Project Scheduling / Time Study
Project Scheduling / Time Study
INTRODUCTION
■ Schedule converts action plan into operating time
table
■ Basis for monitoring and controlling project
■ Scheduling more important in projects than in
production, because unique nature
■ Sometimes customer specified/approved
requirement
■ Based on Work Breakdown Structure (WBS)
2
NETWORK TECHNIQUES
PERT CPM
Program Evaluation and Critical Path Method
Review Technique Developed by El Dupont for
developed by the US Chemical Plant Shutdown
Navy with Booz Project- about
Hamilton Lockheed same time as PERT
on the Polaris
Missile/Submarine
program 1958
3
NETWORK
■ Graphical portrayal of activities and event
■ Shows dependency relationships between
tasks/activities in a project
■ Clearly shows tasks that must precede (precedence)
or follow (succeeding) other tasks in a logical manner
■ Clear representation of plan – a powerful tool for
planning and controlling project
4
Example of Simple Network –
Survey
5
Example of Network –
More Complex
6
DEFINITION OF TERMS IN A NETWORK
■ Activity : any portions of project (tasks) which required
by project, uses up resource and consumes time – may
involve labor, paper work, contractual negotiations,
machinery operations Activity on Arrow (AOA) showed as arrow,
AON – Activity on Node
■ Event : beginning or ending points of one or more
activities, instantaneous point in time, also called ‘nodes’
PRECEEDING SUCCESSOR
ACTIVITY
EVENT
7
Emphasis on Logic in Network Construction
■ Construction of network should be based on logical or
technical dependencies among activities
■ Example - before activity ‘Approve Drawing’ can be
started the activity ‘Prepare Drawing’ must be
completed
■ Common error – build network on the basis of time
logic (a feeling for proper sequence ) see example below
WRONG !!!
CORRECT
✔ 8
Example 1- A simple network
Consider the list of four activities for making a simple product:
9
Sequence of activities
■ Can start work on activities A and B anytime, since neither
of these activities depends upon the completion of prior
activities.
■ Activity C cannot be started until activity B has been
completed
■ Activity D cannot be started until both activities A and C
have been completed.
■ The graphical representation (next slide) is referred to as
the PERT/CPM network
10
Network of Four Activities
Arcs indicate project activities
A D
1 3 4
B C
11
Example 2
Develop the network for a project with following activities and immediate
predecessors:
Activity Immediate
predecessors
A -
B -
C B
D A, C
E C
F C
G D,E,F
12
Network of first five activities
A D
1 3 4
E
B
C 5
2
We need to introduce a
dummy activity
13
Network of Seven Activities
1 A 3 D 4 G
7
dummy E
B
C 5 F
2 6
●Note how the network correctly identifies D, E, and F as the immediate
predecessors for activity G.
14
EXAMPLES OF THE USE OF DUMMYACTIVITY
Network concurrent activities
a
a 2
1 2 1 Dummy
b 3
b
WRONG!!! RIGHT
✔
15
WRONG!!! RIGHT!!!
a d a d
1 1
b e b
2 2 4
e
c f c f
3 3
a precedes d.
a and b precede e,
b and c precede f (a does not precede f)
16
Scheduling with activity time
Activity Immediate Completion
predecessors Time (week)
A - 5
B - 6
C A 4
D A 3
E A 1
F E 4
G D,F 14
H B,C 12
I G,H 2
Total …… 51
This information indicates that the total time required to complete activities is 51
weeks. However, we can see from the network that several of the activities can be
conducted simultaneously (A and B, for example).
17
Earliest start & earliest finish time
■ We are interested in the longest path through the network, i.e.,
the critical path.
18
Arc with ES & EF time
EF = earliest finish time
Activity
2
[ 0 ,5]
A
5
1
t = expected activity
time
19
Network with ES & EF time
D[5,8]
5
2 3
0 ]
E[ ,1
G[1 4
5 6
1 ,6] F[
5]
0,2
1
4
0,
7
A[
4]
C[5,9]
4 26]
5
[24,
4
I
2
1 6
B[0 1]
,6 ,2
6 ] H[9
12
3
20
Activity, duration, ES, EF, LS, LF
EF = earliest finish time
Activity
3
[ 5, 9 ]
C ]
8 , 12
4[
2
LF = latest finish time
LS = latest start time
21
Latest start & latest finish time
■ To find the critical path we need a backward pass calculation.
22
Network with LS & LF time
D[5,8] 5
2 3[7,10]
0]
G[1 10,24
14[
E[ 1
1[5 5,6] [6, 10]
0,2 ]
5[ 0,5]
,6] F 6,
4[
5]
4]
7
A[
0,
4 4 , 26]
C[5,9]
2
4[8,12]
I[
[ 2 4 ,26]
2
1 6
B[0
6[6 ,6] [ 9 , 21]
H , 24]
,12 2
] 12[1
3
23
Slack or Free Time or Float
Slack is the length of time an activity can be delayed without affecting the
completion date for the entire project.
For example, slack for C = 3 weeks, i.e Activity C can be delayed up to 3 weeks
(start anywhere between weeks 5 and 8).
, 9 ] 3
C [ 5
[ 8 , 1 2]
2 4
ES LS EF LF
5 8 9 12
LF-EF = 12 –9 =3
LS-ES = 8 – 5 = 3
LF-ES-t = 12-5-4 = 3
24
Activity schedule for our example
Activity Earliest Latest Earliest Latest Slack Critical
start (ES) start (LS) finish (EF) finish (LF) (LS-ES) path
A 0 0 5 5 0 Yes
B 0 6 6 12 6
C 5 8 9 12 3
D 5 7 8 10 2
E 5 5 6 6 0 Yes
F 6 6 10 10 0 Yes
G 10 10 24 24 0 Yes
H 9 12 21 24 3
I 24 24 26 26 0 Yes
25
IMPORTANT QUESTIONS
■ What is the total time to complete the project?
■ 26 weeks if the individual activities are completed on schedule.
■ What are the scheduled start and completion times for each activity?
■ ES, EF, LS, LF are given for each activity.
■ How long can non-critical activities be delayed before they cause a delay in the
project’s completion time
■ Slack time available for all activities are given.
26
Importance of Float (Slack) and Critical Path
1. Slack or Float shows how much allowance each activity has, i.e how long it
can be delayed without affecting completion date of project
2. Critical path is a sequence of activities from start to finish with zero slack.
Critical activities are activities on the critical path.
4. If any activity on the critical path is shortened or extended, project time will
be shortened or extended accordingly
27
Importance of Float (Slack) and Critical Path (cont)
5. So, a lot of effort should be put in trying to control activities along this path,
so that project can meet due date. If any activity is lengthened, be aware
that project will not meet deadline and some action needs to be taken.
7. Don’t waste resources on non-critical activity, it will not shorten the project
time.
28
PERT For Dealing With Uncertainty
■ So far, times can be estimated with relative certainty, confidence
■ For many situations this is not possible, e.g Research, development, new
products and projects etc.
29
Precedences And Project Activity Times
Immediate Optimistic Most Likely Pessimistic EXP Var S.Dev
Activity Predecessor Time Time Time TE V σ
a - 10 22 22 20 4 2
b - 20 20 20 20 0 0
c - 4 10 16 10 4 2
d a 2 14 32 15 25 5
e b,c 8 8 20 10 4 2
f b,c 8 14 20 14 4 2
g b,c 4 4 4 4 0 0
h c 2 12 16 11 5.4 2.32
I g,h 6 16 38 18 28.4 5.33
j d,e 2 8 14 8 4 2
30
The complete network
d 6
2
(15,25)
j
a (8,4)
(20,4) e
(10,4)
1 f 7
3
b (14,4)
(20,0)
g
c
(4,0)
(10,4) i
(18,28.4)
h 5
4
(11,5.4)
31
Figure 8-13 The complete Network
EF=20 35
d 6
2
a (15,25) j
(20,4) (8,4)
b e
20 43
(20,0) (10,4)
f CRIT. TIME = 43
1 3 7
(14,4)
g
c (4,0)
(10,4) i
(18,28.4)
h 5
4
(11,5.4)
10 24
32
Critical Path Analysis (PERT)
Activity LS ES Slacks Critical ?
a 0 0 0 Yes
b 1 0 1
c 4 0 4
d 20 20 0 Yes
e 25 20 5
f 29 20 9
g 21 20 1
h 14 10 4
i 25 24 1
j 35 35 0 Yes
33
Assume, PM promised to complete the project in the fifty days.
What are the chances of meeting that deadline?
Calculate Z, where
Z = (D-S) / √V
Example,
D = 50; S(Scheduled date) = 20+15+8 =43; V = (4+25+4) =33
Z = (50 – 43) / 5.745
= 1.22 standard deviations.
1.22
34
35
What deadline are you 95% sure of meeting
D = S + 5.745 (1.645)
= 43 + 9.45
= 52.45 days
36
Comparison Between CPM and PERT
CPM PERT
1 Uses network, calculate float or slack,
identify critical path and activities, guides Same as CPM
to monitor and controlling project
3 Used where times can be estimated with Used where times cannot be estimated
confidence, familiar activities with confidence.
Unfamiliar or new activities
37
BENEFITS OFCPM / PERT NETWORK
38
BENEFITS OFCPM / PERT NETWORK (cont.)
39
Gantt Charts
■ Since 1917; Useful for showing work vs time in form of bar charts
e.g.
40