Bangladesh Municipal Development Fund (BMDF)

This document provides a status update on 46 sub-projects being implemented under the Bangladesh Municipal Development Fund Municipal Governance & Services Project. It includes information such as the name of the urban local body, component, contract amount, date of contract agreement, work starting date, completion date, physical and financial progress. The status column at the end summarizes the current progress of each sub-project, such as ongoing drain work, road work, building construction activities like pile cap casting and floor slab construction.

Uploaded by

sadaturpju
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views4 pages

Bangladesh Municipal Development Fund (BMDF)

This document provides a status update on 46 sub-projects being implemented under the Bangladesh Municipal Development Fund Municipal Governance & Services Project. It includes information such as the name of the urban local body, component, contract amount, date of contract agreement, work starting date, completion date, physical and financial progress. The status column at the end summarizes the current progress of each sub-project, such as ongoing drain work, road work, building construction activities like pile cap casting and floor slab construction.

Uploaded by

sadaturpju
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Bangladesh Municipal Development Fund (BMDF)

Municipal Governance & Services Project (MGSP) BMDF (IDA Credit No. 5339-BD)
46 Sub-Project Status
Month: 2-Dec-2019

Physical Progress (%) Financial Progress (%)


Sub-project Contract Date of Completion Financial
Sl. No. Work
Name of ULB Number Component Amount (BDT- Contract Date as per Achived Progress Achived Status
No. of SP Starting Date Till to Till to
with code Mil.) Agreement Contract upto 31-10- (Mill.Tk.) upto 31-
date Date
19 10-19
1 2 3 4 5 6 7 8 9 10 10 11 12 13
W-001-BMDF- Municipal Market
MGSP-3P-
1 Homna 1 128.55 27-Feb-2019 6-Mar-19 5-Mar-20 38% 47% 18.389 14.30% 14.30% GF floor roof shuttering for casting is going on.
HOMNA-17-
MM/01

W-003-BMDF- Mul. Com.


MGSP-3P- Building(SA) All pile casting completed, bracing works and earth
386.86 30-May-2019 30-May-19 31-Mar-20 28% 29% 44.81 0.00 11.58%
CHOTTA-18- works ongoing
2 CCC 2 MM/01
W-004-BMDF- Kitchen Market (FT)
Earth cutting on going, 25 pile cap casting
MGSP-3P-
171.73 27-May-2019 27-May-19 31-Mar-20 20% 23% 25.36 0.00 14.77% completed out of 55 nos., 20% Mat casting
CHOTTA-18-
completed.
KM/02
Kitchen Market & S. Ground floor slab suttering and reinforcement
W-007-BMDF- House binding work on going(33% completed).
MGSP-3P-SIRAJ- 127.79 16-May-2019 23-May-19 31-Mar-20 35% 36% 32.67 0.00 25.56%
18-KM-SH/01

Municipal Market
W-008-BMDF-
19 footing completed out of 19 Footing. All short
MGSP-3P-SIRAJ- 39.09 29-May-2019 7-Jun-19 31-Mar-20 15% 15%
column completed (51 short column)
18-MM/02
3 Sirajgonj 3
Road, Drain, SL
Drain work on going (900m completed out of 2256m),
Road work are ongoing (new road 1000m WBM
W-009-BMDF-
completed), 2.5 km hard bed, soling and widening
MGSP-3P-SIRAJ- 87.98 29-May-2019 1-Jun-19 31-Mar-20 32% 39.60% 12.27 0.00 13.94%
work completed and 383 WBM completed out of
18-R-D-SL-B/03
4.5km. 2000nos Divider making and 50m palasidding
placement

Mul. Com. Building


W-011-BMDF- 69 nos pile cap concreting completed out of 82 nos.
4 Jhenaidah 1 MGSP-3P-JHEN- 185.08 18-Mar-2019 18-Mar-19 16-Mar-20 31% 35% 27.74 14.99% 14.99% Re-bar works for pile cap and pile cap concreting
18-MM/01 ongoing.

W-012-BMDF- Poura Super Market


Basement ,Retaining wall,ram completed, column is on
MGSP-3P-SREE- 53.10 25-Mar-2019 2-Apr-2019 24-Mar-20 30% 32% 13.45 0.00 25.33%
going.preparation for ground floor
18-PSM/01
5 Sreepur 2 Road
W-013-BMDF- 2200m box cutting and 1500m ISG ,1350m As
MGSP-3P-SREE- 113.33 8-May-2019 14-May-19 31-Mar-20 26% 33% completed out of 3700m,780m RCC completed,Rod
18-R-D/02 fixing is on going

W-014-BMDF- Poura Market


All pile cap casting completed within 08.11.2019.
MGSP-3P-NAR- 25.34 29-Apr-2019 8-May-19 31-Mar-20 34% 36% 5.93 23.41%
Basement floor slab casting ongoing.
18-PM/01
Road, Drain & SL-1
420m road is completed out of 4.507km. 1210 nos RCC
W-015-BMDF-
pipes(drain) casting completed out of 2300. 984 m RCC
MGSP-3P-NAR- 287.32 29-Apr-2019 8-May-19 31-Mar-20 15% 16% 28.79 10.02%
U-drain has been constructed. Pipe laying 100m
6 Narsingdi 3 18-R-D/02
completed and going on.
Road, Drain & SL-2
880m road is completed out of 7.611km. 1090 nos
W-016-BMDF-
RCC pipe(drain) casting completed out of 1100, RCC
MGSP-3P-NAR- 282.11 29-Apr-2019 8-May-19 31-Mar-20 18% 19% 43.23 15.32%
Drain 2355m Completed out of 5024m . Pipe laying
18-R-D/03
work 700m completed and ongoing.

1 of 4
Physical Progress (%) Financial Progress (%)
Sub-project Contract Date of Completion Financial
Sl. No. Work
Name of ULB Number Component Amount (BDT- Contract Date as per Achived Progress Achived Status
No. of SP Starting Date Till to Till to
with code Mil.) Agreement Contract upto 31-10- (Mill.Tk.) upto 31-
date Date
19 10-19
1 2 3 4 5 6 7 8 9 10 10 11 12 13
W-018-BMDF-
Auditorium Roof casting completed. Community
MGSP-3P-
7 Sreemongal 1 Community Center 75.59 14-Feb-2019 25-Feb-2019 20-Feb-2020 18% 19% 8.46 11.19% center 2nd floor column casting completd. 3rd floor
SREEM-18-
slab centering and shuttering ongoing.
CC/01
W-019-BMDF- Kitchen Market
Ground floor bottom slab casting 70% completed.Half
MGSP-3P-
35.80 8-May-2019 14-May-19 31-Mar-20 33% 35% 10.83 10.01% 30.24% portion of Ground floor slab shuttering work on going.
PANCH-18-
Septic tank earth excavation work on going.
8 Panchbibi 2 KM/01
W-020-BMDF- Super Market
MGSP-3P-
73.28 8-May-2019 14-May-19 31-Mar-20 41% 44% 9.78 13.35% 13.35% 60% Ground floor slab completed.
PANCH-18-
M.M/02
W-021-BMDF- Municipal Market
4th floor RCC slab completed. 2nd floor brick works
MGSP-3P-
44.77 30-Apr-2019 26-May-19 31-Mar-20 52% 66% 0.00% completed, wall & ceiling plaster work completed and
CHAND-18-
windows fixing is going on.
KM/01
Road
9 Chandpur 2 Shekher Hat to Motkhola Mazar road box cutting and
W-063-BMDF- sand filling work completed. Melitery road to Fridgong
MGSP-3P- 104.11 28-May-2019 15-Jun-19 31-Mar-20 28% 30% 0.00% road WBM on going. Poet Kazi Nazrul road from BNP
CHAND-18-R/04 office road Box cutting is on going. Bagadi road to
Truck ghut to Battala road box cutting is on going.

W-024-BMDF- Kitchen Market (VE) RCC slab casting completed. Brick work 3rd floor
10 Bhola 1 MGSP-3P- 65.50 2-Apr-2019 4-Apr-2019 31-Mar-2020 65% 67% 11.28 17.22% 17.22% comleted and 4th floor on going. In side plaster on
BHOLA-17-KM/02 going. Lift pore RCC work on going.

Municipal Market
About 12 nos pile cap casting completed. Rest pile cap
W-025-BMDF-
casting preparation is in progress. Underground water
MGSP-3P-RAMG- 44.91 9-May-2019 9-Jun-19 31-Mar-2020 24% 25% 10.41 23.18%
reservoir wall casting completed.Septic tank base
18-MM/01
11 Ramgonj 2 casting & wall works completed
Road-Drain & SL
W-026-BMDF- About 1489m WBM completed out of 1906m with
MGSP-3P-RAMG- 41.97 28-May-2019 9-Jun-19 31-Mar-2020 17% 17% 0.00% brick on end edging. About 160m drain casting
18-R-D/02 completed

W-028-BMDF-
Kitchen Market
MGSP-3P-KCC-18- 96.09 29-May-2019 9-Jun-2019 31-Mar-2020 18% 26% 23.99 24.96% 193 nos cast in situ pililing completed out of 300 nos.
(Khalishpur)
KM/01

480m RCC drain base casting and 848m RCC drain wall
W-030-BMDF- casting completed at Mohesswrpasha main road drain.
MGSP-3P-KCC-18-R- Road & Drain-1 187.25 28-May-2019 10-Jun-2019 31-Mar-2020 12% 13% 0.00% 120m base casting completed at 18 no' road drain.
12 KCC 3 D/03 455m RCC drain base casting and 895m RCC drain wall
casting completed at chorerhat main road drain.

1000m RCC drain base casting and 1470m RCC drain


W-034-BMDF-
wall casting completed at KDA avenue. 540m RCC drain
MGSP-3P-KCC- Road & Drain-2 173.88 30-May-2019 10-Jun-19 31-Mar-2020 12% 13% 0.00%
base casting and 1030m RCC drain wall casting
18-R-D/04
completed at abu ahmed road drain.

W-031-BMDF- Earth cutting for drain, pipe laying, RCC Drain wall &
Road, foothpath and
MGSP-3P-DNCC- 184.22 15-May-2019 19-May-19 31-Mar-2020 55% 56% 40.01 21.72% Slab casting work ongoing (2350m out of 2400m),Road
Drain-1
18-R-D/01 work: 500m WBM is on going

W-032-BMDF- Earth cutting for drain, pipe laying, RCC Drain wall &
Road, foothpath and
MGSP-3P-DNCC- 222.21 15-May-2019 2-Jul-19 31-Mar-2020 42% 49% 37.61 16.92% Slab casting work ongoing (3500m out of 4000m) and
Drain-2
13 DNCC 4 18-R-D/02 road work 1200m is on going

2 of 4
Physical Progress (%) Financial Progress (%)
Sub-project Contract Date of Completion Financial
Sl. No. Work
Name of ULB Number Component Amount (BDT- Contract Date as per Achived Progress Achived Status
No. of SP Starting Date Till to Till to
with code Mil.) Agreement Contract upto 31-10- (Mill.Tk.) upto 31-
date Date
19 10-19
13 DNCC
1 2 34 4 5 6 7 8 9 10 10 11 12 13
W-033-BMDF- Earth cutting for drain, pipe laying, RCC Drain wall &
Road, foothpath and
MGSP-3P-DNCC- 223.09 30-May-2019 2-Jul-19 31-Mar-2020 40% 48% 32.12 14.40% Slab casting work ongoing (3900m out of 5000m) and
Drain-3
18-R-D/03 road work 800m is on going
BMDF-MGSP- Solid Waste Mngt.
0.00 0% 0% Evaluation report under BMDF review.
DNCC-G-01 (Equipment)
W-038-BMDF-
WBM-8140 m out of 11416m completed, Palasiding
MGSP-3P-MANIK- Road-1 149.57 29-May-2019 1-Jul-19 31-Mar-2020 30% 33% 0.00%
1000m out of 1280m completed.
18-R/01
14 Manikgonj 2
W-039-BMDF- WBM- 7185 m out of 11645m completed , RCC road
MGSP-3P-MANIK- Road & Drain-2 138.03 30-May-2019 1-Jul-19 31-Mar-2020 31% 32% 0.00% 500 m out of 500m completed. Palasiding- 1000m out
18-R-D/02 of 1350m completed.

Multipurpose
W-042-BMDF- 601 nos sand piling completed out of 1414 nos.
Building(VE) &
MGSP-3P-MONG- 108.85 28-May-2019 16-Jun-19 31-Mar-2020 9% 9% 0.00% Remain number of four circular column concreting
Boundary Market
18-MM/01 completed and 3rd floor shuttering ongoing.
15 Mongla Port 2
Poura Super Market
W-043-BMDF-
cum Com. Cen. All Sub Soil Investigation completed. Materials
MGSP-3P-MONG- 53.56 28-Apr-2019 1-May-19 31-Mar-2020 13% 14% 7.46 13.93%
mobilization and earth excavation ongoing.
18-PM-CC/02

W-044-BMDF-
MGSP-3P- 3290m Drain completed out of 8731m and R-8 850m
Road & Drain-1 217.32 19-May-2019 25-May-19 31-Mar-2020 17% 18% 21.80 10.03%
PABNA-18-R- WBM completed out of 850m.
16 Pabna 2 D/01
W-045-BMDF- 2790m Drain completed out of 8735m and R-3 1100m
MGSP-3P- WBM completed out of 1150m. R-12 R.c.c road work
Road & Drain-2 214.70 19-May-2019 25-May-19 31-Mar-2020 17% 18%
PABNA-18-R- 220m completed out of 500m. R-14 WBM completed
D/02 700m out of 1306m.
Bus Terminal & Fruit
Service building: All (22 nos) short column out of
Market
W-046-BMDF- casting completed. Fruit market: All (20 nos) short
MGSP-3P-CHOW- 117.01 16-Apr-2019 26-Apr-19 31-Mar-2020 25% 26% 0.00% column casting completed. Terminal building: About
18-BT-FM/01 17 nos base casting completed out of 32 nos and 17
nos short column casting completed.
17 Chowmuhani 2
About 650m drain and 590m drain slab completed out
of 1054m. About 275 nos boundary wall column and
W-049-BMDF-
footing casting completed out of 685 nos. About 450m
MGSP-3P-CHOW- Poura Park 82.20 26-May-2019 9-Jun-19 31-Mar-2020 23% 24% 8.72 10.61%
grade beam casting completed. Approximately 95%
18-PP/04
water hyacinths remoed from pond. About 65 nos
pond side railing footing completed.

W-050-BMDF- Road-Drain-1 Drain Completed 1600 m out of 3220m


MGSP-3P- Road Complete 1800 m out of 4720m
138.98 30-May-2019 15-Jun-19 31-Mar-2020 40% 43% 40.37 0.00% 29.05%
SAVAR-18-R-
18 Savar 2 D/01
W-051-BMDF- Road-Drain-2 Drain Completed 1450m out of 3080m
MGSP-3P- WBM completed 500m out of 3255m,
117.84 28-May-2019 15-Jun-19 31-Mar-2020 28% 30% 20.17 17.12%
SAVAR-18-R-
D/02
W-052-BMDF- Kitchen Market GB casting completed. Sand pile completed (1349
MGSP-3P-NOAK- Sand Pile). Soil test is completed. About 35 nos footing
44.28 30-Apr-2019 2-May-19 31-Mar-20 25% 26% 0.00%
18-KM/01 casting completed out of 35 nos. About 35 nos pedestal
column casting completed.
W-053-BMDF- Municipal Market
About 13 nos pile cap casting completed out of 46 nos.
MGSP-3P-NOAK-
19 Noakhali 3 97.11 29-Apr-2019 2-May-19 31-Mar-20 27% 28% 16.76 17% 17.26% Pile driving completed (231) with load test. UGWR
18-MM/02
excavation completed

3 of 4
Physical Progress (%) Financial Progress (%)
Sub-project Contract Date of Completion Financial
Sl. No. Work
Name of ULB Number Component Amount (BDT- Contract Date as per Achived Progress Achived Status
No. of SP Starting Date Till to Till to
with code Mil.) Agreement Contract upto 31-10- (Mill.Tk.) upto 31-
19 Noakhali 3 date Date
19 10-19
1 2 3 4 5 6 7 8 9 10 10 11 12 13
W-054-BMDF- Renovation of Bus Drain work 400m completed out of 410m. Aggregate
MGSP-3P-NOAK- Terminal Sand sub-base ongoing. RCC work of steel structure is
45.72 29-Apr-2019 2-May-19 31-Mar-20 30% 32% 8.07 18% 17.66%
18-BT/03 completed. Brick work of terminal building is
completed.
W-056-BMDF- Road-Drain-Street
MGSP-3P-DHAM- Light 1900m pipe laying completed out of 2175m , 965 nos.
20 Dhamrai 1 70.605 26-May-2019 15-Jun-19 31-Mar-2020 30% 32% 11.99 16.98%
18-R-D-S-L/02 pipe casting completed out of 995 nos.

95% GF slab completed, 1st floor 80 column


W-057-BMDF-
completed.Brick and plastering work all most
21 Nilphamari 1 MGSP-3P-NILPH- Municipal Market 108.57 31-Mar-2019 10-Apr-19 31-Mar-2020 16% 16% 0.00%
completed on horizontal extension portion. Work
18-MM/01
stopped due to embargo from Ministry of Land

W-059-BMDF-
MGSP-3P-
22 Betagi 1 Municipal Market 14.31 29-May-2019 27-Jun-19 31-Mar-2020 25% 26% 0.00% Up to grade bem completed. Septic Tank on going.
BETAGI-18-
MM/01

D1-685 RCC drain wall casting out of 715m,D4-412m


W-061-BMDF- RCC drain wall casting out of 412m,D5-500m RCC drain
23 Kaliakair 1 MGSP-3P-KALIA- Road-Drain 118.37 30-May-2019 9-Jun-19 31-Mar-2020 25% 30% 15.18 12.83% wall casting out of 715m D3-500m drain wall casting
18-R-D/02 out of 1800m; D_7: 250m completed out of 500m R-1
ISG 1800m, ASS 1200m of widening is completed.

Grand Total 44 5297.99 587.64 11.09% 11.09%


US Dollar in Million (100%) 67.06 7.44 Average physical progress
US Dollar in Million (90%) IDA 60.36 6.69

4 of 4