composition as mentioned in BOQ shall conform to Section 16
of these specification.
32-4.3 CENTERING
Centering shall be strong enough to bear the weight of an arch without
any deflection. The surface of centering shall be correctly struck to the
curvature of the soffit of the arch.
400
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
401
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-4.9 MEASUREMENT
It shall be measured by volume. The unit of measurement shall be 100
cubic feet. No deduction shall be made for openings having a
superficial area of one square foot or less.
32-4.10 RATE
32-4.10.1 LABOUR RATE
The unit rate (on labour rate basis) for brickwork in arches shall
include cost of carrying out brickwork, cutting bricks wherever
required, curing and protecting as per above specifications specially
included in the contract. It shall further include the cost of providing,
using and removing scaffolding, shuttering, centering, staging, ladders,
supports and other tools and plants required for carrying out brickwork
as per above specifications.
32-4.10.2 COMPOSITE RATE
The unit rate shall include the cost of bricks, mortar and any other
material required, in addition to the labour rate detailed in Section
32-4.10.1.
402
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-5 CORBELLING
32-5.1 DESCRIPTION
Unless otherwise specified or directed by the Engineer-in-charge,
corbelling shall be affected by 1/4th brick projection in ordinary work
and 1/8th brick projection in a work where greater strength is required.
32-5.3 MEASUREMENT
It shall be measured by volume. The unit of measurement shall be 100
cubic feet. No deduction shall be made for openings having a
superficial area of one square foot or less.
32-5.4 RATE
32-5.4.1 LABOUR RATE
The unit rate (on labour rate basis) for corbelling shall include cost of
carrying, cutting wherever required, curing and protecting as per above
specifications specially included in the contract. It shall further include
the cost of providing, using and removing scaffolding, shuttering,
centering, staging, ladders, supports and other tools and plants required
for carrying out brickwork as per above specifications.
32-5.4.2 COMPOSITE RATE
The unit rate shall include the cost of corbelling, mortar and any other
material required, in addition to the labour rate detailed in Section
32-5.4.1.
403
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-6 COPING
32-6.1 DESCRIPTION
Unless otherwise specified, the top courses of all plinths, parapets,
steps, etc., shall be built in brick on edge. In case of parapet walls the
outside half of the brick shall be weathered and throated. The corners
shall be made by cutting fine bricks or by special bricks of 9" x 9" x 4-
3/8" size to give a radiated and keyed joint.
32-6.3 MEASUREMENT
It shall be measured by volume. The unit of measurement shall be 100
cubic feet. No deduction shall be made for openings having a
superficial area of one square foot or less.
32-6.4 RATE
32-6.4.1 LABOUR RATE
The unit rate (on labour rate basis) for coping shall include cost of
carrying, cutting wherever required, curing and protecting as per above
specifications specially included in the contract. It shall further include
the cost of providing, using and removing scaffolding, shuttering,
centering, staging, ladders, supports and other tools and plants required
for carrying out brickwork as per above specifications.
32-6.4.2 COMPOSITE RATE
The unit rate shall include the cost of coping, mortar and any other
material required, in addition to the labour rate detailed in Section
32-6.4.1.
404
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-7.1 DESCRIPTION
Unless otherwise specified, window sills shall be made by laying brick
on edge over 1½ inch tile creasing to keep the joints in line. The bricks
shall project 3 inches from the face of the wall and shall be weathered
on the upper edge and throated underneath up to 3 inches from either
end.
32-7.3 MEASUREMENT
It shall be measured by volume. The unit of measurement shall be 100
cubic feet. No deduction shall be made for openings having a
superficial area of one square foot or less.
32-7.4 RATE
32-7.4.1 LABOUR RATE
The unit rate (on labour rate basis) for window sill shall include cost of
carrying, cutting wherever required, curing and protecting as per above
specifications specially included in the contract. It shall further include
the cost of providing, using and removing scaffolding, shuttering,
centering, staging, ladders, supports and other tools and plants required
for carrying out brickwork as per above specifications.
32-7.4.2 COMPOSITE RATE
The unit rate shall include the cost of window sills, mortar and any
other material required, in addition to the labour rate detailed in
Section 32-7.4.1.
405
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-8 CORNICES
32-8.1 DESCRIPTION
Unless otherwise specified or directed by the Engineer-in-charge, all
cornices shall be in line with the straight and parallel faces. All
exposed cornices shall be weathered and rendered on top in specified
mortar and throated underneath. The profile shall be checked
constantly with the sheet iron templates. Cornices intended to be
pointed shall be made with specially moulded bricks or bricks cut and
rubbed so as to give mouldings true to drawings. In cornices to be
plastered the bricks shall be roughly cut so as to allow the plaster to
finish true to drawings and templates. Thickness of plaster shall not be
less than half an inch and more than one inch.
32-8.3 MEASUREMENT
The measurement of cornice shall be done by length. The unit of
measurement shall be one running foot.
32-8.4 RATE
32-8.4.1 LABOUR RATE
The unit rate (on labour rate basis) for cornices shall include cost of
carrying, cutting wherever required, curing and protecting as per above
specifications specially included in the contract. It shall further include
the cost of providing, using and removing scaffolding, shuttering,
centering, staging, ladders, supports and other tools and plants required
for carrying out brickwork as per above specifications.
32-8.4.2 COMPOSITE RATE
The unit rate shall include the cost of cornices, mortar and any other
material required, in addition to the labour rate detailed in Section
32-8.4.1.
406
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-9.1 DESCRIPTION
String courses shall comprise bricks laid on edge or flat in one or two
courses as actually specified.
32-9.3 MEASUREMENT
It shall be measured by volume. The unit of measurement shall be 100
cubic feet. No deduction shall be made for openings having a
superficial area of one square foot or less.
32-9.4 RATE
32-9.4.1 LABOUR RATE
The unit rate (on labour rate basis) for string courses shall include cost
of carrying, cutting wherever required, curing and protecting as per
above specifications specially included in the contract. It shall further
include the cost of providing, using and removing scaffolding,
shuttering, centering, staging, ladders, supports and other tools and
plants required for carrying out brickwork as per above specifications.
32-9.4.2 COMPOSITE RATE
The unit rate shall include the cost of string courses, mortar and any
other material required, in addition to the labour rate detailed in
Section 32-9.4.1.
407
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-10.1 DESCRIPTION
Eave bricks shall be laid flat or on edge as specified with a projection
of 3 inches and chamfered 1½ inch on the upper edge.
32-10.3 MEASUREMENT
Eave brickwork shall be measured by length. The unit of measurement
shall be one running foot.
32-10.4 RATE
32-10.4.1 LABOUR RATE
The unit rate (on labour rate basis) for eave brickwork shall include
cost of carrying, cutting wherever required, curing and protecting as
per above specifications specially included in the contract. It shall
further include the cost of providing, using and removing scaffolding,
shuttering, centering, staging, ladders, supports and other tools and
plants required for carrying out brickwork as per above specifications.
32-10.4.2 COMPOSITE RATE
The unit rate shall include the cost of eave brickwork, mortar and any
other material required, in addition to the labour rate detailed in
Section 32-10.4.1.
408
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-11.1 DESCRIPTION
Brickwork in drip courses when made of flat bricks, shall conform to
Section 32-10 of these specifications for Eave Brickwork and
measured at the same rate. When built in brick on edge it shall conform
to Section 32-7 of these specifications for Window Sills and measured
and paid at the same rate.
409
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-12.1 DESCRIPTION
Bricks shall be laid flat or on edge as shown on drawings or as
specified. Each brick shall be set on a layer of at least ¼ inch mortar
with vertical joints filled with mortar and bedded in by tapping with
the handle of the trowel. The width of reimbursement shall be 9 inches
and shall be constructed on sides of the roads sloping towards the
drain; the slope shall be 1/8 of an inch in 9 inches. Cut and dressed
bricks shall be laid in imbursements for laying narrow strips in width
along sides of drain, for all curves, bends, slopes, change of slopes and
irregular areas. No extra amount shall be paid for any difficulty or
complicated items required during execution.
32-12.2 JOINTS
The thickness of the joint shall not be less than ¼ of an inch and not
more than 3/8 of an inch. All joints between bricks and along outer end
and inner side of reimbursement shall be completely filled with mortar
and struck.
32-12.3 BASE
The base concrete shall be of specified thickness.
32-12.4 STRIKE
All strips, sides and narrow width areas shall be filled with bricks on
edge or flat.
32-12.6 MEASUREMENT
The brickwork in reimbursement shall be measured by length. The unit
of measurement shall be one running foot.
410
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-12.7 RATE
32-12.7.1 LABOUR RATE
The unit rate (on labour rate basis) for eave brickwork shall include
cost of carrying, cutting wherever required, curing and protecting as
per above specifications specially included in the contract. It shall
further include the cost of providing, using and removing scaffolding,
shuttering, centering, staging, ladders, supports and other tools and
plants required for carrying out brickwork as per above specifications.
32-12.7.2 COMPOSITE RATE
The unit rate shall include the cost of brickwork in reimbursement,
mortar and any other material required, in addition to the labour rate
detailed in Section 32-12.7.1.
411
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
32-13.1 DESCRIPTION
Bricks shall be laid on end, 3 inches or 4½ inches in thickness as
specified on a bed not less than ¼ of an inch and not more than 3/8 of
an inch thick. All external surface joints shall be struck.
32-13.2 BASE
The base concrete shall be of specified thickness.
32-13.4 MEASUREMENT
It shall be measured by volume. The unit of measurement shall be 100
cubic feet. No deduction shall be made for openings having a
superficial area of one square foot or less.
32-13.5 RATE
32-13.5.1 LABOUR RATE
The unit rate (on labour rate basis) for brickwork in tega shall include
cost of carrying out brickwork, cutting bricks wherever required,
curing and protecting as per above specifications specially included in
the contract. It shall further include the cost of providing, using and
removing scaffolding, shuttering, centering, staging, ladders, supports
and other tools and plants required for carrying out brickwork as per
above specifications.
32-13.5.2 COMPOSITE RATE
The unit rate shall include the cost of bricks, mortar and any other
material required, in addition to the labour rate detailed in Section
32-13.5.1.
412
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–33
STONE
33-1.1 DESCRIPTION
This work shall consist of all stone masonry carrying out work in
accordance with these specifications to dimensions and grades shown
on the drawings.
33-1.2 GLOSSARY
Surface Finishes
Angle Tooled/ Stone dressed so that the tool marks run
Angle Droved diagonally across the face.
Axed A patent axe or a bush hammer having a surface
obtained by using an axe. A surface is said to be
‘fine axed’ when it had been chopped with fine
axe marks. ‘Once-axed is the term used for
rough chopping of a surface with an axe.
Batted (Broad A surface having been obtained by using a
Tooled) batting tool in parallel strokes, each traversing
the full depth of the stone face. The strokes may
be vertical, when it is often referred to as
tooling or oblique at an angle of 45o to 60o. The
result is a regular pattern of fluted cuts in the
stone face. The number of strokes per inch may
very from 8 to 10
Blocking cut Roughly shaping a slab or stone.
Boasted/Droved A stone finished by dressing with boaster.
Boasted for Reduced by rough dressing, usually with a point
Carving tool, approximately the form required by a
sculptor.
Broached (Droved) Worked with a point to show diagonal or
horizontal furrows.
Cloured Hacked or hammer dressed.
Drafted Margin A tooled margin, ¾ of an inch to 2 inches wide
worked on the face of a rough squared stone.
Having a rough face prepared with a hammer.
Hammer Dressed/
Bull Faced
A stone cut with the laminae running vertically
Joint Bedded
and parallel to the joints.
413
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
414
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
415
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
416
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
417
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
the wall.
Corbel A stone or series of stones which project from a
wall and often used as a support.
Corbel Step Crow step in a stepped gable.
Crow step The stone from which steps are formed in a
stepped gable of a wall.
Dressings A general term used for all masonry.
Drum One of the stone composing the shaft of a
column.
Edge Bedded/Joint A stone cut with the laminae running vertically
Bedded rather than horizontally. (Note Edge bedding is
used in the cutting of voussoirs with a view to
distributing strain around the arch and so
helping to avoid breakage and exfoliation when
the stone is submitted to the action of time and
atmosphere.)
Header A stone laid so that its greatest dimension in
the thickness of the wall.
Hearting The infilling which forms the core of a rubble
wall.
Impost The top member of a pier or pillar from which
an arch springs.
Inban/Inband A quoin or jamb stone short on main wall face
and long (for bonding) in return or reveal, c.f.
outban or outband.
Inband Rybat Header stone in a jamb of an opening.
Inbond Header on a reveal or return.
Indenting The omission of stones to from recesses into
which future work can be bonded.
Jamb Stone One of the number of stones forming part of
the vertical surface at the sides of a door or
window opening.
Joggle (1) A projection on one stone to fit into a
corresponding recess in another stone. (2)
Adjacent recesses for filling with cement grout
or mortar.
Kerb/Curb Stone A stone used as an edging (See ‘curb Stone’).
Keystone The central stone of an arch.
Kilt Slight weathering commonly given to stone
steps in the setting.
Kneeler A stone bonded into the wall and forming an
intermediate length of the coping to a gable
end.
Linings Thin slabs of stone or other material used
internally as a non-load-bearing covering.
Lintel (head) A stone which spans, in one piece, the top of an
aperture.
Long Stone/Saving A relieving arch over a lintel.
Mason’s Mitre A mitre worked out of a single piece of stone
and not forming a joint at the mitred angle as in
a joiner’s mitre.
418
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
419
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Walling
Ashlar Masonry consisting of plain blocks of stone,
finely dressed to given dimensions and laid in
their courses.
Block in Course Roughly squared block of stone which may
very in length having worked beds and hammer
dressed face and joints and set in course which
may very in height not exceeding 12 inches.
(Note –Used in heavy engineering masonry).
Brought to Courses Walling, similar to un-coursed rubble, which is
roughly leveled up to courses at intervals and
varies in height according to the locality and
420
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
421
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-1.3 MATERIAL
33-1.3.1 STONE
Stone shall be produced from an approved source and shall conform to
Section 11-1 for stone. Approved sample of the stone shall be retained
as a standard of martial to be furnished at the site of work. All stone
used in the work shall be equal in all respects to the approved samples.
33-1.3.2 MORTAR
33-1.3.2.1 Composition
Mortar shall be used as specified in bill of quantities.
33-1.3.2.2 Preparation
It shall be prepared in accordance with the relevant provisions set forth
in Section 16-2 & 16-3 of these specifications for the specified mortar.
33-1.3.2.3 Water
Water shall conform to Section 1 of these specifications.
422
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
(c) Each stone shall be set with both bed and vertical joints filled
with mortar, except in case of dry stone pitching or masonry
and thoroughly bedded in.
(d) All masonry shall be taken up in truly plumb or at Specified
slope in the case if batter.
(e) Quoins and jambs shall be laid at a true right angle to the bed
corners being straight and vertical. In the case of masonry with
hammer dressed stone a chisel draft one-inch wide shall be
given in each external face to allow accurate plumbing. Quoins
shall be laid using headers and stretchers alternately.
(f) Jambs for door and window opening shall be formed with
quoins of the full height of the course. The length and breadth
of the quoins shall be at least 2½ times X 1¼ times the depth of
the course respectively. For door openings three and for
window openings two of these quoins shall be stone of full
thickness of wall. Door and window frames shall be let into ½
inch in the quoins.
33-1.8 FIXTURE
Holdfasts and similar fixtures shall be built in with the surrounding
stone masonry in their correct position in specified mortar. These shall
be built in as the work progresses and not inserted later on onto space
left for them.
33-1.10 OPENINGS
Door and window openings shall have flat or relieved arches or lintels
spanning across them as shown on the drawing or as specified.
33-1.11 SCAFFOLDING
The contractor shall provide all scaffolding, staging, ladders etc.,
necessary for the work. All walls or other stone masonry of the
building shall be securely braced and protected against damages by
wind and storms during construction. No extra rate will be paid for this
item of work.
33-1.12 CENTRING
The centering for all openings shall be strong enough to support lintels
or arches spanning the openings. They shall be subjected to the
approval of the Engineer-in-charge and shall remain in position till
423
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-1.13 PUTLOGS
Only headers shall be left out to allow a putlog to be inserted and hot
more than one stone shall be left out for each putlog. Under no
circumstances shall putlogs be made immediately under or next to the
impost skew back of arches.
33-1.17 CRAMPS
Cramps, joggles and dowels shall be used whenever specified or
directed by the Engineer-in-charge. Cramps shall be from 6 inches to
12 inches in length, 3/8 inch in thickness and 1 inch to 2 inches in
width, as specified. They have each end turned at right angle. Copper
cramps shall be forged, and set with neat cement. Lead cramps shall be
formed by running molten lead into the dove-tail channels. Joggles and
dowels shall be of double wedge form and made of copper, slate or
similar material and set in neat cement. On no account iron cramps,
joggles or dowels, whether galvanized or otherwise, shall be used.
424
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-1.21 MEASUREMENT
Stone masonry shall be measured by volume. The unit of payment
shall be 100 cubic feet or cubic meter. No deduction shall be made for
opening having a superficial area of 1 sft or less.
33-1.22 RATE
33-1.22.1 LABOUR RATE
The unit rate (on labour basis) shall include the cost of the building
stone masonry, cutting and dressing stone to the specified degree of
refinement, curing and protecting as per above specifications and any
other specifications specially included in the contract. It shall further
include the cost of providing, using and required for building stone
masonry as per above specifications.
425
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-2.1 DESCRIPTION
This work shall consist of dressing & cutting stones. All visible edges
shall be free from chipping.
33-2.7 MEASUREMENT
All cut stone, moulded or ornamental stone shall be measured by
superficial area of each stone unless otherwise specified in BOQ.
426
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-2.8 RATE
The unit rate for dressing /cutting or moulding shall include dressing /
cutting or moulding the stone as per above specifications and stacking
at the site of dressing.
427
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-3(A).1 DESCRIPTION
This work shall consist of carrying out the ashlar masonry in line with
the specified architectural details, dimensions and grades in a
workmanlike manner according to following specifications.
33-3(A).5 BOND
The face stone shall be laid header and stretcher alternately unless
otherwise specified. The headers are arranged to come as nearly as
possible in the middle of the stretchers below and the stone in adjacent
layers shall break joints on the face for at least half the height of the
course, and the bond shall be carefully maintained throughout.
428
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-3(A).7 COURSES
The courses line shall be horizontal and side joint vertical throughout.
33-3(A).8 JAMBS
Jambs in door and window openings shall be formed with quoins of the
full height of the course. Unless otherwise specified, the quoins shall
not be less in breadth than 1½ times or in length less than twice the
depth. At least three quoins in case of doors, and two quoins in case of
window, shall be stones of the full thickness of the wall.
33-3(A).10 MEASUREMENT
Stone masonry shall be measured by volume. The unit of payment
shall be 100 cubic feet or cubic meter. No deduction shall be made for
opening having a superficial area of 1 sft or less.
33-3(A).11 RATE
33-3(A)11.1 LABOUR RATE
The unit rate (on labour basis) shall include the cost of the building
stone masonry, cutting and dressing stone to the specified degree of
refinement, curing and protecting as per above specifications and any
other specifications specially included in the contract. It shall further
include the cost of providing, using and required for building stone
masonry as per above specifications.
429
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-3(B).1 DESCRIPTION
The faces exposed to view shall have a fine dressed chisel draft, one
inch wide, all round the edges and be rough tooled between the drafts,
and on all beds and joints, which shall not exceed 3/8 inch in thickness.
33-3(B).2 MORTAR
The stone shall be set in specified mortar. Mortar shall conform to
Section 16-1 – 16.3 of these specifications.
33-3(B).4 MEASUREMENT
Stone masonry shall be measured by volume. The unit of payment
shall be 100 cubic feet or cubic meter. No deduction shall be made for
opening having a superficial area of 1 sft or less.
33-3(B).5 RATE
33-3(B).5.1 LABOUR RATE
The unit rate (on labour basis) shall include the cost of the building
stone masonry, cutting and dressing stone to the specified degree of
refinement, curing and protecting as per above specifications and any
other specifications specially included in the contract. It shall further
include the cost of providing, using and required for building stone
masonry as per above specifications.
430
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-3(C).1 DESCRIPTION
It shall be similar to Section 33.3(B) of these specifications, except that
the exposed faces of the stone between the drafts shall be left rough as
the stone comes from the quarry. But no rock face or “bushing” shall
project more than 3 inches form plane of drafts. The drafts may be
omitted altogether, except at quoins if required for architectural
purposes or as specified.
431
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-4.1 DESCRIPTION
This work consists of stone facing of specified rough-tooled, rustic
(with or without chisel draft, except at quoins) or chamfered. For a
particular work, facing shall have, as specified, a backing of
brickwork, concrete or rubble masonry.
432
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-4.9 MEASUREMENT
In work of this sort, the face work alone shall be measured for as
ashlar, as is dressed back, according to the type of ashlar masonry 33
(A), (B), (C), true and square on the beds and joints, 1/3rd more is
allowed for header (e.g. in 12 inch courses a thickness of 16 inch from
the face would be measured for as ashlar), and the remainder is
measured for according to the character of the backing.
33-4.10 RATE
22-4.10.1 LABOUR RATE
The unit rate (on labour basis) shall include the cost of the building
stone masonry, cutting and dressing stone to the specified degree of
refinement, curing and protecting as per above specifications and any
other specifications specially included in the contract. It shall further
include the cost of providing, using and required for building stone
masonry as per above specifications.
433
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-5.1 DESCRIPTION
Stone shall be rough tooled on all beds and joints so as to give
rectangular shape. Faces shall be accurately square and all face joints
dressed at right angle to the face for a distance of 4 inches.
33-5.3 LAYING
All courses shall be laid with beds truly horizontal and joints truly
vertical. Each bed and joint shall be full of the mortar specified and
each stone shall be struck with a wooden maul to bring it to a solid
bearing. No face joint shall be thicker than ¼ inch.
33-5.6 MEASUREMENT
It shall be measured by volume. The unit of payment shall be 100
cubic feet or cubic meter. No deduction shall be made for opening
having a superficial area of 1 sft or less.
434
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-5.7 RATE
33-5.7.1 LABOUR RATE
The unit rate (on labour basis) shall include the cost of the building
stone masonry, cutting and dressing stone to the specified degree of
refinement, curing and protecting as per above specifications and any
other specifications specially included in the contract. It shall further
include the cost of providing, using and required for building stone
masonry as per above specifications.
435
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-6.1 DESCRIPTION
Walls built in brickwork, concrete or rubble masonry shall be faced
with ashlar block in course masonry. The work shall comply with
Section 33-5 for Ashlar Block in Course Masonry.
33-6.6 FACE
The face of the stone shall be left rough (but no projection shall exceed
2 inches) without chisel draft, except at quoins, where ½ inch draft
shall be given.
436
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-6.8 MEASUREMENT
Only so much of the face stone as is dressed back full, true and square
from face shall be measured and paid for as block in course. One third
shall be added for headers. The remainder work shall be measured and
paid for according to the character of the backing.
33-6.9 RATE
33-6.9.1 LABOUR RATE
The unit rate (on labour basis) shall include the cost of the building
stone masonry, cutting and dressing stone to the specified degree of
refinement, curing and protecting as per above specifications and any
other specifications specially included in the contract. It shall further
include the cost of providing, using and required for building stone
masonry as per above specifications.
437
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-7.1 DESCRIPTION
This work consists of mortar stone cornices, copings, pillars, string
courses, corbels, brackets, chajjas and similar works shall be made
from stone of uniform color and texture and of the kind specified for
each.
33-7.5 MORTAR
Cornices, string courses, corbels and pillars shall be set in lime mortar
or cement mortar of specified mix. It shall conform to section 16-1 to
16-3 of these specifications.
33-7.6 CHAJJAS
Chajjas in the case of isolated windows, shall consist of a single stone;
in continuous chajjas all joints shall come over the brackets.
33-7.7 JOINTS
No joint shall be more than 1/8 inch in thickness.
438
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-7.9 DOWELS
Coping stones and other similar works are to be cramped or dowelled
and courses of pillars, skew backs and similar works shall be joggled,
wherever specified.
33-7.10 MEASUREMENTS
Cornices, string courses and chajjas shall be measured by length. The
unit of measurement shall be one foot. Copings shall be measured by
volume. The unit of measurement shall be 100 cubic feet or cubic
meter.
33-7.11 RATE
22-7.11.1 LABOUR RATE
The unit rate (on labour rate basis) for cornices/string
courses/copings/chajjas shall include the cost of carrying out
cornices/string courses/copings/chajjas, cutting and dressings stone.
Whenever required, curing and protecting it as per above specifications
and/or any other specifications specially included in the contract. It
shall further include the cost of providing, using and removing
scaffolding, shuttering, centring, staging, ladders, supports and other
tools and plants required for carrying out cornices/string
courses/copings/chajjas as per above specifications.
439
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-8.1 DESCRIPTION
This work consists of course rubble masonry and shall conform to
these specifications.
33-8.3 DRESSING
The face stone shall be square on all joints in masonry. The beds shall
be hammer or chisel-dressed, true and square, for at least 3 inches back
from the face, and the joints for at least 1½ inches. The face of the
stone shall be hammer dressed and “bushing” not to project more than
1 ½ inches.
440
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-8.8 QUOINS
Quoins shall be of the same height as the course in which they occur,
shall be formed of stone at least 1½ feet long and shall be laid stretcher
and header alternately. They shall be laid square on their beds which
shall be fairly dressed to a depth of at least 4 inches.
33-8.10 HEARTING
The interior of the wall, called hearting, shall consist of flat-bedded
stones carefully laid on their proper beds and solidly bedded in mortar.
Chips and spawls of stone are wedged in, wherever necessary, so as to
avoid thick beds or joints of mortar. No dry work or hollow spaces
shall be left any where in the masonry. The face work and hearting
shall be brought up evenly, but the hearting shall not be levelled up at
each course by the use of chips.
33-8.12 MEASUREMENT
It shall be measured by volume. The unit of payment shall be 100
cubic feet or cubic meter. No deduction shall be made for opening
having a superficial area of 1 sft or less.
33-8.13 RATE
33-8.13.1 LABOUR RATE
The unit rate (on labour basis) shall include the cost of the building
course rubble masonry, cutting and dressing stone to the specified
degree of refinement, curing and protecting as per above specifications
and any other specifications specially included in the contract. It shall
further include the cost of providing, using and required for building
stone masonry as per above specifications.
33-8.13.2 COMPOSITE RATE
The unit rate shall include the cost of course rubble masonry, mortar
and any other material required, in addition to the rate detailed above.
441
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-9.1 DESCRIPTION
This work consisting of course rubble masonry (2nd class) shall
conform to Section 33-8 of the specification for Course Rubble
Masonry (1st class) with the following exception.
(a) All stones in a course need not be of the same height, but short
lengths of course shall be made up by two courses, equal in
height to the through course. No course shall be of a height
greater than the course below it. The thickness of the joint shall
not exceed half an inch.
(b) In each course, headers, hammer dressed and of the full height
of the course, shall be placed 5 feet apart. Each header shall
have a breadth not less than the height and shall tail into the
work at least three times its height. Between the headers each
course shall be built of smaller stones not less than 2 inches
thick of which there may be two or three in the height of the
course. These stones need not be dressed but shall be as flat-
bedded as possible. Side joints need not be vertical, but no side
joint shall form an angle with a bed joint sharper than 60o. No
stone shall be less in breadth or length than its height, and care
shall be taken to make the stone in different courses break joint.
All stones shall be set full in mortar. The thickness of joint
shall not exceed 5/8 inch.
33-9.3 MEASUREMENT
It shall be measured by volume. The unit of payment shall be 100
cubic feet or cubic meter. No deduction shall be made for opening
having a superficial area of 1 sft or less.
33-9.4 RATE
33-9.4.1 LABOUR RATE
The unit rate (on labour basis) shall include the cost of the building
course rubble masonry, cutting and dressing stone to the specified
degree of refinement, curing and protecting as per above specifications
and any other specifications specially included in the contract. It shall
442
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
further include the cost of providing, using and required for building
stone masonry as per above specifications.
443
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-10.1 DESCRIPTION
This work consists of random rubble masonry. Stone shall be hammer
dressed on the face and on the sides and beds to such an extent that
weak corners are chipped off and the stones come into close proximity,
when laid. Each stone shall be laid on its quarry bed and shall be
wedged or pinned strongly into position in the wall by spawls or chips
which may show on the face.
33-10.2 JOINTS
No stone shall tail into the wall less than 1½ times its height. The stone
shall be arranged to break joints as much as possible. Care shall be
taken to avoid long continuous vertical joints.
33-10.4 HEARTING
Hearting or interior filling between the front and back face shall
consist of rubble stone, not less than 6 inches in any direction,
carefully laid, hammered down with a wooden mallet into place and
solidly bedded n mortar. Chips and spawls of stone shall be used,
wherever necessary, so as to avoid thick beds or joints of mortar. No
dry work or hollow spaces shall be left anywhere in the body of the
masonry. Hearting shall be laid nearly level with each course except
that at about 3 feet interval vertical “plumbs” projecting 6 to 9 inches
shall be firmly embodied to form a bond between successive courses.
Hearting shall not be brought to the same level as the front and back
stones by the use of chips. The use of chips shall be restricted to only
wedges in the hearting.
444
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-10.6 MEASUREMENT
It shall be measured by volume. The unit of payment shall be 100
cubic feet or cubic meter. No deduction shall be made for opening
having a superficial area of 1 sft or less.
33-10.7 RATE
33-10.7.1 LABOUR RATE
The unit rate (on labour basis) shall include the cost of the building
random rubble masonry, cutting and dressing stone to the specified
degree of refinement, curing and protecting as per above specifications
and any other specifications specially included in the contract. It shall
further include the cost of providing, using and required for building
stone masonry as per above specifications.
445
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-11.1 DESCRIPTION
This work consists of dry rubble masonry and shall conform to the
following specifications.
33-11.3 BEDS
Stone shall be roughly dressed to secure the maximum bedding
surfaces without unduly reducing the size of the stone. Each course
shall be built through the entire thickness of the wall.
33-11.5 FILLING
Wherever required, filling behind dry stone walls shall be done
immediately with stone refuse or chips. Earth shall not be used where
stone refuse is available.
33-11.6 MEASUREMENT
It shall be measured by volume. The unit of payment shall be 100
cubic feet or cubic meter. No deduction shall be made for opening
having a superficial area of 1 sft or less.
446
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-11.7 RATE
33-11.7.1 LABOUR RATE
The unit rate (on labour basis) shall include the cost of the building dry
rubble masonry, cutting and dressing stone to the specified degree of
refinement, curing and protecting as per above specifications and any
other specifications specially included in the contract. It shall further
include the cost of providing, using and required for building stone
masonry as per above specifications.
447
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-12.1 DESCRIPTION
This work consists of stone masonry in Arches and shall conform to
the specifications. All stone masonry in arches shall be finished in a
workmanlike manner, true to dimensions and grades shown on the
drawings and according to the following specifications.
33-12.3 CENTRING
Centring shall be strong enough to bear the weight of an arch without
any deflection. The surface of centring shall be correctly struck to the
curvature of the soffit of the arch.
448
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-12.9 MEASUREMENT
Stone masonry in arches shall be measured by volume. The unit of
payment shall be 100 cubic feet or cubic meter. No deduction shall be
made for opening having a superficial area of 1 sft or less.
449
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
33-12.10 RATE
33-12.10.1 LABOUR RATE
The unit rate (on labour basis) shall include the cost of the building
stone masonry in arches, cutting and dressing stone to the specified
degree of refinement, curing and protecting as per above specifications
and any other specifications specially included in the contract. It shall
further include the cost of providing, using and required for building
stone masonry as per above specifications.
450
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–34
ROOFING
GLOSSARY
Roof The covering or the upper part of a building
constructed to preserve it from exposure to
weather is known as roof.
Type of roofs Roofs can be broadly be divided into following
major types:
Flat roofs The so called flat has a small slope to drain
water from the roof. The various flat roofs
commonly used are as under:
Jack Arch Flat It is constructed in the form of small span brick
Roof arches over R.S. Joists. These joists rest on
walls and spandrels are fitted by cheap inert
materials such as lean concrete (fig-1, Page
481).
Terrace roof The roofing consists of R.C.C. steel joist or
wood beams resting over bed plate on the wall.
The opening between joists is spanned by
wooden joist or steel T-sections over which the
terrace bricks or clay tiles.
R.C.C. slab roof Roof comprises of reinforcement cement
concrete structural members like beams & slab
or simply slab.
Pitched roofs A pitched roof is composed of a framework and
roof covering. Frame generally known as
trusses are placed at suitable distances spanning
the two supports. Terms related to pitch roofing
are as under:
Abutment The sloping intersection of a roof surface with
a part of the structure which rises above.
Barge board A member, usually of timber, fixed along the
edges of a gable and covering the ends of the
horizontal roof members.
Battens Horizontal timber members of small section on
which tiles or slates may be laid. They are
sometimes termed tile or slate battens, or tile or
slate laths.
Bedding The laying of tiles or slates in mortar.
Counter battens Timber members of small section fixed at right
angle or obliquely to the direction of the
battens between them and the surface below.
Dormer A vertical window formed in a sloping roof.
Eaves The lower edge of an inclined roof.
451
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
452
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
flashings.
Slate Head The upper edge of a slate when laid.
Slate Tail The lower edge of a slate when laid.
Soaker Flexible members, usually of metal, lapped
with slates or tiles and bent to form a watertight
joint, as for example at abutments where it is
used in conjunction with cover flashings, or at
mitred hips, valleys and angles.
Tile Fillet Tiles cut and fitted to form a fillet as an
alternative to flashings.
Tilting Piece A fillet, usually of wood, used at eaves or at
open valley gutters to support the slates in the
correct position relative to the roof surface.
Top Edge The upper edge of a roof surface finishing at a
ridge or against a part of the structure which
rises above the roof surface.
Torching The mortar pointing to the heads and/or the
side joints on the underside of the tiles or
slates.
Undercloak A course or courses of tiles or slates laid under
the bedding of slating or tilling at a verge.
Valley The sloping intersection of two inclined roof
surfaces at a re-entrant angle.
Valley, laced A valley in which the courses are not
horizontal, each course being swept up to a tile
and a half, or slate and a half, laid aslant on a
wide board in the valley.
Valley, mitred A valley at which the tiles or slates of each
course are mitred.
Valley, swept A valley in which tiles or slates, made or cut to
a taper, sweep round in horizontal courses.
Types of
pitched roofs
Shed roof It slopes in one direction. This type is used
generally on a temporary structure where
appearance is not important and where it
cannot be seen in connection with other types
to form a ‘lean to’.
Gable roof It slopes in two directions as shown in Fig-3
(page 481). This type of roof is widely in use in
big halls of cinemas, auditoriums, etc. The
most common slopes are between 1:2 to 1:1.
Hip roof It slopes in four directions. This type of roof is
widely in use. Its slope varies similarly as in
case of gable roof.
Gambrel roof It slopes in two directions but there is a break
in the slope on each side. This roof is used for
houses on account of efficient use which can be
made of the space under the roof.
Mansard roof It slopes in four directions, but there is a break
453
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
in the slope.
Deck roof It slopes in four directions, but has a deck at the
top.
Sawtooth roof As shown in Fig-8 (page 482), it is used quite
extensively in industrial buildings on account
of the advantage of sufficient light and good
ventilation that it offers. The steep vertical
faces as shown in figures are mostly glazed and
are kept towards the north.
Shall roof In case of very large openings and massive
structures such as theatres, factories, assembly
halls etc RCC shell roofs are becoming
extremely popular because of the
comparatively thin section which results in
considerable reduction of dead load. The shall
is designed as a membrance and hence it is free
from large bending stress.
Dome roof Domes are similar in construction to shells in
which also very small RCC section provide
roof covering over very large area within
certain height and diameter ratios. They are
particularly constructed from architectural
consideration, in moments and other similar
buildings.
454
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-1.1 DESCRIPTION
This work covers construction of 1st class tile roofing in accordance
with these specifications.
34-1.2 OPERATIONS
The first class tile roofing shall consist of:
(a) First layer of tiles laid in 1:6 cement sand mortar or 1:2 lime-
surkhi mortar resting on battens.
(b) Second layer of tiles in 1:6 cement sand mortar or 1:2 lime-
surkhi mortar laid over a bed half an inch thick 1:6 cement-
sand mortar.
(c) Half an inch thick 1:6 cement sand plaster over second layer of
tiles.
(d) A coat of hot bitumen blinded with sand.
(e) Four inches earthfilling finished with 1 inch mud plaster with
gobri leeping.
34-1.3 MATERIALS
34-1.3.1 BEAMS & BATTENS
Beams and battens shall be of size and types as mentioned in BOQ of
the work.
34-1.3.2 TILES
Unless otherwise specified, tiles used in both the layers shall be of size
12"x6"x1¼" and shall conform to Section 7 of these specifications.
34-1.3.3 CLAY
Clay used in earth filling shall conform to Section 2 of these
specifications.
34-1.3.4 CEMENT MORTAR
It shall conform to section 16-2 of these specifications.
34-1.3.5 BITUMEN
Bitumen shall conform to Section 23 of these specifications.
34-1.3.6 MUD MORTAR
It shall conform to Section 16-1 of these specifications.
455
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
456
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-1.16 KHURRAS
Khurras shall be made before the earth is laid and shall be in
accordance with the Section 34-9 of these specifications.
457
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
of exact size and laid in spaces with 1:3 cement sand mortar. The
filling shall be equal to the battens in height and the outer faces shall
be exactly in line with the edge of the beam.
34-1.20 MEASUREMENTS
First class tile roofing shall be measured by the superficial area of the
roof. The unit of measurement shall be 100 square feet or square meter.
34-1.21 RATE
34-1.21.1 LABOUR RATE
The unit rate shall include:
(a) Laying of first layer of tiles in specified mortar on battens.
(b) Laying of second layer of tiles in specified mortar over half an
inch thick bed of specified mortar.
(c) Laying of half an inch thick cement sand plaster over second
layer of tiles.
(d) Laying of coat of hot bitumen blinded with sand.
(e) Laying of 4-inch earthfilling finished with I-inch mud plaster
with gobri leeping.
(f) Cement plastering portion of parapet against which mud plaster
and earthfilling butt.
(g) Pointing the underside of the tiles with specified mortar.
(h) Filling spaces between battens over the beam.
(i) Providing, using and removing scaffolding, staging, ladders,
supports and other tools and plants required for carrying out the
work as per above specifications. It shall also include making
good of any damaged portion of the walls or other structure on
which the roof is being laid.
NOTE: The rate does not include labour required for the construction of
khurras or any other kind of rain water outlet. The rate also does not include
hoisting and fixing in position, battens and beams. Painting of wooden
beams & battens with preservative, is also not included.
34-1.21.2 COMPOSITE RATE
The unit rate shall include the cost of the materials specified above for
carrying out the work in accordance with above specifications, in
addition to the labour rate detailed in Section 34-1.21.1 of the
specification.
458
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-2.1 DESCRIPTION
Second class tile roofing shall conform to Section 34-1 of these
specification in all respects with the following exceptions:
Only one layer of tiles shall be laid instead of two and their size shall
be 12"x6"x2" as specified in Section 7-1 of these specifications.
459
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-3.1 DESCRIPTION
The work covers construction of Jack Arch roofing in accordance with
specification and the drawing of the work.
34-3.2 OPERATIONS
Jack Arch roofing shall involve the following operations:
(a) Construction of brick segmental arches in specified mortar.
(b) Filling of haunches and crown with specified cement concrete.
(c) Laying of bitumen blinded with sand over half an inch thick
bed of specified mortar.
(d) Earthfilling finished with mud plaster and gobri leeping.
(e) Plastering soffits of arches.
34-3.3 MATERIALS
Materials shall conform to the following specifications:
Bricks – Section 6 of the specifications.
Mortar – Section 16 of the specifications.
Steel – Section 15 of the specifications.
Paints – Section 14 of the specifications.
Concrete – Section 30 of the specifications.
460
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-3.11 KEY
Key shall be driven firmly into position with a wooden mallet and shall
lie truly and centrally of a vertical line through the centre of the span.
461
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-3.12 SLOPE
Unless otherwise specified, the slope in the roof shall be given in R. S.
beams while placing them in position.
462
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-3.21 MEASUREMENTS
Jack Arch roofing shall be measured by the superficial area of the roof.
The unit of measurement shall be 100 square feet or square meter.
34-3.22 RATE
34-3.22.1 LABOUR RATE
(a) Laying of bricks in segmental arches in specified mortar. Cutting
of bricks, whenever required, curing and protecting as per above
specifications and/or any other specifications specially included in
the contract.
(b) Filling of haunches and crown with specified concrete.
(c) Laying of coat of hot bitumen blinded with sand over half an inch
thick bed of specified mortar.
(d) Laying of 3 inches thick earthfilling finished with mud plaster and
gobri leeping.
(e) Plastering of soffits of arches in specified mortar.
(f) Providing, using and removing scaffolding, shuttering, centring,
ladders, supports and use of any other tools and plants, required for
carrying out the work as per above specifications
NOTE: The rate does not include hoisting, fixing in position and painting of R.S.
beam, tie rods or other anchor. The rate also does not include the plastering of bottom
flange of beams.
34-3.22.2 COMPOSITE RATE
The unit rate shall include the cost of all the materials specified above
in carrying out the work in accordance with the above specifications, in
addition to the labour rates detailed above.
463
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-4.1 DESCRIPTION
Jack Arch roof (sprung from the top of beams) shall conform to
Section 34-3 of these specifications in all respects, except the
following:
(a) EXTRA TIE BARS ANCHORAGE
A second length of 3"x3"x3/8" angle iron shall be provided
wherever tie rods are to be provided, to serve as an anchorage
for the other ends of the tie rods which in this case cannot be
anchored to the beams.
464
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-5.1 DESCRIPTION
The work covers the construction of Jack Arch Roofing intended to
carry the flooring of a room shall conform to section 34-3 of these
specifications in all respects, except the following:
Operations referred to in section 34-3.2 (d) and (e) of these
specification shall not be performed.
34-5.2 MEASUREMENTS
Roofing shall be measure by the superficial area of roof. The unit of
measurement shall be square foot or square meter.
34-5.3 RATE
34-5.3.1 LABOUR RATE
The unit rate shall include:
(a) Laying of bricks in segmental arches in specified mortar.
Cutting of bricks, whenever required, curing and protecting as
per above specifications and/or any other specifications
specially included in the contract.
(b) Filling of haunches and crown with specified concrete.
(c) Plastering of soffits of arches in specified mortar.
(d) The cost of providing, using and removing scaffolding,
shuttering, centring, ladders, supports and any other tools and
plants, required for carrying out the work as per above
specifications
NOTE: The rate does not include hoisting, fixing in position and painting of R.S.
beam, tie rods or other anchor. The rate also does not include the plastering of bottom
flange of beams.
34-5.3.2 COMPOSITE RATE
The unit rate shall include the cost of all the materials supplied at site
of work, specified above in carrying out the work, in addition to the
labour rates detailed above.
465
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-6.1 DESCRIPTION
This work covers laying galvanized corrugated steel sheet roofing in
accordance with the specifications on already placed in position
wooden or steel trusses.
34-6.2 MATERIALS
34-6.2.1 GALVANIZED CORRUGATED STEEL SHEETS
These shall conform to Section 18-4 of these specifications.
34-6.2.2 FIXING ACCESSORIES
Hook bolts, screws, bolts, nuts, rivets, washers shall be galvanized or
shall be of any other approved quality.
34-6.2.3 SEALING MATERIAL
It shall be bituminous mastic.
34-6.2.4 FLASHING GUTTERS
These shall conform to Section 34-9 of these specifications.
34-6.3 LAP
(a) End lap shall be minimum of 6 inches for slope and 4 inches
for vertical falls which shall be sealed with specified sealing
material.
(b) Side lap shall be formed on the sides of the sheet, away from
the prevailing direction of wind. The side lap shall vary from
one to two corrugations as specified.
34-6.4 INSULATION
Wherever specified, insulation material of specified quality shall be
laid either between the purlins and the sheet or under purlins
incorporating air gap.
34-6.5 PURLIN
Purlin spacings for roof covering with G.C.S. sheets shall be arranged
with a view to using standard sheets of uniform length throughout, and
the trusses shall be designed for purlin spacings to suit the standard
length of these sheets to avoid unnecessary cuttings. Ridge purlins
shall be as near to the ridge as possible having regard to the type of
ridge capping to be used and the manner in which it is to be fixed.
466
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-6.6 HOLES
The holes for fixing bolts shall be made through crown of the
corrugations and shall be either punched or drilled and shall be 1/16 of
an inch larger in diameter than the bolts or fixing screws to be used.
Holes shall be in the exact position to suit the purlins and no holes for
fixing bolts shall be nearer than 1½ inches to the end of the sheet.
These holes shall be made in a manner that the arrisses of the punched
hole shall come on top when the sheets are laid. Where 4 sheets
overlap, holes shall be drilled and not punched.
467
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
(c) Hip cap shall be cut to the required mitre and shall be close
butted. The slope joints shall be covered with plain ridge cap
which shall be secured through the roof sheet or the slope
runner by one bolt on each side at the same spacing as for the
roof sheets. Hip caps shall have a minimum lap of 6 inches.
34-6.12 MEASUREMENTS
The measurement of corrugated iron sheet roofing shall be done by the
superficial area of the roofing. The unit rate shall be 100 square feet or
square meter.
34-6.13 RATE
34-6.13.1 LABOUR RATE
The unit rate shall include:
(a) Hoisting and fixing of corrugated iron sheets in position with
the specified fixing accessories.
(b) Punching or drilling holes and cutting of sheets.
(c) Providing, using, erecting and removing of scaffolding,
benching ladders, templates and use of other tools and plants
required for carrying out the work in accordance with the above
specifications.
The labour for fixing trusses, purlins, flashing and painting is not
included.
34-6.13.2 COMPOSITE RATE
The unit rate shall include the cost of (i) galvanized corrugated steel
sheet with all the specified overlaps, (ii) all bolts, nuts, hook bolts,
screws and washers required for properly fixing sheets as per above
specifications, in addition to the labour rate detailed in 34-6.13.1. The
unit rate shall not includes the cost of trusses and purlins.
468
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-7.1 DESCRIPTION
This work covers construction of corrugated asbestos cement sheet
roofing in accordance with these specifications on the previously
placed in position the truss and purlins or battens.
34-7.2 MATERIALS
34-7.2.1 CORRUGATED ASBESTOS CEMENT SHEETS
These shall conform to Section 18-2 of these specifications.
34-7.2.2 FIXING ACCESSORIES
Hook bolts, nuts, and screws shall be galvanized or of any other
approved quality. Washers shall be bituminous and galvanized iron or
of any other approved type and quality.
34-7.2.3 SEALING MATERIAL
When specially required, sealing material shall consist of mastic of
approved quality.
34-7.2.4 FLASHING GUTTERS
These shall conform to Section 34-9 of these specifications.
34-7.3 LAP
(a) End lap shall be of a minimum size of 6 inches.
(b) Side lap shall be formed on the sides of the sheet away from the
prevailing wind. It shall be half the corrugation of sheets.
34-7.4 OVERHANGING
The minimum end overhanging in case of eave verges and cable ends
shall be 12 inches. Overhanging verges shall be supported by purlins
over the full width the sheet.
469
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-7.6 HOLES
Holes in sheets shall always be drilled and shall on no account be
punched They shall be 1/16 of an inch larger in diameter than that of
bolt or fixing screw, and shall be drilled through the crown of the
corrugations. Holes shall be drilled in exact position to suit the purlins.
No hole shall be made in valleys of corrugations and closer than 1½
inches from the edge.
34-7.10 MEASUREMENTS
The A.C.C. sheet roofing shall be measured by the superficial area of
the roof. The unit of measurement shall be 100 sq. feet or sq. meter.
470
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-7.11 RATE
34-7.11.1 LABOUR RATE
The unit rate shall include:
(a) Hoisting and fixing of A.C.C. sheets in position with specified
fittings, i.e. nuts, screws, washers, hook bolts, bituminous
washers etc.
(b) Cutting of sheets and drilling of holes.
(c) Providing, using and removing of scaffolding, benching ladders
and use of other tools and plants required for carrying out the
work in accordance with the above specifications.
34-7.11.2 COMPOSITE RATE
The unit rate shall include the cost of (i) A.C.C. sheets with all the
specified overlaps, (ii) all bolts, nuts, screws, washers, etc., required
for the proper fixing of sheets, in addition to the labour rate as detailed
in Section 34-7.11.1.
471
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-8.1 DESCRIPTION
This work covers construction of Khurras, Parnalas and Spouts in
accordance with these specifications. The location of these shall be as
shown on the drawings.
34-8.2 KHURRAS
34-8.2.1 TOP KHURRAS
Unless otherwise specified, top khurras shall be 2 feet x 2 feet and
shall be made of 1:2:4 cement concrete 1½-inch thick, laid on 1:4:8
cement concrete. The outside edge of the khurras shall be lower than
the level of the mud plaster or leepai and the surface shall slope
uniformly from that place to the outlet, which shall be 2 inches lower
than the edges. Concrete shall have a slope 1:1 at the sides so as to be
overlapped by earth and mud plaster. Cement concrete shall be
continued into the outlet so as to ensure a watertight joint.
34-8.2.2 BOTTOM KHURRAS ON ROOF
Unless otherwise specified, bottom khurras on top of verandah or roofs
shall be 2' x 2' and will consist of a 1½" layer of 1:2:4 cement concrete
laid on 1:4:8 cement concrete. The surface shall be shaped like a
saucer drain, the depth of the saucer being 2", and joining up with the
roof drain.
34-8.2.3 BOTTOM KHURRAS ON GROUND
Unless otherwise specified, bottom khurras when used on the ground,
in conjunction with spouts, shall be 4' x 2' and shall consist of bricks
on edge in cement sand mortar 1:3 ratio laid on 3" of 1:4:8 cement
concrete.
34-8.3 PARNALAS
34-8.3.1 REVEALED PARNALAS
Unless otherwise specified, revealed parnalas shall be made by leaving
a channel 7 inches wide and 2¼ inches deep in the wall during
construction, and afterwards plastering the channel with 1:3 cement
sand plaster. The corner of the channels shall be rounded to a radius of
one inch in plastering. If revealed parnalas are left in a wall made of
brickwork in mud, the bricks shall be laid in cement mortar (1:3) for a
depth of 4½ inches from the back and sides of the parnalas, this work
being included in the rate.
34-8.3.2 KHASSI PARNALAS
Unless otherwise specified, khassi parnalas shall consist of two fillets
of cement plaster (1:3) raised 1½ inches and spaced 9 inches apart, the
472
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
space in between being plastered with 1:3 cement sand plaster. The
fillets shall be prismatic in section (but with all corners and angles
rounded), the inner sides being at right angle to the wall and the outer
sides sloping. Unless otherwise specified, khassi parnalas shall in no
case be made on top of the cement or other plaster on the wall, but
made in contact with the brickwork or masonry after raking out the
joints.
34-8.4 SPOUTS
Unless otherwise specified, spouts shall be made of reinforced cement
concrete and shall have an open channel 3¼"x3½" with a semi-circular
bottom. These shall project at least 15 inches from the face of the wall
and shall be built into the wall for a depth of at least 13½ inches. The
part built into the wall shall be sufficiently thickened to provide
adequate support for the overhanging portion. Spouts shall be fixed at a
slope not flatter than 1 in 6 and shall have a lip at the lower edge to
allow water to drip clear.
34-8.6 MEASUREMENTS
The parnalas and drains shall be measured along their length. The unit
of measurement shall be per running foot. The khurras and spouts shall
be measured as a jobs item. The unit of measurement shall be for a
complete unit.
34-8.7 RATE
34-8.7.1 LABOUR RATE
The unit of rate shall include (i) all the labour required for the above
operation and (ii) use of all the tools and plants required for carrying
out work in accordance with the above specifications.
34-8.7.2 COMPOSITE RATE
The unit rate shall include the cost of all materials at site of work
required for carrying out the work as per above specifications, in
addition to the labour rate detailed in Section 34-8.7.1 above.
473
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-9.1 DESCRIPTION
This work covers providing and fixing gutters, flashings in accordance
with these specifications.
34-9.2 MATERIALS
Unless otherwise specified these shall be made from lead, copper, zinc
or galvanized steel sheet:
34-9.2.1 LEAD SHEETS
Lead sheets shall be made from melted lead and shall not be less than
the following weight per foot.
Gutters 6 lbs
Flashings 5 lbs
34-9.2.2 COPPER SHEETS
Copper sheets used for gutter shall be cold rolled and shall not be
thinner than 22 S.W.G. For flashings it shall be dead soft temper and
shall not be thinner than 24 S.W.G.
34-9.2.3 ZINC SHEETS
Zinc sheets shall not be thinner than 20 S.W.G.
34-9.2.4 GALVANIZED STEEL SHEETS
Galvanized steel sheets shall be:
For gutters No.18 S.W.G. to No.22 S.W.G.
For flashings No.20 S.W.G. to No.24 S.W.G.
474
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-9.4 MEASUREMENTS
34-9.4.1 GUTTERS
The measurement of gutters shall be along its length and the unit of
measurement shall be per running foot or meter.
34-9.4.2 FLASHING
The measurement of flashing shall be by the superficial area and its
unit of measurement shall be per square foot or per square meter.
34-9.5 RATE
The rate for gutters and flashings is for completed work fixed in
position, including all laps, supports and other fixing accessories.
475
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-10.1 DESCRIPTION
This work consist of treatment of pre-laid roof slab by application of
bitumen, blinding of bituminous coating with sand, laying of polythene
sheet, earth filling, mud plaster, laying of clay tile grouting of joints
with cement sand mortar according to this specification.
34-10.2 MATERIALS
34-10.2.1 BITUMEN
It shall conform to Section 23 of these specifications.
34-10.2.2 SAND
It shall conform to Section 10-3 of these specifications.
34-10.2.3 POLYTHENE
It shall conform to Section 21 of these specifications.
34-10.2.4 EARTH
It shall conform to Section 2 of these specifications.
34-10.2.5 CLAY TILES
These shall conform to Section 7 of the specification.
34-10.2.6 MORTAR OF CEMENT:SAND (1:3)
It shall conform to Section 16-2 of these specifications.
476
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
rammed and watered. For efficient run of the rain water, the earth
should be laid in accordance with roof drainage profile.
34-10.3.6 MUD PLASTER
Rammed earth surface shall be finished with 1" mud plaster to act as
bedding for tiles.
34-10.3.7 LAYING OF TILES
Clay Tiles 9" x 4½" x 1½" shall be laid on the mud plaster by keeping
maximum joint between the two tiles not more than ¼".
34-10.3.8 CEMENT SAND GROUTING
The joints between the tiles shall be grouted with cement-sand
mortar/slurry. It should be ensued that there shall be no slurry
remained deposited on the flat surface of tiles.
34-10.4 MEASUREMENT
The measurement of roof treatment shall be measured by the
superficial its unit shall be 100 Sft or Sq. Meter.
34-10.5 RATE
34-10.5.1 LABOUR RATE
The rate shall include:
a) Cleaning of the surface of the pre-laid R.C. slab.
b) Heating and spraying of bitumen.
c) Sand blinding.
d) Laying of polythene sheet.
e) Lifting and laying earth on roof including watering and
ramming.
f) Laying of bedding of mud mortar.
g) Laying of tiles.
h) Grouting of joint with cement sand mortar.
i) Cost for providing T&P required for carrying out work in
accordance with above specification.
477
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-11.1 DESCRIPTION
This work shall consist of thermal insulation of pre-laid RCC roof slab
by application of bituminous coating with sand blinding, laying of
polythene sheet, laying thermopore sheet, laying of 3" (average) earth
filling 1" mud plaster, laying of clay tiles 9" x 4½" x 1½" grouting of
joints with cement sand mortar according to this specification.
34-11.2 MATERIALS
34-11.2.1 BITUMEN
It shall conform to Section 23 of these specifications.
34-11.2.2 SAND
It shall conform to Section 10-3 of these specifications.
34-11.2.4 THERMOPORE
It shall conform to Section 20 of these specifications.
34-11.2.5 EARTH
It shall conform to Section 2 of these specifications.
478
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-11.6 MEASUREMENT
The measurement of the treated area shall be surface area its unit shall
be 100 sft.
479
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
34-11.7 RATE
34-11.7.1 LABOUR RATE
The rate shall include:
a) Cleaning of the surface of the pre-laid R.C.C slab.
b) Heating and spraying of bitumen.
c) Sand blinding
d) Laying of polythene sheet.
e) Laying of thermopore sheet.
f) Laying of polythene sheet 500 Micron
g) Lifting and laying earth on roof including watering and
ramping laying of bedding of mud mortar.
h) Laying of bedding of mud mortar.
i) Laying of tiles.
j) Grouting of joint with cement sand mortar.
k) Cost for providing T&P required for carrying of work in
accordance with above specification.
480
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
481
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
482
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
483
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
484
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Fig:12.
Fig:13
Fig:14
485
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Fig:15
Fig:16
Fig:17
486
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Fig:18
Fig:19
Fig:20
487
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–35
FLOORING
GLOSSARY
Floor The tiers or levels which divide a building in
two stages or storeys are called floors. These
are made of materials quite different both in
composition and construction. They range from
relatively thin covering, contributing little or no
structural strength to a building, to much
thicker materials capable of withstanding
reasonable stresses, and in some design,
essential to the strength of the building.
The selection of proper floor has an important
bearing on the building. It affects its
appearance, usefulness and the cost of upkeep.
Types of floor
Earth floors These floors are made of good earth. Earth is
filled to the required level in layers, with each
layer not exceeding 6 inches in thickness. Each
layer is well watered + compacted before
placing the next layer. These floors are
generally used for stables, cattle sheds etc.
Mud floors Earth floors intended for human occupation are
provided with 1" thick mud plaster surface
followed by gobri leeping.
Brick floors Brick floors are very common in areas where
good, hard and well-burnet bricks are cheap
and readily available. They are very durable,
fire resistant and generally used for stores and
godowns.
Tile floors Tiles are placed on lean concrete. A thin layer
of 1:2 cement mortar is placed over the floor
base and tiles of required material shape, size
and thickness are placed over the floor base.
Some of the most common types of tiles used
are:
Clay Tile They are manufactured in different shapes and
designs. Most common size available in the
market are (i) 12"x6"x2" (ii) 12"x6"x1¼"
(iii) 9"x4½"x1½".
Cement concrte / They are precast tiles and are made general in
Mozaic tiles sizes (i) 6"x6" (ii) 8"x8" (iii) 9"x9"
(iv) 12"x12" usually 1" thick.
Glazed tiles They are made of ball clay, China clay, China
488
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
489
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
490
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-1.1 DESCRIPTION
Unless otherwise specified, mud flooring shall be laid in accordance
with the following specifications.
35-1.2 MATERIALS
(a) Earth (clay) shall conform to specifications as contained in
Section 2 of clay.
(b) Mortar shall conform to specification as contained in Section 16-
1 for Mud mortar.
After doing earth filling as per Section 27-3, the surface shall be
finished with one-inch thick mud plaster with gobri leeping
conforming to specifications as contained in Section 36-6 for Mud
plaster of these specifications.
35-1.4 MEASUREMENTS
Mud flooring shall be measured by the superficial area of the floor.
The unit of measurement shall be 100 sq. ft or sq.m.
35-1.5 RATE
35-1.5.1 LABOUR RATE
The unit rate shall include the cost of labour for mud plastering and
“gobri leeping”.
491
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-2.1 DESCRIPTION
Unless otherwise specified, the base of all ground floors shall be laid in
accordance with the following specifications.
35-2.2 MATERIALS
a) Earth (clay) shall conform to the specifications as contained in
Section 2 of these specifications.
b) Sand shall conform in all respects to the specification as
contained for fine aggregate in Section 10.3.
c) Coarse aggregate shall consist of crushed stone or shingle and
conform to the specification as contained in Section 10-4 for
aggregate for base of floor & foundation.
d) If brick ballast is used it shall conform to Section 10-6 of these
specifications.
e) Water shall conform to the specification contained in Section 1.
492
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-2.4 MEASUREMENTS
The components of the base for floors specified in section 35-2.3.2 and
35-2.3.3 shall be measured in volume separately. The unit of
measurement shall be 100 cft or m3.
35-2.5 RATE
35-2.5.1 LABOUR RATE
The unit rate shall include preparation of sub-base, laying and
ramming of base components viz. 35-2.3.2 and 35-2.3.3, use of tools
and plants required for carrying out of the work in accordance with the
above specifications.
493
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-3.1 DESCRIPTION
Unless otherwise specified, brick or tile flooring shall be laid in
accordance with the following specifications.
35-3.2 MATERIALS
(a) Bricks or tiles shall conform to the specifications as contained
in Section 6 for Clay Bricks and Section 7 for Clay Tiles of
these specifications.
(b) Mortar shall conform to the specifications as contained in
Section 16 for Mortar.
35-3.3.3 PATTERN
The laying of bricks or tiles shall be plain, diagonal, herring bone or
any other specified pattern.
35-3.3.4 JOINTS
(a) Where pointing is not to be done, the joints shall not exceed
3/16 inch in thickness. The mortar oozing out of the joints shall
be struck off with trowel or wiped off with damp cloth.
(b) Where pointing is to be done, the joints shall not exceed 3/8
inch in thickness. The mortar in the joint shall be raked out one
inch deep, while it is still green.
494
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-3.3.5 POINTING
Unless otherwise specified, the joints shall be flush pointed with
specified mortar.
35-3.3.9 PROTECTION
Flooring shall be allowed to mature undisturbed, and protected from
the effects of weather. It shall be kept wet for at least 7 days after
completion. If pointing is to be done, it shall be kept wet for at least 7
days after the completion of pointing.
35-3.3.10 SURFACE
Surface shall be finished to specified levels. All joints shall be
uniform, parallel and square. Bricks shall be rubbed to ensure this
where it is very necessary, without extra cost.
35-3.4 MEASUREMENTS
The measurement of brick or tile flooring shall be by the superficial
area. Its unit of rate shall be 100 cubic feet or cubic meter.
35-3.5 RATE
35-3.5.1 LABOUR RATE
The unit rate shall include:
(a) Watering and cleaning of base in case of ground floors and
scrubbing and washing of the base slabs in case of upper floors.
(b) Laying of bedding mortar over the base.
495
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
496
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-4.1 DESCRIPTION
Unless otherwise specified, flagstone flooring shall be laid in
accordance with the following specifications.
35-4.2 MATERIALS
35-4.2.1 STONE
Stone shall conform to the specifications as contained in Section 11 for
Stone.
35-4.2.1.1 Quality
Flagstone shall be hard, durable and fine-grained. Flagstone shall be
procured from the approved querry.
35-4.2.1.2 Size of Flagstone
Flagstone shall not be less than one and a half inches thick. The length
and breadth shall not be less than 12 inches and more than 30 inches.
The size of flagstone shall be such as to give uniform parallel courses.
35-4.2.1.3 Dressing
Flagstone shall be chisel dressed so as to have a flat surface, free from
windings. All edges shall be accurately dressed, truly square to their
full depth. Flagstone projecting over the edges of verandahs or steps
shall have their outer edges bull-nosed.
35-4.2.2 MORTAR
Specified mortar shall conform to Section 16 of these specifications as
actually specified.
35-4.3.2 SOAKING
Flagstone shall be soaked in water for at least one hour before laying.
497
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-4.3.5 PATTERN
Flags shall be laid in the specified pattern. The courses shall be of
uniform width and, unless otherwise specified, parallel to the wall
having the main entrance. Flags shall break joint in adjacent courses by
not less than 8 inches.
35-4.3.6 JOINTS
The thickness of joints shall not be more than 1/8 of an inch. Unless
otherwise specified, the mortar in joints shall be made flush with a
trowel.
35-4.3.7 POINTING
If pointing has been specified the flags shall be laid against wood or
iron strips of uniform thickness, so as to form joints not less than 1/4
inch wide. When a row of flags is laid, the strips shall be removed and
the open joints shall at once be filled with specified mortar, and shall
then be flush pointed with specified mortar.
35-4.4 MEASUREMENTS
The flagstone flooring shall be measured by superficial area. The unit
of measurement shall be 100 sq. ft./sq.m.
35-4.5 RATE
35-4.5.1 LABOUR RATE
It shall include:
(a) Watering & cleaning of bases according to Section 35-3.3.6.
(b) Laying of ¾ inch thick bedding mortar.
(c) Laying of flagstone and filling of joints with specified mortar.
(d) Curing and protection of work.
(e) Use of all tools and plants required for carrying out work as per
above specifications.
The labour for pointing is not included in the rate.
498
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
499
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-5.1 DESCRIPTION
Unless otherwise specified marble flooring shall be constructed in
accordance with the following specifications.
35-5.2 MATERIAL
35-5.2.1 MARBLE STONE SLABS
Marble slabs conform to the specification contained in Section 11-1.
Marble stone slab shall be of the size, type and colour as specified. All
slab shall have a true plain surface and shall be accurately swan, truly
square at edges to the full thickness.
35-5.2.3 MORTAR
Cement sand mortar ratio 1:2 conforming to the specification as
contained in Section 16-2.
35-5.3.4 JOINTS
No joints shall be more than 1/16 of an inch in thickness. Slabs
projecting over the edges of verandah or steps shall have their edges
finished with a bull-nosed ending.
35-5.3.5 LAYING
Slabs shall be laid in position on bedding mortar in specified pattern.
The joints shall be filled with specified putty.
500
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-5.3.6 LEVELS
The surface of marble slabs when laid shall be perfectly true, level,
projected or sloped.
35-5.3.8 GRINDING
After the marble slab has hardened enough, it shall be ground with an
approved type of grinding machine wing rapid cutting carborundum
stones. The floors shall be kept wet during the grinding process. All
materials ground off shall be removed by sweeping and flushing with
water. Then the floor surface shall receive a second grinding followed
by final grinding to remove the film of cement paste and to give the
floor a polish. It shall then be thoroughly washed and all surplus
material removed.
35-5.4 MEASUREMENTS
The measurement of marble flooring shall be done by the superficial
area. The unit of measurement shall be 100 square feet or m2.
35-5.5 RATE
35-5.5.1 LABOUR RATE
The unit rate shall include:
(a) Washing, scrubbing and cleaning of base (in the case of ground
floor).
(b) Laying of bedding mortar.
(c) Laying of marble slabs over bedding mortar and RCC screed.
(d) Filling of joints with white/grey cement with matching
pigment.
501
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
502
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-6.1 DESCRIPTION
The tiles shall be of approved make. These will be of ceramic tiles with
one face glazed and shall be white or coloured as specified in the
schedule of quantities. The thickness used shall be ¼" or 3/8" as
specified.
Unless otherwise specified, tile flooring shall be laid in accordance
with the following specifications.
35-6.2 MATERIALS
(a) Tiles shall conform to the specifications as contained in Section
35-6 for Glazed Tiles.
(b) Mortar shall conform to the specifications as contained in
Section 16-2 for Mortar.
35-6.3.3 PATTERN
The laying of tiles shall be plain, diagonal, or any other specified
pattern.
35-6.3.4 JOINTS
(a) The joints shall not exceed 1/32 inch in thickness. The mortar
oozing out of the joints shall be wiped off immediately with
damp cloth.
503
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-6.3.7 PROTECTION
Flooring shall be allowed to mature undisturbed, and protected from
the effects of weather. It shall be kept wet for at least 7 days after
completion.
35-6.3.8 SURFACE
Surface shall be finished to specified levels. All joints shall be
uniform, parallel and square.
35-6.4 MEASUREMENTS
The measurement of tile flooring shall be by the superficial area. Its
unit of rate shall be 100 sq. ft. or sq.m.
35-6.5 RATE
35-6.5.1 LABOUR RATE
The unit rate shall include:
(a) Watering and cleaning of base in case of ground floors and
scrubbing and washing of the base slabs in case of upper floors.
(b) Laying of bedding mortar over the base.
(c) Laying of tiles in specified mortar over the bedding mortar.
504
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
505
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-7.1 DESCRIPTION
Unless otherwise specified mosaic tile flooring shall be laid in
accordance with the following specifications:
35-7.2 MATERIALS
35-7.2.1 ORDINARY PORTLAND CEMENT
Ordinary Portland Cement shall conform to specification contained in
Section 4.
35-7.2.2 FINE AGGREGATE
Fine aggregate shall conform to Section 10-3 of these specifications.
35-7.2.3 COARSE AGGREGATE
Coarse aggregate shall conform to Section 10-4 of these specifications.
35-7.2.4 WATER
Water shall conform to Section 1 of these specifications.
35-7.2.5 MARBLE CHIPS
Marble chips generally having size of 7 No. & 8 No., or approved size,
colour, grade and quality shall be used.
506
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-7.3.2 WORKSHOP
It is essential that the manufacture of coloured cement floor tiles
should be carried out in a well-constructed and properly ventilated
building which should be free from draught and the direct rays of the
sun. A plant with an output of 90 sq. yds, per day would require
approximately 1500 sq. ft area for manufacturing and stacking the
freshly made tiles; 50' x 30' are good dimensions. To that must be
added the storing room for the finished tiles which should also be free
from draught and direct light.
35-7.3.3 CURING
Curing has a very important bearing on the strength and soundness of
concrete. Tiles should be completely immersed in water as soon as
they are hard enough to be handled safely. (Generally after 6 to 8 hours
of moulding). With a thin product such as a tile, made with semi-dry
concrete, it is practically certain that a very brief total immersion in
water say of 12 hours, will cause the water to soak right through the
tile. After this the tiles should be kept moist resting on their edges in
racks for one week. It is safer to keep the tiles under cover for one
week more before their curing is considered complete.
35-7.3.4 GRINDING
Grinding the mosaic or inlaid tiles is done after thorough curing.
Various types of machines are available for the purpose. Before
polishing, the mosaic or inlaid tiles are levelled off on smoothing and
levelling machine and are retouched with fluid binding cement. They
are then placed in the recesses provided in the revolving table of the
polishing machine. The polishing stone or block (generally a piece of
carborundum) is held in a special holder and is kept in contact with the
tiles by the application of light pressure by the workman; a jet of water
continually plays on the revolving tiles. Polishing starts with a very
coarse type of carborundum stone and finishes with the finest type to
get a good polish.
35-7.3.5 SIZE
The common sizes of tiles are (i) 6"x6" (ii) 8"x8" (iii) 9"x9" and
(iv) 12"x12". The 9"x9" and 12"x12" sizes are used primarily in large
floor areas such as hotels and club lobbies and store rooms. The
smaller sizes are used in bathrooms, kitchen floors and walls.
507
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-7.4.4 JOINTS
No joints shall be more than 1/16 of an inch in thickness. Slabs
projecting over the edges of verandahs or steps shall have their edges
finished with a bull-nosed ending.
35-7.4.5 LAYING
Tiles shall be laid in position on bedding mortar in specified pattern.
The joints shall be filled with specified putty.
35-7.4.6 LEVELS
The surface of tiles when laid shall be perfectly true, level, projected or
sloped.
35-7.5 MEASUREMENTS
The measurement shall be done by the superficial area. The unit of
measurement shall be 100 square feet or m2.
35-7.6 RATE
35-7.6.1 LABOUR RATE
The unit rate shall include:
(a) Washing, scrubbing and cleaning of base (in the case of ground
floor).
(b) Laying of mosaic tiles and filling of joints with specified
mortar including cutting of tiles if required.
(c) Coring and protection of work.
(d) Grinding & polishing.
508
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-8.1 DESCRIPTION
Unless otherwise specified, the conglomerate flooring shall be laid in
accordance with the following specifications.
35-8.2 MATERIALS
(a) Cement Concrete Class-AI
Cement concrete shall conform to the specifications contained
in Section 4.
35-8.3.3 FINISHING
The surface shall be levelled with a wooden trowel. Excessive
trowelling in the early stage shall be avoided. The surface shall be
tested with a straight edge to detect undulations, which, if found, shall
be eliminated. The finer stuff in the concrete which has come to the
surface with the stroking shall be quickly but carefully smoothed with
the steel trowel. When the concrete has hardened sufficiently,
trowelling shall be done with steel trowel. No dry cement or a mixture
of dry cement with sand shall be sprinkled on the surface for hardening
the surface.
35-8.3.4 CURING
The concrete topping shall be cured in accordance with specification
contained in Section 30-13.
509
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-8.4 MEASUREMENTS
The conglomerate floor shall be measured by superficial area. The unit
of measurement shall be 100 square feet or m2.
35-8.5 RATE
35-8.5.1 LABOUR RATE
The unit rate shall include:
(a) Washing, scrubbing and cleaning of base at ground floor.
(b) Dividing into panels mixing, placing, compacting, finishing and
curing of the topping concrete.
(c) Use of all related T&P for carrying out work in accordance
with above specifications.
510
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-9.1 DESCRIPTION
Unless otherwise specified, the conglomerate flooring (two coat work)
shall be laid in accordance with the Specifications contained in Section
35-8 for Conglomerate floor (single coat) except with the following
modifications:
(a) It shall be laid in two layers with a top layer half an inch thick,
wearing surface composed of aggregate (¼" to 3/16") crushed
stone and cement conforming to Specifications contained in
Section 35-10 and a bottom layer of specified thickness.
(b) Unless otherwise specified, the cement concrete for the bottom
layer shall be composed of one cubic foot of cement, 3 cubic
feet of fine aggregate and 6 cubic feet of coarse aggregate by
volume.
(c) Unless otherwise specified, the surface layer shall compose of
one part of cement and two parts of (¼" to 3/16") crushed stone
aggregate by volume.
(d) The bottom layer shall be brought to a level so that top layer
shall have a minimum thickness of half an inch. The bottom
layer shall be thoroughly compacted by tamping but shall not
be finished smooth. While the bottom layer is still plastic, the
top layer shall be placed over it and levelled with a steel float
after light tapping for five minutes.
35-9.3 MEASUREMENTS
The conglomerate floor shall be measured by superficial area. The unit
of measurement shall be 100 square feet or m2.
35-9.4 RATE
35-9.4.1 LABOUR RATE
The unit rate shall include:
(a) Washing, scrubbing and cleaning of base at ground floor.
(b) Dividing into panels mixing, placing, compacting, finishing and
curing of the topping concrete.
511
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
(c) Use of all related T&P for carrying out work in accordance
with above specifications.
512
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-10.1 DESCRIPTION
Unless otherwise specified, terrazzo floor shall be laid in accordance
with the following specifications.
35-10.2 MATERIALS
(a) Marble chips shall be of the approved grade, colour, size and
quality.
(b) Cement shall conform to Section 4 of these specifications. For
laying terrazzo floor. Pigment of specified colour shall be
mixed in white cement wherever required. Quantity of pigment
shall, however, not exceed 12% of the weight of cement.
(c) Fine aggregate shall conform to the Specifications contain in
Section 10-3.
(d) Course aggregate shall conform to the Specifications contain in
Section 10-4.
(e) Water shall conform to the specifications contain in Section 1.
35-10.3.2 PROPORTION
Unless otherwise specified, the cement concrete used for bottom layer
shall be of Class-‘A’, conforming to the Specifications contained in
Section 30 for Cement Concrete. The Terrazzo topping shall consist of
2 parts of marble chips and one part of cement by volume.
35-10.3.3 THICKNESS
The topping shall not be less than 3/8 of an inch thick and shall be laid
mono lithic with the bottom layer of cement concrete (Class‘AI’) of
specified thickness. The total thickness of the topping and cement
concrete shall not be less than I 3/8 inches.
513
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-10.3.7 LAYING
The top course shall be laid over the bottom course of concrete within
36 hours after the bottom course of concrete has been laid. If laying of
top course is delayed by more than the specified time, a slurry of neat
cement shall be brushed on to it immediately before the topping is laid.
The terrazzo mix shall be placed on the bottom concrete and
compacted by tamping.
35-10.3.8 CURING
After laying the top course, the surface shall be covered with damp
hessian cloth and every precaution shall be taken to prevent its being
subjected to the effects of weather. The flooring shall be maintained in
a damp condition till it is fit for grinding.
514
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-10.3.10 FINISHING
After final grinding the floor shall be thoroughly washed. Tartaric Acid
or powder oxalic acid shall be sprinkled over the floor and rubbed with
gunny bags wrapped round rods. The floor shall be allowed to dry and
then more oxalic or tartaric acid shall be rubbed with cloth pads. When
floor is completely dry, the final gloss shall be given by an approved
wax polish.
35-10.4 MEASUREMENTS
The terrazzo floor shall be measured by the superficial area. Its unit of
measurement shall be 100 square feet or m2.
35-10.5 RATE
35-10.5.1 LABOUR RATE
The unit rate shall include
(a) Preparing surface of bottom concrete.
(b) Dividing into panels, mixing, pouring, curing, surface grinding,
final finishing and polishing.
(c) Providing, using tools and plants for carrying out work in
accordance with the above specifications including POL and
electricity consumption charges.
515
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-11.1 DESCRIPTION
Unless otherwise specified dry brick paving shall be done in
accordance with the following specifications.
35-11.2 MATERIALS
(a) Bricks shall conform to Section 6 of these specifications for
clay bricks.
(b) Sand shall conform to Section 10-3 of these specifications for
Fine Aggregate.
(c) Mud mortar shall conform to Section 16-1 of these
specifications for Mud Mortar.
35-11.4 LAYING
Bricks shall be laid dry, on edge or flat in the specified pattern over
half an inch thick mud plaster given on the surface. The joints shall not
exceed one quarter of an inch in thickness. After laying the bricks the
joints shall be sand grouted.
35-11.5 MEASUREMENTS
The measurement of dry brick paving shall be by the superficial area.
Its unit of measurement shall be cft or cubic meter.
35-11.6 RATE
35-11.6.1 LABOUR RATE
It shall include:
(i) Preparation of surface.
(ii) Laying of mud plaster.
(iii) Laying of bricks on mud plaster and grouting with sand.
(iv) Use of all the tools and plants required to carryout work
according to the above specifications.
(v) Sweeping away all surplus sand and cleaning away all debris or
broken bricks.
35-11.6.2 COMPOSITE RATE
The unit rate shall include the cost of brick, mortar and sand supplied
at site of work, in addition to the labour rate detailed in Section 35-
11.6.1.
516
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-12.1 DESCRIPTION
Wooden floor shall be either hollow floor with planking of required
size and thickness fixed on floor bearer frames or wooden block
flooring fixed on concrete bed by bituminous adhesive. All timber
shall conform to Specification contained in Section 12 and shall be
specified species.
35-12.5 PRESERVATIVES
All joists, wall plates, bearers, and the underside of planking shall be
given two coats of hot wood preservative such as solignum, creosote,
or coal tar, as directed by the Engineer-in-charge.
517
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
35-12.7 JOINTS
The planks shall be planed true on one side (on both sides for uncoiled
upper floors), the edges to be planed, rebated or tongued and grooved
as directed by the Engineer-in-charge. Unless otherwise specified, the
edges shall be tongued and grooved, with concealed joints for teak
wood floors, and rebated joints for other floors.
35-12.10 PLANNING
After the floor has been laid, it shall be planed in both directions and
made perfectly smooth. All depressions in the wood, nail holes and all
small defects of every kind, where permitted by the Engineer-in-charge
to remain in the work, shall unless otherwise specified, be filled with
"Beaumontage" or wax used for stopping/filling holes or other defects.
35-12.11 MEASUREMENTS
The measurements of wood flooring shall be done by the superficial
area. The unit of measurement shall be sq.ft/sq.m.
35-12.12 RATE
The unit rate shall include the floor boarding laid and fixed in position
and planned in both directions, provision of brass screws in the case of
teak wood floor where concealed fixing is not employed. Works like
sand papering, oiling, waxing, staining or varnishing are not covered
and shall be paid for separately. The unit rate does not include joists,
wall plates, bearers, beams, rolled steel joists, rails, concrete or
masonry pillars. Payment for these shall be made separately.
518
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
519
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
520
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Fig:6, Squared
521
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Fig:9, Rebated
522
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
523
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
524
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Fig:14, Splayed
Fig:15, Forked
525
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–36
SURFACE RENDERINGS
36-1 GENERAL DEFECTS IN PLASTER
& THEIR REMEDIES
36-1.1 GENERAL
Unless otherwise specified or directed by the Engineer-in-charge the
following measures shall be adopted to remedy defects and faults
incidental to plaster work.
(a) Fine aggregate (sand) shall be clean and free from all
impurities. It shall be washed before use.
(b) Lime shall be properly staked before use.
(c) A proper key shall be provided.
(d) The background shall be kept moist, but excessive moisture
shall be avoided.
(e) Proper curing shall be done to eliminate excessive and rapid
thermal changes.
(f) Each coat shall be allowed to dry before the next is applied.
36-1.2.1 CRACKS
Cracks briefly occur on account of:
(a) Structural defects in building and discontinuity of surface.
(b) Plastering on very wet background.
(c) Old surface not properly prepared.
(d) Over-rapid drying.
(e) Excessive shrinkage of the plaster owing to thick coats and
richer mixes.
526
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-1.5 SCAFFOLDING
The scaffolding for plaster shall always be double.
527
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
(f) Special care has been taken of cornices and moulding sections.
The templates shall be thoroughly checked and compared with
the approved drawing.
(g) All ornamental work is true to design and securely fixed and
bonded.
(h) If Keene's or other hard plaster angles are specified, they have
been duly executed.
(i) In external stucco, rough cast, or pebble-dashing, the coats are
of even thickness and are uniformly laid.
(j) The plastered surface struck with the knuckles does not give
hollow sound, If it rings hollow, it is an indication of
insufficient adhesion between various coats of plaster.
528
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-2.1 DESCRIPTION
This works shall consist of plastering brick work or stone masonry or
concrete with cement sand mortar of specified proportions and
thickness in conformity with lines and dimensions shown on the
drawings and shall conform with these specifications.
36-2.3 MORTAR
Cement sand mortar shall conform to Section 16-2 of these
specifications. The ingredients of mortar shall be proportioned as
mentioned in the BOQ of the contract.
36-2.5 PLASTERING
Unless otherwise specified or directed by the Engineer-in-charge or his
authorized subordinate in writing, wooden screeds three inches wide
and having a thickness equal to the plaster shall be fixed vertically 8
529
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
feet to 10 feet apart to act as gauges and guides in applying the plaster.
The arrises shall then be plastered for a space of four inches on each
side and up to the ceiling, except in case of openings where it shall run
around them. This plaster shall also serve as a guide for thickness etc.
Unless otherwise specified or directed by the Engineer-in-charge all
corners and arrises shall be rounded off to a radius of 3/4 inch only and
no more. This work is included in the unit rate of plastering. The
mortar shall be laid on the wall between the screeds, using a plasterer's
float for the purpose and pressing mortar so that the raked joints are
properly filled. The plaster shall then be finished off with a wooden
straight-edge reaching across the screeds. The straight-edge shall be
worked on the screeds with an upward and sideways motion, two
inches or three inches at a time. Finally the surface shall be finished off
with a plasterer's wooden float. Metal floats shall not be used. The
plaster shall be laid to a true and plumb surface and tested frequently
with a straight-edge and plumb-bob. The straight-edge shall not be less
than 10 feet in length. As the work proceeds, all horizontal lines and
surfaces shall be tested with a level, and all jambs and corners with a
plumb-bob. All mouldings and decorations shall be worked true to
template and shall be neat, clean, level, and parallel, or truely plumb,
as the case may be. Unless otherwise specified, plaster shall not exceed
half an inch in thickness and shall not be less than quarter of an Inch at
the thinnest part.
36-2.6 CURING
The plastered surface shall be protected from the sun, hot winds by wet
screens till it has hardened sufficiently to remain unaffected by the
external application of water. It shall then be watered and kept damp
for a period of at least ten days and allowed to dry as slowly as
possible.
36-2.7 DEFECTS
36-2.8 MEASUREMENTS
Plastering shall be measured by the superficial area, no deduction
being made for the openings of doors or windows of any size or
additions or returns and soffits from any of the two sides. The unit of
measurement shall be 100 sq. ft. or one sq. meter. Ornamental work to
finished and plastered shall be measured and paid separately and their
unit of measurement shall be 1 foot or 1 metre (linear).
530
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-2.9 RATE
The unit rate shall include:
531
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-3.1 DESCRIPTION
The work shall consist of plastering brickwork or stone masonry with
lime cement sand mortar in conformity with lines and dimensions as
shown on the drawing and in accordance with these specifications.
36-3.3 MORTAR
The mortar shall conform to Section 16-4 of these specifications. The
ingredients of mortar shall be proportioned as mentioned in the BOQ
of the contract.
36-3.4 PLASTERING
Unless otherwise specified or directed by the Engineer-in-charge or his
authorized subordinate in writing, wooden screeds three inches wide
and having a thickness equal to the plaster shall be fixed vertically 8
feet to 10 feet apart to act as gauges and guides in applying the plaster.
The arrises shall then be plastered for a space of four inches on each
side and up to the ceiling, except in case of openings where it shall run
around them. This plaster shall also serve as a guide for thickness etc.
Unless otherwise specified or directed by the Engineer-in-charge all
corners and arrises shall be rounded off to a radius of 3/4 inch only and
no more. This work is included in the unit rate of plastering. The
mortar shall be laid on the wall between the screeds, using a plasterer's
float for the purpose and pressing mortar so that the raked joints are
properly filled. The plaster shall then be finished off with a wooden
straight-edge reaching across the screeds. The straight-edge shall be
worked on the screeds with an upward and sideways motion, two
inches or three inches at a time. Finally the surface shall be finished off
with a plasterer's wooden float. Metal floats shall not be used. The
plaster shall be laid to a true and plumb surface and tested frequently
with a straight-edge and plumb-bob. The straight-edge shall not be less
than 10 feet in length. As the work proceeds, all horizontal lines and
surfaces shall be tested with a level, and all jambs and corners with a
plumb-bob. All mouldings and decorations shall be worked true to
template and shall be neat, clean, level, and parallel, or truely plumb,
as the case may be. Unless otherwise specified, plaster shall not exceed
half an inch in thickness and shall not be less than quarter of an Inch at
the thinnest part.
532
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
After completion, plaster shall be kept wet for 10 days and shall be
protected during that period from extreme fluctuations of temperature
and weather.
36-3.6 DEFECTS
36-3.7 MEASUREMENTS
Plastering shall be measured by the superficial area, no deduction
being made for the openings of doors or windows of any size or
additions or returns and soffits from any of the two sides. The unit of
measurement shall be 100 sq. ft. or sq. meter. Ornamental work to
finished and plastered shall be measured and paid separately and their
unit of measurement shall be 1 foot or 1 metre (linear).
36-3.8 RATE
The unit rate shall include:
533
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-4.1 DESCRIPTION
This work shall consist of coloured cement sand plastering and
polishing on brickwork or stone work with coloured cement putty
conforming to the lines and dimensions as shown on the drawing and
in accordance with these specifications.
36-4.2 USE
When it is not required to subsequently paint, distemper or colour-
wash the cement plaster, it shall be finished to the final colour and
polished. Plasterer's putty shall be used for the finishing coat.
36-4.6 MEASUREMENTS
Plastering shall be measured by the superficial area, no deduction
being made for the openings of doors or windows of any size or
additions or returns and soffits from any of the two sides. The unit of
measurement shall be 100 sq. ft. or one sq. meter. Ornamental work to
finished and plastered shall be measured and paid separately and their
unit of measurement shall be 1 foot or 1 metre (linear).
534
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-4.7 RATE
The unit rate shall include:
535
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-5.1 DESCRIPTION
This work shall consist of coloured lime plaster and polishing on
brickwork or stone work with coloured lime putty conforming to the
lines and dimensions as shown on the drawing and in accordance with
these specifications.
36-5.2 USE
When it is not required to subsequently paint, distemper or colour-
wash the lime plaster, it shall be finished to the final colour and
polished. Plasterer's putty shall be used for the finishing coat.
536
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-5.7 MEASUREMENTS
Plastering shall be measured by the superficial area, no deduction
being made for the openings of doors or windows of any size or
additions or returns and soffits from any of the two sides. The unit of
measurement shall be 100 sq. ft. or sq. meter. Ornamental work to
finished and plastered shall be measured and paid separately and their
unit of measurement shall be 1 foot or 1 metre (linear).
36-5.8 RATE
The unit rate shall include:
537
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-6.1 DESCRIPTION
The work shall consist of applying mud plaster on walls, roofs and
floors in conformity with lines and dimension shown on the drawings
and in accordance with these specifications.
36-6.2 MORTAR
Mud mortar shall conform to Section 16-1 of these specifications.
36-6.4 PLASTERING
The arrises shall be plastered for a space of four inches on each side
and up to the ceiling, except in case of openings where it shall run
around them. This plaster shall also serve as a guide for thickness etc.
Unless otherwise specified or directed by the Engineer-in-charge all
corners and arrises shall be rounded off to a radius of ¾ inch only and
no more. This work is included in the unit rate of plastering. The
mortar shall then be spread evenly over the wall so as to be not more
than 3/4 inch thick. After spreading, the mortar shall be floated with a
straight-edge, till the surface is perfectly smooth, level and true. The
plaster shall be laid to a true and plumb surface and tested frequently
with a straight-edge and plumb-bob. The straight-edge shall not be less
than 10 feet in length. As the work proceeds, all horizontal lines and
surfaces shall be tested with a level, and all jambs and corners with a
plumb-bob. All mouldings and decorations shall be worked true to
template and shall be neat, clean, level and parallel or truly plumb as
shown of drawings. Unless otherwise specified, plaster shall not
exceed ¾" in thickness on walls and 1" on floors and roofs. Any cracks
that open out during drying shall be filled with liquid cow-dung.
36-6.5 FINISH
When the surface has dried, it shall be leeped over and finished off
with a trowel or float in the case of walls and roofs. In the case of
538
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
In all other respects, not specified here, this shall conform to the
Sections of 36-1 & 36-2 of these specifications.
36-6.7 MEASUREMENTS
Plastering shall be measured by the superficial area, no deduction
being made for the openings of doors or windows of any size or
additions or returns and soffits from any of the two sides. The unit of
measurement shall be 100 sq. ft. or one sq. meter. Ornamental work to
finished and plastered shall be measured and paid separately and their
unit of measurement shall be 1 foot or 1 metre (linear).
36-6.8 RATE
The unit rate shall include:
539
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-7.1 DESCRIPTION
This specification covers the minimum requirement for full-thickness
(in accordance with table 5, page 547) interior gypsum plastering on
metal, masonry, or monolithic concrete bases designed or prepared to
receive gypsum plaster.
36-7.3 PROTECTION
Plasters and other cementitious materials shall be kept dry until used;
they shall be stored off the ground, under cover, and away from walls
with condensation and other damp surfaces. Metal products shall be
protected, which stored, against rusting
36-7.5 MATERIALS
This shall conform to Section 5 of these specifications.
36-7.5.1 GYPSUM CASTING AND MOLDING PLASTER
This shall conform to ASTM Specification C 59.
540
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
541
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
542
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
543
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
544
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-7.8 APPLICATION
36-7.8.1 GENERAL
Plaster shall be applied by hand or machine as specified herein.
36-7.8.2 PLASTER THICKNESS
36-7.8.2.1 Gypsum plaster shall be applied to the thickness specified in table 5
(page 547). Plaster thickness shall be measured from the face plane of
all plaster bases.
545
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Table 4A
Proportion of Gypsum to Not More than Lime/Aggregate, with Dry and Wet Equivalent
546
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Table 4B
Trowel Finishes of Lime Putty Gaged With Gypsum Gaging
Plaster Proportions
Proportions of Fine Aggregate
Not Less Than Not More Than Per
½ ft3 (0.014 m3) 1 ft3 (0.028 m3) 100 ft3 (45.4 kg)gypsum gauging
or 1/8 ft3 (0.0035 m3) ¼ ft3 (0.007 m3) 1 lb (22.7 kg) dry hydrated lime
or 1 U.S. gal (3.78 L) 2 U.S. gal (7.57 L) 1 ft3 (0.028 m3) lime putty
or 1 pt (0.473 L) 1 pt (0.946 L) 1 U.S. gal (3.78 L) lime putty
Table 5
Thickness of Plaster
Thickness of Plaster Including Finish
Plaster Base
Coat, in. (mm)
Metal plaster base 5/8 (16) min
All other types of plaster base ½ (13) min
Unit masonry 5/8 (16) min
Monolithic concrete surfaces:
Vertical 5/8 (16) min
Horizontal 1/8 (3) to 5/8 (10)
547
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
548
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
(2) Brown coat shall be applied on the rib side of the metal lath, or on
the backside of the scratch coat followed by the brown coat applied
over the face of the scratch coat.
36-7.8.3.6 Studless Solid Partitions (Gypsum Lath and Plaster)
Partitions shall be not less than 2 inch (51mm) thick and shall be three-
coat work on both sides.
36-7.8.3.6.1 Scratch coat shall be applied approximately 3/8 inch (9.5mm) thick
with not less than 3/16" (4.8mm) thickness at any point. The
application shall be started at the side opposite the temporary bracing,
then on the braced side without removing the bracing. The thickness
shall be the same on both sides.
36-7.8.3.6.2 The brown coat shall be applied to the side opposite the bracing after
the scratch coat has set and is partially dry. The bracing shall be
removed when this brown coat has set and is partially dry. Both sides
shall have been brought to 1/16 to 1/8 inch (1.6mm to 3.2mm) of the
required thickness leaving a surface ready to receive a finish coat (see
36-7.8.3.4.2), which will bring the partition to an overall thickness of
not less than 2 inch (51mm).
36-7.8.3.7 Studless Solid Partitions (Multiple-Thickness Gypsum Lath and
Plaster)
Partitions shall be not less than 2 inch (51mm) thick with three coats
on each side. Each side shall be not less than ½ inch (12.7mm) thick.
36-7.8.3.8 Gypsum Lath Ceilings Attached by Clips
Plastered ceiling with clip attached gypsum lath shall be covered with
three-coat work with the scratch coat not less than 3/16 to ¼ inch
(4.8mm to 6.4mm) thick over the face of the gypsum lath. The total
thickness of scratch and brown coats shall be not less than 7/16 inch
(11mm).
549
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
type of float surface used (wood, carpet, cork, rubber, or other) and the
length of time between trowel application and floating (take-up).
36-7.8.4.3.1 The mixes in 36-7.8.4.2.1 and 36-7.8.4.2.2 used for float finish shall be
applied in accordance with 36-7.8.4.3.
36-7.8.4.4 Texture or special finishes shall be applied in accordance with the
printed directions of the manufacturer.
36-7.8.4.5 Job mixed finishes shall be applied in accordance with 36-7.8.4.2 or
36-7.8.4.3. The texture or special finish coat shall reduce the total
thickness by not more than 1/16 inch (1.6mm) while matching the
approved sample as closely as possible.
36-7.8.4.5.1 Special finishes shall not reduce the combined thickness of the base
coat and finish coat to less than that specified in table 5 (page 547).
36-7.8.4.5.2 Acoustical plaster and finish shall be applied in accordance with the
printed directions of the manufacturer.
36-7.9 MEASUREMENT
As per Section 36-2.8 of these specifications.
36-7.10 RATE
The unite rates shall include:
550
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-8 POINTING
36-8.1 DESCRIPTION
This work shall consist of pointing on brick masonry walls, roofs &
floors in accordance with these specifications.
36-8.3 POINTING
551
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
552
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-8.7 CURING
Lime pointed work shall be kept wet for five days and cement pointed
work for 10 days after completion. The work shall be protected during
that period from extreme fluctuations of weather.
36-8.8 MEASUREMENTS
36-8.9 RATE
The unit rate for pointing shall include:
553
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
554
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-9 WHITEWASHING
36-9.1 DESCRIPTION
This work shall consist of whitewashing on plastered and cement
concrete surfaces in accordance with these specifications.
Whitewash shall be prepared from pure fat lime brought to the site of
work in an unslaked condition and in order to slake the lime water
shall be added to it in a tub till the mixture attains the consistency of
cream, and is allowed to rest for 24 to 48 hours. It shall then be
strained through coarse cloth and 115 gm of glue or gum or rice
dissolved in hot water shall be added to each cubic foot of it.
36-9.4 APPLICATION
(a) Whitewash shall be applied with a brush. Each coat shall
consist of four strokes, one in each direction.
(b) Each coat of whitewash shall be allowed to dry and inspected
by the Engineer-in-charge or his authorized subordinate. The
next coat shall not be applied unless the previous one has been
555
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
approved by either of them. A dry coat must not show any sign
of cracking, nor must whitewash come off readily on fingers
when rubbed.
(c) Whitewash, when completed, shall form an opaque coat of
uniform white colour, through which the old work does not
show and shall present a smooth regular surface free from
powdery matter.
36-9.5 MEASUREMENTS
Whitewashing shall be measured by superficial area. The deduction
shall be made for openings of any size from one side only, whether
whitewashing is done on one or two sides. The unit of measurement
shall be 100 square feet of one sq.meter.
36-9.6 RATE
The unit rate shall include:
556
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-10.1 DESCRIPTION
The work shall consist of applying cement wash on the concrete
surface in accordance with these specifications.
Cement wash is simply a thin grout made of Portland cement and water
and of such a consistency that it can be applied with a brush. Fine sand
is sometimes added. This wash may be coloured, if desired, but with
certain tints it is desirable to use white Portland cement. Paints
consisting of two parts of Portland cement to one part of lime are
usually used.
36-10.4 APPLICATION
(a) Cement wash shall be applied with a brush. Each coat shall
consist of four strokes, one in each direction.
(b) Each coat of Cement wash shall be allowed to dry and
inspected by the Engineer-in-charge or his authorized
subordinate. The next coat shall not be applied unless the
previous one has been approved by either of them. A dry coat
must not show any sign of cracking, nor must whitewash come
off readily on fingers when rubbed.
(c) Cement wash, when completed, shall form an opaque coat of
uniform cement colour, through which the old work does not
show and shall present a smooth regular surface free from
powdery matter.
36-10.6 MEASUREMENTS
Whitewashing shall be measured by superficial area. The deduction
shall be made for openings of any size from one side only, whether
557
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-10.7 RATE
The unit rate shall include:
558
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-11.1 DESCRIPTION
The work shall consist of colour washing on the specified surface in
accordance with these specifications.
36-11.4 APPLICATION
(a) New or scraped surface shall be given a coat of whitewash,
prior to colour-wash.
(b) Old surface, when the colour-wash is satisfactory, shall be
given only one new coat of colour-wash.
(c) When replacing one colour with another of a lighter shade, the
old colour shall be thoroughly scraped and a coat of whitewash
given before the new colour is applied.
(d) Each coat of colour-wash shall be allowed to dry and shall be
inspected by the Engineer-in-charge or his authorized
subordinate. The next coat shall not be applied unless the
previous one has been approved by either of them.
(e) The completed wall shall be of u uniform colour, free from
blots, lines or cut shades, and shall present a smooth regular
surface which shall neither crack nor come off readily on
fingures when rubbed.
(f) Each room shall be finished in one operation and work shall not
start in a room so late that it cannot be finished the same day.
559
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-11.6 MEASUREMENTS
Whitewashing shall be measured by superficial area. The deduction
shall be made for openings of any size from one side only, whether
whitewashing is done on one or two sides. The unit of measurement
shall be 100 square feet of one sq.meter.
36-11.7 RATE
The unit rate shall include:
560
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-12.1 DESCRIPTION
The work shall consist of furnishing and applying vinyl emulsion on a
surface in accordance with these specifications.
36-12.2 MATERIALS
Vinyl emulsion manufactured by the approved manufacturers shall be
used.
36-12.4 MIXING
Vinyl emulsion mix shall be prepared strictly in accordance with the
maker's instructions or as directed by the Engineer-in-charge, and the
quantity shall be just sufficient for the day's work.
36-12.5 APPLICATION
(a) Vinyl emulsion shall be applied only with proper brushes. The
brushes shall be washed in hot water after each day’s work and
hung up to dry. Old brushes caked with dry emulsion mix shall
not be allowed to be used on the work.
561
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-12.7 MEASUREMENTS
Whitewashing shall be measured by superficial area. The deduction
shall be made for openings of any size from one side only, whether
whitewashing is done on one or two sides. The unit of measurement
shall be 100 square feet of one sq.meter.
36-12.8 RATE
The unit rate shall include:
36-12.8.1 LABOUR RATE
When only labour rate is to be paid.
(a) The preparation of surface as per Section 36-12.3 of these
specifications.
(b) The provision, erection and removal of scaffolding and ladders
(shot with gunny bags at both ends to prevent damage to the
floor and walls).
(c) The protection of floor, fixed furniture, doors and windows, as
well as all such places and things as are not to be whitewashed.
These places and things shall be protected from all droppings
and slashes of whitewash, if any, and cleaned.
(d) Provision of all tools and brushes required for whitewashing.
36-12.8.2 COMPOSITE RATE
When rate for completed job is to be paid, it includes all items
mentioned in section 36-12.8.1 and cost of all material used at site of
work in whitewashing.
562
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-13.1 DESCRIPTION
The work shall consist of providing, furnishing and applying plastic
emulsion on a surface in accordance with these specifications.
36-13.2 GENERAL
Emulsions consist of a polymer latex, a plasticizer, a stabilizer and
thickening agent, together with colouring pigments. Paints of this kind
are used internally for decorating non-absorbent surfaces such as tone-
plaster, or cement-asbestos sheeting. Occasionally they are used on
wood but not on metal. They are easily applied by brush or roller but
are not suitable for external use. The most commonly used plastic
emulsion paints are polyvinyl acetate (PVA) based; PVA being a
synthetic, resin. They range from matt to oil-gloss finish; the flat and
egg-shell gloss types being best for damp walls since the glossier types
are apt to blister if used in this way. All PVA based paints will resist
alkali attack; they are, however, acid in the liquid state and, may,
therefore, foster the corrosion of iron and steel. For this reason, these
paints should not be used in steel paint kettles. They work easily, are
free from persistent smell while drying and dry rapidly. They are not
suitable, for situation where maximum protective action is required.
The paint in the can will not withstand frost and in this respect
resembles distemper. They can be washed from 3 to 7 days after
application. The best surfaces on which to apply them are brick,
retarded semi-hydrate plaster or renderings, softer surfaces such as un-
gauged lime plaster or smooth hard surfaces such as highly-trowelled
Keene’s cement are likely to cause trouble and special primers should
be used in such cases. Further notes on emulsion paints are given
below:
(a) Paints of this kind should not be applied to soft or friable
surfaces such as old lime plasters or lime washes; even more
care is needed in the preparation of such surfaces than is
necessary with oil-gloss paints. Emulsion paints are not
recommended for use in situations where condensation may
occur such as in kitchens and bathrooms nor on highly
trowelled smooth plasters.
(b) Emulsion paints will not adhere to oily or greasy surfaces.
(c) The use of such paints on difficult surfaces may be facilitated
by the use of a suitable oily primer.
(d) Some emulsion paints are not suitable for external use on
brickwork or renderings although polyvinyl acetate (PVA)
emulsion paints can sometimes be so used in off-white or fawn
563
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-13.3 MATERIALS
Plastic emulsion manufactured by the approved manufacturers shall be
used.
36-13.5 MIXING
Plastic emulsion mix shall be prepared strictly in accordance with the
maker's instructions or as directed by the Engineer-in-charge, and the
quantity shall be just sufficient for the day's work.
564
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
36-13.6 APPLICATION
(a) Plastic emulsion shall be applied only with proper brushes. The
brushes shall be washed in hot water after each day’s work and
hung up to dry. Old brushes caked with dry emulsion mix shall
not be allowed to be used on the work.
(b) Plastic emulsion shall be applied quickly and boldly leaving no
dry edges. The brush shall be dipped in emulsion and stroked
cross-wise on the wall, then immediately stroked up and down
and stopped.
(c) Unless otherwise or directed two men shall work on wall
together, one working from the ceiling downwards as far as he
can reach and the other following him applying the plastic
emulsion from below. No patchy overlap shall be allowed
under any circumstances.
(d) On newly-plastered walls two coats over one coat of priming
shall be applied.
(e) On old walls covered with one or two coats of hard dry
whitewash free from efflorescence or kalar, one coat without
priming coat shall be applied.
(f) The consumption of emulsion should be in accordance with
spreading power as prescribed by the manufacturer.
36-13.8 MEASUREMENTS
Whitewashing shall be measured by superficial area. The deduction
shall be made for openings of any size from one side only, whether
whitewashing is done on one or two sides. The unit of measurement
shall be 100 square feet of one sq.meter.
36-13.9 RATE
The unit rate shall include:
565
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
566
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–37
WOOD WORK
37-1 GENERAL
37-1.1 DESCRIPTION
This work shall consist of converting timber, conforming to Section 12
of these specifications into a desired shape for use in making doors,
windows, roofs, floors, stairs, frames, bridges, centrings, shores, struts
and large gates etc.
37-1.2 GLOSSARY
Woodwork is the process of converting timber into a desired shape and
erecting it into its final position. It is mostly carpenter’s and jointer’s
work.
Apron Lining A board used to form a finish at the edges of
the floor around a stair well.
Architrave The trim to a door, window or other opening.
(Note: Not to be confused with facing.)
Arris A sharp external angle.
Back Lining A thin member closing a jamb or head of a
cased frame, (figure 6 page 611)
Baluster A vertical individual member of a balustrade.
(figure 8 page 612)
Balustrade The infilling between a handrail and a string,
landing or floor. (figure 8 page 612)
Battened and The assembly of this type of shutter is
Ledged Shutter composed of vertically
V-jointed, tongued and grooved battens tied
together by a cross.
Battened, Ledged Same as battened and ledged, but braced
and Braced Shutter against sag.
Bead A rounded moulding, which may have one or
two quirks.
Bead Butt A panel, flush with the framing, finished with a
bead on two opposite edges only (figure-4 page
611).
Bead Flush A panel, flush with the framing, finished with a
bead on all edges (Figure-4 page 611).
Bed Mould A moulding under a window beard or shelf.
Blockings Pieces of timber fixed as stiffeners in the angles
of casings, as in the heads of sash windows,
stairs, etc (figure-5 & 8 page 611 & 612).
567
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
568
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
569
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
570
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
571
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
572
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
573
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
574
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
575
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
576
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-1.3 TIMBER
Unless otherwise specified timber shall conform to Section 12 of these
Specifications. The Engineer-in-charge shall at his option inspect all
logs or sleepers before they are used and may reject any he considers
defective. Timber so rejected shall be removed at once from the site of
work at the cost of contractor.
37-1.4 FINISH
All woodwork shall be neatly and truly finished to the exact
dimensions specified.
37-1.5 JOINTS
Unless otherwise specified, all joints shall be simple tenon and mortise
joints with the end of the tenon exposed to view. All mortise and tenon
joints or scarfs shall fit truly and fully, without filling. Where
specified, in the case of special high class joinery, the end of the tenon
shall not show. Joints shall be painted with specified lead paint before
the frames are put together. Glue shall not be sued in joints which are
exposed to weather, and in such exposed work any hard stopping shall
be done with tight driven plugs.
37-1.8 FIXING
All woodwork shall be fixed in accordance with the drawings or the
instructions of the Engineer-in-charge.
577
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-1.9 WORKMANSHIP
All workmanship shall be of the best type and all joints shall fit
accurately without wedging or filling. After the wood work has been
erected, the contractor shall, if any undue shrinkage or bad
workmanship is discovered, forthwith correct the defect without any
extra charge.
37-1.10 BEARING
All beams and girders shall be bedded on plates with not less than 9
inches bearing. All joists shall bear not less than 4½ inches on wall
plates, and every purling or batten supported on a wall shall have a
bearing in the direction of its length equal to its own depth subject to a
minimum of 4 inches.
37-1.12 PRESERVATIVES
All portions of timber built into or against or close to masonry or
concrete, and all junctions or rafters, purlins, beams and wall plates
shall be given two coats of hot solignum, creosote or other wood
preservative approved by the Engineer-in-charge.
37-1.13 PLANKS
All scantling planks etc. shall be sawn straight and shall have uniform
thickness. They shall be sawn in the direction of the grain and shall
have full measurement from end to end. All planks and scantlings shall
be sawn 1/16 inch in excess of actual measurement to allow planing.
They shall be supplied with straight square edge, or rebated, ploughed,
tongued or dwelled, as may be directed.
578
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-1.17 MEASUREMENTS
The measurement of woodwork or planking shall be the net
measurement after fixing in position. No allowance is to be made for
waste, overlaps, rebates or the dimensions supplied beyond those
specified. The length of each piece, however, shall be taken overall so
as to include projections for tenons or scarfs. The unit of measurement
shall be square feet or square meter.
37-1.18 RATE
37-1.18.1 LABOUR RATE
The unit rate for wood work shall include the cost of labour involved
to carry out wood work according to above specifications, fixed in
position and with the exposed arrises finished with a bead or bead and
quirk as specified. The rate shall further include the cost of labour
employed for following operations:
(a) Fixing all spikes, mails, screws, glue.
(b) Bevelled heading joints to boarding.
(c) Boring for bolts as required.
(d) Cleaning of wrought face.
(e) Cramping and wedging.
(f) Fixing with hardwood or male bamboo pins, nails, spikes, hoop
iron and wire in any position.
(g) Halving, tabling, lapping, notching, framing, straight, splay,
circular or birds-mouth cutting, splayed and bevelled ends, and
mitres, fair or returned ends, as required.
(h) Punching and clenching nails.
(i) Treating plugs with wood preservative.
(j) All notchings, firrings, or squarings to ballies, necessary to
obtain level bedding, boarding or fixings.
(k) Rebates and chambers to door and window frames where
required.
The rebate shall further include the use of all tools, plant and
scaffolding, staging and ladders, etc., where necessary.
Note – Sometimes timber in the form of log or wrought (wholly or
partially) is supplied to the contractor from the Government stores or
from a dismantled building. In such cases the cost of timber so
supplied shall be deducted from the cost of the finished work. Where
the contractor’s schedule contains no rate for similar materials the cost
579
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
580
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-2.1 DESCRIPTION
This work shall consist of making doors and windows from the
specified kind of timber in accordance with these specifications.
37-2.2 MATERIALS
Unless otherwise specified timber shall conform to section 12 of these
specification.
37-2.3 WORKMANSHIP
Unless otherwise specified the workmanship of doors and windows
shall conform to Section 37-1.8 of these specifications for Wood Work
(General) in all respects, except those specified hereunder.
37-2.7 REBATES
Chowkats shall have a rebate cut to receive the leaves. The rebate shall
be ½ inch deep and its width shall be equal to the thickness of the leaf.
The other side shall be finished with a bead and quirk, or other simple
moulding, unless wire gauze is to be fitted. Where the plaster butts
581
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
against the chowkat ½ inch deep rebate with a slight cut back shall be
given to serve as key to the plaster.
582
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-2.12 SEASONING
All door and window leaves shall be cut out and framed together, as
soon as possible after the commencement of the work, and stacked in
the shade to season. They shall not be wedged and glued for four
months where possible and where the contract time permits. If it is not
possible, they shall be wedged and glued just prior to being hung.
Before final gluing, all portions in which defects appear shall be
replaced.
37-2.14 GLUING
All tenons at the final aassembly of the doors shall be glued and
wedged at top and bottom of the tenon with glued wedges.
Immediately after gluing, the frames shall be tightly clamped and so
left till the glue has set.
37-2.15 HINGES
Unless otherwise specified, leaves shall be hung on hinges of the size
and the number specified in table 1 (page 605). These hinges are to be
of an approved type and quality. They shall be counter sunk into the
chowkat as well as in the leaf; the recesses being cut to the exact size
and depth of the hinge, no subsequent packing shall be allowed. Two
inch screws shall be used with 5 inches to 6 inches hinges and 1 ½
inches for smaller sizes.
37-2.16 FITTINGS
The contractor shall deposit in the office of the Engineer-in-charge one
sample of each fitting to be used in the work. Unless otherwise
specified, fittings shall be of the number, size and type given in table 1
(page 605).
583
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-2.18 SCREWS
Screws of such diameter shall be used as fill completely the holes and
cups in the fittings which they secure, and shall be oiled before being
inserted. Unless the head can be counter-sunk flush with the fittings,
round headed screws shall be used. Brass fittings of specified type
shall be secured with brass screws.
37-2.19 CHOCKS
Hinged chocks shall invariably be fitted to all doors and windows to
keep them open. Chocks shall be of hardwood and swung on 3 inches
butt hinges and shall act on a sheet metal protector fixed to the door
stile.
37-2.20 STOPS
Wooden stops of a size suitable for the leaf concerned shall be fixed to
the door or window chowkats to prevent the leaf from damaging the
plaster of the jamb when fully opened.
37-2.21 MEASUREMENTS
The measurement of doors and windows shall be done by the
superficial area of the clear opening in brickwork or masonry. In case
of circular or other similar joinery, measurement shall be taken of the
net area. In the absence of any special rate being paid, measurement
shall be taken of the least squares or rectangles to contain the opening
in question. In case of double doors the superficial area of chowkat
shall be included in one door only.
37-2.22 RATE
37-2.22.1 LABOUR RATE
(a) The unit rate shall include the cost of labour involved in
making and erecting doors and windows of the specified sizes
complete in all respects, with fittings and furniture according to
above specifications in specified places.
(b) The rate shall also include the use of ladders, support, staging
and scaffolding for executing woodwork according to above
specifications.
584
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
(c) The rate shall further include the cost of labour involved in
applying two coats of wood preservatives on the chowkats.
37-2.22.2 COMPOSITE RATE
The unit rate shall include the cost of all materials supplied at site in
addition to the labour rate as detailed in Section 37-2.22.1.
585
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-3.1 DESCRIPTION
This work shall consist of making panelled doors and windows
conforming to figure 1 to 7 (page 610 to 612).
37-3.2 TIMBER
Unless otherwise specified timber (wood) shall conform to Section 12
of these specifications.
37-3.3 DIMENSIONS
Unless otherwise specified the dimensions of doors and windows shall
be as shown on the approved drawing.
37-3.6 PANELS
(a) Panels shall be made of solid wood or hard board or water-
resistant plywood having both sides properly finished. They
shall be truly cut and framed into rebates to a depth not less
586
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-3.8 GLAZING
All glazing shall be done in accordance with the Section 37-12 of these
specifications. If specified, the doors and windows of bedroom and
bathroom shall be glazed with blind glass up to full eye level. The
glass panels of appropriate sizes shall be fitted into (3/8 inch) rebates
and shall be retained in position with a thin layer of putty which shall
be covered with wood beading.
37-3.9 MEASUREMENTS
The measurement shall be done by the superficial area of the clear
opening in brickwork or masonry. In case of circular or other similar
joinery, measurement shall be taken of the net area. In the absence of
any special rate being paid, measurement shall be taken of the least
squares or rectangles to contain the opening in question. In case of
double doors the superficial area of chowkat shall be included in one
door only.
37-3.10 RATE
37-3.10.1 LABOUR RATE
(a) The unit rate shall include the cost of labour involved in
making and erecting doors and windows of the specified sizes
complete in all respects, with fittings and furniture according to
above specifications in specified places.
(b) The rate shall also include the use of ladders, support, staging
and scaffolding for executing woodwork according to above
specifications.
587
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
(c) The rate shall further include the cost of labour involved in
applying two coats of wood preservatives on the chowkats.
37-3.10.2 COMPOSITE RATE
The unit rate shall include the cost of all materials supplied at site in
addition to the labour rate as detailed in Section 37-3.10.1.
588
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-4.1 DESCRIPTION
This work shall consist of making doors and windows in accordance
with these specifications.
37-4.2 TIMBER
Unless otherwise specified timber (wood) shall conform to Section 12
of these specifications.
37-4.5 BATTENS
Battens shall butt into rebates in the top (or frieze) rail and the bottom
rail and shall pass over the braes and the lock rail. Battens shall not be
more than 5 inches wide and shall all be parallel and uniform in width.
The joints shall be ploughed and tongued and finished with a bead and
quirk on the outside. Battens shall be secured with two screws at each
end and with one screw over each brace and the lock rail.
589
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-4.7 MEASUREMENTS
The measurement shall be done by the superficial area of the clear
opening in brickwork or masonry. In case of circular or other similar
joinery, measurement shall be taken of the net area. In the absence of
any special rate being paid, measurement shall be taken of the least
squares or rectangles to contain the opening in question. In case of
double doors the superficial area of chowkat shall be included in one
door only.
37-4.8 RATE
37-4.8.1 LABOUR RATE
(a) The unit rate shall include the cost of labour involved in
making and erecting doors and windows of the specified sizes
complete in all respects, with fittings and furniture according to
above specifications in specified places.
(b) The rate shall also include the use of ladders, support, staging
and scaffolding for executing woodwork according to above
specifications.
(c) The rate shall further include the cost of labour involved in
applying two coats of wood preservatives on the chowkats.
37-4.8.2 COMPOSITE RATE
The unit rate shall include the cost of all materials supplied at site in
addition to the labour rate as detailed in Section 37-4.8.1.
590
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-5.1 DESCRIPTION
This work shall consist of making wooden ledged & braced doors and
windows in accordance with these specifications.
37-5.2 TIMBER
Unless otherwise specified timber (wood) shall conform to Section 12
of these specifications.
37-5.5 HANGING
The chowkat shall be rebated to a depth equal to the full thickness of
doors, i.e. the battens plus ledges. The doors shall be hung with the
battens inside and the ledges outside. Hinges shall be fixed to the
ledges.
591
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-5.7 MEASUREMENTS
The measurement shall be done by the superficial area of the clear
opening in brickwork or masonry. In case of circular or other similar
joinery, measurement shall be taken of the net area. In the absence of
any special rate being paid, measurement shall be taken of the least
squares or rectangles to contain the opening in question. In case of
double doors the superficial area of chowkat shall be included in one
door only.
37-5.8 RATE
37-5.8.1 LABOUR RATE
(a) The unit rate shall include the cost of labour involved in
making and erecting doors and windows of the specified sizes
complete in all respects, with fittings and furniture according to
above specifications in specified places.
(b) The rate shall also include the use of ladders, support, staging
and scaffolding for executing woodwork according to above
specifications.
(c) The rate shall further include the cost of labour involved in
applying two coats of wood preservatives on the chowkats.
37-5.8.2 COMPOSITE RATE
The unit rate shall include the cost of all materials supplied at site in
addition to the labour rate as detailed in Section 37-5.8.1.
592
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-6.1 DESCRIPTION
This work shall consist of making ledged doors and windows in
accordance with these specifications.
37-6.2 TIMBER
Unless otherwise specified timber (wood) shall conform to Section 12
of these specifications.
37-6.4 ERECTION
Country doors shall be hung on pivot with the battens outside and
ledges inside.
37-6.6 MEASUREMENTS
The measurement shall be done by the superficial area of the clear
opening in brickwork or masonry. In case of circular or other similar
joinery, measurement shall be taken of the net area. In the absence of
any special rate being paid, measurement shall be taken of the least
squares or rectangles to contain the opening in question. In case of
double doors the superficial area of chowkat shall be included in one
door only.
593
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-6.7 RATE
37-6.7.1 LABOUR RATE
(a) The unit rate shall include the cost of labour involved in
making and erecting doors and windows of the specified sizes
complete in all respects, with fittings and furniture according to
above specifications in specified places.
(b) The rate shall also include the use of ladders, support, staging
and scaffolding for executing woodwork according to above
specifications.
(c) The rate shall further include the cost of labour involved in
applying two coats of wood preservatives on the chowkats.
37-6.7.2 COMPOSITE RATE
The unit rate shall include the cost of all materials supplied at site in
addition to the labour rate as detailed in Section 37-6.7.1.
594
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-7.1 DESCRIPTION
This work shall consist of making wooden clerestory windows in
accordance with these specifications.
37-7.2 TIMBER
Unless otherwise specified timber (wood) shall conform to Section 12
of these specifications.
37-7.3 CHOWKATS
Unless otherwise specified the chowkets of clerestory windows shall
be so fixed as to project 3/8 inch from the inner face of the wall.
37-7.4 CLEATS
Unless other wise specified brass cleats of the slanting single button
type approved by the Engineer-in-charge shall be fixed by two brass
screws to the polished wooden teak blocks with chamfered edges. The
wooden blocks shall be 2"x3 ½"x1/4" and shall be firmly fixed to the
wall by means of plugs and screws of an approved type.
37-7.5 LEAVES
The leaves shall be hung 1 inch off center so as to take them self-
closing. In order to open them a cord (stout, non-twisting picture cord)
shall be provided with a hard wood weight at one end (to keep the cord
in position over the cleat).
37-7.7 MEASUREMENTS
The measurement shall be done by the superficial area of the clear
opening in brickwork or masonry. In case of circular or other similar
joinery, measurement shall be taken of the net area. In the absence of
any special rate being paid, measurement shall be taken of the least
squares or rectangles to contain the opening in question. In case of
595
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-7.8 RATE
37-7.8.1 LABOUR RATE
(a) The unit rate shall include the cost of labour involved in
making and erecting doors and windows of the specified sizes
complete in all respects, with fittings and furniture according to
above specifications in specified places.
(b) The rate shall also include the use of ladders, support, staging
and scaffolding for executing woodwork according to above
specifications.
(c) The rate shall further include the cost of labour involved in
applying two coats of wood preservatives on the chowkats.
37-7.8.2 COMPOSITE RATE
The unit rate shall include the cost of all materials supplied at site in
addition to the labour rate as detailed in Section 37-7.8.1.
596
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-8.1 DESCRIPTION
This work shall consist of making wire gauzed doors in accordance
with these specifications.
37-8.2 TIMBER
Unless otherwise specified timber (wood) shall conform to Section 12
of these specifications.
37-8.3 MATERIAL
Unless otherwise specified leaves of wire gauze doors shall be made
from deodar, irrespective of the wood used in making the chowkats or
the other leaves hung from the same chowkat.
37-8.3.1 CHOWKAT
Wire gauzed doors shall normally be hung on the same chowkat as
other doors, and the rate shall include the provision of extra depth in
the chowkat to take the rebate for the wire gauze leaf. Where wire
gauze doors are hung on a separate chowkat a special rate shall be
settled.
37-8.3.2 WIRE GAUZE
Unless other wise specified wire gauze shall be of best quality and
uniformly woven wire webbing 12x12 meshes to squarer inch made
from 22 gauge galvanized iron wire. All wire gauze panels shall be in
one piece, no joints being allowed in the gauze.
37-8.4 FIXING
Wire gauze shall be fixed to the frame of the leaf after being stretched
from out to out o rebate and nailed down taut by nails spaced at not
more than 2 inches and then fixed by a fillet of ¾ inch x ¾ inch
screwed into a rebate of that size. The screws shall not be less then 1¼
inches in length, nor spaced farther than 9 inches. All exposed arrises
of the fillet shall be finished with a small neat mould.
597
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-8.9 MEASUREMENTS
The measurement of doors shall be done by the superficial area of the
clear opening in brickwork or masonry. In case of circular or other
similar joinery, measurement shall be taken of the net area. In the
absence of any special rate being paid, measurement shall be taken of
the least squares or rectangles to contain the opening in question. In
case of double doors the superficial area of chowkat shall be included
in one door only.
37-8.10 RATE
37-8.10.1 LABOUR RATE
(a) The unit rate shall include the cost of labour involved in
making and erecting doors and windows of the specified sizes
complete in all respects, with fittings and furniture according to
above specifications in specified places.
(b) The rate shall also include the use of ladders, support, staging
and scaffolding for executing woodwork according to above
specifications.
(c) The rate shall further include the cost of labour involved in
applying two coats of wood preservatives on the chowkats.
37-8.10.2 COMPOSITE RATE
The unit rate shall include the cost of all materials supplied at site in
addition to the labour rate as detailed in Section 37-8.10.1.
598
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
(c) Double hung wire gauze windows shall close flush with the
chowkat without the meeting stiles projecting in any way.
599
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
(b) The cost of the chowkat shall be included in the rate, the
measurement being out to out of chowkat.
600
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-11.1 DESCRIPTION
This work shall consist of fixed wire gauze in accordance with these
specifications.
601
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-12 GLAZING
37-12.1 DESCRIPTION
This work shall consist of glazing in accordance with these
specifications.
602
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
603
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
37-12.10 MEASUREMENTS
In measuring glazier’s work all fractional parts under half an inch shall
be omitted and all above that taken as one inch. Curved or irregularly
shaped pieces shall be measured as the least rectangle from which that
can be cut. Measurement shall be made net from inside to inside of
rebate. The unit of measurement shall be one square foot of one square
meter.
37-12.11 RATE
37-12.11.1 LABOUR RATE
The unit rate shall include the cost of labour involved in carrying out
glazing in accordance with above specifications. It shall also include
provision of all tools and plant required for glazing. It shall further
include removal of all ladders, scaffoldings, staging and supports
required for glazing.
37-12.11.2 COMPOSITE RATE
The unit rate shall include cost of all materials required for glazing
supplied at site of work in addition to the labour rate as detailed in
Section 37-12.11.1.
604
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
TABLE NO. 1
Size of chowkat
Width of styles
master style or
Hinged chocks
Lock or freize
Top of master
rails ledges or
Top of under
Thickness of
Handles (u)
bottom rail
Door stops
braces (h)
s of type
Batten of
Line No.
leaves
style
style
Lin of doors
size
rail
(e)
Remarks.
No. and
windows
(a)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
GLAZED OR
PARTLY
GLAZED
FRAMED
DOORS(Panelled
or battened).
1. Double 3"x4½" 4 1¾" 3½" 6-4" 1-9" 1-9" 1-9" 6"-p 3-6" 2-4" 2-6" 1 a. Dimensions given are
upto 4"x7" out toout of the chowkat
containing the leaves
except where marked (a)
2. Double 3½"x 6 2" 4" 6-5" 1-(0) 1-9" 1-(0) 8"-p 3-8" 2-6" 2-6" 2 Where the dimensions of
exceeding 4½ " each leaf is given
4"x7" up
5"x8"
3 Double 3½"x5" 6 2" 4½" 6-5" 1-(0) 1-12" 1-(0) 10"-p 3- 2-9" 2- 3 b.No.chowkat doors
exceeding 10" 12"
5"x8"
4. Single upto 3"x4½" 4 1¾" 4" 3-5" 1-9" 1-9" : 8"-q 2-6" 1-4" 1-6" 4 Will fit into rebate in the
3"x6 ½ " walls and lintel.
5. Single upto 3"x4½" 4 2" 4½" 3-5" 1-(0) 1-9" : 10"-q 2-6" 1-6" 1-8" 5 c.Dimension given is for
3”x6 ½ " a chowkat carrying two
sets of leaves.
605
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
FRAMED DOORS
PANELLED OR
BATTENED
6. Double 3"x4½" 4 1¾" 4" 6-4" 2-9" 2-9" 2-9" : 3-5" 2-4" 2-6" 6. d. Chowkat to be the
upto 4"x7" same as for main door or
window.
7. Double 3½"x 6 2" 4½" 6-5" 2-(0) 2-9" 2-(0) : 3-8" 2-6" 2-8" 7. e. Number to be
exceeding 4½" increased by 2;
4"x7" upto
5"x8"
8. Double 3½"x5" 6 2" 5" 6-6" 2-(0) 2-12" 2-(0) : 3- 2-8" 2- 8 If there is no sill.
exceeding 10" 12"
5"x8"
9 Single upto 3"x4½" 4 1¾" 4" 3-5" 1-9" 1-9" : 1-9" 2-6" 1-4" 1-6" 9 f.1½" deodar ledges and
3"x6 ½" braces
10. Single 3"x4½" 4 2" 4½" 3-5" 1-(0) 1-9" : 1-9" 2-6" 1-6" 1-8" 10 And 1 inch battens.
exceeding
3"x6 ½ "
11 Garrage (b) - 2½" 6" 6- : : : 14"-p (t) (t) : 11 g.1 ½ " ledges and
doors : f 18"i braces, 1 inch battens.
LEDGED AND BRACED
DOORS.
12. Double 5"x4½" 4 2½" 4" 6- 1-9" 1-9" 1-9" 6"-p. 3-9" 2-4" 2-6" 12 h.(i) Meeting styles may
upto 4"x7" g. 8"(k) be 3 quarter of the
dimensions given
13 Double 3½"x 6 2½" : 6- 1-12" 1-9" 1- 8"-p 3-5" 2-4" 2-6" 13 ii) For doors upto
exceeding 4½" g. 10" 12" 7",8"and above 8" in
4"x7" (k) height the lockrails
should be 6",7"and wide,
respectively and the
bottom rails 8",9"and 10"
wide respectively.
606
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
14 Single upto 3"x4½" 4 2¼" 4" 3- 1-9" 1-9" : 8"-q 2-6" 1-4" 1-6" 14
3"x6 ½ " 8"(k)
15. Single 3"x4½" 6 2¼" 4½" 3- 1-12" 1-9" : 8"-q. 2-6" 1-4" 1-6" 15
exceeding g. 10"
3"x6 ½ " (k)
LEDGED DOORS AND
COUNTRY DOORS.
16. Double all 3½"x 4 2¼" 4" 6-8" 1-® : : 1-(R) : : : 16 i. Strap hinges hung on 1
sizes: 4½" g. (k) inh diameter paintles
fixed to hold fasts which
are embeddedin cement
concrete blocks let in to
the wall.
17. Single all 3½"x 4 2¼" 4" 3- : : : 2-(R) : : : 17
sizeas 4½" 10"
(k)
WIRE GAUZED DOORS. k.Cross garnet or “T”
hinges-dimension given
is the length of the strap.
18 Double 3"x5" : 1 ½ 4" 4-5" 1-9" 1-9" : : 2-8" 2-4" : 18 l.Single acting spring
upto 4"x7" (c) " (l) hinges.
19 Double 3½"x : 1¾" 4½" 6-5" 1-(0) 1-(0) : : 2-8" 2-5" : 19 m.Two double action
exceeding 5½" (c) (l) spring hinges per leaf; no
4"x7" blanks.
20. Single upto 3"x5" : 1½" 4" 2-5" : : : 1-4" 1-8" 1-4" : 22 o.Length to be such that
3"x6 ½ " (c) (1) the bolt is 6 feet 3 inch
from the floor.
21 Single 3½"x : 1¾" 4½" 3-5" : : : 1-4" 1-8" 1-5" : 21 p.Black japanned
exceeding 5½ " (c) (l) wrought steel safety hasp
3"x6 ½ " (strap convering up
fixing screws).
607
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
SWING DOORS ALL q. Galvanized iron safety
VARIETIES door bolt with staple for
padlock.
22 Size of leaf 3"x4½" 4 1½" 4" 2-4" : : : : : : : 22 r. Good quality
upto 3"x6 (m.) galvanized iron or
½ "(a) japanned chain and
staple.
23. Size of leaf 3"x4½" 4 1½" 4" 2-4" : : : : : : : 23 s. Non-twist coloured
exceeding (m.) cord with wooden
3"x6 ½ weight; also brass cleat
"(a) on wooden shield fixed
to the wall
WINDOWS : t. Two 24" tower bolts
fitted to the bottom of
styles and working in
eyes fixed to door stops,
fixed in the floor.
24 Glazed 3"x3½" 4 1½" 2¾" 4-4" 1-(0) 1-4" 1-(0) : 2-5" 2-4" 2-5" 24 u. Handles to be of best
double pressed steel, black
upto 3"x5" japlanned. Dimensions
given are overall
25 Glazed 3"x4" 4 1¾" 2¾" 4-4" 1-(0) 1-6" 1-(0) : 2-6" 2-4" 2-5" 25
double
exceeding
3"x5" upto
4"x5"
26 Glazed 3"x4½" 4 2" 3" 4-5" 1-(0) 1-9" 1-(0) : 2-8" 2-5" 2-6" 26
double
exceeding
4"x5"
27 Glazed 3"x3½" 4 1½" 3" 2-4" 1-(0) 1-4" : : 1-8" 1-4" 1-5" 27
single upto
2"x5"
608
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
28 Glazed 3"x4" 4 1¾" 3" 2-5" 1-(0) 1-6" : : 1-8" 1-4" 1-5" 28
single
exceeding
2"x5"
29 Fanlights (d) 2 1½" 2½"x 2-4" : 2-4" : : 1-8" : : 29
3"
30 Clerestory 3"x3" 2 1½" 3" Poin (s) : : : : : : 30
windows t
31 Battened 3"x4" 4 2¼" 3" 2-8" : : : 1-(R) : : : 31
double all g (k)
sizes
32 Battened 3"x4" 4 3¼" 3" 2-8" : : : 1-(R) : : : 32
single all g (k)
size
33 Wire 3"x4¾" : 1½" 3" 2-4" 1-(0) 1-4" : : L: : : 33
gauzed (c)
upto
2"x5"(a)
34 Wire 3"x5" : 1½" 3½" 2-4" 1-(0) 1-4" : : : : : 34
gauzed
exceeding
2"x5"(a)
35 Wire 2"x2½" : 1½" 2½" 2-4" : 2-3" : : 1-4" : : 35
gauzed
shutters to
C.S.
windows
609
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Dowel Joint
Fig:2, Tongued and Grooved Joint
610
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
611
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
612
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
613
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
614
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
615
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
616
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Fig:18
617
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Fig:19
618
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
619
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
620
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Fig:25
621
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
622
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–38
38-1.1 DESCRIPTION
This work shall consist of furnishing and application of paints, varnish
and other protection to the surface of wood and metal in accordance
with these specifications.
38-1.2 GLOSSARY
By painting is meant the application of paint, varnish, enamel and
other protective coating in a liquid form to the surface of wood, metal,
brick, or other materials to form a thin coating or film which solidifies
and sticks to the surface.
Preparation of Assuming the wood to be properly seasoned.
wooden surface The surface to be painted is prepared by
carrying out operations of rubbing with fine
grade sand paper, knotting, priming and
stopping.
Rubbing
Rubbing is continued till the surface becomes
perfectly smooth.
Knotting
Knotting is done before the application of a
priming coat to cover all knots in wood so as to
prevent any exudation of resin or any mark
from showing, through the three common
methods of knotting: (i) Lime knotting (ii)
Ordinary size knotting, and (iii) Patent
knotting. Knots in deodar or other resinous
woods are painted over with hot lime and
scraped off after 24 hours.
Priming
Priming coat is the first coat applied to fill the
pores of wood and prepare a smooth base for
the subsequent painting.
Stopping
This mean the filling up of nail holes, cracks
and other inequalities to level the surface.
French polish It is a spirit varnish applied to the prepared
wood surface with a polishing pad and soft
cloth and not with a brush, with quick and light
623
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
624
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
625
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
626
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
627
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
628
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
629
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-1.3 WEATHER
Unless otherwise specified, no painting shall be done during wet,
foggy or dusty weather or in the direct rays of the hot sun.
630
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-1.7 PAINT
Paint shall be of an approved make and quality.
38-1.8 PAINTING
(a) Paint shall be applied with proper brushes of approved quality
or spraying machine as specified.
(b) Paint shall be constantly stirred, while it is being applied. It
shall be stirred with a smooth stick and under no circumstances
with a brush.
(c) When more than one coat has to be given, every coat must be
completely dry, rubbed and all dust removed before the next is
applied.
(d) Each coat shall differ slightly in tint from the preceding one, to
distinguish quickly between each coat. The last coat shall be of
the tint required for the finished work.
(e) Each coat shall be approved by the Engineer-in-charge before
the next is applied.
(f) All coats shall be applied evenly and properly, so that the work
does not show any hair or brush marks, or drops of paints. The
method of crossing and laying off shall be normally applied,
the latter in the direction of grains in the case of wood work.
(g) Paint, when not in use, shall be kept away from the air. The
surface of the kegs of ground and mixed paints which have
been partly used shall be covered with water.
38-1.9 MEASUREMENTS
Painting and varnishing shall be measured by superficial area. The unit
of measurement shall be 100 square feet or one square meter. Moulded
work of all kinds, unless otherwise specified, shall be measured by
running the tape over and into all elevations and depressions. In the
case of other classes of work painted on both sides the flat area of the
surface on one side, including glazing and chowkat, shall be multiplied
by the factors given below to arrive at the correct measurement of both
sides for the purpose of making payment.
(a) Panelled or battened doors and windows 2 times
(b) Glazed or partly glazed doors or windows 2 times
(c) Plate glass windows (large glazed area) 1 time
(d) Wire guaze doors or windows 1 time
(e) Trellis work 2 times
631
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-1.10 RATE
38-1.10.1 LABOUR RATE
The unit rate shall include the cost of cleaning, preparing and painting
the surface according to the above specifications or any other
specifications specially included in the contract. It shall further include
the cost of providing, using and removing scaffoldings, supports,
ladders, shot with gunny bags at both ends, brushes or spraying
machines of approved type and any other tool or plant required for
doing painting as per above specifications and removal with turpentine
or other approved methods of all defects from the painted surface to
leave it perfect in every respect. It shall further include the cost of all
allied operations like the removal of stains, smears, splashes and
droppings on the walls, floors, glazing, furniture and other places.
38-1.10.2 COMPOSITE RATE
The unit rate shall include the cost of supplying paints of approved
quality, paint remover in case of painting old work and all other
material required for doing painting as per above specifications at site
of work in addition to the labour rate as detailed in Section 38-1.10.1.
632
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-2.1 DESCRIPTION
This work shall cover painting the new woodwork in accordance with
these specifications.
38-2.3 PAINT
Paint shall be of an approved make and quality.
38-2.3.1 PRIMING OR FIRST COAT OF PAINT
Woodwork shall be properly primed before being fixed in position. In
the absence of approved ready made priming paint it shall be prepared
by mixing the following ingredients:
(a) For inside work (except in white and very pale shade):
(i) White lead 10 lbs
(ii) Red lead ¼ lbs
(iii) Boiled linseed oil 4 pints
(iv) Raw linseed oil 2 pints
(v) Turpentine 1 pint
633
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-2.5 MEASUREMENTS
Painting shall be measured by superficial area. The unit of
measurement shall be 100 square feet or one square meter. Moulded
work of all kinds, unless otherwise specified, shall be measured by
running the tape over and into all elevations and depressions. In the
case of other classes of work painted on both sides the flat area of the
surface on one side, including glazing and chowkat, shall be multiplied
by the factors given below to arrive at the correct measurement of both
sides for the purpose of making payment.
(a) Panelled or battened doors and windows 2 times
(b) Glazed or partly glazed doors or windows 2 times
(c) Plate glass windows (large glazed area) 1 time
(d) Wire guaze doors or windows 1 time
(e) Trellis work 2 times
(f) Grated doors and windows and other grating 1 time
634
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-2.6 RATE
38-2.6.1 LABOUR RATE
The unit rate shall include the cost of cleaning, preparing and painting
the surface according to the above specifications or any other
specifications specially included in the contract. It shall further include
the cost of providing, using and removing scaffoldings, supports,
ladders, shot with gunny bags at both ends, brushes or spraying
machines of approved type and any other tool or plant required for
doing painting as per above specifications and removal with turpentine
or other approved methods of all defects from the painted surface to
leave it perfect in every respect. It shall further include the cost of all
allied operations like the removal of stains, smears, splashes and
droppings on the walls, floors, glazing, furniture and other places.
38-2.6.2 COMPOSITE RATE
The unit rate shall include the cost of supplying paints of approved
quality, paint remover in case of painting old work and all other
material required for doing painting as per above specifications at site
of work in addition to the labour rate as detailed in Section 38-2.6.1.
635
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-3.1 DESCRIPTION
This work shall cover repainting of wooden surface in accordance with
these specifications.
636
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-3.3 PAINT
Paint shall be of an approved make and quality.
38-3.4 PAINTING
(a) After preparing and treating the surface, it shall be painted
according to Section 38-2 of these specifications for “Painting
New Wood Work”.
(b) If old paint is completely removed the cost of removal is not to
be included in the rate for first coat, but shall be payable
separately.
(c) If old paint is firm and is not removed completely but the
surface is only rubbed and treated, the rate for the first coat of
paint shall include the cost of treatment also.
637
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-3.6 MEASUREMENTS
Painting shall be measured by superficial area. The unit of
measurement shall be 100 square feet or one square meter. Moulded
work of all kinds, unless otherwise specified, shall be measured by
running the tape over and into all elevations and depressions. In the
case of other classes of work painted on both sides the flat area of the
surface on one side, including glazing and chowkat, shall be multiplied
by the factors given below to arrive at the correct measurement of both
sides for the purpose of making payment.
(a) Panelled or battened doors and windows 2 times
(b) Glazed or partly glazed doors or windows 2 times
(c) Plate glass windows (large glazed area) 1 time
(d) Wire guaze doors or windows 1 time
(e) Trellis work 2 times
(f) Grated doors and windows and other grating 1 time
(g) Palisade fencing 0.6 time
Note: In the case of chowkat having two rebates, one for wooden
door and the other for wire gauze shutter, the surface area of the
chowkat shall be included in the measurement of only one door.
38-3.7 RATE
38-3.7.1 LABOUR RATE
The unit rate shall include the cost of cleaning, preparing and painting
the surface according to the above specifications or any other
specifications specially included in the contract. It shall further include
the cost of providing, using and removing scaffoldings, supports,
ladders, shot with gunny bags at both ends, brushes or spraying
machines of approved type and any other tool or plant required for
doing painting as per above specifications and removal with turpentine
or other approved methods of all defects from the painted surface to
leave it perfect in every respect. It shall further include the cost of all
allied operations like the removal of stains, smears, splashes and
droppings on the walls, floors, glazing, furniture and other places.
38-3.7.2 COMPOSITE RATE
The unit rate shall include the cost of supplying paints of approved
quality, paint remover in case of painting old work and all other
material required for doing painting as per above specifications at site
of work in addition to the labour rate as detailed in Section 38-3.7.1.
638
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-4 VARNISHING
38-4.1 DESCRIPTION
This work shall cover varnishing of wooden surface in accordance with
these specifications.
38-4.3 APPLICATION
Varnish shall then be applied in very thin coats with a special fine-
haired varnishing brush and not with an ordinary paintbrush. Unless
otherwise specified, the best copal varnish, as described under Section
38-4 of these specification for “Varnishes” shall be used. If more than
one coat have been specified the first coat shall be rubbed with the fine
sand paper. Other coats shall be applied as directed by the Engineer-in-
charge.
38-4.4 MEASUREMENT
Varnishing shall be measured by superficial area. The unit of
measurement shall be 100 square feet or one square meter. Moulded
work of all kinds, unless otherwise specified, shall be measured by
running the tape over and into all elevations and depressions. In the
639
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
case of other classes of work painted on both sides the flat area of the
surface on one side, including glazing and chowkat, shall be multiplied
by the factors given below to arrive at the correct measurement of both
sides for the purpose of making payment.
(a) Panelled or battened doors and windows 2 times
(b) Glazed or partly glazed doors or windows 2 times
(c) Plate glass windows (large glazed area) 1 time
(d) Wire guaze doors or windows 1 time
(e) Trellis work 2 times
(f) Grated doors and windows and other grating 1 time
(g) Palisade fencing 0.6 time
Note: In the case of chowkat having two rebates, one for wooden
door and the other for wire gauze shutter, the surface area of the
chowkat shall be included in the measurement of only one door.
38-4.5 RATE
38-4.5.1 LABOUR RATE
The unit rate shall include the cost of preparing, cleaning, rubbing,
knotting, stopping the surface and applying varnish on it as per above
specifications. It shall also include the cost of providing, using and
removing scaffoldings, supports, ladders shot with gunny bags at both
ends, fine-haired special brushes for varnishing and any other tool or
plant required for doing varnishing as per above specifications and
removal of all defects from the varnished surface to leave it perfect in
every respect. It shall further include the cost of all allied operations
like the removal of stains, smears, splashes and droppings on the walls,
floor, glazing, furniture and other places.
38-4.5.2 COMPOSITE RATE
The unit rate shall include the cost of supplying varnish of an approved
quality and all other materials required for doing varnishing as per
above specifications at site of works in addition to the labour rate as
detailed in Section 38-4.5.1.
640
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-5.1 DESCRIPTION
This work shall cover wax polishing of wooden surface in accordance
with these specifications. Wax polishing shall be done where a dull
polish, which shall not destroy the natural colour and graining of teak
or shisham.
38-5.3 MATERIALS
(a) Bee’s wax
(b) Linseed oil
(c) Turpentine
38-5.5 APPLICATION
38-5.5.1 FIRST COAT
Bee’s wax polish as prepared above shall be applied with a clean cloth
pad and rubbed continuously for at least half an hour.
38-5.5.2 SECOND COAT
When the surface is quite dry the second coat shall be applied in the
same manner and rubbed continuously for an hour or till the surface
has dried.
641
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-5.7 MEASUREMENT
It shall be measured by superficial area. The unit of measurement shall
be 100 square feet or one square meter. Moulded work of all kinds,
unless otherwise specified, shall be measured by running the tape over
and into all elevations and depressions. In the case of other classes of
work painted on both sides the flat area of the surface on one side,
including glazing and chowkat, shall be multiplied by the factors given
below to arrive at the correct measurement of both sides for the
purpose of making payment.
(a) Panelled or battened doors and windows 2 times
(b) Glazed or partly glazed doors or windows 2 times
(c) Plate glass windows (large glazed area) 1 time
(d) Wire guaze doors or windows 1 time
(e) Trellis work 2 times
(f) Grated doors and windows and other grating 1 time
(g) Palisade fencing 0.6 time
Note: In the case of chowkat having two rebates, one for wooden
door and the other for wire gauze shutter, the surface area of the
chowkat shall be included in the measurement of only one door.
38-5.8 RATE
38-5.8.1 LABOUR RATE
The unit rate shall include the cost of preparing, cleaning, rubbing,
knotting, stopping the surface and applying varnish on it as per above
specifications. It shall also include the cost of providing, using and
removing scaffoldings, supports, ladders shot with gunny bags at both
ends, fine-haired special brushes for varnishing and any other tool or
plant required for doing varnishing as per above specifications and
removal of all defects from the varnished surface to leave it perfect in
every respect. It shall further include the cost of all allied operations
like the removal of stains, smears, splashes and droppings on the walls,
floor, glazing, furniture and other places.
642
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
643
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-6.1 DESCRIPTION
This work shall cover French polishing of wooden surface in
accordance with these specifications.
38-6.3 MATERIALS
(a) Pure chalk
(b) Powder linseed oil and bee wax 3:1 boiled
(c) Plaster of Paris paste in water or raw linseed oil.
38-6.4 APPLICATION/POLISHING
(a) After the surface has been prepared it shall be first coated with
a filler composed of 5 lbs of whiting mixed with 1/3rd of a
gallon of mentholated spirit and then rubbed with sand paper. A
thin coat of polish shall then be applied. The surface shall then
be rubbed with sand paper before the second and subsequent
coats are applied.
(b) Alternatively, plaster of Paris, red ochre (sufficient to tint it),
and linseed oil are mixed together to form a stiff paste which
shall be applied sparingly and rubbed hard on the surface to till
up the pores or the wood. Prior to this a piece of rag moistened
with linseed oil shall be rubbed on the surface.
(c) The surface shall be rubbed smooth with fine glass paper a few
hours later and then polished.
(d) Unless otherwise specified, two coats of French polish of an
approved type shall be applied.
(e) To finish off, the surface shall be rubbed lightly and quickly
with a circular motion by means of a piece of flannel rolled into
the from of a rubber, covered with a place of rag slightly
damped with methylated spirit. If the rag sticks, the surface
shall be touched with linseed oil.
644
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-6.6 MEASUREMENT
It shall be measured by superficial area. The unit of measurement shall
be 100 square feet or one square meter. Moulded work of all kinds,
unless otherwise specified, shall be measured by running the tape over
and into all elevations and depressions. In the case of other classes of
work painted on both sides the flat area of the surface on one side,
including glazing and chowkat, shall be multiplied by the factors given
below to arrive at the correct measurement of both sides for the
purpose of making payment.
(a) Panelled or battened doors and windows 2 times
(b) Glazed or partly glazed doors or windows 2 times
(c) Plate glass windows (large glazed area) 1 time
(d) Wire guaze doors or windows 1 time
(e) Trellis work 2 times
(f) Grated doors and windows and other grating 1 time
(g) Palisade fencing 0.6 time
Note: In the case of chowkat having two rebates, one for wooden
door and the other for wire gauze shutter, the surface area of the
chowkat shall be included in the measurement of only one door.
38-6.7 RATE
38-6.7.1 LABOUR RATE
The unit rate shall include the cost of preparing, cleaning, rubbing,
knotting, stopping the surface and applying varnish on it as per above
specifications. It shall also include the cost of providing, using and
removing scaffoldings, supports, ladders shot with gunny bags at both
ends, fine-haired special brushes for varnishing and any other tool or
plant required for doing varnishing as per above specifications and
removal of all defects from the varnished surface to leave it perfect in
every respect. It shall further include the cost of all allied operations
like the removal of stains, smears, splashes and droppings on the walls,
floor, glazing, furniture and other places.
38-6.7.2 COMPOSITE RATE
The unit rate shall include the cost of supplying varnish of an approved
quality and all other materials required for doing varnishing as per
above specifications at site of works in addition to the labour rate as
detailed in Section 38-6.7.1.
645
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-7.1 DESCRIPTION
This work shall cover painting of woodwork with solignum, creosote
or coal tar for wood preservation in accordance with these
specifications. Solignum, creosote or coal tar which ever has been
specified shall be of an approved quality.
38-7.2 MATERIALS
38-7.2.1 QUALITY
Solignum, creosote or coal tar, whichever has been specified, shall be
obtained from approved manufacturers.
38-7.2.2 HEATING AND PREPARING PAINT
(a) Before applying solignum, creosote or coal tar shall be heated
to just short of boiling
(b) If tar is specified, it shall be thinned with kerosene oil or
common country spirit in the following proportions:
4 part tar to 1 part kerosene, or 1 gallon tar to ½ pint
country spirit;
2 lbs unslaked lime shall be mixed with 1 gallon of tar
to prevent its running.
The mixture shall then be heated to a near boiling point.
38-7.3 APPLICATION
(a) It shall be then applied with a stiff flat brush or a spraying
machine as specified.
(b) The paint shall be stirred occasionally while it is being applied.
(c) The ends of the timber pieces shall be liberally coated and,
where possible, dipped in the hot solignum or creosote.
(d) Where more than one coat has to be applied, subsequent coats
shall be applied when the previous one has dried.
38-7.5 MEASUREMENT
It shall be measured by superficial area. The unit of measurement shall
be 100 square feet or one square meter. Moulded work of all kinds,
646
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-7.6 RATE
38-7.6.1 LABOUR RATE
The unit rate shall include the cost of preparing, cleaning, rubbing,
knotting, stopping the surface and applying varnish on it as per above
specifications. It shall also include the cost of providing, using and
removing scaffoldings, supports, ladders shot with gunny bags at both
ends, fine-haired special brushes for varnishing and any other tool or
plant required for doing varnishing as per above specifications and
removal of all defects from the varnished surface to leave it perfect in
every respect. It shall further include the cost of all allied operations
like the removal of stains, smears, splashes and droppings on the walls,
floor, glazing, furniture and other places.
38-7.6.2 COMPOSITE RATE
The unit rate shall include the cost of supplying varnish of an approved
quality and all other materials required for doing varnishing as per
above specifications at site of works in addition to the labour rate as
detailed in Section 38-7.6.1.
647
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-8.1 DESCRIPTION
This work shall cover painting ironwork above water level in
accordance with these specifications.
38-8.2 MATERIALS
Paint shall be obtained from the approved manufacturers.
38-8.3 WEATHER
(a) Painting of iron work shall not be done in damp, wet, stormy or
extremely hot weather.
(b) Too quick drying in the baking heat of a summer sun shall also
be avoided.
648
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
(a) On new work, three coats shall be applied but on old work it is
sufficient to have two coats only.
(b) Each coat shall preferably vary slightly form the preceding one
in shade, in order to ascertain that full number of coats have
actually been applied.
38-8.7 MEASUREMENT
It shall be measured by superficial area. The unit of measurement shall
be 100 square feet or one square meter. Moulded work of all kinds,
unless otherwise specified, shall be measured by running the tape over
and into all elevations and depressions. In the case of other classes of
work painted on both sides the flat area of the surface on one side,
including glazing and chowkat, shall be multiplied by the factors given
below to arrive at the correct measurement of both sides for the
purpose of making payment.
(a) Panelled or battened doors and windows 2 times
(b) Glazed or partly glazed doors or windows 2 times
(c) Plate glass windows (large glazed area) 1 time
(d) Wire guaze doors or windows 1 time
(e) Trellis work 2 times
(f) Grated doors and windows and other grating 1 time
(g) Palisade fencing 0.6 time
Note: In the case of chowkat having two rebates, one for wooden door and the other
for wire gauze shutter, the surface area of the chowkat shall be included in the
measurement of only one door.
38-8.8 RATE
38-8.8.1 LABOUR RATE
The unit rate shall include the cost of preparing, cleaning, rubbing,
knotting, stopping the surface and applying varnish on it as per above
specifications. It shall also include the cost of providing, using and
removing scaffoldings, supports, ladders shot with gunny bags at both
ends, fine-haired special brushes for varnishing and any other tool or
plant required for doing varnishing as per above specifications and
removal of all defects from the varnished surface to leave it perfect in
every respect. It shall further include the cost of all allied operations
like the removal of stains, smears, splashes and droppings on the walls,
floor, glazing, furniture and other places.
38-8.8.2 COMPOSITE RATE
The unit rate shall include the cost of supplying varnish of an approved
quality and all other materials required for doing varnishing as per
above specifications at site of works in addition to the labour rate as
detailed in Section 38-8.8.1.
649
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-9.1 DESCRIPTION
This work shall cover painting ironwork which remains under water in
accordance with these specifications.
38-9.2 MATERIALS
Paint used shall be obtained from approved manufacturers.
38-9.5 PROTECTION
Work thus painted shall not be immersed in water until it has been
dried up; one week shall be generally sufficient for this purpose
depending upon the weather.
38-9.7 MEASUREMENT
It shall be measured by superficial area. The unit of measurement shall
be 100 square feet or one square meter. Moulded work of all kinds,
unless otherwise specified, shall be measured by running the tape over
and into all elevations and depressions. In the case of other classes of
work painted on both sides the flat area of the surface on one side,
including glazing and chowkat, shall be multiplied by the factors given
650
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
38-9.8 RATE
38-9.8.1 LABOUR RATE
The unit rate shall include the cost of preparing, cleaning, rubbing,
knotting, stopping the surface and applying varnish on it as per above
specifications. It shall also include the cost of providing, using and
removing scaffoldings, supports, ladders shot with gunny bags at both
ends, fine-haired special brushes for varnishing and any other tool or
plant required for doing varnishing as per above specifications and
removal of all defects from the varnished surface to leave it perfect in
every respect. It shall further include the cost of all allied operations
like the removal of stains, smears, splashes and droppings on the walls,
floor, glazing, furniture and other places.
38-9.8.2 COMPOSITE RATE
The unit rate shall include the cost of supplying varnish of an approved
quality and all other materials required for doing varnishing as per
above specifications at site of works in addition to the labour rate as
detailed in Section 38-9.8.1.
651
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–39
CLADDING
39-1 BRICK CLADDING
39-1.1 DESCRIPTION
This specification covers providing and laying brick cladding of
specified size in 1:3 Cement sand mortar using red posso mortar (1 part
cement and 3 parts surkhi) including filling the space between wall and
cladding using 1:5 cement sand mortar including cost of steel nails 6"
long @ 2'-0" c/c horizontally and vertically, cutting bricks as per
drawing and site requirements as directed by the Engineer-in-charge.
39-1.2 MATERIALS
39-1.2.1 CLADDING UNIT
It shall conform to Section 6 & 7 of these specifications except size.
39-1.2.4 WATER
Water shall conform to the provision and requirement set forth in
Section 1 of these specifications.
39-1.2.5 MORTAR
It shall conform to Section 16-2 of these specifications.
39-1.4 MEASUREMENTS
The brick cladding will be measured in superficial area. The unit of
measurements shall be 1-sft.
652
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
39-1.5 RATE
39-1.6 LABOUR RATE
The unit rate (on labour rate basis) for cladding shall include the cost
of carrying out cladding work, cutting gutka or bricks as the case may
be, wherever required, curing, using and removing scaffolding,
shuttering, centering, staging, ladders, supports and other tools and
plants required for carrying out the cladding work as per above
specifications.
653
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Providing and Laying Terrazzo wall finish ½" thick using one part of
white cement and 2 parts of marble chips of specified gauge over ½"
thick roughened surface of cement sand plaster ratio 1:3 including
making panels as per site requirements by means of aluminum U-
Channel ½" x 3/8" size and G.I. screws, fixed in plumb, straight and
level and then washing with narrial (Coir) brush and water to required
extent complete in all respects.
39-2.1 DESCRIPTION
Unless otherwise specified wash terrazzo shall be laid in accordance
with the following specifications:
39-2.2 BASE
Unless otherwise specified plaster used for bottom layer shall be of the
ratio 1:3 cement sand mortar.
39-2.3 THICKNESS
Unless otherwise specified the terrazzo thickness shall not be less than
3/8" and shall be laid monolithic with bottom layer of cement sand
plaster of specified thickness.
654
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
39-2.6 LAYING
The bottom layer of cement sand plaster shall conform to Section 39-
2.2 of these specifications with its surface made rough for adequate
adhering of top terrazzo layer. After laying and curing of bottom layer
Aluminium U-Channel ½" x 3/8", unless otherwise specified, shall be
fixed by means of screws according to site requirements for making
panels. A terrazzo topping 3/8" to ¾" thick consisting of one part of
white cement or ordinary Portland cement as specified and 2 parts of
marble chips, well mixed, is laid with trowel and float. In order to
achieve good results water added to the mix shall be just sufficient to
produce a workable plastic mix. Whichever method is adopted for
terrazzo topping, not more than 70% of the surface should be covered
with marble chippings. After sustaining of the material it shall be
washed with coir brush and water to required extent.
655
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
39-3.1 DESCRIPTION
Providing and laying local porcelain/ceramic tile cladding using
approved colour, design and pattern laid in white cement with pigment
to match the colour and shade of ceramic tiles over a bed of roughened
cement sand plaster in the ratio of 1:2, ¾" thick including labour for
cutting tiles according to site requirements, washing and cleaning top
surface of tiles with detergent complete in all respects. Unless
otherwise specified, porcelain/ceramic tile cladding work shall be
executed in accordance with the Section 39-3 of these specifications
true to dimensions and pattern as shown on the drawing.
39-3.2 MATERIALS
39-3.2.1 PORCELAIN/CERAMIC TILES
It shall conform to Section 8 of these specifications.
39-3.2.2 WATER
Water shall conform to the provision and requirement set forth in
Section-1 of these specifications.
39-3.2.3 MORTAR
Cement:Sand mortar shall conform to Section 16-2 of these
specifications.
39-3.3 BASE
Unless otherwise specified cement sand plaster (1:2) as base on walls
having thickness of ½" to ¾" as specified, shall be provided with
roughened surface. It shall conform to Section 36-2 of these
specifications.
39-3.4 LAYING
After laying of base and proper curing the ceramic tiles cladding shall
be laid using cement sand mortar (1:2), ¾" thick and joints will be
filled with white cement and pigment mortar.
39-3.5 MEASUREMENTS
The ceramic tile cladding shall be measured in superficial area. The
unit of measurement shall be 1-sft.
656
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
39-3.6 RATE
39-3.6.1 LABOUR RATE
The unit rate (on labour rate basis) shall include the cost of laying of
porcelain/ceramic tiles, cutting tiles wherever required, curing, using
and removing scaffolding, shuttering, centering, staging, ladders,
supports and other tools and plants required for carrying out ceramic
tile work on walls.
657
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
39-4.1 DESCRIPTION
Providing and laying cast stone cladding of specified size, thickness,
colour, texture and design over ¾" thick cement sand mortar ratio (1:3)
with pigment having joints ½" to 3/8" size filled with mortar of same
material according to drawing and site requirements.
39-4.2 MATERIALS
39-4.2.1 CAST STONE
It shall conform to Section 11-3 of these specifications.
39-4.2.2 WATER
Water shall conform to Section-1 of these specifications.
39-4.2.3 MORTAR
Cement:Sand mortar of 1:3 ratio shall conform to Section 16-2 of these
specifications.
39-4.3 MEASUREMENTS
The cast stone cladding work shall be measured in superficial area. The
unit of measurement shall be 1-sft.
39-4.4 RATE
39-4.4.1 LABOUR RATE
The unit rate (on labour rate basis) shall include the cost of laying of
cast stone cladding, cutting cast stone whenever required, curing, using
and removing scaffolding, shuttering, ladders, supports and other tools
and plants required for carrying out cast stone cladding work on walls.
658
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–40
FALSE CEILING
40-1 GENERAL
40-1.1 DESCRIPTION
This specification covers providing and fixing false ceiling under the
roof. Unless otherwise specified false ceiling shall be carried out in
accordance with the specifications true to dimension and as shown on
the drawing.
40-1.2 MATERIAL
i) Aluminium Alloy Tees shall be of size 1-½" x 1".
ii) Aluminium Alloy Angles shall be of size 1"x1"
iii) Plastic plugs of approved quality & steel screws not less than
1½" size shall be used.
iv) Ceiling Boards as specified.
40-1.3 OPERATION
Before start the work height of false ceiling shall be marked on the
surrounding walls.
i) The ceiling area shall be dividend into 2 feet sq panel.
ii) Unless otherwise specified, the false ceiling shall be laid over
angle and tee runners.
iii) Unless otherwise specified angles and tee runners shall be of
aluminium & of specified shade or powder quoted in approved
colour.
iv) Angle runners shall be fastened with walls at the correct height
by means of plastic plug and screws driven into wall at
intervals not more then 2-ft.
v) Tee runners shall be suspended with G.I wire 14 SWG
anchored with plastic plug and screws driven in roof at
intervals not more then 2-ft accurately.
vi) Tee crosses shall be resting on tee angle runners and fastened
tightly.
vii) Board of specified material size and thickness shall be fixed in
the frame.
659
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
40-1.4 MEASUREMENT
The false ceiling shall be measured by area. The unit for measurement
shall be sq.ft/ sq. mtr.
40-1.5 RATE
40-1.6 LABOUR RATE
The unit rate for false ceiling shall include the cost of labour involved
to carry out false ceiling according to the specifications, fixed in
position, at specified height in true lines and level.
The rate shall further include the cost of labour employed for following
operations.
i) Drilling of holes in walls & ceiling.
ii) Fixing of plastic plug and screws.
iii) Fastening of tee runners with G.I wire 14 SWG gauge.
iv) Fastening of angle runners with walls.
v) Cutting of ceiling boards in specified size where required.
vi) Fixing of ceiling boards
660
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
40-2.1 DESCRIPTION
This specification covers providing and fixing false ceiling with
thermopore sheet under the roof. Unless otherwise specified false
ceiling shall be carried out in accordance with the specifications true to
dimension and as shown on the drawing.
40-2.2 MATERIALS
35-2.2.1 THERMOPORE SHEET
i) These shall conform to Section 20 of these specifications.
ii) These shall be of approved design.
iii) Size 2'x2'x¾".
iv) Density of Thermopore sheet shall be 20kg/m3.
40-2.4 MEASUREMENT
The false ceiling shall be measured by area. The unit for measurement
shall be sq.ft/ sq. meter.
40-2.5 RATE
40-2.5.1 LABOUR RATE
The unit rate for false ceiling shall include the cost of labour involved
to carry out false ceiling according to the specifications, fixed in
position, at specified height in true lines and level. The rate shall
further include the cost of labour employed for following operations.
(a) Drilling of holes in walls & ceiling.
(b) Fixing of plastic plug and screws.
(c) Fastening of tee runners with G.I wire 14 SWG gauge.
(d) Fastening of angle runners with walls.
(e) Cutting of ceiling boards in specified size where required.
(f) Fixing of ceiling boards
661
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
662
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
40-3.1 DESCRIPTION
This specification covers providing and fixing false ceiling with
Gypsum Board. Unless otherwise specified false ceiling shall be
carried out in accordance with the specifications true to dimension and
as shown on the drawing.
40-3.2 MATERIALS
40-3.2.1 GYPSUM BOARD
(a) It shall conform to the Section 13-3 of these specifications.
(b) It shall be of approved design and quality.
(c) Size 2'x2'x3/8".
40-3.2.2 OTHER MATERIALS
As mentioned in Section 40-1.2 of these specifications.
40-3.4 MEASUREMENT
The false ceiling shall be measured by area. The unit for measurement
shall be sq.ft/ sq. meter.
40-3.5 RATE
40-3.5.1 LABOUR RATE
The unit rate for false ceiling shall include the cost of labour involved
to carry out false ceiling according to the specifications, fixed in
position, at specified height in true lines and level. The rate shall
further include the cost of labour employed for following operations.
(a) Drilling of holes in walls & ceiling.
(b) Fixing of plastic plug and screws.
(c) Fastening of tee runners with G.I wire 14 SWG gauge.
(d) Fastening of angle runners with walls.
(e) Cutting of ceiling boards in specified size where required.
(f) Fixing of ceiling boards
663
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
40-4.1 DESCRIPTION
This specification covers providing and fixing false ceiling with Plaster
of Paris under the roof. Unless otherwise specified false ceiling shall
be carried out in accordance with the specifications true to dimension
and as shown on the drawing.
40-4.2 MATERIALS
40-4.2.1 PLASTER OF PARIS BOARD/SHEETS
(a) Plaster of Paris shall conform to Section 5 of these
specifications.
(b) Plaster of Paris sheet size 2'x2'x½" of approved design shall be
used manufactured at site of work.
40-4.2.2 OTHER MATERIALS
As mentioned in Section 40-1.2 of these specifications.
40-4.4 MEASUREMENT
The false ceiling shall be measured by area. The unit for measurement
shall be sq.ft/ sq. meter.
40-4.5 RATE
40-4.5.1 LABOUR RATE
The unit rate for false ceiling shall include the cost of labour involved
to carry out false ceiling according to the specifications, fixed in
position, at specified height in true lines and level. The rate shall
further include the cost of labour employed for following operations.
(a) Drilling of holes in walls & ceiling.
(b) Fixing of plastic plug and screws.
(c) Fastening of tee runners with G.I wire 14 SWG gauge.
(d) Fastening of angle runners with walls.
(e) Cutting of ceiling boards in specified size where required.
(f) Fixing of ceiling boards
40-4.5.2 COMPOSITE RATE
The unit rate shall include the cost of all materials required in addition
to the labour rate detail in para 40-4.5.1 above.
664
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
40-5.1 DESCRIPTION
This specification covers providing and fixing false ceiling with MDF
Board under the roof. Unless otherwise specified false ceiling shall be
carried out in accordance with the specifications true to dimension and
as shown on the drawing.
40-5.2 MATERIAL
40-5.2.1 MDF BOARD
(a) MDF board shall be of approved design, density, and of
specified manufacturer.
(b) Size 2"x2"x3/8" or as specified.
40-5.4 MEASUREMENT
The false ceiling shall be measured by area. The unit for measurement
shall be sq.ft/ sq. meter.
40-5.5 RATE
40-5.5.1 LABOUR RATE
The unit rate for false ceiling shall include the cost of labour involved
to carry out false ceiling according to the specifications, fixed in
position, at specified height in true lines and level. The rate shall
further include the cost of labour employed for following operations.
(a) Drilling of holes in walls & ceiling.
(b) Fixing of plastic plug and screws.
(c) Fastening of tee runners with G.I wire 14 SWG gauge.
(d) Fastening of angle runners with walls.
(e) Cutting of ceiling boards in specified size where required.
(f) Fixing of ceiling boards
40-5.5.2 COMPOSITE RATE
The unit rate shall include the cost of all materials required in addition
to the labour rate detail in para 40-5.5.1 above.
665
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–41
41-1.1 DESCRIPTION
This specification covers providing and laying Damp Proof Course
horizontally or vertically of specified material in specified ratio. Unless
otherwise specified Damp Proof Course shall be laid in accordance
with the specifications.
41-1.2 MATERIALS
a) Cement shall confirm to the Section 4 of these specifications.
b) Fine aggregate shall confirm to the Section 10-3 of these
specifications.
c) Coarse aggregate shall confirm to the Section 10-4 of these
specifications.
d) Water shall confirm to the Section 1 of these specifications.
e) Bitumen shall confirm to the Section 23 of these specifications.
41-1.3 OPERATION
Unless otherwise specified, concrete DPC shall consist of laying of
cement concrete of specified thickness over the masonry wall covering
entire width of the wall.
41-1.4 CONCRETE
Unless otherwise specified , cement concrete in DPC shall be of ratio
1:2:4 by volume and shall conform to Section 30 of these specification
for cement concrete.
666
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
41-1.7 FINISHING
The surface shall be leveled with a wooden trowel. The fines in the
concrete which have come to the surface with the stroking quickly but
carefully smoothened with the steel trowel.
41-1.8 CURING
Unless otherwise specified, the DPC shall be cured by water curing for
a period of seven days and then surface shall be allowed to dry.
41-1.11 MEASUREMENT
The cement concrete DPC shall be measured by superficial area. The
unit of measurement shall be 100-Sq ft/ Sq. Mtr.
41-1.12 RATE
41-1.12.1 LABOUR RATE
The unit rate shall included
a) Washing and cleaning of masonry base.
b) Mixing, placing, finishing and curing of toping concrete.
c) Laying coat of bitumen.
d) Laying a layer of ploythene sheet.
667
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
41-2.1 DESCRIPTION
This specification covers providing and laying Damp Proof Course of
cement sand plaster of specified ratio and thickness. Unless otherwise
specified cement sand plaster damp proof course shall be laid in
accordance with the specifications.
41-2.2 MATERIALS
41-2.2.1 Cement shall confirm to the Section 4 of these specifications.
41-2.2.2 Fine aggregate shall confirm to the Section 10-3 of these
specifications.
41-2.2.3 Water shall confirm to the Section 1 of these specifications.
41-2.2.4 Bitumen shall confirm to the Section 23 of these specifications.
41-2.2.5 Unless otherwise specified, cement sand mortar shall confirm to
Section 16-2 of these specifications for preparation of mortar.
41-2.3 OPERATION
Unless otherwise specified, DPC shall consist of applying cement sand
plaster of specified thickness and ratio over the masonry work
horizontally/vertically.
41-2.6 PLASTERING
Plastering shall be done in accordance with Section 36-2 of these
specifications for cement plaster.
668
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
41-2.9 MEASUREMENT
The cement sand plaster DPC shall be measured by superficial area.
The unit of measurement shall be 100-sq ft/ sq.m.
41-2.10 RATE
41-2.10.1 LABOUR RATE
The unit rate shall included:
a) Washing and cleaning of masonry base.
b) Mixing, placing, finishing and curing of cement sand plaster.
c) Laying coat of bitumen.
d) Laying a layer of ploythene sheet.
669
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
41-3.1 DESCRIPTION
This specification covers providing and laying Marble Damp Proof
Course of specified thickness. Unless otherwise specified marble damp
proof course shall be laid in accordance with the specifications.
41-3.2 MATERIAL
41-3.2.1 MARBLE SLAB
a) Marble Slab shall be conforming to the specifications contained
in Section 11-1 of these specifications.
b) Marble stone slab shall be of specified thickness, width in
accordinace to the wall to be covered and appropriate length.
c) All slabs shall have a true plain surface and shall be accurately
sawn, truly square at edges to full thickness. The slabs at
corners shall be cut at 450 angle.
41-3.2.2 MORTAR
Cement sand Mortar 1:2 conforming to the specification as contained
in Section 16-2.
41-3.3.3 JOINTS
No joints shall be more then 1/16 of an inch in thickness.
41-3.3.4 LAYING
Slabs shall be laid in position on bedding mortar and shall cover full
width of masonry wall, the joints shall be filled with specified mortar.
41-3.3.5 LEVELS
The surface of the Marble DPC Slabs when laid shall be perfect and
true in levels.
670
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
The Marble DPC shall be kept watered for seven day. Three clear days
shall be given for setting before any one is allowed to walk over.
Further work shall not be executed before seven days after laying of
DPC.
41-3.4 MEASUREMENT
The measurements of Marble DPC shall be done by the superficial
area. The unit of measurement shall be 100-Sq feet / Sq. meter.
41-3.5 RATE
41-3.5.1 LABOUR RATE
The unit rate shall include.
i) Washing scrubbing & cleaning of masonry base.
ii) Laying of bedding Mortar.
iii) Laying of marble DPC slabs over bedding Mortar.
iv) Filling of joints with specified mortar.
671
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
41-4.1 DESCRIPTION
This specification covers providing and laying Damp Proof Course of
Jutoid of specified thickness. Unless otherwise specified cement sand
plaster damp proof course shall be laid in accordance with the
specifications.
41-4.2 MATERIALS
41-4.2.1 JUTOID
a) Normal weight of jutoid shall be 3.5-kg/sq.m.
b) Manufactured by an approved manufacturer through Punjab
Buildings Department.
41-4.2.2 MORTAR
Cement:Sand mortar of 1:2 ratio shall conform to Section 16-2 of these
specifications.
41-4.4 LAYING
Jutoid D.P.C is laid over the walls & it shall cover full width of the
wall.
41-4.5 LAP
A minimum of 3” lap shall be provided.
41-4.6 RATE
41-4.6.1 LABOUR RATE
The unit rate shall include, cleaning surface & laying of Jutoid D.P.C.
41-4.6.2 COMPOSITE RATE
The unit rate shall include the cost of materials specified for carrying
out work in addition to the labour rate as detail in Section 41-4.6.1
above except the cost of cement sand plaster which will be paid
separately if required & executed.
672
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–42
42-1 DESCRIPTION
The work covered under this section comprises of the following:
(a) Providing & fixing in position aluminium doors and windows
complete with handles, locks, nylon wheels, vinyl weather
strips etc. as shown on the drawings and specified hereunder.
(b) Providing & fixing glass of specified quality and thickness to
windows and door.
673
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
42-3.2 HARDWARE
Iron mongery, fitting, handles and locks shall be of bronze, stainless
steel and aluminium as shown on the drawings or as stated in the Bill
of Quantities.
42-3.3 GLASS
The solar control float glass if specified shall conform to the latest
revised BS 952. “First grade imported tinted bronze float glass shall be
sued subject to approval. The quality, kind, thickness and size of the
glass shall be as shown on the drawings or called for in the Bill of
Quantities.
42-3.4 SEALANTS
The external joints between the building openings, window frames etc.
shall be formed to details shown on drawing and grooves shall be
caulked with mastic sealants. External jointing sealants are to be
suitable for the type and exposure of building. Material shall not be of
a standard lower than one part polysulphade rubber sealant conforming
to BS 5215 and shall be applied strictly in accordance with the
manufacture’s instructions. The colour and quality of sealant shall be
subject to approval. Where joints to be sealed are deep the sealant must
be supported by suitable polythene backing.
674
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
42-4 SAMPLES
42-4.1 The contractor shall submit, for approval, samples of each type of door
and window showing the quality of materials, workmanship and finish.
The samples of iron mongery, fittings and fixtures shall also be got
approved before purchases are made by the contractor.
42-4.2 The samples of glass for each type of glazing alongwith specifications
of the manufacturer of special quality shall be submitted for approval
before firm orders are placed for suppliers.
42-5.2 FIXING
The fixing of doors and windows to concrete openings shall be carried
out in an approved method as indicated in the drawings or as directed.
Provision of necessary groove or rebate and hold-fasts in the concrete
shall be made in the form work and no holing or drilling shall be
allowed in the exposed concrete finishes. These shall be erected in
position after the building structure is completed and by using proper
hold-fasts as shown on drawings or counter sunk bolts and screws as
directed in accordance with site requirements.
675
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
42-5.3 HANDLING
Care shall be taken in handling metal doors, windows, etc., during
transportation and at site. These shall be stored under cover and shall
be installed only by skilled mechanics, set plumb, level, in alignment
and properly braced to prevent distortion.
42-5.4 PROTECTION
42-5.4.1 The joint between window and doorframes and the building should be
caulked with approved building mastic for total weatherproofing.
42-5.4.2 After installation, doors, and windows shall be protected form
construction hazards that will interfere with their operation or damage
their appearance or finish. They shall be cleaned on inside and outside
of all mortar, plaster, paint of other foreign matter to present a neat
appearance. Hardware and moving parts shall be lubricated.
42-6 GLAZING
42-6.1 The work of fixing glazing to doors, windows shall be carried out with
the type and quality of glass specified for each door and window and
as indicated in the drawings or as directed.
42-6.2 The glazing of “Antisun” float glass should be in accordance with the
recommendations of BS C.P. 152: 1972 and subsequent amendment.
42-6.3 The sizes of glass indicated on the drawings are approximate only, and
the actual sizes required shall be determined by measuring the frames
to receive the glass. All glass shall be factory labelled on each pane
and the label shall not be removed until finally approved. Glass will be
fixed with best quality mastic compound of approved make suitable for
the type of glass or with special bead or moulding as shown on the
drawing or as directed. Special rubber lining and weather proof brush
joints for sliding surfaces shall be provided where indicated.
42-6.4 Antisun float glass shall be fixed using flexible compounds, sealants,
performed strips or gaskets as per recommendation of the door/window
manufacturer. The design shall allow for an edge clearance of at least
3mm (1/8") all around unless any dimension exceeds 1500mm (60")
when the clearance shall be at least 5mm (3/16") edge cover shall be
adequate to retain the glass in position under the design wind loading.
The rebate detph edge clearance plus edge cover shall not be less than
11mm (7/16") for 6mm glass. The width of the rebate platform must
accommodate the glass, the front and back compound, and glazing
bead. The bead depth should not be less than the rebate depth. Setting
block, distance pieces, and location blocks shall be used as appropriate.
Glass shall be protected against damage. After inspection, any labels,
and paint spots shall be removed and glass shall be washed clean.
Damages or broken glass shall be removed and glass shall be washed
clean. Damages or broken glass shall be removed and replaced before
acceptance at not extra expense. After the installation of ‘Anitsun’
float glass it shall be cleaned using a soft cloth with water and mild
soap or liquid detergent, followed by rinsing with clean water and
drying.
676
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
42-7 MEASUREMENT
Payment for doors and windows will be made by measuring clean
opening area in brickwork or concrete in square feet/meters.
42-8 RATE
Rates for all the items under this Section shall cover the cost of
furnishing all the materials labour, scaffoldings and appliances at site
and performing all operations in connection with their installation in
accordance with instructions. It is particularly mentioned that the rates
for fixing doors and windows etc. shall include fixing of all finished
hardware iron mongery fittings such as locks, peg stays, handles, push
plates, kicking plates, door-closers, glazing, flexible compounds,
rubber lining and appliances at site and performing all operations in
accordance with the drawings and specifications.
677
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
SECTION–43
WALLCOVERING/ARCHITECTURE COATING
43-1 DESCRIPTION
This specification covers the performance, quality, packaging, and
marking characteristics of flexible wall covering as a finished product.
43-2 TERMINOLOGY
43-1.1 DEFINITION
43-1.1.1 Wallcovering
A flexible product designed to cover walls and ceilings for decorative
or functional purpose, or both.
678
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
43-1.2.11 Register
The designed meeting of all parts and colors of a pattern.
43-1.2.12 Run
A unit of production which may include more than one lot.
43-1.2.13 Seconds
Finished material not meeting the quality criteria in accordance with
Classification F 793 and this specification.
43-1.2.14 Selvage
An undecorated edge which must be trimmed away to allow for correct
pattern match or uniform continuity of color.
43-1.2.15 Waste edge
A decorated edge that must be trimmed away to allow for correct
pattern match or uniformity of color.
43-1.2.16 Shading
43-1.2.16.1 Color wariation – difference within the same lot of wallcovering.
43-1.2.16.2 Luster variation – difference in gloss level within the same lot of
wallcovering.
43-1.2.16.3 Texture variation – difference in embossing within the same lot of
wallcovering.
43-1.2.17 Split bolt
A bolt consisting of two or three separate lengths of material.
43-3 APPEARANCE
There shall be no appreciable difference in shading except on those
finished products in which natural decorative characteristics are being
simulated. These variances must be clearly stated in writing at the
point of purchase. To determine whether there is an appreciable
difference, suspend three sequential 8-ft (2.4-m) strips at eye level in a
vertical position, as on the wall, under illumination be between 100 to
150 fc (1000 to 1500 lx), and view the strips from a distance between 4
and 8 ft (1.2 and 2.4m). An appreciable difference is one which is
noticeable when one strip is compared with the others.
679
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
680
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
Table 1
Property Section Category I Category II Category III Category IV Category V Category VI
Reference Decorative Decorative Decorative Type I Type II Type III
only with medium with high Commercial Commercial Commercial
Serviceability Serviceability Serviceability Serviceability Serviceability
Minimum 7.3 23 h 46 h 200 h 200 h 200 h
colorfastness
Minimum 7.4 100 cycles 100 cycles 100 cycles 100 cycles 100 cycles
washability
Minimum 7.7 50 cycles 200 cycles 300 cycles 500 cycles
scrubbability
Minimum 7.8 200 cycles 300 cycles 1000 cycles
abrasion (220 girt) (220 girt) (220 girt)
resistance
Minimum 7.9 40 lb 50 lb 100 lb
breaking
strength
MD 30 lb 55 lb 95 lb
(machine
direction)
CMD
(cross
machine
direction)
Minimum 7.6 Good Good Good Good
crocking
resistance
Minimum 7.5 Reagents Reagents Reagents Reagents
stain 1 to 9 1 to 9 1 to 12 1 to 12
resistance
Minimum 7.10 12 25 50
tear
resistance
Minimum 7.11 2 2 2
block
resistance
Minimum 7.12 2 lb/in 3 lb/in 3 lb/in
coating
adhesion
Minimum 7.13 No change No change No change
cold
cracking
resistance
Minimum 7.14 Pass Pass Pass
heat aging
resistance
Maximum 7.15 25 25 25
flame spread
Maximum 7.15 50 50 50
smoke
development
Maximum 7.19
shrinkage
MD 2 2 2
(machine
direction)
CMD 1 1 1.5
(cross
machine
direction)
681
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
43-8 CERTIFICATION
When specified in the purchase order or contract, a manufacturer’s or
supplier’s certification shall be furnished to the purchaser stating that
sample representing each lot of the material have been manufactured,
tested, and inspected in accordance with this specification and the
requirements have been met.
682
Punjab Buildings Department Standard Specifications for Execution of
Building Works Draft 2006
43-12 MEASUREMENT
Wallcovering/Architecture Coating shall be measured by superficial
area. The unit of measurement shall be 100 square feet.
43-13 RATE
The unit rate shall be full compensation for all costs or complying with
the provision of this section and as directed by the Engineer-in-charge.
683
REFERENCES
Sr.
Title of Books
No.
1 P.W.D. Buildings and Roads specifications Volume I 1936
2 Standard specification for Road and Bridge construction 1971, Punjab Highway Department.
3 M.E.S. specifications.
4 BRE Digests.
5 Time Saver Standards for Architecture Design Data.
6 General specifications, National Highway Authority December 1998.
7 Building Code of Pakistan, Ministry of Housing and Works Environment & Urban Affairs Division.
8 Schedule of Rates Volume I, Part I specifications for Materials of construction 1964.
9 Schedule of Rates Volume I, Part II, specification for Execution of Works 1967.
10 AASHTO (Part 1-A) specifications 2002.
11 AASHTO (Part 1-B) specifications 2002.
12 AASHTO (Part 2-A) Tests 2002.
13 AASHTO (Part 2-B) Tests 2002.
14 ACI Manual of Concrete Practice 2000 Part-1.
15 ACI Manual of Concrete Practice 2000 Part-2.
16 ACI Manual of Concrete Practice 2000 Part-3.
17 ACI Manual of Concrete Practice 2000 Part-4.
18 ACI Manual of Concrete Practice 2000 Part-5.
19 Pakistan Standard specifications.
20 Architectural Graphic Standards to 10th Edition by Thon Ray Hoke, JR, FAIA.
21 Paint Pigment Varnish Lac Quer Manufacturing by EIRI consultants & Engineers.
22 Papers on Building Construction No. 282.
23 Soil Mechanics by Tshelotarioff.
24 The Indus Civilization by Wheeler.
25 Simple Examples of Concrete Design by Faber
26 Foundations Design simply Explained by Faber
27 The Condensed Chemical Dictionary by Rose.
28 Design of Prestressed Concrete Structures by Lin T.Y.
29 Foundation Engineering (Leonards).
30 Foundation Engineering (Hanson)
31 Principle of Soil Mechanics by Scott.
32 Fundamentals of Soil Mechanics by Taylor.
33 Description Geometry by Steve M.
34 Plane Geometry Problem with Salutions by Marcus.
35 Plane & Spherical Trigonometry by Kaj L.
36 Decay of Timber and Its Prevention by Findlay.
37 Dictionary of Building Materials by Kinniburgh W.
38 ACI Specification for Structural Concrete for Building.
39 Foundation Design and Construction by Tomilson M.J.
40 The Chemistry of Cement and Concrete by Lea F.M.
41 ASTM American Society for Testing Material Part-4 Steel, Concrete.
42 ASTM American Society for Testing Material Part-13 Cement, Lime, Gypsum.
43 ASTM American Society for Testing Material Part-14, Concrete, Mineral, Aggregates.
44 Mc Graw Hill Dictionary of Scientific and Technical Terms.
45 “The Properties of Ground Water” by Georg Mathess.
46 “Water Quality and its Control” by James C.Lamb.
47 Properties of Concrete by A.M Neville.
48 Civil Engineering Hand Book by Khanna.
49 Pakistan Standard specifications.
50 ASTM Journal of the American Ceramics Society
51 ASTM Journal of the American Ceramics Society
52 ASTM Publication on Lime
53 ASTM Specification for Steel Bars and Concrete Reinforcement
54 ASTM Papers on Building Construction No.282
55 ASTM Standards Including Testing (Part-1) Ferrous Metals Specifications
Sr.
Title of Books
No.
56 ASTM Standards Including Testing (Part-2) Non-Ferrous Metals Spcifications
57 ASTM Standards Including Testing (Part-4) Cement, Lime, Gypsum, Mortar, Concrete, Mineral
Aggregates, Bituminous Materials Soils
58 ASTM Standards Including Testing (Part-5) Asbestos, Cement Products
59 ASTM Standards Including Testing (Part-6) Paper, Packaging, Wood, Adhesive, Cellulose, Leather
60 ASTM Standards Including Testing (Part-7) Petroleum Products and Lubricants
61 ASTM Standards Including Testing (Part-8) Paint, Coal, Coke, Fuels, Chemical
62 ASTM Standards Including Testing (Part-10) Textiles, Soap, Minrals Materials, Wax Polishes
63 ASTM American Society for Testing Material Part-4 Steel, Concrete
64 ASTM American Society for Testing Material Part-14 Concrete, Mineral, Aggregates
65 ASTM Publication News Material Testing and Design
66 ASTM Annual Book of ASTM Standard Cement, Lime, Gypsum
67 Annual Book of Standard Sec-4 Concrete
68 Annual Book of ASTM Standard Sec:4 Vol-04.08 Soil and Rock
69 Annual Book of ASTM Standard Sec:4 Vol-04.09 Soil and Rock
70 Annual Book of ASTM Standards 2003 Vol-04.03 Construction Road & Paving Materials Vehicle-
Pavement System
71 Annual Book of ASTM Standards 2003 Vol-04.04 Roofing, Water, Water Proofing and Bituminous
Material
72 Annual Book of ASTM Standards 2003 Vol-06.01 Paints Related Coating & Aromatics Test Chemical
73 Annual Book of ASTM Standards 2003 Vol-04.07 Thermal Insulations, Environment Acustics
Construction, Fire
74 Masonry Test Methods and Specifications for the Building Industry 4th ed
75 Annual Book of ASTM Standard 2004 Section One Iron and Steel Products Vol- 01.04 Steel, Structural,
Reinforcing, Pressure Vessel, Railway
76 Building Codes (41st ed Vol-1) 2004
77 Building Codes (41st ed Vol-2) 2004
78 Building Codes (41st ed Vol-3) 2004
79 Building Codes (41st ed Vol-4) 2004
80 Annual Book of ASTM Standards 2005 (Section Eleven Vol-11.01 Water-l) Water and Environmental
Technology
81 Annual Book of ASTM Standards 2005 (Section Eleven Vol-11.02 Water-ll) Water and Environmental
Technology
82 Chemical Process Industries by Nonis R Share
83 The Science of Daylight by Wash, John W. E
84 Appropriate Building Materials by Roland Stulz.
85 Princples of Structural Stability Theory by Alexander Chajes.
86 Structural Brick Work by Handry Arnold.
87 Concrete Construction Handbook Joseph J.
88 Materials for Civil and Highway Engineers Kenneth N.
89 Design of Concrete Structures (8th Ed.) by Winter Nilson.
90 Rocks and Minerals by Milan S.P.A.
91 The Properties of Ground Water by Mathess
92 The Stability of Slopes by Bramhead E.N.
93 Modern Prestressed Concrete Design by Ramah Swamy
94 Design of Precast Concrete by Robert A. Hartland.
95 Concrete Manual, A Water Resources Technical Publication by Tohn Wiley & sons.
96 Composition & Properties of Concrete by Troxell Davis Kelly.
97 Brick and Tile Making by Willi Bender
98 Composite Schedule of Rates 1979 by Govt. of Punjab.
99 The Art and Science of Brick Making by Ashfaq Hasan.
100 The Art and Science of Brick Making by Ashfaq Hasan.
101 Dictionary of Civil Engineering by Johns Scott.
102 Innovative Application of Shells and Spatial Forms Vol.I by Ramaswamy G. S.
103 Innovative Application of Shells and Spatial Forms Vol.II Ramaswamy G.S.
104 Encyclopaedia of Scientific & Technical Terms (Physics) by Chhatwal G.R.
Sr.
Title of Books
No.
105 Encyclopaedia of Scientific & Technical Terms (Scientific & Technical Terms) Chhatwal G.R.
106 Water Proofing of Masonry Construction/Concrete by Thema.
107 Pile Foundations by Dinesh Mohan.
108 A Text book of Soil Mechanics by Sehgal.
109 Engineering Materials for Highways & Buildings by Khalid Hassan Siddique.
110 Civil Engineering Hand Book Vol.I by Vazirani V.N.
111 Civil Engineering Hand Book Vol.II by Vazirani V.N.
112 Civil Engineering Hand Book Vol.III by Vazirani V.N.
113 Soil Mechanics in Engineering Practice (2nd Ed.) by Terzaghi Karl
114 Brick Work Vol.III by Bailey H.
115 Dictionary fo Chemistry by Sherp D.W.A.
116 Dictionary of Science by Uvarove B.
117 Engineering Properties of Soil and Their Measurement by Joseph E.Bowles.
118 Dictionary of Engineering by Sybil Mark.
119 Materials of Construction (4th Ed.) by Smith R.C.
120 Termite Control Measures in Buildings by Singh Y.
121 Brick Making in Developing Countries by John Pezzey.
122 Appropriate Building Materials for Low Cost Housing Vol.II by C.I.B.
123 Fiber Reinforced Cement Composite by Balaqurets P.N.
124 Properties of Concrete (3rd Ed.) by Neville A.M.
125 Earth Manual by Usinterior Power.
126 Indian Architecture by Percy Brown.
127 Dictionary of Geology by Whitten D.G.A.
128 Ground Water Resources Pakistan by Nazir Ahmad.
129 Water Resources of Pakistan by Nazir Ahmad.
130 Concrete Admixtures Hand Book Ramchandra.
131 Concrete Repair Vol.II by Alberdean.
132 Concrete Repair by Alberdean.
133 Concrete Repair Vol.III by Aberdeen.
134 ACI Manual of Concrete Practice (Part-1)1997 Materials and General Properties Concrete
135 ACI Manual of Concrete Practice (Part-2)1997 Construction Practices and Inspection Pavements
136 ACI Manual of Concrete Practice (Part-3)1997 use of Concrete in Buildings, Design, Specification, and
Related Topics
137 ACI Manual of Concrete Practice (Part-4)1997 Bridges, Substructures, Sanitary, and Other Special
Structures, Structural Properties
138 ACI Manual of Concrete Practice (Part-5)1997 Masonry Precast Concrete, Special Processes
139 ACI Manual of Concrete Practice (Part-5) 1998 Masonry Precast Concrete, Special Processes
140 ACI Manual of Concrete Practice (Part-4) 1998 Bridges, Substructures, Sanitary, and Other Special
Structures, Structural Properties
141 Geotechnical Engineering Foundation Design by John N. Cernia.
142 Foundation Engineering Hand Book by Hbai Yand.
143 ACI Manual of Concrete Practice ((Part-1) 1998 Materials and General Properties of Concrete
144 ACI Manual of Concrete Practice (Part-2) 1998 Construction Practices and Inspection Pavements
145 ACI Manual of Concrete Practice (Part-5) 1999 Masonry Precast Concrete, Special Processes
146 ACI Manual of Concrete Practice (Part-3) 1999 use of Concrete in Buildings, Design, Specification, and
Related Topics
147 ACI Manual of Concrete Practice (Part-1) 1999 Materials and General Properties Concrete
148 ACI Manual of Concrete Practice (Part-2) 1999 Construction Practices and Inspection Pavements
149 ACI Manual of Concrete Practice (Part-4) 1999 Bridges, Substructures, Sanitary, and Other Special
Structures, Structural Properties
150 Building Materials by Duggal S.K.
151 ACI Manual of Concrete Practice (Part-1) 2000 Materials and General Properties Concrete
152 Condensed Chemical Dictionary (Ed. 13th) by Hawley's Richard.
153 Prestressed Concrete Structures (5th Ed) by Dayaratnam P.
154 Design of Concrete Mixes (Ed. 3rd) by Krishna Raju N.
155 Portland Cement (Ed. 2nd) by Thomas Telfora.
156 Reinforced Concrete Design, Part I,II by Solomon S.K.
Sr.
Title of Books
No.
157 Mathematics for the Fundamentals of Engineering by Max Kurtz.
158 Soil Property (Ed. 4th) Cheng Liu.
159 Statistical Analysis for Engineering by Wesley Barnes J.
160 Analysis of Plate and Shells by Philip L. Gould
161 Shreves Chemical Process Industry by George T. Austin.
162 Concrete Bridges H.B. by Raina V.K.
163 Chemistry and Physics Handbook by David R. Lide.
164 Road Building in the Tropics by Millard R.S.
165 The Shell Bitumen Hand Book by Stephen Brown.
166 Waste Materals used in Concrete Manufacturing by Chandra.
167 Dictionary of Scientific & Technical Terms by McGraw Hill
168 Design of Concrete Structures by Nilson
169 Cobuild Learner's Dictionary by Collins
170 Concise Thesaurus by Collins
171 Dictionary of Mechanical Engineering Terms by Horner's
172 Gem Measurements & Conversions by Collins
173 Expansive Clay Soil and Vegetative Influence on Shallow Foundations by Vipulananda.
174 Slope Stability 2000 by Griffiths
175 Portland Cements Production, Properties and Applications by Abdul Majid.
176 Lightweight Aggregate Concrete (science,technology and applications) by Satish Chandra.
177 Design of Plate and Shell Structures by Maan H. Jawad
178 Handbook of Fillers by Geoge Wypych.
179 Stone Sampler by Marmo
180 Clays by Meunier.
BRITISH STANDARDS
181 Methods for Tensile Testing of Metals BS 18:Part 2. 1971.
182 Specifications for Asbestos-Cement Slates and Sheets BS 690 : Part 2: 1971.
183 Specifications for Wrought Steels BS 970: Part 1&3 : 1971.
184 Wood Windows BS 644: Part 1: 1989.
185 Finishes ofr Wooden Furniture BS 3962: Part 2,3,4,5 & 6 : 1980.
186 Finishes ofr Wooden Furniture BS 3962: Part 2 & 3 : 1983.
187 Clear finishes for wooden furniture BS 3962 : Part 6: 1975.
188 Assessment and labelling of textile floor coverings tested BS 5287: 1988.
189 Assessment and labelling of textile floor coverings tested BS 5287: 1976.
190 Backed flexible PVC flooring BS 5085 : Part 1&2 : 1976.
191 Asbestos-cement slates BS 690: Part 5: 1975.
192 Bonding agents for USE with gypsum plasters and Cement BS 5270: Part 1: 1989.
193 Polyvinyle acetate (PVAC) emulsion bonding agents for internal use with gypsum building plaster BS
5270: 1976.
194 Asbestos-cement slates BS 690: Part 5: 1976.
195 Powder organic coatings for application and stoving to aluminium alloy extrusion, sheet and preformed
sections for external architectural purpose, and for the finish on aluminium alloy extrusions, sheet and
preformed sections coating with powder organic coating BS 6496: 1984.
196 Anodic oxide coatings on wrought aluminium for external architectural applications BS 3987:1974.
197 Low heat Portland cement BS 1970: Part 2: 1974.
198 Asbestos-cement slates and sheets BS 690: Part 4: 1974.
199 Design and installation of natural stone cladding and lining BS 8298: 1989.
200 Stoving Organic Finishes on Aluminium Extrusions and Preformed Sections for External Architecturla
Application.
201 Plywood BS 6566: Part 1,2,3,4,5,6,7&8: 1985.
202 Unbacked flexible PVC flooring BS 3261: Part 1: 1973.
203 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.19.1: 1985
204 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.22.1: 1985
205 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.26.5: 1985
206 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.28.1: 1985
207 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.33.3: 1985
208 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.26.3: 1985
Sr.
Title of Books
No.
209 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.18.3: 1985
210 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.20.3: 1985
211 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.24.1: 1985
212 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.32.4: 1985
213 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.24.2: 1985
214 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.12.3: 1986
215 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.12.1: 1986
216 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.22.3: 1986
217 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.12.4: 1986
218 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.29.1: 1986
219 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.16.1: 1986
220 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.12.5: 1986
221 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.22.1: 1986
222 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Part 4:1989
223 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.34.2: 1989
224 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.20.1: 1989
225 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.21.1: 1986
226 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.20.4: 1986
227 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.16.2: 1986
228 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.37.1: 1986
229 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.1.5: 1985
230 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.1.4: 1985
231 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.10.1: 1985
232 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.7.1: 1987
233 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.12.5: 1986
234 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.34.1: 1987
235 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.10.2: 1989
236 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.26.4: 1989
237 Testing concrete BS 1881: Part 120: 1983.
238 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.8.1: 1985
239 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.10.4: 1985
240 Sampling and analysis of iron, steel and other ferrous metals BS 6200: Subsection 3.18.2: 1985
241 Preparation of steel substrates before application of paints and related products BS 7079: Part
C1,C3&C4: 1989.
242 Methods for Tensile Testing of Metals BS 18:Part 2. 1970.
243 Paint colours for building purposes BS 4800: 1989.
244 Paint colours for building purposes BS 4800: 1981.
245 Paints BS 3900: Part A8,A13&A14: 1986.
246 Flashpoint of Petroleum and related products BS 6664: Part 1,3&4: 1986.
247 Assessment of resistance to fungal growth BS 3900: Part G6: 1989.
248 Examination and preparation of samples for testing BS 3900: Part A2: 1983.
249 Standard panels for paints testing BS 3900: Part A3: 1986.
250 Determination of flow time by use of flow cups BS 3900: Part A6: 1983.
251 Determination of flow time by use of flow cups BS 3900: Part A6: 1986.
252 Determination of volume of dry coating (non-volatile matter) obtained from a given volume of liquid
coating BS 3900: Part A10: 1985.
253 Rapid test for determination of danger classification by flashpoint BS 3900: Part A13&A14: 1978.
254 Determination of natural spreading rate by brush application BS 3900: Part A16: 1986.
255 Coating of test panels at a specified spreading rate BS 3900: Part A17: 1986.
256 Determination of 'soluble' lead in the solid matter in liquid paints: method for use in conjunction with The
257 Determination of total lead in paints and similar materilas BS 3900: Part B4: 1986.
258 Preparation of steel substrates before application of paints & related products BS3900:PartB5:1986
259 Determination of 'soluble' lead content BS 3900: Part B6: 1989.
260 Determination of 'soluble' antimony content BS 3900: Part B7: 1986.
261 Determination of 'soluble' barium content BS 3900: Part B8: 1986.
262 Determination of 'soluble' cadmium content BS 3900: Part B9: 1986.
263 Determination of hexavalent chroimium content of solid matter BS 3900: Part B10:1986.
Sr.
Title of Books
No.
264 Determination of 'soluble' mercury content BS 3900: Part B 12: 1986.
265 Rapid method for estimation of lead in liquid paints BS 3900: Part B15: 1987.
266 Determination of colour and colour difference measurement BS 3900: Part D9: 1986.
267 Determination of colour and colour difference principles BS 3900: Part D8: 1986.
268 Measurement of specular gloss of non-metallic paint films at 20 o, 60o and 85o BS: Part D5: 1980
269 Determination of fineness of grind BS 3900: Part C6: 1983.
270 Pressure test for stackability BS 3900: Part C7: 1982.
271 Methods for evaluation of the compatibility of a product with a surface to be painted BS 3900: Part C9:
1982.
272 Determination of contrast ratio (opacity) of light-coloured paints at a fixed spreading rate, using
polyester film BS 3900: Part D6: 1982.
273 Determination of hiding power of white and light-coloured paints by the Kubelka-Munk method BS 3900:
Part D7: 1983.
274 Particleboard BS 5669: Part 2&5: 1989.
275 Steel Windows Generally for Domestic and Similar Buildings BS 990: Part 2: 1972.
276 Plywood BS 1455: August 1972
277 Determining thermal insulating properties BS 874: Part 2 Section 2.2: 1988.
278 Determining thermal insulating properties BS 874: Part 1: 1986.
279 Determining thermal insulating properties BS 874: Part 2 section 2.1: 1986.
280 Determining thermal insulating properites BS 874: Part 3 section 3.1: 1987.
281 Thermal insulation materials BS 3958: Part 5: 1986.
282 Thermal insulation materials BS 3958: Part 2&4: 1982.
283 Thermal insulation materials BS 3958: Part 3: 1985.
284 Inorganic thermal insulating materials BS 2972: 1989.
285 Methods of Test for Paints BS 3900.
286 Pigments for Paints BS 3483: Introduction: march 1974.
287 Particleboard BS 5669: Part 1: 1989.
288 Graduated dial scales for ophthalmic instrucment BS 6903-1987.
289 Clay and calcium silicate pavers for flexible pavements BS 6677: Part 1,2&3: 1986
290 Straightedges BS 5204: Part 2: 1977.
291 Corrosion resisting high silicon iron castings BS 1591: 1975.
292 Protective coating of iron and steel structures against corrosion BS 5493: 1977.
293 Slating and tiling BS 5534: Part 1&2: 1990
294 Ready-mixed building mortars BS 4721: 1981.
295 Carbon steel bars for the reinforcement of concrete BS 4449: 1988.
296 Fibre building boards BS 1142: 1989.
297 Agricultural food products BS 6215: Part 2: 1981.
298 Cast stone BS 1217: 1975.
299 Supersulphated cement BS 4248: 1974.
300 Low heat Portland cement BS 1370: 1979.
301 Mosaic Parquet panels BS 4050: Part 1: 1977.
302 Suspended safety chairs and cradles for use in the construction industry BS 2830:1973.
303 Clay Bricks and Blocks BS 3921: May: 1974.
304 Wall and floor tiling BS 5385: Part 3&4: 1986.
305 Determination of colour and colour difference calculation BS 3900: Part D10: 1986.
306 Bend test (Conical mandrel) BS 3900: Part E11: 1985.
307 Indentation Test (spherical or pyramidal) BS 3900: Part E12: 1986.
308 Notes for guidance on the operation of artificail weathering apparatus to BS 3900: Part F3 1971
309 Determination of resistance to humidity (continuous condensation) BS 3900: Part F9: 1982.
310 Determination of resistance to cathodic disbonding of coatings for use in marine environments BS
3900: Part F10: 1985.
311 Determination of resistance to cathodic disbonding of coatings for use on land-based buried structures
BS 3900: Part F11: 1985.
312 Determination of resistance to neutral salt spray BS 3900: Part F12: 1985.
313 Filiform corrosion test on steel BS 3900: Part F13: 1986.
314 Designation of quantity and size of common types of defect: general principles and pictorial scales for
Sr.
Title of Books
No.
315 Designation of intensity, quantity and size of common types of defect: general principles and rating
schemes BS 3900: Part H1: 1983.
316 Designation of degree of blistering BS 3900: Part H2: 1983.
317 Designation of degree of rusting BS 3900: Part H3: 1983.
318 Designation of degree of cracking BS 3900: Part H4: 1983.
319 Designation of degree of flaking BS 3900: Part H5: 1983.
320 Sampling of coating powders BS 3900: Part J1: 1987.
321 Determinationn of particle size distribution of coating powders by sieving BS 3900: Part J2: 1987.
322 Determination of the gelation time of coating powders BS 3900: Part J3: 1987.
323 Determination of the storage stability of coating powders BS 3900: Part J4: 1987.
324 Preparationn of steel substrates before application of paints and related products BS 7079: Part C2:
1989.
325 Determination of loss of mass on heating coating powders BS 3900: Part J5: 1988.
326 Determination of the preventive action of wood preservatives against Reticulitermes santonensis de
Feytaud (Laboratory method) BS 6240: 1982.
327 Determination of the toxic values of wood preservatives against Reticulitermes santonensis de Feytaud
(Laboratory method) BS 6239: 1982.
328 One-part gun grade polysulphide-based sealants BS 5215: 1986.
329 Wrought aluminium and aluminium alloys for general engineering purposes: bars, extruded round tubes
and sections BS 1474:1987.
330 Glass for glazing BS 952: Part 1&2: 1978.
331 Aluminium alloy windows BS 4873: 1986.
332 Serverity levels for discontinuities in steel castings BS 4080: Part 1&2: 1989.
333 Cold-reduced tinplate and cold-reduced blackplate BS 2920:1973.
334 Cold-rolled steel sections BS 2994: 1976.
335 Rigid urethane foam for building applications BS 4841: Part 1: 1975.
336 Expanded polystyrene boards BS 3837: Part 1: 1986.
337 Rigid urethane foam in slab form for transport containers, refrigerator cabinets and cold stores BS
4840:1973.
338 Toughened polystyrene (SB) moulding and extrusion materials BS 3126:1987.
339 Expanded polystyrene boards BS 3837: 1977.
340 Thermal insulation of roofs exxternally by means of sprayed rigid polyurethane (PUR) or
polyisocyanurate (PIR) foam BS 7021:1989.
341 Elastomeric threads BS 5421: Part 1&2: 1978.
342 Rigid polyurethane (PUR) and polyisocyanurate (PIR) foam for building applications BS 4841: Part
3:1987.
343 Rigid polyurethane (PUR) foam in slab form BS 4840:Part 1:1985.
344 Rigid urethane foam for building applications BS 4841: Part 2: 1975.
345 Rigid urethane foam when dispensed or sprayed on a construciton site BS 5241:1975.
346 Rigid polyurethane (PUR) and polyisocyanurate (PIR) foam when dispensed or sprayed on a
construction site BS 5241: Part 1: 1989.
347 Steel wire for hose reinforcement BS 3592: Part 1: 1986.
348 Stainless and heat-resisting steel round wire BS 1554:1981.
349 Structural steel sectionns BS 4:Part 1: 1980
350 Corrosion testing of metallic coatings BS 5466: Part 1&2: 1977.
351 Bending dimensions and scheduling of reinforcement for concrete BS 4466:1981.
352 Steel wire for hose reinforcement BS 3592: Part 1&2: 1986.
353 Corrosion testing of metallic coatings BS 5466: Part 7: 1982.
354 Windows, doors and rooflights BS 8213:Part 4: 1990.
355 Corrosion testing of metallic coatings BS 5466: part 4&5: 1979.
356 Corrosion testing of metallic coatings BS 5466: Part 8&9: 1986.
357 Approval testing of velding procedures BS 4870: Part 4 : 1988.
358 Mild steel wire for general engineering purposes BS 1052:1980.
359 Scheduling, dimensioning, bending and cutting of steel reinforcement for concrete BS 4466:1989.
360 Approval testing of welding procedures BS 4870: Part 3: 1985.
361 Clindical maximum thermometers (meercury-in-glass) BS 691:1979.
Sr.
Title of Books
No.
362 Steel pipes and tubes for pressure purposes: carbon and carbonn manganese steel with specified
elevated temperature properties BS 3602: Part 1: 1978.
363 Approval testing of welding procedures BS 4870: Part 1: 1974.
364 Steel pipes and tubes for pressure purposes: carbon and carbonn manganese steel with specified
365 Wrought steels for mechanical and allied engineering purposes BS 970: Part 1&2: 1983.
366 Determination and verification of the effective depth of carburized and hardened cases in steels bS
6479: 1984.
367 Wrought steels BS 970: Part 6: 1973.
368 Steel pipes and tubes for pressure purposes carbon and carbon manganese steel with specified
elevated temperature properties BS 3602: Part 2: 1978.
369 Matchboarded wooden door leaves for external use BS 459: 1988.
370 Asbestos-cement slates and sheets BS 690: Part 2: 1981.
371 Asbestos-cement slates and sheets BS 690: Part 3: 1973.
372 Approval testing of welding procedures BS 4870: Part 2: 1982.
373 Approval tseting of welding procedures BS 4870: Part 1: 1981.
374 Fusion welding of steel castings BS 4570:1985.
375 Corrosion testing of metallic coatings BS 5466: Part 6: 1982.
376 Fusion welding of steel castings BS 4570: Part 2: August 1972.
377 Portland Cement BS 12: 1958.
378 Wall tiling BS 5385: Part 1&2: 1978.
379 Expanded polystyrene boards BS 3837: Part 2 : 1990.
380 Adhesives for use with ceramic tiles and mosaics BS 5980: 1980.
381 Slating and tiling BS 5534: Part 1: 1978
382 Glazed ceramic tiles and tile fittings for internal walls BS 1281: July 1974.
383 Glazed ceramic tiles and tile fittings for internal walls BS 1281: 1974.
384 Wall and floor tiling BS 5385: Part 1: 1990
385 Thermal insulating materials BS 3858: Part 6: 1972.
386 Precast concrete paving blocks BS 6717: Part 1: 1986.
387 Solid rubber flooring BS 1711: 1975.
388 Concrete flooring tiles and fittings BS 1197: Part 2: 1973.
389 Precast concrete paving blocks BS 6717: Part 3: 1989
390 Rubber mats for electrical purposes BS 921:1976.
391 Rubber gloves for electrical purposes BS 697: 1986.
392 Rubber gloves for electrical purposes BS 697: 1977.
393 Determining thermal insulating properties with definitions of thermal insulating terms BS 874: 1973.
394 Particleboard BS 5669: Part 4: 1989.
395 Ceramic floor and wall tiles BS 6431: Part 1: 1983
396 Ceramic floor and wall tiles BS 6431: Part 2: 1984
397 Ceramic floor and wall tiels BS 6431: Part 3,4&5: 1986.
398 Ceramic floor and wall tiels BS 6431: Part 6: 1984
399 Ceramic floor and wall tiels BS 6431: Part 7: 1986.
400 Ceramic floor and wall tiels BS 6431: Part 8: 1986.
401 Ceramic floor and wall tiels BS 6431: Part 9: 1984.
402 Ceramic floor and wall tiels BS 6431: Part 9: 1984.
403 Ceramic floor and wall tiels BS 6431: Part 10: 1984.
404 Ceramic floor and wall tiels BS 6431: Part 11: 1983.
405 Ceramic floor and wall tiels BS 6431: Part 12: 1983.
406 Ceramic floor and wall tiels BS 6431: Part 13: 1986.
407 Ceramic floor and wall tiels BS 6431: Part 14: 1983.
408 Ceramic floor and wall tiels BS 6431: Part 15: 1986.
409 Ceramic floor and wall tiels BS 6431: Part 17: 1986.
410 Ceramic floor and wall tiels BS 6431: Part 19: 1984.
411 Ceramic floor and wall tiels BS 6431: Part 20: 1984.
412 Ceramic floor and wall tiels BS 6431: Part 21: 1984.
413 Ceramic floor and wall tiels BS 6431: Part 22: 1986.
414 Ceramic floor and wall tiels BS 6431: Part 26: 1986.