Project: EPM Gantt Chart Date: Sun 8/12/19

The document outlines the project plan for installing a new lift. It includes 43 tasks over 4 phases from 2019 to 2034. The project planning phase involves team meetings, design, cost estimation and authorization. Next, construction involves removing materials, building the platform, walls, conduits and interior. Installation encompasses electrical, mechanical, safety and security work. Finally, commissioning consists of pilot testing, review and project handover.

Uploaded by

MeliRampersand
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
106 views1 page

Project: EPM Gantt Chart Date: Sun 8/12/19

The document outlines the project plan for installing a new lift. It includes 43 tasks over 4 phases from 2019 to 2034. The project planning phase involves team meetings, design, cost estimation and authorization. Next, construction involves removing materials, building the platform, walls, conduits and interior. Installation encompasses electrical, mechanical, safety and security work. Finally, commissioning consists of pilot testing, review and project handover.

Uploaded by

MeliRampersand
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID WBS Task Name Duration Start Finish 2024

2019 2024 2029 2034 2039


1 1 Project Planning 10 days Tue 1/10/19 Fri 11/10/19
2 1.1 Project planning and Team Meeting1 day Tue 1/10/19 Tue 1/10/19
3 1.2 Sketch & Design 3 days Wed 2/10/19 Fri 4/10/19
4 1.3 Electrical Design 1 day Sat 5/10/19 Sat 5/10/19
5 1.4 3D Drawing 2 days Mon 7/10/19 Tue 8/10/19
6 1.5 Cost Estimation 2 days Wed 9/10/19 Thu 10/10/19
7 1.6 JKKP Authorization 1 day Fri 11/10/19 Fri 11/10/19
8 2 Construction 20 days Sat 12/10/19 Mon 4/11/19
9 2.1 Unnecessary Materials & 5 days Sat 12/10/19 Thu 17/10/19
Components Removal

10 2.2 Platform Construction 2 days Fri 18/10/19 Sat 19/10/19


11 2.3 Shaft's Supporting wall construction3 days Mon 21/10/19Wed 23/10/19
12 2.4 Building conduits 3 days Thu 24/10/19 Sat 26/10/19
13 2.5 landing door construction 3 days Mon 28/10/19Wed 30/10/19
14 2.6 Lift Machine room 2 days Thu 31/10/19 Fri 1/11/19
15 2.7 Lift Interior (wall panels, ceiling & 2 days Sat 2/11/19 Mon 4/11/19
flooring)

16 3 Installation 25 days Tue 5/11/19 Tue 3/12/19


17 3.1 Electrical 7 days Tue 5/11/19 Tue 12/11/19
18 3.1.1 Wiring 2 days Tue 5/11/19 Wed 6/11/19
19 3.1.2 Ventilation 2 days Thu 7/11/19 Fri 8/11/19
20 3.1.3 Lift control System 1 day Sat 9/11/19 Sat 9/11/19
21 3.1.4 Trunking installation 1 day Mon 11/11/19Mon 11/11/19
22 3.1.5 lighting and speakers 1 day Tue 12/11/19 Tue 12/11/19
23 3.2 Mechnical 8 days Wed 13/11/19Thu 21/11/19
24 3.2.1 Buffer Spring 2 days Wed 13/11/19Thu 14/11/19
25 3.2.2 Control Box 1 day Fri 15/11/19 Fri 15/11/19
26 3.2.3 Roof pulley system 2 days Sat 16/11/19 Mon 18/11/19
27 3.2.4 Traction system & Counter weight2 days Tue 19/11/19 Wed 20/11/19
28 3.2.5 lift door controllers 1 day Thu 21/11/19 Thu 21/11/19
29 3.3 Safety and security 6 days Fri 22/11/19 Thu 28/11/19
30 3.3.1 Emergency alarm 1 day Fri 22/11/19 Fri 22/11/19
31 3.3.2 CCTV 1 day Sat 23/11/19 Sat 23/11/19
32 3.3.3 Fire extinguishers 1 day Mon 25/11/19Mon 25/11/19
33 3.3.4 Intercom 1 day Tue 26/11/19 Tue 26/11/19
34 3.3.5 Weight measuring system 2 days Wed 27/11/19Thu 28/11/19
35 4 Commisioning 11 days Fri 29/11/19 Wed 11/12/19
36 4.1 Pilot testing 7 days Fri 29/11/19 Fri 6/12/19
37 4.1.1 Site clean up 2 days Fri 29/11/19 Sat 30/11/19
38 4.1.2 Testing 2 days Mon 2/12/19 Tue 3/12/19
39 4.1.3 Feedback 1 day Wed 4/12/19 Wed 4/12/19
40 4.1.4 Pilot Run 2 days Thu 5/12/19 Fri 6/12/19
41 4.2 Review 2 days Sat 7/12/19 Mon 9/12/19
42 4.2.1 Close meeting 1 day Sat 7/12/19 Sat 7/12/19
43 4.2.2 Project handover 1 day Mon 9/12/19 Mon 9/12/19

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: EPM gantt chart
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Sun 8/12/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress