Analytics Exercise 9-1

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Running Head: INVENTORY MANAGEMENT

Inventory Managemennt

Name.

Institutional Affiliation.

Date.
INVENTORY MANAGEMENT 2

Companies should make a MRP, that is, the Material Requirement Plan to efficiently

tackle the market demand in order to make more profits. The Engine Assembly plan was as

follows:

Engine Assembly Master Schedule


Week 1 2 3 4 5 6 7 8 9 10 11 12
Quantity 15 5 7 10 15 20 10 8 2 16

The master schedule as indicated shows that:

I Engine=1 Gearbox

1 Gearbox=1 Shaft

For the gear box, the beginning inventory for the gearbox in week one was 17 gear boxes. The

scheduled receipts in week two was 5, with a lead time of 2 weeks. For the input shafts, the

beginning inventory was 40 input shafts. The scheduling receipts in the second week was 22,

with a lead time of three weeks. Calculations were done using excel workbook. The following

were the results for the MRP.


INVENTORY MANAGEMENT 3

Gear box requirements


Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross Requirements 15 5 7 10 0 15 20 10 0 8 2 16
Scheduled Receipts 5
Projected Available Balance 2 2 10 0 0 15 -5 0 0 18 16 0
Net Requirements 5 10 15 20 10 8 2 16
Planned Order Receipt
Planned Order Release 5 10 15 20 10 8 2 16
From E12 for 2 Weeks Lead Time

Input shaft requirements


Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross Requirements 30 30 40 20 0 16 4 32
Scheduled Receipts 22
Projected Available Balance 10 32 32 0 0 0 0 0 0 0 0 0
Net Requirements 38 20 16 4 32
Planned Order Receipt
Planned Order Release 38 20 16 4 32
From F24 for 3 Weeks Lead Time

Starting with the gearbox, the gross requirements for this particular item was obtained

directly from the demand corresponding the week. For example, in week five, there was no

demand, hence the gross requirement was zero at that particular week. However, for the input

shafts, the gross requirement was obtained by:

¿ Lead time∗planned order release ( Gear box )

¿ 2∗planned order release ( Gear box )

The net requirement was obtained by subtracting the projected available balance from the gross

requirement in both items.

You might also like