Sym1itbm 9030241013,9030241015 1011 Ex1
Sym1itbm 9030241013,9030241015 1011 Ex1
Sym1itbm 9030241013,9030241015 1011 Ex1
1/26/2011
The document provides a proposal for developing knowledge management system at Don Bosco
School, Hinjewadi Pune as suggested by Nipun Consultants, Pune.
1
Table of Contents
1 Preface ................................................................................................................................ 3
2 Scope of Work .................................................................................................................... 3
3 Client Dependencies & Commitment ................................................................................. 4
4 Project Effort & Duration ................................................................................................... 5
5 Price, Terms & Conditions ................................................................................................. 5
5.1 Price............................................................................................................................. 5
5.2 Pricing Model .............................................................................................................. 6
5.3 Set-Offs & Discounts .................................................................................................. 6
5.4 Taxes & Duties ............................................................................................................ 6
5.5 Validity of proposal ..................................................................................................... 6
6 Payment terms .................................................................................................................... 7
7 Commencement of Work.................................................................................................... 7
2
1 Preface
Don Bosco School (Here in after called DBS) is public school located in Hinjewadi,
Pune affiliated to Central Board of Secondary Education, New Delhi. It is school of great
repute with over 15 years in existence. The school provides education up to 10th Standard
with English as a medium of instruction.
1. A software tool that would aid the delivery of contents by the teachers by using
computers, projectors and audio systems in class rooms for 8th,9th & 10th standards.
2. A library of contents in self running mode accessed by students through kiosks
placed in library.
3. A tool for providing self based evaluation on each topic or subject accessed through
kiosks placed in library.
Based on the above stated requirements NC proposes following options for solution:
Option A: An On Premise model based on web server architecture with server in school
premises.
2 Scope of Work
Option A: (System Requirement study along with implementation)
3
Conducting a System Requirement Study for understanding the user requirements in
detail.
Developing architecture for proposed system.
Building a prototype model for the system.
4
Schedule Plan
The estimated time for each of the activities specified is given below:
Sr Activity Duration
No.
1 System Requirement Study 4 Weeks
2 Developing architecture for proposed system 2 Weeks
3 Building a prototype model 3 Weeks
4 Procuring Hardware (Desktops/ Kiosks/ Servers/ 2 Weeks
Routers)
5 Developing tools for accomplishing specified 6 Weeks
objectives:
Content delivery
Self delivery mode
Self based evaluation
6 Setting up infrastructure 2 Weeks
7 Deploying the system & achieving user acceptance 2 Weeks
8 Providing necessary training 2 Weeks
Total 23 Weeks
Option B
The estimated time for each of the activities is specified is given below:
Sr Activity Duration
No.
1 System Requirement Study 4 Weeks
2 Developing architecture for proposed system 2 Weeks
3 Building a prototype model 3 Weeks
Total 9 Weeks
Option A
5
Sr Activity Pricing
No.
1 System Requirement Study Rs. 2,00,000
2 Developing architecture for proposed system Rs. 1,25,000
3 Building a prototype model Rs. 1,25,000
4 Procurement of H/W (Based on Market Prices of the Rs 12,00,000 (Approx)
components required)
5 Developing tools for accomplishing specified Rs. 4,00,000
objectives:
Content delivery
Self delivery mode
Self based evaluation
Option B:
Sr Activity Pricing
No.
1 System Requirement Study Rs. 2,00,000
2 Developing architecture for proposed system Rs. 1,25,000
3 Building a prototype model Rs. 1,25,000
Total Rs. 4,50,000
6
against this proposal by DBS within Six months of submission of this proposal, then all
the conditions & pricing of the proposal stands void.
6 Payment terms
The payment schedule for both Option ‘A & B’ will be as per following norms:
1. 80% of stated amount before the start of each activity of the project.
2. 20% of amount within 15 days of accomplishment of the specific activity.
7 Commencement of Work
The work would be commenced by NC within 2 weeks of release of purchase order &
accomplishment of down payment, amounting to 80% amount of first activity for either
of options.