Ref. Num.

: 160816RFQ010

Date : 17 September 2020

To : Gian C. Villatuya
Design & Sales Engineer

Description Quantity Material Cost Labor Cost Total Cost

Tensar RE 520 Geogrids 7,793.17 sq.m 35 sq.m 272,760.95


Tensar RE 560 Geogrids 1,666.80 sq.m 35 sq.m 58,338.00
Modular Blocks 6,855.00 pc 45.5 pc 311,902.50
Pins 13,710.00 pc 0.75 pc 10,282.50
Lean Concrete 11.59 cu.m 4,850.00 cu.m 680 cu.m 64,092.70
Grave (g1) 164.00 cu.m 1,250.00 cu.m 55 cu.m 214,020.00
Geotextile 1,308.15 sq.m 10 sq.m 13,081.50
Backfill & Compaction 3,785.55 cu.m 290 cu.m 1,097,809.50

2,042,287.65

Description Quantity Unit Cost Total Cost


Preliminaries
Site Office 1 lot 30,000.00 ̷ lot 30,000.00
Barracks of Workers 1 lot 50,000.00 ̷ lot 50,000.00
Warehouse 1 lot 35,000.00 ̷ lot 35,000.00
Service Vehicle 1 lot 20,000.00 ̷ lot 20,000.00
Utilities 1 lot 15,000.00 ̷ lot 15,000.00
Technical Supervision & Testing
Supervision 1 lot 60,000.00 ̷ lot 60,000.00
Testing (G1) 1 lot 30,000.00 ̷ lot 30,000.00
Mobilization
Equipment
Excavator 1 lot 80,000.00 ̷ lot 80,000.00
Roller Compactor 1 lot 60,000.00 ̷ lot 60,000.00
Walk behind 1 lot 5,000.00 ̷ lot 5,000.00
Manpower 1 lot 20,000.00 ̷ lot 20,000.00
EHS
PPE 1 lot 15,000.00 ̷ lot 15,000.00
Safety Officer 1 lot 26,000.00 ̷ lot 26,000.00
Bollards, Caution 1 lot 10,000.00 ̷ lot 10,000.00
Tape, etc.
Clean up 1 lot 32,000.00 ̷ lot 32,000.00

488,000.00

TOTAL AMOUNT 2,530,287.65


MICHAEL Y. SALVEDIA