Saudi Aramco Inspection Checklist 6232

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 19
At a glance
Powered by AI
The document discusses requirements and guidelines for properly handling, storing, preserving, rigging, and preparing centrifugal pumps for shipment according to industry standards.

The document outlines requirements from API 610, API 686, 31-SAMSS-004, and Saudi Aramco procedures for properly securing pumps, wrapping exposed components, and following vendor instructions.

API RP 686 Section 2 and Attachment 3 provide details on rigging and lifting pumps safely according to industry best practices.

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Handling, Storage & Preserv. Insp of Centrifugal Pumps SAIC-G-2003 30-Apr-13 MECH-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

JIGCC POWER BLOCK PROJECT 10-01525-0004 SEPCO2


EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
S-0134-0001-B-10 lube oil Package EPC=04 A10
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
IGCI-A10-73-A0001-DA
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
7-8-2017@ 9:15 7-8-2017@ 9:15 SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
SATIP-G-005-01 1-Jan-00
SAUDI ARAMCO INSPECTION LEVEL
W
CONTRACTOR INSPECTION LEVEL
H
NO
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A. General Requirements

Storage, handling & preservation of equipment is implemented & follows


a project approved construction and/or quality procedure.
The procedure includes:
A) Vendor or Manufacturer's recommendations Schedule Q,
A1 B) API 610 & API 686 Requirements Attach. IV,
C) 31-SAMSS-004 requirements Para. 6
D) This checklist &
attachments Note:
List project procedure ____________________________

Vendor has provided to purchaser the instructions necessary to preserve


the integrity of the storage preparation after equipment arrives at the job
31-SAMSS-004,
A2 site and before start-up (per API RP 686).
Para. 1 (scope)
API 610 Para. 7.4.2). See Attachment 1 for API 686 Checklist
Complete Appendix B & Attach to this Checklist

31-SAMSS-004,
A3 All rotors are properly secured to prevent axial and radial movement.
Para. 7.4.1

31-SAMSS-004,
A4 Coupling spacers are found removed once received the shipment.
Para. 7.4.3.1

Small or fragile components are found tagged, wrapped in waterproof 31-SAMSS-004,


A5
material and packed in a box, fastened to the unit skid or baseplate. Para. 7.4.8

Typical Requirement - Exposed shafts and shaft couplings are wrapped


with waterproof, moldable waxed cloth or volatile corrosion inhibitor
paper. The seams are sealed with oil proof adhesive tape. (API 610 31-SAMSS-004,
A6
Para. 7.4.3.10). See Attachment 2 Ensure that Para. 2.5
all listed requirements in Attachment 2 are met regarding
preparation for Shipment & Initial Preservation

Related Rigging & Lifting of equipment follows API RP 686 Sect. 2.


See Attachment 3 for 31-SAMSS-004,
A7
API 686 Section 2 Details. Even small Para. 1 (scope)
pumps can be damaged by improper lifts.

REMARKS:

ATTACHMENTS: ATTACHMENT 1 - API RP 686 JOBSITE RECEIVING & PROTECTION REQMTS


ATTACHMENT 2 - API RP 610 PREPARATION FOR SHIPMENT (PROTECTION REQMTS)
ATTACHMENT 3 - API RP 686 RIGGING & LIFTING
REFERENCE DOCUMENTS: 1. Schedule Q - Project Quality Requirements, (Latest edition)
2. 31-SAMSS-004 -- Centrifugal Pumps, (30 April 2012)
3. API 610 -- Centrifugal Pumps for Petroleum, Heavy Duty Chemicals, and Gas Industry Services, (Eleventh Edition, September 2010)
4. SAES-G-005 -- Centrifugal Pumps, (28 July 2009)
5. API 686 -- Recommended Practices for Machinery Installation & Installation Design (SECOND EDITION, DECEMBER 2009)

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Page 1 of 19
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Handling, Storage & Preserv. Insp of Centrifugal Pumps SAIC-G-2003 30-Apr-13 MECH-
ATTACHMENT 1 - API RP 686 JOBSITE RECEIVING & PROTECTION REQMTS
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Handling, Storage & Preserv. Insp of Centrifugal Pumps SAIC-G-2003 30-Apr-13 MECH-
ATTACHMENT 2 - API RP 610 PREPARATION FOR SHIPMENT (PROTECTION REQMTS)
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Handling, Storage & Preserv. Insp of Centrifugal Pumps SAIC-G-2003 30-Apr-13 MECH-

ATTACHMENT 3 - API RP 686 RIGGING & LIFTING

REMEMBER, EVEN SMALL PUMPS CAN BE DAMAGED


BY IMPROPER LIFTS
REMEMBER, EVEN SMALL PUMPS CAN BE DAMAGED
BY IMPROPER LIFTS