This daily landscape report summarizes activities at Al-Yamamah Palace in Riyadh on August 31, 2020. It details 85 staff working with various equipment to maintain different zones, including the Yamamah Garden, Royal/Main Villa, and VIP area. Two obstacles are noted - construction activities obstructing operations and maintenance work, and excavation by subcontractors damaging landscape areas and irrigation networks.
This daily landscape report summarizes activities at Al-Yamamah Palace in Riyadh on August 31, 2020. It details 85 staff working with various equipment to maintain different zones, including the Yamamah Garden, Royal/Main Villa, and VIP area. Two obstacles are noted - construction activities obstructing operations and maintenance work, and excavation by subcontractors damaging landscape areas and irrigation networks.
This daily landscape report summarizes activities at Al-Yamamah Palace in Riyadh on August 31, 2020. It details 85 staff working with various equipment to maintain different zones, including the Yamamah Garden, Royal/Main Villa, and VIP area. Two obstacles are noted - construction activities obstructing operations and maintenance work, and excavation by subcontractors damaging landscape areas and irrigation networks.
This daily landscape report summarizes activities at Al-Yamamah Palace in Riyadh on August 31, 2020. It details 85 staff working with various equipment to maintain different zones, including the Yamamah Garden, Royal/Main Villa, and VIP area. Two obstacles are noted - construction activities obstructing operations and maintenance work, and excavation by subcontractors damaging landscape areas and irrigation networks.
Download as XLSX, PDF, TXT or read online from Scribd
Download as xlsx, pdf, or txt
You are on page 1/ 1
Al-Yamamah Palace - Riyadh
Daily Landscape & Irrigation Activity Report
Date 31/08/2020 Report Serial Number: MMK-22 CIT's Manpower Equipment in Use Consumables Trade No. Trade No. Trade No. Project Engineer/PM 1 Ride-On Lawn Mowers 3 Urea Fertilizer Project Manager 1 Walk Behind Lawn Mowers 2 NPK Fertilizer Supervisors 3 Hedge Trimmers 3 Iron Chelates Leadsmen 3 Edge Trimmers 1 Pesticides Plumbers 4 Blower Machine 2 Furadan Gardeners 71 Chain Saw Fungicides Sprayer Machine Herbicides Absent/sick 2 Hand Tools Peat moss Total 85 Pick-up 1 Potting Soil Dyna 1 Organic Fertilizer Bobcat 1 Man lift - Boom Truck Brush cutter 2 Observations Location/Description Zone Subzone Activity Yamamah Garden C Manual irrigation Collection of garbage and removal Weeding in the grass area Royal/Main Villa A&E Weeding in all Royal Zone and continue Trimming around Oasis E1, E2, E3 & E4 Flower bed cultivation in all Main Villa Edging in D1 to D7 area continue Palm fronds removal G1, E and F area Garbage removal in all zones and continue Irrigation Mainline 200mm repaired at G area Plantation of ground cover around oasis Collection of Dry leave all parts of main villa Large Trees trimming at D 12 area & continue Collection of garbage and removal Tree and Palm basin cleaning in all zones VIP area B Collection of dry leaves, garbage and litter Collection of garbage and removal Construction activities going on almost all the planters Obstacle 1 in main villa, obstructing O & M activities Destroying and damaging our Landscape areas and irrigation network as per attached updated drawing 2 (August 23, 2020) of damaged area due to excavation done by sub contractors Prepared and submitted by: Approved by: Name : Muhammad Majid Khan Name : Eng. Mohammed Al Ghul E-Signature : MMK Signature :