MCA Port Overview Final PDF
MCA Port Overview Final PDF
MCA Port Overview Final PDF
gh/mca/pt/280906
2
OVERVIEW OF THE FRAMEWORK
Technical parameters
Performance standards
pc/coi
3
PUBLIC PRIVATE PARTNERSHIP IN PORTS
Concession period
Concession period The guiding principle for determining project-specific
to be normally
concession period should normally be the capacity of the
thirty years
respective port terminal to handle the expected cargo at the
end of the proposed concession period. However, in the
case of port terminals, capacity constraints would normally
be addressed by construction of additional terminals at the
same or adjacent ports. As such, it would be advantageous to
allow a longer concession period both from the perspective
of the concessionaire as well as the Government. The Major
Port Trust Act, 1963 stipulates a maximum period of 30 years
and unless there are reasons for making an exception, the
concession period should normally be fixed at 30 years.
Selection of Concessionaire
Competitive bidding Selection of the Concessionaire will be based on open
on single parameter
will be the norm competitive bidding. All project parameters such as the
concession period, tariff, price indexation and technical
parameters are to be clearly stated upfront, and short-listed
bidders will be required to specify the proportion of revenues
from user charges that they are willing to share with the Port
Trust. The bidder who offers the highest revenue share should
win the contract. In exceptional cases where instead of offering
a revenue share, the bidders seek a capital grant/ subsidy
from the Government/ Trust, the bidder who seeks the lowest
gh/mca/pt/280906
4
OVERVIEW OF THE FRAMEWORK
Concession fee
The rationale for the above fee structure is that in the Concession fee should
be levied when revenue
initial years, debt service obligations would entail substantial streams can sustain it
outflows. Over the years, however, the Concessionaire will
have an increasing surplus in its hands owing to the declining
debt service and rising revenues. Recognising this cash flow
pattern, the concession fee to be offered by the Concessionaire
will be based on an ascending revenue-share structure.
Risk allocation
pc/coi
5
PUBLIC PRIVATE PARTNERSHIP IN PORTS
Financial close
Project implementation Unlike other agreements for private infrastructure projects
must commence as per
which neither define a time-frame for achieving financial
agreed timeframe
close, nor specify the penal consequences for failure to do
so, the MCA stipulates a time limit of 180 days for achieving
financial close (extendable for another 120 days on payment
of a penalty), failing which the bid security shall be forfeited.
By prevalent standards, this is a tight schedule, which is
achievable only if all the parameters are well defined and the
requisite preparatory work has been undertaken.
gh/mca/pt/280906
6
OVERVIEW OF THE FRAMEWORK
Port tariffs
Construction
pc/coi
7
PUBLIC PRIVATE PARTNERSHIP IN PORTS
Right of substitution
Lenders will have the In the port sector, the project assets do not constitute
right of substitution
adequate security for lenders. It is the project revenue streams
that constitute the mainstay of their security. Lenders would,
therefore, require assignment and substitution rights so that the
concession can be transferred to another company in the event of
failure of the Concessionaire to operate the project successfully.
The MCA accordingly provides for such substitution rights.
Force majeure
Concessionaire will The MCA contains the requisite provisions for dealing
be protected against
with force majeure events. In particular, it affords protection
political actions
to the Concessionaire against political actions that may have a
material adverse effect on the project.
Termination
gh/mca/pt/280906
8
OVERVIEW OF THE FRAMEWORK
pc/coi
9
PUBLIC PRIVATE PARTNERSHIP IN PORTS
Miscellaneous
Conclusion
Private participation Together with the Schedules, the proposed framework
should improve
addresses the issues that are likely to arise in financing of port
efficiencies and reduce
costs projects on BOT basis. The proposed regulatory and policy
framework contained in the MCA is critical for attracting
private investment with the concomitant efficiencies and lower
costs, necessary for accelerating growth.
gh/mca/pt/280906
10