FP12 - Integrated Change Control Process RV 1
FP12 - Integrated Change Control Process RV 1
Project
Integrated Change
Control Process
Multi Prospect
Management (MPM)
2020
MPM TEAM:
Andrew Leithead
Shekhar Shrestha
Akinjide Akinjobi
Emeraude Marie Sandy Myrtil
The Burj Khalifa Project Integrated Change Control Process
Table of Contents
1
The Burj Khalifa Project Integrated Change Control Process
Performing Integrated Change Control is the process of reviewing all change requests; approving
changes and managing changes to deliverables, project documents, and the project management
plan; and communicating the decisions 1. This process reviews all requests for changes to project
documents, deliverables, or the project management plan and determines the resolution of the
change requests. The performing change control process in the Burj Khalifa will be conducted from
project start through completion. MPM Project Manager will have the ultimate responsibility for
change control process. Changes may be requested by any stakeholders involved with the project
and may occur at any time throughout the project life cycle. Once the project is baselined such for
scope, schedule and cost or project management plan, any change deviating from the baseline plan
or any other deviation in the Project Management Plan must go through the change control
process. All the change request must be recorded in writing as recommended in this process
document.
1
As per PMBOK defined in Perform Integrated Change Control.
2
The Burj Khalifa Project Integrated Change Control Process
The Burj Khalifa will categories the change in two main category for delegating the authority for
making decision. The first category of change which does not affect the Project Management plan,
baselines, policies and procedure, project charter, contracts and statement of works, the project
manager will have the authority to make decision on such changes. In the other hand, the second
category of change which does affect those key elements ( Project Management plan, baselines,
policies and procedures, project charter etc.), such change request will be approved, deferred or
rejected by Change Control Board comprising of Project Sponsor, Project Manager and senior
representative from relevant stakeholder entity like customer, experts and others as per relevance.
The Burj Khalifa’s definition for change for key area will be as follows:
Schedule change: Any deviation from schedule plan of the activity which may deviate
outside the range of acceptable level of tolerance;
Budget change: Any deviation from project budget or cost of the item which may deviate
outside the range of acceptable level of tolerance in cost and budget;
Scope change: Any deviation from scope of project in product, service or results which may
have impact on the project objective and goals;
Project document change: Any change or modification in the project documentation
The Burj Khalifa Project will form a Change Control Board comprising of as follows personnel:
Project Sponsor
Project Manager
Authorized representative of stakeholder
Subject Matter Experts (SME)
Functional Managers
Others ( as per need)
Project Manager will function as member secretary of the Change Control Board. All the
communication and administrative functions are managed by Project Manager.
The flowchart of the change control process in the Burj Khalifa will be as follows:
3
The Burj Khalifa Project Integrated Change Control Process
9. Manage the
Project to the
updated plan
4.Submit to the CCB Project Manager Plan and organize a CCB meeting,
and review of the Discuss and assess the change request,
change. Look for the different options and
5.Making decision Change Control Making decision on the change request
on Change Board (CCB) based on the analysis and different
options,
Request can be approved or rejected or
deferred,
6.Record in change Project Manager Entry into the change log
log and update its Update the change log
status
7.Update the Project Project Manager Revise the plan related to the knowledge
Management Plan area of change,
Update the Project Management Plan
8.Communicate the Project Manager Inform to the requesting stakeholder about
change to the the decision of change,
stakeholder Inform to the other relevant stakeholders
who may have impact of decision on
change
9.Manage the Project Manager Implementation of activities as per the
project to the Project Team updated management plan
updated plan manager Monitor progress to the updated
management plan
Record the completion of change request
Close the change request.
5
The Burj Khalifa Project Integrated Change Control Process
Short Description
Requestor Estimate of
Priority
Date raised
Raised by
Change Request
Assessment
Detailed description
6
The Burj Khalifa Project Integrated Change Control Process
Small change?
Assigned on
Change Request
Analysis
Impact analysis
Scope Impact
Description
Schedule Impact
Description
Cost Impact
Description
7
The Burj Khalifa Project Integrated Change Control Process
Impact of not
implementing
Alternatives
Completion ccriteria
for change request
Estimated effort
Estimated cost
Analyzed Priority of
Request
Resources
Estimates validated on
Estimates validated by
Analysed by
Change Request
Decision
Decision
8
The Burj Khalifa Project Integrated Change Control Process
Rationale for
decision
Approved
resources
Approved cost
Comments
---------------------------------------------
Printed Name, Signature, Date
Decision Maker:
-----------------------------------------
Printed Name, Signature, Date
9
The Burj Khalifa Project Integrated Change Control Process
5. Change Log
A Change Log is a list containing some of the information about all the Change Requests.
10
The Burj Khalifa Project Integrated Change Control Process
Project PCR ID Short description Raised by Priority Date raised Owner Target date Status Status date
Number
References:
1. A guide to Project Management Body of Knowledge, 6th edition (PMBOK Guide), PMI, 2017.
2. Integrated Change Control Process, Strelka, OBS MPM, 2020
3. EPS Green Factory in Tripoli, Shake ITUP, OBS, MPM
11