FACTOR METHOD
WIND LOAD – LONGITUDINAL SECTION
COMPUTATION OF STIFFNESS
I
K=
L
Where:
bh3
I=
12
L = Length of beams and column
SIZES OF COLUMNS AND BEAMS
COLUMNS, in mm BEAMS, in mm HEIGHT, in meters
FIRST FLOOR 500 500 450 500 4
SECOND FLOOR 450 450 400 450 4
STIFFNESS COMPUTATIONS, in mm3
FOR COLUMNS, x 10 4 mm3
GROUND TO SECOND FLOOR 130.2
SECOND FLOOR TO ROOF TOP 85.4
FOR BEAMS, x 10 4 mm3
WIDTH, in meters 2ND FLOOR LEVEL ROOF LEVEL
B1 6 78.1 50.6
B2 5 93.8 60.8
B3 5 93.8 60.8
B4 6 78.1 50.6
B5 5 93.8 60.8
B6 5 93.8 60.8
B7 6 78.1 50.6
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph
COMPUTATION OF GIDER FACTOR, G FOR EACH JOINT
∑k COLUMN
G=
∑ k @ JOINT
ROOF LEVEL SECOND FLOOR LEVEL
C-D 0.628 B-E 0.734
D-C 0.434 E-B 0.556
D-I 0.434 E-H 0.556
I-D 0.413 H-E 0.535
I-J 0.413 H-K 0.535
J-I 0.434 K-H 0.556
J-O 0.434 K-N 0.556
O-J 0.434 N-K 0.556
O-P 0.434 N-Q 0.556
P-O 0.413 Q-N 0.535
P-U 0.413 Q-T 0.535
U-P 0.434 T-Q 0.556
U-V 0.434 T-W 0.556
V-U 0.628 W-T 0.734
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph
COMPUTATION OF COLUMN FACTOR, C
C = 1 – GIRDER FACTOR
ROOF LEVEL SECOND FLOOR LEVEL
B-C 0.266 A-B 1
C-B 0.372 B-A 0.266
E-D 0.444 F-E 1
D-E 0.566 E-F 0.444
H-I 0.465 G-H 1
I-H 0.587 H-G 0.465
K-J 0.444 L-K 1
J-K 0.566 K-L 0.444
N-O 0.444 M-N 1
O-N 0.566 N-M 0.444
Q-P 0.465 R-Q 1
P-Q 0.587 Q-R 0.465
T-U 0.444 S-T 1
U-T 0.566 T-S 0.444
W-V 0.266 X-W 1
V-W 0.372 W-X 0.266
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph
COMPUTATION OF GIRDER MOMENT FACTOR
GMF = SUM OBTAINED x k
ROOF LEVEL SECOND FLOOR LEVEL
GMFCD 0.845 x 50.6 = 42.753 GMF BE 1.012 x 78.1 = 79.059
GMF DC 0.748 x 50.6 = 37.844 GMF EB 0.923 x 78.1 = 72.120
GMF DI 0.640 x 60.8 = 38.926 GMF EH 0.824 x 93.8 = 77.268
GMF ID 0.630 x 60.8 = 38.276 GMF HE 0.813 x 93.8 = 76.252
GMF IJ 0.630 x 60.8 = 38.276 GMF HK 0.813 x 93.8 = 76.252
GMF JI 0.640 x 60.8 = 38.926 GMF KH 0.824 x 93.8 = 77.268
GMF JO 0.651 x 50.6 = 32.936 GMF KN 0.835 x 78.1 = 65.181
GMFOJ 0.651 x 50.6 = 32.936 GMF NK 0.835 x 78.1 = 65.181
GMFOP 0.640 x 60.8 = 38.926 GMF NQ 0.824 x 93.8 = 77.268
GMF PO 0.630 x 60.8 = 38.276 GMFQN 0.813 x 93.8 = 76.252
GMF PU 0.630 x 60.8 = 38.276 GMFQT 0.813 x 93.8 = 76.252
GMFUP 0.640 x 60.8 = 38.926 GMFTQ 0.824 x 93.8 = 77.268
GMFUV 0.748 x 50.6 = 37.844 GMFTW 0.923 x 78.1 = 72.120
GMFVU 0.845 x 50.6 = 42.753 GMFWT 1.012 x 78.1 = 79.059
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph
COMPUTATION OF COLUMN MOMENT FACTOR
CMF = SUM OBTAINED x k
2ND FLOOR TO ROOF LEVEL (k = 85.4) GROUND TO 2ND FLOOR (k = 130.2)
CMF CB 0.505 x 85.4 = 43.129 CMF BA 0.766 x 130.2 = 99.723
CMF BC 0.452 x 85.4 = 38.596 CMF AB 1.133 x 130.2 = 147.511
CMF DE 0.788x 85.4 = 67.284 CMF EF 0.944 x 130.2 = 122.858
CMF ED 0.727 x 85.4 = 62.055 CMF FE 1.222 x 130.2 = 159.079
CMF IH 0.820 x 85.4 = 70.035 CMF HG 0.965 x 130.2 = 125.679
CMF HI 0.759 x 85.4 = 64.818 CMF GH 1.233 x 130.2 = 160.490
CMF JK 0.788 x 85.4 = 67.284 CMF KL 0.944 x 130.2 = 122.858
CMF KJ 0.727 x 85.4 = 62.055 CMF LK 1.222 x 130.2 = 159.079
CMF ON 0.788 x 85.4 = 67.284 CMF NM 0.944 x 130.2 = 122.858
CMF NO 0.727 x85.4 = 62.055 CMF MN 1.222 x 130.2 = 159.079
CMF PQ 0.820 x 85.4 = 70.035 CMF QR 0.965 x 130.2 = 125.679
CMF QP 0.759 x 85.4 = 64.818 CMF RQ 1.233 x 130.2 = 160.490
CMF UT 0.788 x 85.4 = 67.284 CMF TS 0.944 x 130.2 = 122.858
CMF TU 0.727 x 85.4 = 62.055 CMF ST 1.222 x 130.2 = 159.079
CMF VW 0.505 x 85.4 = 43.129 CMF WX 0.766 x 130.2 = 99.723
CMF WV 0.452 x 85.4 = 38.596 CMF XW 1.133 x 130.2 = 147.511
∑Q 950.511 ∑Q 2194.555
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph
COMPUTATION OF CONSTANT, N X
FORMULA:
∑ H (h)
N X=
∑QCOLUMN
WHERE:
N X – Moment constant @ x-storey
∑ H - Sum of lateral forces for x-storey
∑ Q - Sum of column moments factor for the storey
h – Height of every storey
2ND STOREY
∑H = 6 + 3 = 9
∑ Q = 950.511
h=4
9 (4)
N X=
950.511
N X =0.037874
1ST STOREY
∑ H = 6 + 3 + 7.50 + 4.00 = 20.5
∑ Q = 2194.555
h=4
20.5(4 )
N X=
2194.555
N X =0.037365
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph
COMPUTATION OF COLUMN MOMENT
CM =N X (CMF)
2ND STOREY 1ST STOREY
CM CB 43.129 x 0.037874= 1.633 CM BA 99.723 x0.037365 = 3.726
CM BC 38.596 x 0.037874 = 1.462 CM AB 147.511 x 0.037365 = 5.512
CM DE 67.284 x 0.037874 = 2.548 CM EF 122.858 x 0.037365 = 4.591
CM ED 62.055 x 0.037874 = 2.350 CM FE 159.079 x 0.037365 = 5.944
CM IH 70.035 x 0.037874 = 2.653 CM HG 125.679 x 0.037365 = 4.696
CM HI 64.818 x 0.037874 = 2.455 CM GH 160.490 x 0.037365 = 5.997
CM JK 67.284 x 0.037874 = 2.548 CM KL 122.858 x 0.037365 = 4.591
CM KJ 62.055 x 0.037874 = 2.350 CM LK 159.079 x 0.037365 = 5.944
CM ON 67.284 x 0.037874= 2.548 CM NM 122.858 x 0.037365 = 4.591
CM NO 62.055 x 0.037874= 2.350 CM MN 159.079 x 0.037365 = 5.944
CM PQ 70.035 x 0.037874= 2.653 CM QR 125.679 x 0.037365 = 4.696
CM QP 64.818 x 0.037874= 2.455 CM RQ 160.490 x 0.037365 = 5.997
CM UT 67.284 x 0.037874 = 2.548 CM TS 122.858 x 0.037365 = 4.591
CM TU 62.055 x 0.037874 = 2.350 CM ST 159.079 x 0.037365= 5.944
CM VW 43.129 x 0.037874 = 1.633 CM WX 99.723 x 0.037365 = 3.726
CM WV 38.596 x 0.037874= 1.462 CM XW 147.511 x 0.037365 = 5.512
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph
COMPUTATION OF JOINT FACTOR, J FOR GIRDER
∑ M Columnmoment @ joint
J=
∑ Q GMF @ joint
ROOF LEVEL 2ND FLOOR LEVEL
1.633 0.0382 1.462+3.726 0.0656
@ Joint C= @ Joint B=
42.753 79.059
2.548 0.0332 2.350+4.591 0.0465
@ Joint D= @ Joint E=
37.844+38.926 72.120+77.268
2.653 0.0347 2.455+ 4.696 0.0469
@ Joint I = @ Joint H=
38.276+38.276 76.252+76.252
2.548 0.0355 2.350+ 4.591 0.0487
@ Joint J = @ Joint K=
38.926+32.936 77.268+65.181
2.548 0.0355 2.350+ 4.591 0.0487
@ Joint O= @ Joint N =
38.926+32.936 77.268+65.181
2.653 0.0347 2.455+ 4.696 0.0469
@ Joint P= @ Joint Q=
38.276+38.276 76.252+76.252
2.548 0.0332 2.350+ 4.591 0.0465
@ Joint U= @ Joint T =
37.844+38.926 77.267+72.120
1.633 0.0382 1.462+3.726 0.0656
@ Joint V = @ Joint W =
42.753 79.059
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph
COMPUTATION OF GIRDER MOMENTS
ROOF LEVEL SECOND FLOOR LEVEL
GM CD 42.753 x 0.0382 = 1.633 GM BE 79.059 x 0.0656 = 5.188
GM DC 37.844 x 0.0332 = 1.256 GM EB 72.120 x 0.0465 = 3.351
GM DI 38.926 x 0.0332 = 1.292 GM EH 77.268 x 0.0465 = 3.590
GM ID 38.276 x 0.0347 = 1.326 GM HE 76.252 x 0.0469 = 3.575
GM IJ 38.276 x 0.0347 = 1.326 GM HK 76.252 x 0.0469 = 3.575
GM JI 38.926 x 0.0355 = 1.380 GM KH 77.268 x 0.0487 = 3.765
GM JO 32.936 x 0.0355 = 1.168 GM KN 65.181 x 0.0487 = 3.176
GM OJ 32.936 x 0.0355 = 1.168 GM NK 65.181 x 0.0487 = 3.176
GM OP 38.926 x 0.0355 = 1.380 GM NQ 77.268 x 0.0487 = 3.765
GM PO 38.276 x 0.0347 = 1.326 GM QN 76.252 x 0.0469 = 3.575
GM PU 38.276 x 0.0347 = 1.326 GM QT 76.252 x 0.0469 = 3.575
GM UP 38.926 x 0.0332 = 1.292 GM TQ 77.268 x 0.0465 = 3.590
GM UV 37.844 x 0.0332 = 1.256 GM TW 72.120 x 0.0465 = 3.351
GM VU 42.753 x 0.0382 = 1.633 GM WT 79.059 x 0.0656 = 5.188
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph
WIND LOAD – LONGITUDINAL SECTION
(FACTOR METHOD)
SUMMARY TABLE
JOINTS MEMBERS MOMENT (kN·m)
GIRDER COLUMN
A A-B 5.512
B-A 3.726
B B-E 5.188
B-C 1.462
C C-B 1.633
C-D 1.633
D D-C 1.256
D-E 2.548
D-I 1.292
E-B 3.351
E E-D 2.350
E-F 4.591
E-H 3.590
F F-E 5.944
G G-H 5.997
H-G 4.696
H H-E 3.575
H-I 2.455
H-K 3.575
I I-D 1.326
I-H 2.653
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph
I-J 1.326
J-I 1.380
J J-K 2.548
J-O 1.168
K-J 2.350
K K-H 3.765
K-L 4.591
K-N 3.176
L L-K 5.944
M M-N 5.944
N-K 3.176
N N-M 4.591
N-O 2.350
N-Q 3.765
O-J 1.168
O O-N 2.548
O-P 1.380
P P-O 1.326
P-Q 1.768
P-U 1.326
Q Q-N 3.575
Q-P 2.455
Q-R 4.696
Q-T 3.575
R R-Q 5.997
S S-T 5.944
T-Q 3.590
T T-S 4.591
T-U 2.350
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph
T-W 3.351
U U-P 1.292
U-T 2.548
U-V 1.256
V V-U 1.633
V-W 1.633
W W-T 5.188
W-V 1.462
W-X 3.726
X X-W 5.512
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph
UNIVERSITY OF BATANGAS
COLLEGE OF ENGINEERING
CIVIL ENGINEERING DEPARTMENT
STRUCTURAL DESIGN 1 (REINFORCED CONCRETE)
LABORATORY
TWO STOREY OFFICE BUILDING
GONZALES, SARAH MAE T.
1100779
ENGR. RONALD ALBAY
JUNE 27, 2017
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph
Campuses: Hilltop | MH del Pilar | Pallocan East | Pallocan West | Lipa
Telephone Numbers: +63 43 723 1446 | 980 0041
Website: www.ub.edu.ph