Method Statement For Finishing Works
Method Statement For Finishing Works
Method Statement For Finishing Works
Method Statement
For
Finishing Works Rev (0.0)
Februry 2020
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
Tel No. 002- 035446231 & 0105339344
Fax No. 002- 035232580
E mail :[email protected]
INDEX
1. INTRODUCTION 4
1.1 SCOPE OF WORK 4
2. CREW & EQUIPMENT 4
2.1 PERSONNEL 4
2.2 EQUIPMENTS 4
SAFETY REGULATION 4
2.3.1 Personal Protective Equipments (PPE) 4
2.3.2 House Keeping 4
2.3.3 Equipment Control 4
2.3.4 Fire Control 4
2.3.5 Traffic Control 4
2.3.6 Falling From Heights Control 5
3. DEFINITION OF PROCESS 5
3.1 Cement Solid Brick Work 5
3.1.1 Generals 5
3.1.2 Materials 5
3.1.3 Installation 5
3.1.4 Concrete Lintel 5
3.2 Cement and Sand Mortar Plaster Finish 6
3.2.1 Generals 6
3.2.2 Materials 6
3.2.3 Application 6
3.3 Raised Floor and Anti-Static Carpet Tiles 6
3.3.1 General 6
3.3.2 Materials 6
3.3.3 Installation 7
3.4 Porcelain Floor Tiles 7
3.4.1 General 7
3.4.2 Materials 7
3.4.3 Installation 7
3.4.4 Grouting 8
3.5 Granite Floor Tiles 8
3.5.1 General 8
3.5.2 Materials 8
3.5.3 Installation 8
3.5.4 Grouting 9
2
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
Tel No. 002- 035446231 & 0105339344
Fax No. 002- 035232580
E mail :[email protected]
3
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
Tel No. 002- 035446231 & 0105339344
Fax No. 002- 035232580
E mail :[email protected]
1. INTRODUCTION
1.1 SCOPE OF WORK
The method statement is prepared for finishing work for "Lekela Substation 220 kV"
4
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
Tel No. 002- 035446231 & 0105339344
Fax No. 002- 035232580
E mail :[email protected]
3. DEFINITION OF PROCESS
3.1 CEMENT SOLID BRICK WORK
3.1.1 GENERAL
• Cement solid brick work will be of the type and thickness approved by the owner and will be
properly coordinated with other work.
• The source of supply for materials will not be changed aft er the work has started.
• Cement solid brick units will be true to size, without cracks, chips and splits.
• The Contractor could start using the design mix after getting the owner approval.
3.1.2 MATERIALS
• All materials will be selected as per the contract and it will be tested according to the test plan
approved by the owner.
• All the tested for mortar will be performed as per the test plan approved by the owner.
• The Contractor will submit all solid brick accessories to the owner for approval.
3.1.3 INSTALLATION
• All cement solid brick will be wetted before laying.
• All cement solid brick will be laid plumbed, leveled and accurately spaced.
• The cement solid brick will be laid on full mortar bedding and in such a way that no crakes are
formed between the cement solid bricks and the mortar at the time the cement solid brick is placed.
5
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
Tel No. 002- 035446231 & 0105339344
Fax No. 002- 035232580
E mail :[email protected]
3.2.1 GENERAL
• Cement will be stored off the ground and away from damp surfaces.
• The Contractor could start using the design mix after getting the owner approval.
3.2.2 MATERIALS
• All materials will be selected as per the contract and it will be tested according to the test plan
approved by the owner
• All the tested for mortar will be performed as per the test plan approved by the owner.
• The Contractor will submit all plaster accessories to the owner for approval.
3.2.3 APPLICATION
• Surfaces will be cleaned of dust and other foreign matter.
• Before the plaster work is started, masonry surfaces shall be wetted thoroughly with clean water.
• Apply dash coat on masonry surfaces with approved desig n mix.
• Metal corner beads and other accessories will be checked carefully for alignment before work is
started.
• Plastered surfaces will be smooth and free from rough area, cracks and blemishes.
3.3.1 GENERAL
• Raised access flooring is a complete portable assembly of modular anti-static carpet tiles on an
elevated support system (understructure) forming an accessible under floor cavity to
accommodate electrical and mechanical services.
3.3.2 MATERIALS
3.3.2.1 FLOOR PANELS
The contractor will provide manufacturer’s standard modular anti-static carpet tiles
of size and construction indicated, that are interchangeable with other standard
floor tiles, easily placed and removed without disturbing adjacent panels by one
person using portable lifting device.
The contractor will submit raised floor system to the owner approval.
6
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
Tel No. 002- 035446231 & 0105339344
Fax No. 002- 035232580
E mail :[email protected]
3.3.2.2 UNDERSTRUCTURE
The contractor will provide manufacturer's standard galvanized steel pedestal assembly
including
square galvanized steel base and the column with provisions for height
adjustment.
Provide galvanized steel cap
(head)
Protect steel components against corrosion with manufacturer’s standard paint finish.
3.3.3 INSTALLATlON
• Squaring room needed before starting.
• The surveyor will mark the exact level on perimeter of room.
• The contractor will install steel pedestal every 60cm. in both directions depending on the
approval shop drawing.
• Install the head above pedestals to reach the height adjustment.
• Before installing the tiles Contractor will make sure that all mechanical, electrical and communication
items
have been installed inspected and tested.
• Pulling a string between walls at final finishing installing tiles.
• Checking level of tile using spirit level.
3.4.1 GENERAL
• Tiles work will not start until the plumbing, electrical works and other trades have been completed
and tested
• The tiles should be protected before the start of any other activities in the area.
3.4.2 MATERIALS
• Porcelain floor tiles will be 400*400*9mm and as per the approved sample.
• All tiles will be of first class quality
• All tiles will be of uniform size and even surface, free from warps, chipped corners and other
imperfections affecting on quality.
• The contractor could start using the design mix after getting the owner approval.
• Colors and quality will be subject for approval of the owner.
• The contractor will submit carpet as per the owner approval.
3.4.3 INSTALLATION
• Surfaces under porcelain tiles will be cleaned.
• Provide clean sand under porcelain tiles.
• Tiles will be soaked in clean water for about 1/2 hour before setting them
• Squaring room needed before starting.
• The tiles will be installed using approved mix design mortar.
• Setting tile onto uniform position.
• Using plastic spacers for uniform spaces between tiles.
7
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
Tel No. 002- 035446231 & 0105339344
Fax No. 002- 035232580
E mail :[email protected]
3.4.4 GROUTING
• Tiles will be wetted before applying grout.
• Joints 3mm or less in width will be grouted with approved cementations grout.
• Upon completion of the work, all surfaces of glazed tiles will be properly cleaned
3.5.1 GENERAL
• Tiles work will not start until the plumbing, electrical works and other trades have been completed
and tested.
• The tiles should be protected before the start of any other activities in the area.
3.5.2 MATERIALS
• Granite floor and wall tiles will be of first class quality
• All tiles will be of uniform size and even surface, free from warps, chipped corners and other
imperfections affecting on quality.
• The contractor could start using the design mix after getting the owner approval.
• Colors and quality will be subject for approval of the owner.
3.5.3 INSTALLATION
8
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
Tel No. 002- 035446231 & 0105339344
Fax No. 002- 035232580
E mail :[email protected]
3.5.4 GROUTING
• Tiles will be wetted before applying grout.
• Joints 3mm or less in width will be grouted with approved grout.
• Upon completion of the work, all surfaces of tiles will be properly cleaned.
3.6.1 GENERAL
• Tiles work will not start until the plumbing, e lect rical works and other trades have been completed
and tested
• The work of the trades in the area where work is to be done will be protected from damage.
3.6.2 MATERIALS
• All tiles will be of first class quality.
• All tiles will be of uniform size and even surface, free from warps, chipped corners and other
imperfections affecting on quality.
• The contractor could start using the design mix after getting the owner approval.
• Colors and quality will be subject for approval of the owner
3.6.3 INSTALLATION
• Surfaces of interior masonry wall will be clean and sufficiently rough to provide strong bond
• Scratch coat will be applied to masonry as backing for wall tiles.
• Tiles will be soaked in clean water for about 1/2 hour before setting them.
• The tiles will be installed using approved mix design mortar.
• Squaring wall needed before starting.
• Setting tile onto uniform position.
• Using plastic spacers for uniform spaces between tiles.
• Checking plumb of tiles using spirit level.
9
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
Tel No. 002- 035446231 & 0105339344
Fax No. 002- 035232580
E mail :[email protected]
3.6.4 GROUTING
• Tiles will be wetted before applying grout.
• Joints 3mm or less in width will be grouted with approval cementations grout.
• Upon completion of the work, all surfaces of glazed tiles will be properly cleaned.
3.7.1 GENERAL
• Tiles work will not start until the plumbing, electrical works and other trades have been completed
and tested.
• The tiles should be protected before the start of any other activities in the area.
3.7.2 MATERIALS
• All tiles will be of first class quality
• All tiles will be of uniform size and even surface, free from warps, chipped corners and other
imperfections affecting on quality.
• The contractor could start using the design mix after getting the owner approval
• Colors and quality will be subject for approval of the owner.
3.7.3 INSTALLATION
• Surfaces will be cleaned
• Floor tiles installation will be not started until after wall installation has been completed.
• Before tiles installation, the structure floor will be tested for levelness or uniformity of slope if the
floor is found defective; it will be properly corrected to attain the required slope.
• Tiles will be soaked in clean water for about 1/2hour before setting them.
• Squaring room needed before starting.
• Provide clean sand under ceramic tiles.
• The tiles will be installed using approved mix design mortar.
• Setting tile onto uniform position.
• Using plastic spacers for uniform spaces between tiles
• Checking level of tiles using spirit level.
• Restrict access when tiles are freshly laid.
3.7.4 GROUTING
• Tiles will be wetted before applying grout.
• Joints 3mm or less in width will be grouted with approval cementations grout.
• Upon completion of the work, all surfaces of glazed tiles will be cleaned with a soap
powder and clean water
10
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
Tel No. 002- 035446231 & 0105339344
Fax No. 002- 035232580
E mail :[email protected]
3.8.1 GENERAL
• Tiles work will not start until the plumbing, electrical works and other trades have been
complete and tested.
• The tiles should be protected before the start of any other activities in the area.
3.8.2 MATERIALS
• All tiles will be of first class quality.
• All tiles will be of uniform size and even surface, free from warps, chipped corners and other
imperfections affecting on quality.
• Tile shape and quality will be subject for approval of the owner.
3.8.3 INSTALLATION
• Surfaces will be cleaned.
• In the battery room the floor finish will be 6mm min. thick.
• Non-slip alkali resistance ceramic floor tiles with a low surface permeability.
• Squaring room needed before starting
• The tiles will be bedded on alkaline resistance adhesive
• Setting tile onto uniform position.
• Using plastic spacers for uniform spaces between tiles.
• Checking le v e l of tiles using spirit level
• Restrict access when tiles are freshly laid.
3.8.4 GROUTING
• Approved alkaline resistance grout will be filling spaces between tiles.
• Movement joints at the perimeter of the tilling and any intermediate movement joints will
have alkaline resistance filler and be finished w i t h an alkaline resistance sealant.
• Cleaning tiles surfaces after grouting.
3.9.1 GENERAL
• All material will be delivered to the site in unopened containers with brand name and type clearly
marked.
• Carefully handle and store materials in dry enclosures.
11
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
Tel No. 002- 035446231 & 0105339344
Fax No. 002- 035232580
E mail :[email protected]
3.9.2 MATERIALS
• False ceiling materials will be of the best quality avai l abl e and will be obtained from a single
manufacturer approved by the owner
• The contractor will be submitting shop drawing to the owner for approval
3.9.3 INSTALLATION
• The surveyor will mark the exact location for perimeter angle on the wall
• Hangers will be installed above the main beams typically every 1.20cm.
• Install main beam 360 every 1.20m.
• Install cross tees 60&120 every 0.60m.
• Before installing the tiles the contractor will make sure that all mechanical, electrical ,
communication and fire items have been installed, inspected and tested
3.10 PAINTING
3.10.1 GENERAL
• Painting work will not be started until the electrical, HVAC embedded works and other
trades have been completed and tested.
3.10.2 MATERIALS
• Paint materials will be of the best quality available and will be obtained from a single
manufacturer approved by the owner.
• All materials will be delivered to the site in unopened, sealed and labeled containers
of the paint manufacturer.
• Colors will be as shown in a painting color schedule to be approved by the owner.
3.10.3 APPLICATION
• All surfaces will be cleaned
• Hardware, electrical fixtures and similar accessories will be removed or suitably masked
during preparation and painting operations.
• Priming will be done after cleaning the surfaces.
• Putting of new walls and putting of cracks and minor surface defects will be done after the
priming coat has been applied and has dried properly
• Paint will not be applied to wet or damp surfaces
• Paint will be considered dry when an addition coat can be applied.
• The finished surfaces will be free from drops, sags and brush marks and exhibiting good
coverage.
12
BRAUNS EGYPT FOR REAL ESTATE & CONTRACTING
Construction of Lekela Substation Project 220 kv
Organization Chart
APPENDIX A
Project Manager
Site Manager
HSE Engineer Q.C Manager Site Engineer Surveing Engineer Store Keeper