Cost of the Project and Means of Finance

Amounts
in lakhs
Cost of Project
Schedule
S. No. Particulars
Nos.
1. Land 1
2. Cost of Construction 2
3 Animals 3
4 Machinery & Acessories 4
5. Electrical Equipments&Erections
6. Pre Operative Expenses
8. Margin for Working Capital
Total

Means of Finance

S. No. Particulars Ratio

1. Equity 26%
2. Term Loan 74%
Total

Term loan Disbursment Schedule

Particulars October
Land 15.00
Cost of Construction 50.06
Animals 0.00
Machinery & Acessories 83.01
Electrical Equipments&Erections 1.88
Total Monthly Requirement 149.95
Cumulative Monthly Requirement 149.95

Schedule for procurement of animals


Particulars October

Buffalos
Cows
Bulls

Total 0

No. of Days

Total Cost of Buffaloes 0


Total Cost of Cows 0
Total Cost of Bulls 0
Monthly Requirement 0
f Finance

100000

Total
(Rs.In Lakhs)
20.00
66.75
370.00
110.68
2.50
0.50
3.79
574.22

Value
(Rs.In Lakhs)

146.77
427.45
574.22

Debt Portion 75%

November December January Feburary March April


0 0 0 0 0 0
0 0 0 0 0 0
0.00 29.63 29.63 29.63 31.50 31.50
0 0 0 0 0 0
0 0 0 0 0 0
0.00 29.63 29.63 29.63 31.50 31.50
149.95 179.57 209.20 238.82 270.32 301.82
November December January Feburary March April

50 50 50 50 50
5 5 5 5 5
0 0 0 5 5

0 55 55 55 60 60

0 3750000 3750000 3750000 3750000 3750000


0 200000 200000 200000 200000 200000
0 0 0 0 250000 250000
0 3950000 3950000 3950000 4200000 4200000
May June July August September Total
0 0 0 0 0
0 0 0 0 0
25.88 25.88 25.88 24.00 24.00
0 0 0 0 0
0 0 0 0 0
25.88 25.88 25.88 24.00 24.00
327.70 353.57 379.45 403.45 427.45
May June July August September Total

40 40 40 40 40 450
5 5 5 5 5 50
5 5 5 25
0
50 50 50 45 45 525

3000000 3000000 3000000 3000000 3000000


200000 200000 200000 200000 200000
250000 250000 250000 0 0
3450000 3450000 3450000 3200000 3200000
Schedules to Cost of Project

Schedule - 1 - Cost of Land

Area in
Particulars Rate/Acre Total Cost
Acres

Land Area 10.00 200,000 2,000,000

SCHEDULE : 2 - Cost of Construction of Sheds

Area Per Cost of


No of Total Area (in
Particulars Animal In Construction
Animals sq. ft.)
Sq.ft. per sq.ft.

Buffalos 50 200 250.00 12,500.00


Cows 50 200 250.00 12,500.00
Bulls 50 200 25.00 1,250.00
Storage Yard 10 200 525.00 5,250.00

Cost of Construction of Sheds


Cost of Construction of Office Room 500 750

Total Cost of Construction

SCHEDULE : 3 - Cost of Animals

No. Of Cost per


Particulars Total Cost
Aninmals Animal

Buffalos 450 75000 33750000


Cows 50 40000 2000000
Bulls 25 50000 1250000

Total 525 37000000

SCHEDULE : 4 - Cost of Machinery & Equipment

S.No Details of Items needed Nos Total Cost


1 Tractor (60 HP) 1 620,000
2 Tractor Implements 250,000
3 Cattle / Fodder Truck 1,500,000
4 Personal Vehicle 900,000
5 Tata - 207 250,000
6 Seed - Cum ferti drill 50,000
7 Feed Mill 200,000
8 Fodder Mill 200,000
10 Chaff Cutters 200,000
11 Baler 250,000
12 Mud Pump 2 50,000
13 Presurre washers 100,000
14 Milking Equipment 1,200,000
15 Water Tankers 200,000
16 Cans / Utensils 300,000
17 Computor 100,000
18 Lap top 50,000
19 Office furniture 125,000
20 Motor Cycles 120,000
21 Feed basket 100,000
22 Fooder block machine 200,000
23 TV/VCP 50,000
24 FM Radio Station 500,000
25 Reapers 150,000
26 Fodder Harvester 500,000
27 Azolla Tanks 100,000
28 Shiftable Electric Fencing 200,000
29 Silpaulin Sheets 500,000
30 Fodder compacting Press 250,000
31 Electric Fencing 500,000
32 CBG equipment 1,000,000
33 Solar water heaters 100,000
34 Solar lighting systems 253,000

TOTAL 11,068,000

22136 15150

SCHEDULE : 5 - Working Capital

Particulars Year 1 Year 2 Onwards 2010-11 2011-12

Current Assets
Inventory 0.5 18.1
Green Fodder 1 4.00 0.2 7.2
Dry Fodder 1 4.00 0.2 5.0
Concentrate Feed 0.25 1.00 0.2 5.8
Accounts Receivables 0.25 1.00 1.2 29.3
Advances to Suppliers 3% 10% 0.3 10.6
Pre paid Insurance 12.5 0.0
Other CA 0.4% 2% 0.2 5.3
Total Current Assets 14.7 63.2

Current Liabilities
Accounts Payable 0.25 1.00 0.26 8.87
Other Current Liabilities 0.5% 2% 0.15 4.01
Total Current Liabilities 0.4 12.9
Non Cash Working Capital 14.3 50.3
Margin for Working Capital 3.8 25.3
Short Term Debt 10.5 25.0

27% 50%

Computation of tax

Provision for Income Tax 2.18 21.17 59.91


Advance Tax Paid 80% 1.7 16.9 47.9
Total Cost

2,500,000
2,500,000
250,000
1,050,000

6,300,000
375,000

6,675,000

500
as pre nabard

2012-13 2013-14 2014-15 2015-16 2016-17

22.8 22.8 22.8 22.8 22.8


9.0 9.0 9.0 9.0 9.0
6.6 6.6 6.6 6.6 6.6
7.2 7.2 7.2 7.2 7.2
40.6 40.6 40.6 40.6 40.6
13.3 13.3 13.3 13.3 13.3
0.0 0.0 0.0 0.0 0.0
7.3 7.3 7.3 7.3 7.3
84.0 84.0 84.0 84.0 84.0

11.08 11.08 11.08 11.08 11.08


4.59 4.59 4.59 4.59 4.59
15.7 15.7 15.7 15.7 15.7
68.3 68.3 68.3 68.3 68.3
68.3 68.3 68.3 68.3 68.3

100% 100% 100% 100% 100%

64.60 69.16 73.61 77.58


51.7 55.3 58.9 62.1
Projected Profitability Statement
PARTICULARS Schedules 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16

INCOME
Income from Sale of Milk A 55.44 337.68 473.76 473.76 473.76 473.76
Sale Value of Heifers B 0.00 8.10 8.10 8.10 8.10 8.10
Sale of Manure (Dung) C 1.31 5.25 5.25 5.25 5.25 5.25
Total 56.75 351.03 487.11 487.11 487.11 487.11

OPERATING EXPENSES:-
Cost of Dry Fodder D 2.06 21.66 26.97 26.97 26.97 26.97
Cost of Green Fodder E 1.82 15.11 19.78 19.78 19.78 19.78
Cost of Concentrate Feed F 8.58 69.63 86.21 86.21 86.21 86.21
Healthcare Expenses G 0.88 6.30 6.30 6.30 6.30 6.30
Insurance H 4.16 16.65 16.65 16.65 16.65 16.65
Salaries & Wages I 6.99 55.92 55.92 55.92 55.92 55.92
Electrical Charges J 0.55 5.25 5.25 5.25 5.25 5.25
Carriage & Handling Charges 0.55 3.38 4.74 4.74 4.74 4.74
Lease Rent for land (10000 per acre) 30 3.00 3.00 3.00 3.00 3.00 3.00
Other Expenses 0.55 3.38 4.74 4.74 4.74 4.74
Cost of Production 29.15 200.27 229.55 229.55 229.55 229.55

Gross Profit 27.60 150.76 257.56 257.56 257.56 257.56


Administrative expenses 1.39 8.44 11.84 11.84 11.84 11.84
Selling & General Expenses 0.55 3.38 4.74 4.74 4.74 4.74
Cost of Sales 31.09 212.09 246.13 246.13 246.13 246.13
EBIDTA 25.66 138.94 240.98 240.98 240.98 240.98
Depreciation 5.93 22.90 19.79 17.12 14.81 12.83
EBIT 19.74 116.05 221.19 223.86 226.16 228.15
Interest on Term Loan 12.98 50.39 44.92 33.80 22.69 11.58
Interest on Working Capital Loan 0.35 3.38 0.00 0.00 0.00 0.00
Profit Before Tax 6.41 62.28 176.27 190.06 203.47 216.57
Less:-Provision for Tax 33.99% 2.18 21.17 59.91 64.60 69.16 73.61
Profit after tax 4.23 41.11 116.36 125.46 134.31 142.96

Profitability Ratios
Gross Profit % 49% 43% 53% 53% 53% 53%
EBIDTA % 45% 40% 49% 49% 49% 49%
PBT% 11% 18% 36% 39% 42% 44%
PAT % 7% 12% 24% 26% 28% 29%
2016-17

473.76
8.10
5.25
487.11

26.97
19.78
86.21
6.30
16.65
55.92
5.25
4.74
3.00
4.74
229.55

257.56
11.84
4.74
246.13
240.98
11.12
229.85
1.62
0.00
228.23
77.58
150.66

53%
49%
47%
31% 0
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF!
#REF!
… Projected Funds Flow Statement
INR Lakhs
PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17

Sources of Funds
Long Term Sources
Net Profit 4.2 41.1 116.4 125.5 134.3 143.0 150.7
Depreciation 5.9 22.9 19.8 17.1 14.8 12.8 11.1
Increase in Share Capital…
Paidup Capital 146.8 - - - - - -
Increase in Term Liabilities…
Term Loans 427.4 - - - - - -
Long Term Sources 584.4 64.0 136.1 142.6 149.1 155.8 161.8
Short Term Sources
Increase In…
Sundry Creditors 0.3 8.6 2.2 - - - -
Provision for tax 2.2 19.0 38.7 4.7 4.6 4.5 4.0
Other Current Liabilities 0.1 3.9 0.6 - - - -
WC Borrowings 10.5 14.5 - - - - -
Decrease In…
Inventory - - - - - - -
Sundry Debtors - - - - - - -
Advances to Suppliers - - - - - - -
Advance tax paid - - - - - - -
Pre paid expenses - 12.5 - - - - -
Other Current Assets - - - - - - -
Short Term Sources 13.1 58.4 41.5 4.7 4.6 4.5 4.0
… Projected Funds Flow Statement
INR Lakhs
PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17

Uses of Funds
Long Term Uses
Increase in…
Fixed Assets 200.4 - - - - - -
Animals 370.0 - - - - - -
Decrease In…
Term Loans - 42.7 85.5 85.5 85.5 85.5 42.7
Unsecured Loans
Long Term Uses 570.4 42.7 85.5 85.5 85.5 85.5 42.7
Short Term Uses
Decrease In…
Sundry Creditors - - - - - - -
Provision for tax - - - - - - -
Other Current Liabilities - - - - - - -
WC Borrowings - - 25.0 - - - -
Increase In…
Inventory 0.5 17.6 4.7 - - - -
Sundry Debtors 1.2 28.1 11.3 - - - -
Advances to Suppliers 0.3 10.3 2.7 - - - -
Advance tax paid 1.7 15.2 31.0 3.7 3.6 3.6 3.2
Pre-paid Insurance 12.5 - - - - - -
Other Current Assets 0.2 5.1 2.0 - - - -

Short Term Uses 16.4 76.2 76.7 3.7 3.6 3.6 3.2

Opening Balance - 10.6 14.1 29.6 87.6 152.1 223.3


Add / (Less) : LT Surplus / (Deficit) 13.9 21.3 50.7 57.1 63.6 70.3 119.0
Add / (Less) : ST Surplus / (Deficit) (3.4) (17.8) (35.2) 0.9 0.9 0.9 0.8
Closing Balance 10.6 14.1 29.6 87.6 152.1 223.3 343.1
Schedule- A
Income from sale of Milk

PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15

Buffaloes

Number of Animals 200 450 450 450 450


Breeding Ratio 100% 100% 100% 100% 100%
Average Lactation Days Per year 75 200 280 280 280
Avg milk yield per animal (in Lts) 14 14 14 14 14
Avg. Yield of Milk (in Lts) 210000 1260000 1764000 1764000 1764000
Avg. price per Litre 24 24 24 24 24
Annual Income (Rs. In Lakhs) 50.4 302.4 423.36 423.36 423.36

Cows

Number of Animals 20 50 50 50 50
Breeding Ratio 100% 100% 100% 100% 100%
Average Lactation Days Per year 75 210 300 300 300
Avg milk yield per animal (in Ltr) 14 14 14 14 14
Avg. Yield of Milk (in Ltr) 21000 147000 210000 210000 210000
Avg. price per Litre 24 24 24 24 24
Annual Income (Rs. In Lakhs) 5.04 35.28 50.4 50.4 50.4

Total Income per annum (Rs. In Lakhs) 55.44 337.68 473.76 473.76 473.76

Schedule - B
Revenue from sale of Heifers

PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15

No. of Heifers available for sale 0 405 405 405 405


Avg. Sale price per Heifer (in Rs.) 2000 2000 2000 2000 2000
Annual Sale Value (Rs. In Lakhs) 0 8.1 8.1 8.1 8.1

Schedule - C
Sale value of Manure

PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15

No. Animals 131.25 525 525 525 525


Sale price of Dung per animal per year (Rs) 1000 1000 1000 1000 1000

Annual Sale Value (Rs. In Lakhs) 1.31 5.25 5.25 5.25 5.25
Schedule - D
Cost of Dry Fodder

PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15

Buffaloes & Cows

Lactation Period
Number of Animals 220 500 500 500 500
Number of Days 75 205 290 290 290
Feed require per animal per day (Kgs) 5 5 5 5 5
Feed cost per kg 2.5 2.5 2.5 2.5 2.5
Annual feed cost (Rs. In Lakhs) (a) 2.06 12.81 18.13 18.13 18.13

Non - Lacation Period


Number of Animals 220 500 500 500 500
Number of Days - 75 75 75 75
Feed require per animal per day (Kgs) 7 7 7 7 7
Feed cost per kg 2.5 2.5 2.5 2.5 2.5
Annula feed cost (Rs. In Lakhs) (b) 0.00 6.56 6.56 6.56 6.56

Bulls

Number of Animals 0 25 25 25 25
Number of Days 90 365 365 365 365
Feed require per animal per day (Kgs) 10 10 10 10 10
Feed cost per kg 2.5 2.5 2.5 2.5 2.5
Annual feed cost (Rs. In Lakhs) (c) 0.00 2.28 2.28 2.28 2.28

Total Cost of Dry Fodder (a+b+c) 2.06 21.66 26.97 26.97 26.97

Schedule - E
Cost of Green Fodder

PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15

Buffaloes & Cows

Lactation Period
Number of Animals 220 500 500 500 500
Number of Days 75 205 290 290 290
Feed require per animal per day (Kgs) 22 22 22 22 22
Feed cost per kg 0.5 0.5 0.5 0.5 0.5
Annual feed cost (Rs. In Lakhs) (a) 1.82 11.28 15.95 15.95 15.95

Non - Lacation Period


Number of Animals 220 500 500 500 500
Number of Days - 75 75 75 75
Feed require per animal per day (Kgs) 18 18 18 18 18
Feed cost per kg 0.5 0.5 0.5 0.5 0.5
Annula feed cost (Rs. In Lakhs) (b) 0.00 3.38 3.38 3.38 3.38

Bulls

Number of Animals 0 25 25 25 25
Number of Days 365 365 365 365
Feed require per animal per day (Kgs) 10 10 10 10 10
Feed cost per kg 0.5 0.5 0.5 0.5 0.5
Annual feed cost (Rs. In Lakhs) (c) 0.00 0.46 0.46 0.46 0.46

Total Cost of Green Fodder (a+b+c) 1.82 15.11 19.78 19.78 19.78

Schedule - F
Cost of Concentrate Feed

PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15

Buffaloes & Cows

Lactation Period

Number of Animals 220 500 500 500 500


Number of Days 75 205 290 290 290
Feed require per animal per day (Kgs) 4 4 4 4 4
Feed cost per kg 13 13 13 13 13
Annual feed cost (Rs. In Lakhs) (a) 8.58 53.30 75.40 75.40 75.40

Non - Lacation Period


Number of Animals 220 500 500 500 500
Number of Days - 160 75 75 75
Feed require per animal per day (Kgs) 1 1 1 1 1
Feed cost per kg 13 13 13 13 13
Annula feed cost (Rs. In Lakhs) (b) 0.00 10.40 4.88 4.88 4.88

Bulls

Number of Animals 0 25 25 25 25
Number of Days 365 365 365 365
Feed require per animal per day (Kgs) 5 5 5 5 5
Feed cost per kg 13 13 13 13 13
Annual feed cost (Rs. In Lakhs) (c) 0.00 5.93 5.93 5.93 5.93

Total Cost of Concentrate Feed (a+b+c) 8.58 69.63 86.21 86.21 86.21

Schedule - G
Heathcare Expenses
PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15

All animals
Number of Animals 220 525 525 525 525
Cost per Animals ( in Rs.) 400 1200 1200 1200 1200
Total Annual Cost (Rs. In Lakhs) 0.88 6.3 6.3 6.3 6.3

Schedule - H
Insurance

PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15

No. of Animals 220 525 525 525 525


Insurace Cost Per Animal Per year (@4.5%) 16.65 16.65 16.65 16.65 16.65
Annual Cost of Insurance 16.65 16.65 16.65 16.65 16.65

Insurance to P&L A/c 4.16 16.65 16.65 16.65 16.65


Pre paid Insurance 12.49

Schedule - I
Salaries & Wages

PARTICULARS (at 100% capacity-500 animals) No of Employees Salaries


Per Month Per Year
(in. Rs) (Rs. Lakhs)
Doctor 2 30000 7.2
Manager 12 10000 14.4
Accounts 2 8000 1.92
Skilled Workers 24 5000 14.4
Un-Skilled Workers 50 3000 18

Total Cost (Rs. In Lakhs) 55.92

PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15

Total Cost (Rs. In Lakhs) 13.98 55.92 55.92 55.92 55.92


% Increase in Salaries 0% 0% 0% 0%
Capacity (%) 50% 100% 100% 100% 100%
Total Cost (Rs. In Lakhs) 6.99 55.92 55.92 55.92 55.92

Schedule - J
Electricity/Disel Charges

No. of Animals 220 525 525 525 525


Average cost per animal per annum 1000 1000 1000 1000 1000
Total Electricity/Disel charges (in Lakhs) 0.55 5.25 5.25 5.25 5.25
2015-16 2016-17

450 450
100% 100%
280 280
14 14
1764000 1764000
24 24
423.36 423.36

50 50
100% 100%
300 300
14 14
210000 210000
24 24
50.4 50.4

473.76 473.76

2015-16 2016-17

405 405
2000 2000
8.1 8.1

2015-16 2016-17

525 525
1000 1000

5.25 5.25
2015-16 2016-17

500 500
290 290
5 5
2.5 2.5
18.13 18.13

500 500
75 75
7 7
2.5 2.5
6.56 6.56

25 25
365 365
10 10
2.5 2.5
2.28 2.28

26.97 26.97

2015-16 2016-17

500 500
290 290
22 22
0.5 0.5
15.95 15.95

500 500
75 75
18 18
0.5 0.5
3.38 3.38

25 25
365 365
10 10
0.5 0.5
0.46 0.46

19.78 19.78

2015-16 2016-17

500 500
290 290
4 4
13 13
75.40 75.40

500 500
75 75
1 1
13 13
4.88 4.88

25 25
365 365
5 5
13 13
5.93 5.93

86.21 86.21
2015-16 2016-17

525 525
1200 1200
6.3 6.3

2015-16 2016-17

525 525
16.65 16.65
16.65 16.65

16.65 16.65

2015-16 2016-17

55.92 55.92
0% 0%
100% 100%
55.92 55.92

525 525
1000 1000
5.25 5.25
Princpal Amount 427.45
Rate of Interest (%) 13%
Repayment Period 6
Moratorium Period 1

Instl Instalment Princpal Yearly Yearly


No. Month Outstanding Interest Instalment Interest Instalment

1 October 149.95 1.62 -


2 November 149.95 1.62 -
3 December 179.57 1.95 -
4 January 209.20 2.27 -
5 February 238.82 2.59 -
6 March 270.32 2.93 - 12.98 -
7 April 301.82 3.27 -
8 May 327.70 3.55 -
9 June 353.57 3.83 -
10 July 379.45 4.11 -
11 August 403.45 4.37 -
12 September 427.45 4.63 -
13 October 427.45 4.63 7.12
14 November 420.32 4.55 7.12
15 December 413.20 4.48 7.12
16 January 406.08 4.40 7.12
17 February 398.95 4.32 7.12
18 March 391.83 4.24 7.12 50.39 42.74
19 April 384.70 4.17 7.12
20 May 377.58 4.09 7.12
21 June 370.45 4.01 7.12
22 July 363.33 3.94 7.12
23 August 356.21 3.86 7.12
24 September 349.08 3.78 7.12
25 October 341.96 3.70 7.12
26 November 334.83 3.63 7.12
27 December 327.71 3.55 7.12
28 January 320.59 3.47 7.12
29 February 313.46 3.40 7.12
30 March 306.34 3.32 7.12 44.92 85.49
31 April 299.21 3.24 7.12
32 May 292.09 3.16 7.12
33 June 284.97 3.09 7.12
34 July 277.84 3.01 7.12
35 August 270.72 2.93 7.12
36 September 263.59 2.86 7.12
37 October 256.47 2.78 7.12
38 November 249.34 2.70 7.12
39 December 242.22 2.62 7.12
40 January 235.10 2.55 7.12
41 February 227.97 2.47 7.12
42 March 220.85 2.39 7.12 33.80 85.49
43 April 213.72 2.32 7.12
44 May 206.60 2.24 7.12
45 June 199.48 2.16 7.12
46 July 192.35 2.08 7.12
47 August 185.23 2.01 7.12
48 September 178.10 1.93 7.12
49 October 170.98 1.85 7.12
50 November 163.85 1.78 7.12
51 December 156.73 1.70 7.12
52 January 149.61 1.62 7.12
53 February 142.48 1.54 7.12
54 March 135.36 1.47 7.12 22.69 85.49
55 April 128.23 1.39 7.12
56 May 121.11 1.31 7.12
57 June 113.99 1.23 7.12
58 July 106.86 1.16 7.12
59 August 99.74 1.08 7.12
60 September 92.61 1.00 7.12
61 October 85.49 0.93 7.12
62 November 78.37 0.85 7.12
63 December 71.24 0.77 7.12
64 January 64.12 0.69 7.12
65 February 56.99 0.62 7.12
66 March 49.87 0.54 7.12 11.58 85.49
67 April 42.74 0.46 7.12
68 May 35.62 0.39 7.12
69 June 28.50 0.31 7.12
70 July 21.37 0.23 7.12
71 August 14.25 0.15 7.12
72 September 7.12 0.08 7.12 1.62 42.74

177.97 427.45

Particulars 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16


Interest 12.98 50.39 44.92 33.80 22.69 11.58
Princpal - 42.74 85.49 85.49 85.49 85.49
2016-17
1.62 177.97
42.74 427.45
Projected Profitability Statement

PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16


LIABILITIES:-
Share Capital 146.77 146.77 146.77 146.77 146.77 146.77
Reserves & Surplus 4.23 45.34 161.70 287.15 421.47 564.42
Term Liabilities
Term Loan 427.45 384.70 299.21 213.72 128.23 42.74
Short term borrowings 10.50 25.00 0.00 0.00 0.00 0.00
Current Liabilities 2.58 34.04 75.58 80.27 84.83 89.28
591.53 635.86 683.27 727.92 781.30 843.22

ASSETS:-
Gross Block 200.43 200.43 200.43 200.43 200.43 200.43
Less:- Depreciation 5.93 28.82 48.61 65.73 80.55 93.38
Net Block 194.5 171.6 151.8 134.7 119.9 107.1
Live Stock 370.00 370.00 370.00 370.00 370.00 370.00
Current Assets 16.44 80.15 131.89 135.64 139.29 142.85
Cash Surplus 10.59 14.10 29.56 87.58 152.13 223.32
591.53 635.86 683.27 727.92 781.30 843.22

Difference 0.00 0.00 0.00 0.00 0.00 0.00


(Rs. in Lakhs)
2016-17

146.77
715.08

0.00
0.00
93.25
955.10

200.43
104.50
95.9
370.00
146.02
343.15
955.10

0.00
0
#REF!
#REF!

Debt Service Coverage Ratio

PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17

Source
Net Profit 4.23 41.11 116.36 125.46 134.31 142.96 150.66
Interest on Term Loan 12.98 50.39 44.92 33.80 22.69 11.58 1.62
Depreciation 5.93 22.90 19.79 17.12 14.81 12.83 11.12
Cash Inflows 23.13 114.40 181.06 176.38 171.82 167.37 163.40

Repayments
Instalments of Term Loan 0.00 42.74 85.49 85.49 85.49 85.49 42.74
Interest on Term Loan 12.98 50.39 44.92 33.80 22.69 11.58 1.62
12.98 93.13 130.41 119.29 108.18 97.07 44.37

DSCR 1.78 1.23 1.39 1.48 1.59 1.72 3.68

AVERAGE DSCR 1.84

Internal Rate of Return (IRR) 63%

PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17

Cash Outflows -574.22


Cash Inflows 18.72 97.27 165.80 164.89 164.10 163.43 162.85
-574.22
937.06
63%
34

Depreciation Statement

Gross Block
PARTICULARS Rate 2010-11 2011-12
Land 0% 20.00 20.00
Buildings 10% 67.25 67.25
Plant & Machinery 15% 110.68 110.68
Electrical Equipments & Erections 15% 2.50 2.50
200.43 200.43

No. of Months 3 12

Depreciation
PARTICULARS 2010-11 2011-12
Land 0.00 0.00
Buildings 1.68 6.56
Plant & Machinery 4.15 15.98
Electrical Equipments & Erections 0.09 0.36
5.93 22.90

Cumulative Depreciation
PARTICULARS 2010-11 2011-12
Land 0.00 0.00
Buildings 1.68 8.24
Plant & Machinery 4.15 20.13
Electrical Equipments & Erections 0.09 0.45
5.93 28.82

Net Block
PARTICULARS 2010-11 2011-12
Land 20.00 20.00
Buildings 65.57 59.01
Plant & Machinery 106.53 90.55
Electrical Equipments & Erections 2.41 2.05
194.50 171.61
35

2012-13 2013-14 2014-15 2015-16 2016-17


20.00 20.00 20.00 20.00 20.00
67.25 67.25 67.25 67.25 67.25
110.68 110.68 110.68 110.68 110.68
2.50 2.50 2.50 2.50 2.50
200.43 200.43 200.43 200.43 200.43

12 12 12 12 12

2012-13 2013-14 2014-15 2015-16 2016-17


0.00 0.00 0.00 0.00 0.00
5.90 5.31 4.78 4.30 3.87
13.58 11.55 9.81 8.34 7.09
0.31 0.26 0.22 0.19 0.16
19.79 17.12 14.81 12.83 11.12

2012-13 2013-14 2014-15 2015-16 2016-17


0.00 0.00 0.00 0.00 0.00
14.14 19.45 24.23 28.53 32.40
33.71 45.26 55.07 63.41 70.50
0.76 1.02 1.24 1.43 1.59
48.61 65.73 80.55 93.38 104.50

2012-13 2013-14 2014-15 2015-16 2016-17


20.00 20.00 20.00 20.00 20.00
53.11 47.80 43.02 38.72 34.85
76.97 65.42 55.61 47.27 40.18
1.74 1.48 1.26 1.07 0.91
151.82 134.70 119.88 107.05 95.93
Summary of Performance Analysis

PARTICULARS 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17

Net Sales 56.75 351.03 487.11 487.11 487.11 487.11 487.11


Gross Profit 27.60 150.76 257.56 257.56 257.56 257.56 257.56
Gross Profit % to Sales 49% 43% 53% 53% 53% 53% 53%
EBIDTA 25.66 138.94 240.98 240.98 240.98 240.98 240.98
% EBIDTA to Sales 45% 40% 49% 49% 49% 49% 49%
Depreciation 5.93 22.90 19.79 17.12 14.81 12.83 11.12
Interest 13.33 53.76 44.92 33.80 22.69 11.58 1.62
Profit Before Tax 6.41 62.28 176.27 190.06 203.47 216.57 228.23
% PBT to Sales 11% 18% 36% 39% 42% 44% 47%
Profit After Tax 4.23 41.11 116.36 125.46 134.31 142.96 150.66
% PAT to Sales 7% 12% 24% 26% 28% 29% 31%

Equity Capital 146.77 146.77 146.77 146.77 146.77 146.77 146.77


Reserves & Surplus 4.23 45.34 161.70 287.15 421.47 564.42 715.08
Tangible Net Worth 151.00 192.12 308.47 433.93 568.24 711.20 861.85
Term Loans 427.45 384.70 299.21 213.72 128.23 42.74 0.00
Debt Equity Ratio 2.83 2.00 0.97 0.49 0.23 0.06 0.00

Current Assets 16.44 80.15 131.89 135.64 139.29 142.85 146.02


Current Liabilities 2.58 34.04 75.58 80.27 84.83 89.28 93.25
Working Capital Gap 13.86 46.11 56.31 55.37 54.46 53.57 52.78
Working Capital Limits 10.50 25.00 0.00 0.00 0.00 0.00 0.00
Current Ratio 6.36 2.35 1.74 1.69 1.64 1.60 1.57
(Excluding TL Installments)

Fixed Assets 194.50 171.61 151.82 134.70 119.88 107.05 95.93


Fixed Assets Turnover Ratio 0.29 2.05 3.21 3.62 4.06 4.55 5.08

DSCR 1.78 1.23 1.39 1.48 1.59 1.72 3.68


Average DSCR
TOL/TNW 2.92 2.31 1.22 0.68 0.37 0.19 0.11
200000
100
20,000,000.00
240,000,000.00

1.84