Bangladesh Municipal Development Fund (BMDF)
Bangladesh Municipal Development Fund (BMDF)
Municipal Governance & Services Project (MGSP) BMDF (IDA Credit No. 5339-BD)
46 Sub-Project Status
Month: 2-Dec-2019
Municipal Market
W-008-BMDF-
19 footing completed out of 19 Footing. All short
MGSP-3P-SIRAJ- 39.09 29-May-2019 7-Jun-19 31-Mar-20 15% 15%
column completed (51 short column)
18-MM/02
3 Sirajgonj 3
Road, Drain, SL
Drain work on going (900m completed out of 2256m),
Road work are ongoing (new road 1000m WBM
W-009-BMDF-
completed), 2.5 km hard bed, soling and widening
MGSP-3P-SIRAJ- 87.98 29-May-2019 1-Jun-19 31-Mar-20 32% 39.60% 12.27 0.00 13.94%
work completed and 383 WBM completed out of
18-R-D-SL-B/03
4.5km. 2000nos Divider making and 50m palasidding
placement
1 of 4
Physical Progress (%) Financial Progress (%)
Sub-project Contract Date of Completion Financial
Sl. No. Work
Name of ULB Number Component Amount (BDT- Contract Date as per Achived Progress Achived Status
No. of SP Starting Date Till to Till to
with code Mil.) Agreement Contract upto 31-10- (Mill.Tk.) upto 31-
date Date
19 10-19
1 2 3 4 5 6 7 8 9 10 10 11 12 13
W-018-BMDF-
Auditorium Roof casting completed. Community
MGSP-3P-
7 Sreemongal 1 Community Center 75.59 14-Feb-2019 25-Feb-2019 20-Feb-2020 18% 19% 8.46 11.19% center 2nd floor column casting completd. 3rd floor
SREEM-18-
slab centering and shuttering ongoing.
CC/01
W-019-BMDF- Kitchen Market
Ground floor bottom slab casting 70% completed.Half
MGSP-3P-
35.80 8-May-2019 14-May-19 31-Mar-20 33% 35% 10.83 10.01% 30.24% portion of Ground floor slab shuttering work on going.
PANCH-18-
Septic tank earth excavation work on going.
8 Panchbibi 2 KM/01
W-020-BMDF- Super Market
MGSP-3P-
73.28 8-May-2019 14-May-19 31-Mar-20 41% 44% 9.78 13.35% 13.35% 60% Ground floor slab completed.
PANCH-18-
M.M/02
W-021-BMDF- Municipal Market
4th floor RCC slab completed. 2nd floor brick works
MGSP-3P-
44.77 30-Apr-2019 26-May-19 31-Mar-20 52% 66% 0.00% completed, wall & ceiling plaster work completed and
CHAND-18-
windows fixing is going on.
KM/01
Road
9 Chandpur 2 Shekher Hat to Motkhola Mazar road box cutting and
W-063-BMDF- sand filling work completed. Melitery road to Fridgong
MGSP-3P- 104.11 28-May-2019 15-Jun-19 31-Mar-20 28% 30% 0.00% road WBM on going. Poet Kazi Nazrul road from BNP
CHAND-18-R/04 office road Box cutting is on going. Bagadi road to
Truck ghut to Battala road box cutting is on going.
W-024-BMDF- Kitchen Market (VE) RCC slab casting completed. Brick work 3rd floor
10 Bhola 1 MGSP-3P- 65.50 2-Apr-2019 4-Apr-2019 31-Mar-2020 65% 67% 11.28 17.22% 17.22% comleted and 4th floor on going. In side plaster on
BHOLA-17-KM/02 going. Lift pore RCC work on going.
Municipal Market
About 12 nos pile cap casting completed. Rest pile cap
W-025-BMDF-
casting preparation is in progress. Underground water
MGSP-3P-RAMG- 44.91 9-May-2019 9-Jun-19 31-Mar-2020 24% 25% 10.41 23.18%
reservoir wall casting completed.Septic tank base
18-MM/01
11 Ramgonj 2 casting & wall works completed
Road-Drain & SL
W-026-BMDF- About 1489m WBM completed out of 1906m with
MGSP-3P-RAMG- 41.97 28-May-2019 9-Jun-19 31-Mar-2020 17% 17% 0.00% brick on end edging. About 160m drain casting
18-R-D/02 completed
W-028-BMDF-
Kitchen Market
MGSP-3P-KCC-18- 96.09 29-May-2019 9-Jun-2019 31-Mar-2020 18% 26% 23.99 24.96% 193 nos cast in situ pililing completed out of 300 nos.
(Khalishpur)
KM/01
480m RCC drain base casting and 848m RCC drain wall
W-030-BMDF- casting completed at Mohesswrpasha main road drain.
MGSP-3P-KCC-18-R- Road & Drain-1 187.25 28-May-2019 10-Jun-2019 31-Mar-2020 12% 13% 0.00% 120m base casting completed at 18 no' road drain.
12 KCC 3 D/03 455m RCC drain base casting and 895m RCC drain wall
casting completed at chorerhat main road drain.
W-031-BMDF- Earth cutting for drain, pipe laying, RCC Drain wall &
Road, foothpath and
MGSP-3P-DNCC- 184.22 15-May-2019 19-May-19 31-Mar-2020 55% 56% 40.01 21.72% Slab casting work ongoing (2350m out of 2400m),Road
Drain-1
18-R-D/01 work: 500m WBM is on going
W-032-BMDF- Earth cutting for drain, pipe laying, RCC Drain wall &
Road, foothpath and
MGSP-3P-DNCC- 222.21 15-May-2019 2-Jul-19 31-Mar-2020 42% 49% 37.61 16.92% Slab casting work ongoing (3500m out of 4000m) and
Drain-2
13 DNCC 4 18-R-D/02 road work 1200m is on going
2 of 4
Physical Progress (%) Financial Progress (%)
Sub-project Contract Date of Completion Financial
Sl. No. Work
Name of ULB Number Component Amount (BDT- Contract Date as per Achived Progress Achived Status
No. of SP Starting Date Till to Till to
with code Mil.) Agreement Contract upto 31-10- (Mill.Tk.) upto 31-
date Date
19 10-19
13 DNCC
1 2 34 4 5 6 7 8 9 10 10 11 12 13
W-033-BMDF- Earth cutting for drain, pipe laying, RCC Drain wall &
Road, foothpath and
MGSP-3P-DNCC- 223.09 30-May-2019 2-Jul-19 31-Mar-2020 40% 48% 32.12 14.40% Slab casting work ongoing (3900m out of 5000m) and
Drain-3
18-R-D/03 road work 800m is on going
BMDF-MGSP- Solid Waste Mngt.
0.00 0% 0% Evaluation report under BMDF review.
DNCC-G-01 (Equipment)
W-038-BMDF-
WBM-8140 m out of 11416m completed, Palasiding
MGSP-3P-MANIK- Road-1 149.57 29-May-2019 1-Jul-19 31-Mar-2020 30% 33% 0.00%
1000m out of 1280m completed.
18-R/01
14 Manikgonj 2
W-039-BMDF- WBM- 7185 m out of 11645m completed , RCC road
MGSP-3P-MANIK- Road & Drain-2 138.03 30-May-2019 1-Jul-19 31-Mar-2020 31% 32% 0.00% 500 m out of 500m completed. Palasiding- 1000m out
18-R-D/02 of 1350m completed.
Multipurpose
W-042-BMDF- 601 nos sand piling completed out of 1414 nos.
Building(VE) &
MGSP-3P-MONG- 108.85 28-May-2019 16-Jun-19 31-Mar-2020 9% 9% 0.00% Remain number of four circular column concreting
Boundary Market
18-MM/01 completed and 3rd floor shuttering ongoing.
15 Mongla Port 2
Poura Super Market
W-043-BMDF-
cum Com. Cen. All Sub Soil Investigation completed. Materials
MGSP-3P-MONG- 53.56 28-Apr-2019 1-May-19 31-Mar-2020 13% 14% 7.46 13.93%
mobilization and earth excavation ongoing.
18-PM-CC/02
W-044-BMDF-
MGSP-3P- 3290m Drain completed out of 8731m and R-8 850m
Road & Drain-1 217.32 19-May-2019 25-May-19 31-Mar-2020 17% 18% 21.80 10.03%
PABNA-18-R- WBM completed out of 850m.
16 Pabna 2 D/01
W-045-BMDF- 2790m Drain completed out of 8735m and R-3 1100m
MGSP-3P- WBM completed out of 1150m. R-12 R.c.c road work
Road & Drain-2 214.70 19-May-2019 25-May-19 31-Mar-2020 17% 18%
PABNA-18-R- 220m completed out of 500m. R-14 WBM completed
D/02 700m out of 1306m.
Bus Terminal & Fruit
Service building: All (22 nos) short column out of
Market
W-046-BMDF- casting completed. Fruit market: All (20 nos) short
MGSP-3P-CHOW- 117.01 16-Apr-2019 26-Apr-19 31-Mar-2020 25% 26% 0.00% column casting completed. Terminal building: About
18-BT-FM/01 17 nos base casting completed out of 32 nos and 17
nos short column casting completed.
17 Chowmuhani 2
About 650m drain and 590m drain slab completed out
of 1054m. About 275 nos boundary wall column and
W-049-BMDF-
footing casting completed out of 685 nos. About 450m
MGSP-3P-CHOW- Poura Park 82.20 26-May-2019 9-Jun-19 31-Mar-2020 23% 24% 8.72 10.61%
grade beam casting completed. Approximately 95%
18-PP/04
water hyacinths remoed from pond. About 65 nos
pond side railing footing completed.
3 of 4
Physical Progress (%) Financial Progress (%)
Sub-project Contract Date of Completion Financial
Sl. No. Work
Name of ULB Number Component Amount (BDT- Contract Date as per Achived Progress Achived Status
No. of SP Starting Date Till to Till to
with code Mil.) Agreement Contract upto 31-10- (Mill.Tk.) upto 31-
19 Noakhali 3 date Date
19 10-19
1 2 3 4 5 6 7 8 9 10 10 11 12 13
W-054-BMDF- Renovation of Bus Drain work 400m completed out of 410m. Aggregate
MGSP-3P-NOAK- Terminal Sand sub-base ongoing. RCC work of steel structure is
45.72 29-Apr-2019 2-May-19 31-Mar-20 30% 32% 8.07 18% 17.66%
18-BT/03 completed. Brick work of terminal building is
completed.
W-056-BMDF- Road-Drain-Street
MGSP-3P-DHAM- Light 1900m pipe laying completed out of 2175m , 965 nos.
20 Dhamrai 1 70.605 26-May-2019 15-Jun-19 31-Mar-2020 30% 32% 11.99 16.98%
18-R-D-S-L/02 pipe casting completed out of 995 nos.
W-059-BMDF-
MGSP-3P-
22 Betagi 1 Municipal Market 14.31 29-May-2019 27-Jun-19 31-Mar-2020 25% 26% 0.00% Up to grade bem completed. Septic Tank on going.
BETAGI-18-
MM/01
4 of 4