The Project Will Cover The Whole Block 3 of Barangay Puntod, Cagayan de Oro City

The clean-up drive program will involve students from Capitol University College of Nursing participating in cleaning Block 3 of Barangay Puntod, Cagayan de Oro City over the course of a week in February and March 2020. They will prepare starting in December 2019, collect payment from members by February 4th, implement the clean-up on March 19th from 8-10am, and evaluate the program on February 25th. The budget includes supplies, transportation, food and drinks, and miscellaneous expenses totaling 1,146 Philippine pesos.

Uploaded by

Tyron Chua
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
88 views5 pages

The Project Will Cover The Whole Block 3 of Barangay Puntod, Cagayan de Oro City

The clean-up drive program will involve students from Capitol University College of Nursing participating in cleaning Block 3 of Barangay Puntod, Cagayan de Oro City over the course of a week in February and March 2020. They will prepare starting in December 2019, collect payment from members by February 4th, implement the clean-up on March 19th from 8-10am, and evaluate the program on February 25th. The budget includes supplies, transportation, food and drinks, and miscellaneous expenses totaling 1,146 Philippine pesos.

Uploaded by

Tyron Chua
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

D.

Coverage

The project will cover the whole Block 3 of Barangay Puntod, Cagayan de Oro City.

7. Methodology
The clean-up drive program will be participated by a group of student from Capitol

University College of Nursing, 2nd year students in Purok 3, Barangay Puntod, Cagayan De Oro

City. This program covers a week of planning for the intervention and the flow and strategies in

order to attain the objective of the project.

In implementing this activity of clean-up drive preparation will start on December 14 2019

to February 25 2020 as it will serve as start end of the clean-up drive implementation. On

February 4, 2020 will be the deadline planned amount to be paid with each member and it will be

collected from 8 t0 1pm in the afternoon. March 19, 2020 will be the implementation date from

8am-10am in the morning. Earlier than the said time will be the preparation for the students’

orientation who will be participating in the said activity. On the February 25, 2020 is the

evaluation of the clean-up drive proposed activity. The partners identified as being vital part of

the project from being Barangay officials and the approval of the University or the waver for the

students for their parents. All are needed for effective program that will be able to develop

sanitation and cleanliness that will ensure safety of the community and to protect bath public

health and environment living in Barangay Puntod, Cagayan De Oro City. This will also set as an

example for environment, for the people living there in Barangay Puntod, Cagayan De Oro City.

This program will benefit not just the people of the chosen barangay but will help influence other

barangay to take care of their environment and to discipline their selves to maintain a clean and

green surrounding. This will improve their health in order to avoid any diseases that could harm

them. Clean-up drive will be a way to help them become a citizen that is aware and who has

advocate for better living.


8. Detailed Budgetary Requirements

Transportation (13 persons) Php 156.00

CU to Puntod =
Supplies

Trash bag =120

Walis Tingting =180 Php 665.00

Gloves =200
Mask = 65

Dustpan =100

Foods and Drinks

Water = 130 Php 280.00

Biscuits = 150
Other Miscellaneous expenses

Printing = 15 Php 45.00

Sticker paper = 30

Total Php 1,146.00

9. Detailed schedule of activities

DATE TIME ACTIVITY PEOPLE


December 14, 2019

To Start and end of preparation for


3:00-5:00 pm ALL
February 25, 2020 project implementation
Handing over the Authorization

letter to the Barangay officials

for the approval of surveying the


February 1, 2020 1:00-2:00pm ALL
place

Deadline of planned amount to


ALL
February 4, 2020 1:00-2:00pm be paid by each members
Gathering of materials needed

February 5, 2020 8:00am-10:00am for the clean-up drive ALL


Call time - 7:00am

Departure time - 7:30am

Preparation - 8:00am
February 19, 2020 8:00am-10:00am ALL
Start of activity - 10:00am

February 25, 2020 1:00pm-2:00pm Evaluation ALL