Swamp Dredging
Swamp Dredging
Swamp Dredging
DAFTAR ISI
1. INTRODUCTION 5
1.1. Background................................................................................................................... 5
1.2. Objectives..................................................................................................................... 6
1.3. Scope............................................................................................................................ 6
1.4. Associated Document...................................................................................................6
1.5. Pipeline Reference........................................................................................................6
1.6. Abbreviation.................................................................................................................. 7
1.7. Unit................................................................................................................................ 7
2. REFERENCES 8
2.1. Indonesian Regulations and Codes...............................................................................8
2.2. International Codes and Standards...............................................................................8
2.3. Project Documents and Others Reference....................................................................8
3. SUMMARY and CONCLUSIONS 9
3.1. Summary....................................................................................................................... 9
3.2. Conclusions................................................................................................................... 9
4. DESIGN DATA 10
4.1. Pipeline Design Life.....................................................................................................10
4.2. Geumetic Datum dan Coordinate System...................................................................10
4.3. Key Facilities Location.................................................................................................10
4.4. Pressure and Temperature..........................................................................................10
4.5. Pipeline Mechanical Properties...................................................................................11
4.6. Internal Corrosion Allowance.......................................................................................11
4.7. Manufacture Wall Thickness Tolerance.......................................................................12
4.8. Environment Data........................................................................................................12
4.8.1. Seabed Bathymetry (Water Depth)............................................................................12
4.8.2. Wave and Current Data.............................................................................................12
4.8.3. Seawater Parameters................................................................................................13
5. DESIGN CRITERIA and METHODOLOGY 14
5.1. Internal Pressure Containment....................................................................................14
5.2. Collapse Due to External Pressure..............................................................................15
5.3. Buckling due to Combined Bending and External Pressure........................................15
SWAMP DREDGING PROSEDURE
1. INTRODUCTION
1.1. Background
Bunyu terminal receives oil production from Bunyu Main Gathering Station and carry
100,000 barrels of oil to the tanker using a 1460 m loading lines twice a month. PT
Pertamina Asset 5 plans to replace the 16" export loading lines from the Bunyu Facility
Terminal to the Pipeline End Manifold (PLEM) because the existing facilities has been
operating since 1985. The existing 16" export loading lines at Bunyu Terminal are shown in
figure below.
The purpose of this project is to replace the new Subsea Loading Line from the existing
Subsea Loading Line by installing 16" NPS new pipelines from the Bunyu Facility Terminal
to the End Manifold Pipeline (PLEM) with the length of ± 1460m, and also installing 1 set of
PLEM along with a new flexible hose as a replacement for existing PLEM and flexible hose.
1.2. Objectives
verify the nominal wall thickness and material grade selected for subsea pipeline as part
of Bunyu Terminal Project. The minimum wall thickness required for pressure
containment, external collapse and propagation buckling is calculated in accordance with
ASME B31.4 and supplemented by API RP 1111
1.3. Scope
The purpose of this document is present the procedure for installing the 14” pipeline with
surface pull method from the PLB MITRASINDO 2 to the Tambak Lorok shore line using
single drum winch with 35MT capacity. The single drum winch shall be located
approximately 5m near at KP 198.245, whilst PLB MITRASINDO 2 shall be located at KP
197.145
Following table listed all documents that referred by and related to this report.
Table 1.4-1. Related Document
The Submarine pipeline and Riser that is required to be installed as part Bunyu Terminal
Project is described in table below.
SWAMP DREDGING PROSEDURE
Pipeline OD
Description Origin Termination Service
(mm)
16” NPS
Bunyu Facility
Export Loading 406.4 PLEM Crude Oil
Terminal
Lines Pipeline
1.6. Abbreviation
1.7. Unit
International Unit System (SI) shall be applied in this document, unless otherwise
noticed. Any conversion in parenthesis may be provided where appropriate
SWAMP DREDGING PROSEDURE
2. REFERENCES
Unless the edition of any code, standard or document is specifically referenced, the
latest edition will apply. The following Government Regulation, Standard and Code,
shall be followed, but not limited to
In general the Construction Superintendent has overall responsibilities for all push pull
operation while the onshore construction supervisor, barge master, and surveyor will
liaise with him to ensure the push pull operation is maintained as per planning and
requirement.
The push pull activity will start after the pre-trench activity and the onshore preparation
at Tambak Lorok site completed, and pipe haul barge ready at site. The pulling shall be
conducted by 35 Ton single drum winch at onshore site which will be located
approximately at KP 198.245.
The pipe will be welded on board MITRASINDO 2 start from KP 197.145, 1100 m in
front of land fall point (KP 197.145). Along 1100 m pulling, the pipes and the pulling
cable will be floated using 208 liters floatation drums as the buoyancy agent (16 drums
per joint pipe).
There will be a bamboo/wooden stake every 25m that will be staggered at both side of
shore approach portion trench area from KP 198.245 until KP 197.145. These bamboos
installed before pre-trench activity commenced as a border marking of trench area.
After the trenching operation completed, these bamboos will be kept in position to keep
the pipe align with the trench line when the pipe pulled from the onshore
Location Coordinate
Facility
Northin Eastin
g (m) g (m)
Start Point : KP 197.145 9 233 439
657.268 066.47
End Point : KP 198.245 9 232 438
630.072 668.06
4.3. Marine Spreads
Contractor will provides marine spreadsheet to support all activities during shore
pull work phase. Contractor will classify the marine spreadsheet according to
work phase as describe in the following table.
N
Vessel Name Vessel Purpose
o
5. TECHNICAL REQUIREMENT
5.1. General
During the mobilisation of the MITRASINDO 2, the following work status shall be ready:
All works and procedures under this specification shall be subjected to inspection by
COMPANY/Representative. All the defective works not conforming to this
specification shall be repaired at cost of CONTRACTOR/SUB CONTRACTOR.
6. DETAIL PROCEDURE
6.1. Preparation
Push pull activity will be commenced upon confirmation of readiness the below items:
Onshore Site Preparation
1. Standard arm excavator will be used to clear and level the general area of winch
and excavate the hold back anchor behind the winch location. This excavator will
be moved on the site via road.
2. Bench mark and bamboo stake at both side of the trench ROW to be built
staggered every 25 meters distance from KP 198.245 to KP 197.145 prior to
commencement of pre-trenching work and push pull.
3. Mobil lighting will be installed on site to support work in night at required area and
will be adjusted based on site condition. Mobil generator set will be used as power
source.
4. Safety zones will be marked. Safety zones as required for winch operator and
access space. These areas will be protected by using barricades. For safety
reason, trenched soil area will be protected using temporary fences.
Pre-trenching Work
Push pull activity will be commenced after the completion of pre-trenching work and
the pipe barge haul at site. Cofferdam is installed properly surrounding the facilities to
avoid flooded by sea current and sea wall is opened as necessary for access of the
pipe entering the ORF area. The detail and procedures of this pre-trenching works
including cofferdam, protection and reinforcement of cable tray and existing pipes
provided in Doc. KJG4-TLE-3300-02-OF-PR-003, Pre-trenching Procedure
Using echo sounder, the pre-trenching can be monitored width and depth using the
following procedure:
After all of trip pre-trenching performed by TSHD from 188.814 to 195.100 KP
surveyor will survey the result of pre-trenching, so we know actual the depth that
has been reached.
During a survey conducted by the surveyor bathymetric, TSHD will stand by until
the surveyor finish survey (actual dredging produced).
SWAMP DREDGING PROSEDURE
On the plan by using TSHD, pre-trenching pas will be done approximately in four
passes, and each completed pass pre-trenching surveyor will return to the actual
measurement of the depth and volume produced.
If the target has been reached, the pre-trenching work has been completed for
this area, but if the target is not reached then TSHD will be back next pass again
until the target is reached.
Work pass shall start at KP 188.814 and TSHD shall continue pass until it
reached KP 195.100. The subsequent pass shall then return to KP 188.814. This
process will be repeated until the required trench depth is achieved.
If required, shorter passes shall be undertaken to complete pre-trenching in a
piecemeal fashion.
For the acceptance criteria can be completed if reaches dredging depth of 3
meter. The target of pipe burial is minimum 2 meters burial from Top of Pipe, refer
to drawing KJGI-PGS-3300-OS-DG-006 Rev 0).
7. APPENDICES
LAMPIRAN A