RAB Nadita Fasya Fersi 2
RAB Nadita Fasya Fersi 2
RAB Nadita Fasya Fersi 2
KETERANGAN :
1 HARGA BELUM TERMASUK PROFIT, OVERHEAD Dan PPN
2 HARGA BBM MERUPAKAN HARGA INDUSTRI (Sumber PERTAMINA)
3 HARGA KAYU MENGIKUTI HARGA YANG DITETAPKAN OLEH DINAS KEHUTANAN KAB. MUNA
1 Galian Fondasi
<> Galian Type 1:
Panjang = 21.40 m
Lebar Atas = 1.10
Lebar Bawah = 0.82
Tinggi = 0.70
(La + Lb)/2 = 0.96 m
(La + Lb)/2) x t = 0.67
(La + Lb)/2) x t x p = 14.38 m3
Volume = 14.38 m3
Volume = 5.46 m3
Volume = 3.68 m3
2 Pasangan Batu 1 : 4
A Pasangan Bata Dinding Datar
<> Panjang = 21.40 m
Lebar Atas = 0.25
Lebar Bawah = 0.70
Tinggi = 0.70
(La + Lb)/2 = 0.48 m
(La + Lb)/2) x t = 0.33
(La + Lb)/2) x t x p = 7.12 m3
Volume = 7.12 m3
Luas Pengurang
Kusen Pintu = 1.72 x 2 Bh = 3.44
Kusen Jendela = 0.56 x 13 Bh = 7.28
Ventilasi Atas = 0.15 x 8 Bh = 1.2
Kolom Praktis = 4.52
Jumlah = 16.44
Volume = 38.04 m2
IV PEKERJAAN BETON
1 Pekerjaan Sloof Beton 15/15
A Bekisting
Panjang = 21.40 m1
Lebar = 0.30 m1
Vol = 6.42 m2
B Pembesian
<> Tul. Utama
Panjang = 21.40 m
Jumlah Besi = 4.00 Bh
Jumlah = 85.60 m
Berat Jenis Besi 10 = 0.62 Kg/m
Sub.Vol = 53.07 Kg
<> Tul. Sengkang
Panjang = 21.40 m
Jarak Behel = 0.15 m
Jumlah Behel = 143.67 Bh
Panj / Behel = 0.51 m
Panj. Tot. Besi Behel = 73.27 m
Berat Jenis Besi 6 = 0.22 Kg/m
Sub.Vol = 16.12 Kg
Volume = 69.19 Kg
C Beton
Panjang = 21.40
Lebar = 0.15
Tebal = 0.15
Volume = 0.48 m3
V PEKERJAAN PLESTERAN
1 Pek. Plester Pas.Bata 1 : 4
Volume = 76.08 m2
VI PEKERJAAN ATAP
1 Pekerjaan Atap Seng Gelombang Kecil
Panjang = 9.49
Lebar = 9.26
Volume = 87.88 m2
2 Pekerjaan Nook Atap Seng Gelombang Kecil
Volume = 7.59 m2
2 Gording
Panjang = 8.25 m
Jumlah = 8.00 Bh
Tot Panjang = 66.00 m1
Lebar = 0.06
Tebal = 0.12
Vol = 0.48 m3
3 Rangka Atap
Panjang = 8.25
Lebar = 7.36
Volume = 60.72 m2
4 Lesplank
Panjang Bawah = 8.25 m
Jumlah = 2.00 Bh
Panjang Samping = 3.60 m
Jumlah = 2.00 Bh
2 Plafond Tripleks
Bagian Dalam = 25.71 m2
Bagian Luar = 10.98 m2
Volume 36.69 m2
3 Les Plafond
X = 32.08 m1
Y = 32.50 m1
64.58 m1
Lebar = 0.04 m1
Volume = 2.58 m2
Jendela
Panjang = 3.70
Lebar = 0.15
Tebal = 0.05
Jumlah = 13.00
Sub Vol = 0.36 m3
Layang - Layang
Panjang = 3.79
Lebar = 0.15
Tebal = 0.05
Jumlah = 4.00
Sub Vol = 0.11 m3
Volume = 0.55 m3
J.1
Panjang = 5.70 m
Lebar = 0.15 m
Jumlah = 3.00 m
Sub.Volume = 0.00 m2
Jalusi Atas
Panjang = 9.54 m
Lebar = 0.15 m
Jumlah = 4.00 m
Sub.Volume = 5.72 m2
Volume = 5.72 m2
IV PEKERJAAN LANTAI
1 Lantai Bagian Dalam
Bagian Dalam = 31.85 m2
Sub. Vol 31.85 m2
2 Teras
Bagian Teras = 8.58 m2
Sub. Vol 8.58 m2
Volume = 40.43 m2
PEMERNTAH KABUPATEN MUNA
DINAS PEDIDIKAN DAN KEBUDAYAAN
JALAN AHMAD YANI NO. 2 KENDARI
WILAYAH BARAT
NO URAIAN SATUAN
(Rp)
1 2 3
BAHAN TOKO
I SEMEN
1 Semen / PC (50 Kg) Zak 76,950.00
2 Semen Warna Putih/PC (40 Kg) Kg 5,300.00
3 Kapur Pasang Kg 42,500.00
II BAHAN BESI DAN KAWAT
1 Besi Beton / Baja Tulangan Polos U 24 Kg 13,149.00
2 Kawat Beton (Kawat Bindrat) Kg 30,250.00
3 Baut/Mur Kg 28,450.00
4 Paku Campuran (5, 7, 10 cm ) Kg 19,700.00
7 Paku Seng Kg 48,400.00
8 Paku Tripleks Kg 35,100.00
9 Besi Strip m1 80,188.00
10 Paku Kayu Bh 1,000.00
III BAHAN ALMINIUM
1 Besi Holow 20 x 40 mm, Panjang 6 m Btg 18,400.00
2 Besi Holow 40 x 40, Panjang 6 m m1 24,917.00
3 Baut (screw driver) bh 937.00
5 Profil C 75.100 Btg 117,000.00
6 Reng U 0.45 m1 67,000.00
7 Baut Truss BH 450.00
8 Baut Reng BH 400.00
IV BAHAN KERAMIK
1 Keramik Putih 40 x 40 cm BH 11,584.00
2 Keramik Putih 40 x 40 cm Doz 72,400.00
V BAHAN KACA
1 Kaca Bening 3 mm M2 156,400.00
VI BAHAN LANGIT-LANGIT
1 Polywood 9mm Lembar 158,000.00
2 Tripleks 3mm Lembar 62,450.00
VII LIST PROFIL PLAFOND
1 3 x 3 cm panjang 4 m Batang 17,100.00
VIII BAHAN ATAP
1 Genteng Multi Roof Color (77x100 cm) Lembar 42,750.00
2 Nok Genteng Sakura Roof Clasic Std (P=91 cm) BH 37,250.00
IX BAHAN CAT DAN MINYAK
1 Cat Tembok Aries Kg 10,600.00
2 Cat Tembok Metrolite Kg 43,675.00
3 Cat Avian Kg 42,100.00
4 Cat Meni Kayu Besi Kg 22,675.00
5 Plamur Tembok Kg 19,000.00
6 Kwas Rol Buah 36,750.00
7 Minyak Cat Kg 28,450.00
8 Minyak Bekisting Ltr 3,000.00
10 Amplas Halus Lbr 4,200.00
11 Lem Kayu Fox Kg 21100
482
1 2 3
X KUNCI - KUNCI
1 Kunci Tanam 2 Kali Putar T Buah 141,750.00
2 Grendel Jendela Biasa Buah 7,875.00
3 Engsel Pintu H Kuningan Psg 26,250.00
4 Engsel Jendela H Kupu-kupu Kuningan Psg 10,500.00
5 Hak Angin Biasa Buah 6,563.00
XII BAHAN SANITASI
1 Wastafel Dinding Set 459,333.00
2 Pompa Air 450 Watt, Head 9 m Buah 916,667.00
XIII BAHAN PIPA
1 Pipa PVC ø 1/2" AW 4 m Batang 30,993.00
2 Pipa PVC ø3/4" AW 4 m Batang 36,017.00
3 Pipa PVC ø 1" AW 4 m Batang 42,250.00
4 Stop Kran 1/2" Buah 16,500.00
5 Sealent Kg 20,000.00
BAHAN LOKAL
I TANAH TIMBUNAN
3 Tanah Timbunan Biasa M3 77,256.84
II PASIR
1 Pasir Urug M3 139,500.00
2 Pasir pasang M3 139,500.00
3 Pasir Beton M3 217,200.00
III BATU
1 Batu Merah Biji 892.00
2 Kerikil Kali Maligano M3 290,285.26
3 Kerikil Pecah (Maligano Pecah manual) M3 525,000.00
4 Batu Belah 15/25-25/35 cm M3 155,400.00
7 Batu Gunung 2 - 3 cm (Pecah manual) M3 325,000.00
V BAHAN KAYU
1 Papan Kayu Klas II A (Sejenis) M3 2,360,000.00
2 Papan Perancah M3 1,625,000.00
3 Balok Kayu Jati M3 4,250,000.00
4 Balok Kayu Bayam M3 4,250,000.00
5 Balok Kayu Kalapi M3 4,250,000.00
6 Balok Kayu Klas II A (Sejenis) M3 2,360,000.00
7 Balok Kayu Klas II (Sejenis) M3 1,835,000.00
8 Balok Perancah M3 1,625,000.00
9 Dolken Ø 5 Cm Batang 5,750.00
VI ALAT BANTU
1 Alat Bantu Set 2,500.00
UPAH KERJA
1 Mandor Org/Hari 125,000.00
2 Kepala Tukang Org/Hari 150,000.00
3 Tukang
- Tukang Listrik Org/Hari 125,000.00
- Tukang Batu Org/Hari 125,000.00
- Tukang Kayu Org/Hari 125,000.00
- Tukang Besi Org/Hari 125,000.00
- Tukang Cat Org/Hari 125,000.00
4 Pekerja
- Pekerja Terlatih Org/Hari 100,000.00
- Pekerja Agak terlatih Org/Hari 100,000.00
- Pekerja Tak terlatih Org/Hari 100,000.00
Keterangan :
1. Harga BBM Merupakan Harga Industri (Sumber Pertamina)
2. Harga Kayu Diperoleh Dari Penjual Kayu
3. Harga Satuan Belum Termasuk Keuntungan, Over Head dan PPn
483
Jenis Pekerjaan : Pembomgkaran 1m3 Dinding Tembok Bata
Satuan / Unit : m3
Analisa : SNI Rev 2015
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 2.0000 100,000.00 200,000.00
Tukang L.02 OH -
Kepala Tukang L.03 OH -
Mandor L.04 OH 0.0900 125,000.00 11,250.00
Jumlah Tenaga Kerja 211,250.00
B BAHAN :
-
-
-
Jumlah Harga Bahan -
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 211,250.00
E OVERHEAD ₰ PROVIT 10% x D 21,125.00
F HARGA SATUAN PEKERJAAN (D + E) 232,375.00
Jenis Pekerjaan : Pembomgkaran 1m3 Beton Bertulang
Satuan / Unit : m1
Analisa : AHSP PU A.2.2.1.13
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 13.3340 100,000.00 1,333,400.00
Tukang L.02 OH -
Kepala Tukang L.03 OH -
Mandor L.04 OH 0.6660 125,000.00 83,250.00
Jumlah Tenaga Kerja 1,416,650.00
B BAHAN :
-
-
-
Jumlah Harga Bahan -
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 1,416,650.00
E OVERHEAD ₰ PROVIT 10% x D 141,665.00
F HARGA SATUAN PEKERJAAN (D + E) 1,558,315.00
Jenis Pekerjaan : Menurunkan Atap Seng
Satuan / Unit : 10 m2
Analisa : SNI L.8
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.8.1 OH 0.5000 100,000.00 50,000.00
Tukang OH -
Kepala Tukang OH -
Mandor L.8.1 OH 0.0500 125,000.00 6,250.00
Jumlah Tenaga Kerja 56,250.00
B BAHAN :
-
-
-
Jumlah Harga Bahan -
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 56,250.00
E OVERHEAD ₰ PROVIT 10% x D 5,625.00
F HARGA SATUAN PEKERJAAN (D + E) 6,187.50
Jenis Pekerjaan : Membongkar Rangka Atap Lama
Satuan / Unit : 1m2
Analisa : SNI Rev. 2005
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.8.1 OH 0.1000 100,000.00 10,000.00
Tukang OH 0.0250 125,000.00 3,125.00
Kepala Tukang OH 0.0025 150,000.00 375.00
Mandor L.8.1 OH 0.0050 125,000.00 625.00
Jumlah Tenaga Kerja 14,125.00
B BAHAN :
-
-
-
Jumlah Harga Bahan -
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 14,125.00
E OVERHEAD ₰ PROVIT 10% x D 1,412.50
F HARGA SATUAN PEKERJAAN (D + E) 15,537.50
Jenis Pekerjaan : Bonkaran Plafond (Bongaran Tidak Dipaakai Laagi)
Satuan / Unit : m2
Analisa : SNI Rev. 2005
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.8.1 OH 0.1250 100,000.00 12,500.00
Tukang OH -
Kepala Tukang OH -
Mandor L.8.1 OH 0.0050 125,000.00 625.00
Jumlah Tenaga Kerja 13,125.00
B BAHAN :
-
-
-
Jumlah Harga Bahan -
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 13,125.00
E OVERHEAD ₰ PROVIT 10% x D 1,312.50
F HARGA SATUAN PEKERJAAN (D + E) 14,437.50
Jenis Pekerjaan : Membongkar Lantai Lama
Satuan / Unit : 1m2
Analisa : SNI Rev. 2005
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.5.1 OH 0.0500 100,000.00 5,000.00
Tukang -
Kepala Tukang -
Mandor L.5.1 OH 0.0100 125,000.00 1,250.00
Jumlah Tenaga Kerja 6,250.00
B BAHAN :
-
-
-
Jumlah Harga Bahan -
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 6,250.00
E OVERHEAD ₰ PROVIT 10% x D 625.00
F HARGA SATUAN PEKERJAAN (D + E) 6,875.00
Jenis Pekerjaan : Pengukuran Dan Pemasangan Bowplank
Satuan / Unit : m1
Analisa : AHSP PU A.2.2.1.4
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.1000 100,000.00 10,000.00
Tukang L.02 OH 0.1000 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.0100 150,000.00 1,500.00
Mandor L.04 OH 0.0050 125,000.00 625.00
Jumlah Tenaga Kerja 24,625.00
B BAHAN :
Kayu Balok 5/7 Cm m3 0.1200 -
Paku 2'' - 3'' Kg 0.0200 -
Kayu Papan 3/20 Cm m3 0.0070 -
Jumlah Harga Bahan -
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 24,625.00
E OVERHEAD ₰ PROVIT 10% x D 2,462.50
F HARGA SATUAN PEKERJAAN (D + E) 27,087.50
Jenis Pekerjaan : Galian Tanah Biasa Sedalam 1 m
Satuan / Unit : m3
Analisa : AHSP PU A.2.3.1.1
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.7500 125,000.00 93,750.00
Mandor L.04 OH 0.0250 125,000.00 3,125.00
Jumlah Tenaga Kerja 96,875.00
B BAHAN :
-
-
Jumlah Harga Bahan -
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 96,875.00
E OVERHEAD ₰ PROVIT 10% x D 9,687.50
F HARGA SATUAN PEKERJAAN (D + E) 106,562.50
Jenis Pekerjaan : Mengurug Kembali Galian
Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.9
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.2500 100,000.00 25,000.00
Mandor L.04 OH 0.0833 125,000.00 10,412.50
Jumlah Tenaga Kerja 35,412.50
B BAHAN :
-
-
Jumlah Harga Bahan -
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 35,412.50
E OVERHEAD ₰ PROVIT 10% x D 3,541.25
F HARGA SATUAN PEKERJAAN (D + E) 38,953.75
Jenis Pekerjaan : Pengurugan Kembali Galian Tanah
Satuan / Unit : m3
Analisa : AHSP PU A.2.3.1.9
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.3000 100,000.00 30,000.00
Mandor L.04 OH 0.0100 125,000.00 1,250.00
Jumlah Tenaga Kerja 31,250.00
B BAHAN :
Tanah Timbunan Biasa m3 1.2000 77,256.84 92,708.21
-
Jumlah Harga Bahan 92,708.21
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 123,958.21
E OVERHEAD ₰ PROVIT 10% x D 12,395.82
F HARGA SATUAN PEKERJAAN (D + E) 136,354.03
Jenis Pekerjaan : Urugan Pasir
Satuan / Unit : m3
Analisa : AHSP PU A.2.3.1.11
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.3000 100,000.00 30,000.00
Mandor L.04 OH 0.0100 125,000.00 1,250.00
Jumlah Tenaga Kerja 31,250.00
B BAHAN :
Pasir Urugan m3 1.2000 139,500.00 167,400.00
-
Jumlah Harga Bahan 167,400.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 198,650.00
E OVERHEAD ₰ PROVIT 10% x D 19,865.00
F HARGA SATUAN PEKERJAAN (D + E) 218,515.00
Jenis Pekerjaan : Pemasangan Batu Kosong (Anstamping)
Satuan / Unit : m3
Analisa : AHSP PU A.3.2.1.9
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.7800 100,000.00 78,000.00
Tukang L.02 OH 0.3900 125,000.00 48,750.00
Kepala Tukang L.03 OH 0.0390 150,000.00 5,850.00
Mandor L.04 OH 0.0390 125,000.00 4,875.00
Jumlah Tenaga Kerja 137,475.00
B BAHAN :
Batu Belah m3 1.2000 155,400.00 186,480.00
Pasir Urug m3 0.4320 139,500.00 60,264.00
Jumlah Harga Bahan 246,744.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 384,219.00
E OVERHEAD ₰ PROVIT 10% x D 38,421.90
F HARGA SATUAN PEKERJAAN (D + E) 422,640.90
Jenis Pekerjaan : Pemasangan Fondasi Batu Belah Camp 1Pc : 4Ps
Satuan / Unit : m3
Analisa : AHSP PU A.3.2.1.2
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 1.5000 100,000.00 150,000.00
Tukang L.02 OH 0.7500 125,000.00 93,750.00
Kepala Tukang L.03 OH 0.0750 150,000.00 11,250.00
Mandor L.04 OH 0.0750 125,000.00 9,375.00
Jumlah Tenaga Kerja 264,375.00
B BAHAN :
Batu Belah m3 1.2000 155,400.00 186,480.00
Semen Portland Kg 163.0000 1,539.00 250,857.00
Pasir Pasang m3 0.5200 139,500.00 72,540.00
Jumlah Harga Bahan 509,877.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 774,252.00
E OVERHEAD ₰ PROVIT 10% x D 77,425.20
F HARGA SATUAN PEKERJAAN (D + E) 851,677.20
Jenis Pekerjaan : Pas. Bata Merah 5x11x22 Cm , 1/2 Batu Camp 1 : 2
Satuan / Unit : m2
Analisa : AHSP PU A.3.2.1.7
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.3000 100,000.00 30,000.00
Tukang L.02 OH 0.1000 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.0100 150,000.00 1,500.00
Mandor L.04 OH 0.0150 125,000.00 1,875.00
Jumlah Tenaga Kerja 45,875.00
B BAHAN :
Bata Merah Buah 70.0000 892.00 62,440.00
Semen Portland Kg 18.9500 1,539.00 29,164.05
Pasir Pasang m3 0.0380 139,500.00 5,301.00
Jumlah Harga Bahan 96,905.05
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 142,780.05
E OVERHEAD ₰ PROVIT 10% x D 14,278.01
F HARGA SATUAN PEKERJAAN (D + E) 157,058.06
Jenis Pekerjaan : Pemasangan Bata 1Pc : 4Ps
Satuan / Unit : m³
Analisa : AHSP PU A.3.2.1.9
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.3000 100,000.00 30,000.00
Tukang L.02 OH 0.1000 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.0100 150,000.00 1,500.00
Mandor L.04 OH 0.0150 125,000.00 1,875.00
Jumlah Tenaga Kerja 45,875.00
B BAHAN :
Bata Merah Buah 70.0000 892.00 62,440.00
Sement Portland Kg 11.5000 1,539.00 17,698.50
Pasir Pasang m3 0.0430 139,500.00 5,998.50
Jumlah Harga Bahan 86,137.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 132,012.00
E OVERHEAD ₰ PROVIT 10% x D 13,201.20
F HARGA SATUAN PEKERJAAN (D + E) 145,213.20
Jenis Pekerjaan : Membat Beton Mutu f ʹc = 14,5 Mpa K.175 Slump 120 ± 20
mm
Satuan / Unit : m3
Analisa : AHSP PU A.4.1.1.5
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 1.6500 100,000.00 165,000.00
Tukang L.02 OH 0.2750 125,000.00 34,375.00
Kepala Tukang L.03 OH 0.0280 150,000.00 4,200.00
Mandor L.04 OH 0.0830 125,000.00 10,375.00
Jumlah Tenaga Kerja 213,950.00
B BAHAN :
Semen Portland Kg 326.0000 1,539.00 501,714.00
Pasir Beton Kg 760.0000 155.14 117,908.57
Kerikil (Max 30 mm) Kg 1,029.0000 388.89 400,166.67
Air Ltr 215.0000 70.00 15,050.00
Jumlah Harga Bahan 1,034,839.24
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 1,248,789.24
E OVERHEAD ₰ PROVIT 10% x D 124,878.92
F HARGA SATUAN PEKERJAAN (D + E) 1,373,668.16
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 1.2000 100,000.00 120,000.00
Tukang L.02 OH 0.2000 125,000.00 25,000.00
Kepala Tukang L.03 OH 0.0200 150,000.00 3,000.00
Mandor L.04 OH 0.0600 125,000.00 7,500.00
Jumlah Tenaga Kerja 155,500.00
B BAHAN :
Semen Portland Kg 230.0000 1,539.00 353,970.00
Pasir Beton Kg 893.0000 155.14 138,542.57
Kerikil (Max 30 mm) Kg 1,027.0000 240.74 247,240.74
Air Ltr 200 70.00 14,000.00
Jumlah Harga Bahan 753,753.31
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 909,253.31
E OVERHEAD ₰ PROVIT 10% x D 90,925.33
F HARGA SATUAN PEKERJAAN (D + E) 1,000,178.64
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.5200 100,000.00 52,000.00
Tukang Kayu L.02 OH 0.2600 125,000.00 32,500.00
Kepala Tukang L.03 OH 0.0260 150,000.00 3,900.00
Mandor L.04 OH 0.0260 125,000.00 3,250.00
Jumlah Tenaga Kerja 91,650.00
B BAHAN :
Kayu Kelas III m3 0.0400 1,625,000.00 65,000.00
Paku 5 - 10 Cm Kg 0.3000 19,700.00 5,910.00
Minyak Bekisting Ltr 0.1000 3,000.00 300.00
Jumlah Harga Bahan 71,210.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 162,860.00
E OVERHEAD ₰ PROVIT 10% x D 16,286.00
F HARGA SATUAN PEKERJAAN (D + E) 179,146.00
Jenis Pekerjaan : Pembesian 10 Kg Dengan Besi Polos
Satuan / Unit : Kg
Analisa : AHSP PU A.4.1.1.17
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.0700 100,000.00 7,000.00
Tukang Besi L.02 OH 0.0700 125,000.00 8,750.00
Kepala Tukang L.03 OH 0.0070 150,000.00 1,050.00
Mandor L.04 OH 0.0400 125,000.00 5,000.00
21,800.00
B BAHAN :
Besi Beton Polos/ Ulir Kg 10.500 13,149.00 138,064.50
Kawat Beton Kg 0.150 30,250.00 4,537.50
Jumlah Harga Bahan 142,602.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 164,402.00
E OVERHEAD ₰ PROVIT 10% x D 16,440.20
F HARGA SATUAN PEKERJAAN PER 1 Kg (D + E) / 10 18,084.22
Jenis Pekerjaan : Membat Beton Mutu f ʹc = 16,9 Mpa K.200 Slump (12 ** 2)
Cm,W/C = 0,61
Satuan / Unit : m3
Analisa : AHSP PU A.4.1.1.6
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 1.6500 100,000.00 165,000.00
Tukang L.02 OH 0.2750 125,000.00 34,375.00
Kepala Tukang L.03 OH 0.0280 150,000.00 4,200.00
Mandor L.04 OH 0.0830 125,000.00 10,375.00
Jumlah Tenaga Kerja 213,950.00
B BAHAN :
Semen Portland Kg 352.0000 1,539.00 541,728.00
Pasir Beton Kg 731.0000 155.14 113,409.43
Kerikil (Max 30 mm) Kg 1,031.0000 240.74 248,203.70
Air Ltr 215.0000 70.00 15,050.00
Jumlah Harga Bahan 918,391.13
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 1,132,341.13
E OVERHEAD ₰ PROVIT 10% x D 113,234.11
F HARGA SATUAN PEKERJAAN (D + E) 1,245,575.25
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 1.6500 100,000.00 165,000.00
Tukang L.02 OH 0.2750 125,000.00 34,375.00
Kepala Tukang L.03 OH 0.0280 150,000.00 4,200.00
Mandor L.04 OH 0.0830 125,000.00 10,375.00
Jumlah Tenaga Kerja 213,950.00
B BAHAN :
Semen Portland Kg 371.0000 1,539.00 570,969.00
Pasir Beton Kg 698.0000 155.14 108,289.71
Kerikil (Max 30 mm) Kg 1,047.0000 240.74 252,055.56
Air Ltr 215.0000 70.00 15,050.00
Jumlah Harga Bahan 946,364.27
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 1,160,314.27
E OVERHEAD ₰ PROVIT 10% x D 116,031.43
F HARGA SATUAN PEKERJAAN (D + E) 1,276,345.70
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 1.6500 100,000.00 165,000.00
Tukang L.02 OH 0.2750 125,000.00 34,375.00
Kepala Tukang L.03 OH 0.0280 150,000.00 4,200.00
Mandor L.04 OH 0.0830 125,000.00 10,375.00
Jumlah Tenaga Kerja 213,950.00
B BAHAN :
Semen Portland Kg 384.0000 1,539.00 590,976.00
Pasir Beton Kg 692.0000 155.14 107,358.86
Kerikil (Max 30 mm) Kg 1,039.0000 388.89 404,055.56
Air Ltr 215.0000 70.00 15,050.00
Jumlah Harga Bahan 1,117,440.41
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 1,331,390.41
E OVERHEAD ₰ PROVIT 10% x D 133,139.04
F HARGA SATUAN PEKERJAAN (D + E) 1,464,529.45
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 1.6500 100,000.00 165,000.00
Tukang L.02 OH 0.2750 125,000.00 34,375.00
Kepala Tukang L.03 OH 0.0280 150,000.00 4,200.00
Mandor L.04 OH 0.0830 125,000.00 10,375.00
Jumlah Tenaga Kerja 213,950.00
B BAHAN :
Semen Portland Kg 406.0000 1,539.00 624,834.00
Pasir Beton Kg 684.0000 155.14 106,117.71
Kerikil (Max 30 mm) Kg 1,026.0000 240.74 247,000.00
Air Ltr 215.0000 70.00 15,050.00
Jumlah Harga Bahan 993,001.71
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 1,206,951.71
E OVERHEAD ₰ PROVIT 10% x D 120,695.17
F HARGA SATUAN PEKERJAAN (D + E) 1,327,646.89
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 1.6500 100,000.00 165,000.00
Tukang L.02 OH 0.2750 125,000.00 34,375.00
Kepala Tukang L.03 OH 0.0280 150,000.00 4,200.00
Mandor L.04 OH 0.0830 125,000.00 10,375.00
Jumlah Tenaga Kerja 213,950.00
B BAHAN :
Semen Portland Kg 413.00 1,539.00 635,607.00
Pasir Beton Kg 681.00 155.14 105,652.29
Kerikil (Max 30 mm) Kg 1,021.00 240.74 245,796.30
Air Ltr 215.00 70.00 15,050.00
Jumlah Harga Bahan 1,002,105.58
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 1,216,055.58
E OVERHEAD ₰ PROVIT 10% x D 121,605.56
F HARGA SATUAN PEKERJAAN (D + E) 1,337,661.14
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.5400 100,000.00 54,000.00
Tukang Kayu L.02 OH 0.2700 125,000.00 33,750.00
Kepala Tukang L.03 OH 0.0270 150,000.00 4,050.00
Mandor L.04 OH 0.0540 125,000.00 6,750.00
Jumlah Tenaga Kerja 98,550.00
B BAHAN :
Kayu Kelas III m3 0.013 1,625,000.00 21,666.67
Paku 5 - 10 Cm Kg 0.400 19,700.00 7,880.00
Minyak Bekisting Ltr 0.200 3,000.00 600.00
Jumlah Harga Bahan 30,146.67
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 128,696.67
E OVERHEAD ₰ PROVIT 10% x D 12,869.67
F HARGA SATUAN PEKERJAAN (D + E) 141,566.33
Jenis Pekerjaan : Memasang Bekisting Untuk Kolom
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.22
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.6600 100,000.00 66,000.00
Tukang Kayu L.02 OH 0.3300 125,000.00 41,250.00
Kepala Tukang L.03 OH 0.0330 150,000.00 4,950.00
Mandor L.04 OH 0.0660 125,000.00 8,250.00
Jumlah Tenaga Kerja 120,450.00
B BAHAN :
Kayu Kelas III m3 0.0133 1,625,000.00 21,666.67
Paku 5 - 10 Cm Kg 0.4000 19,700.00 7,880.00
Minyak Bekisting Ltr 0.2000 3,000.00 600.00
Balok Kayu Kelas II m3 0.0102 1,835,000.00 -
Plywood Tebal 9 mm Lbr 0.3500 158,000.00 -
Dolken @ 4 -10 Pnj 4 m Btg 0.6667 5,750.00 3,833.33
Jumlah Harga Bahan 33,980.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 154,430.00
E OVERHEAD ₰ PROVIT 10% x D 15,443.00
F HARGA SATUAN PEKERJAAN (D + E) 169,873.00
Jenis Pekerjaan : Pemasangan Bekisting Untuk Balok
Satuan / Unit : m2
Analisa : AHSP PU A.4.1.23
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.6600 100,000.00 66,000.00
Tukang Kayu L.02 OH 0.3300 125,000.00 41,250.00
Kepala Tukang L.03 OH 0.0330 150,000.00 4,950.00
Mandor L.04 OH 0.0660 125,000.00 8,250.00
Jumlah Tenaga Kerja 120,450.00
B BAHAN :
Kayu Kelas III m3 0.0133 1,625,000.00 21,666.67
Paku 5 - 10 Cm Kg 0.4000 19,700.00 7,880.00
Minyak Bekisting Ltr 0.2000 3,000.00 600.00
Balok Kayu Kelas II m3 0.0102 2,360,000.00 24,072.00
Plywood Tebal 9 mm Lbr 0.3500 158,000.00 55,300.00
Dolken @ 4 -10 Pnj 4 m Btg 0.6667 5,750.00 3,833.33
Jumlah Harga Bahan 113,352.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 233,802.00
E OVERHEAD ₰ PROVIT 10% x D 23,380.20
F HARGA SATUAN PEKERJAAN (D + E) 257,182.20
Jenis Pekerjaan : Pemasangan Bekisting Untuk Lantai
Satuan / Unit : m2
Analisa : AHSP PU A.4.1.24
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.6600 100,000.00 66,000.00
Tukang Kayu L.02 OH 0.3300 125,000.00 41,250.00
Kepala Tukang L.03 OH 0.0330 150,000.00 4,950.00
Mandor L.04 OH 0.0330 125,000.00 4,125.00
Jumlah Tenaga Kerja 116,325.00
B BAHAN :
Kayu Kelas III m3 0.0400 1,625,000.00 65,000.00
Paku 5 - 10 Cm Kg 0.4000 19,700.00 7,880.00
Minyak Bekisting Ltr 0.2000 3,000.00 600.00
Balok Kayu Kelas II m3 0.0150 2,360,000.00 35,400.00
Plywood Tebal 9 mm Lbr 0.3500 62,450.00 21,857.50
Dolken @ 4 -10 Pnj 4 m Btg 6.0000 5,750.00 34,500.00
Jumlah Harga Bahan 165,237.50
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 281,562.50
E OVERHEAD ₰ PROVIT 10% x D 28,156.25
F HARGA SATUAN PEKERJAAN (D + E) 309,718.75
Jenis Pekerjaan : Pemasangan Bekisting Untuk Tangga
Satuan / Unit : m2
Analisa : AHSP PU A.4.1.1.26
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.6600 100,000.00 66,000.00
Tukang Kayu L.02 OH 0.3300 125,000.00 41,250.00
Kepala Tukang L.03 OH 0.0330 150,000.00 4,950.00
Mandor L.04 OH 0.0330 125,000.00 4,125.00
Jumlah Tenaga Kerja 116,325.00
B BAHAN :
Kayu Kelas III m3 0.0300 1,625,000.00 48,750.00
Paku 5 - 10 Cm Kg 0.4000 19,700.00 7,880.00
Minyak Bekisting Ltr 0.1500 3,000.00 450.00
Balok Kayu Kelas II m3 0.0150 2,360,000.00 35,400.00
Plywood Tebal 9 mm Lbr 0.3500 158,000.00 55,300.00
Dolken @ 4 -10 Pnj 4 m Btg 2.0000 5,750.00 11,500.00
Jumlah Harga Bahan 159,280.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 275,605.00
E OVERHEAD ₰ PROVIT 10% x D 27,560.50
F HARGA SATUAN PEKERJAAN (D + E) 303,165.50
Jenis Pekerjaan : Membuat Kolom Praktis Ukr. 11 x 11 Cm
Satuan / Unit : m1
Analisa : AHSP PU A.4.1.1.35
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.1800 100,000.00 18,000.00
Tukang Batu L.02 OH 0.0200 125,000.00 2,500.00
Tukang Kayu L.02 OH 0.0200 125,000.00 2,500.00
Tukang Besi L.02 OH 0.0200 125,000.00 2,500.00
Kepala Tukang L.03 OH 0.0600 150,000.00 9,000.00
Mandor L.04 OH 0.0900 125,000.00 11,250.00
Jumlah Tenaga Kerja 45,750.00
B BAHAN :
Kayu Kelas III m3 0.0020 1,625,000.00 3,250.00
Paku 5 - 10 Cm Kg 0.0100 19,700.00 197.00
Minyak Bekisting Ltr 1.0000 3,000.00 3,000.00
Besi Beton Polos Kg 3.0000 13,149.00 39,447.00
Kawat Beton Kg 0.4500 30,250.00 13,612.50
Semen Portland Kg 4.0000 1,539.00 6,156.00
Pasir Beton m3 0.0060 217,200.00 1,303.20
Kerikil m3 0.0090 525,000.00 4,725.00
Jumlah Harga Bahan 71,690.70
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 117,440.70
E OVERHEAD ₰ PROVIT 10% x D 11,744.07
F HARGA SATUAN PEKERJAAN (D + E) 129,184.77
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.1800 100,000.00 18,000.00
Tukang Batu L.02 OH 0.0200 125,000.00 2,500.00
Tukang Kayu L.02 OH 0.0200 125,000.00 2,500.00
Tukang Besi L.02 OH 0.0200 125,000.00 2,500.00
Kepala Tukang L.03 OH 0.0600 150,000.00 9,000.00
Mandor L.04 OH 0.0900 125,000.00 11,250.00
Jumlah Tenaga Kerja 45,750.00
B BAHAN :
Kayu Kelas III m3 0.0020 1,625,000.00 3,250.00
Paku 5 - 10 Cm Kg 0.0100 19,700.00 197.00
Minyak Bekisting Ltr 1.0000 3,000.00 3,000.00
Besi Beton Polos Kg 3.0000 13,149.00 39,447.00
Kawat Beton Kg 0.4500 30,250.00 13,612.50
Semen Portland Kg 4.0000 1,539.00 6,156.00
Pasir Beton m3 0.0060 217,200.00 1,303.20
Kerikil m3 0.0090 525,000.00 4,725.00
Jumlah Harga Bahan 71,690.70
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 117,440.70
E OVERHEAD ₰ PROVIT 10% x D 11,744.07
F HARGA SATUAN PEKERJAAN (D + E) 129,184.77
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.3000 100,000.00 30,000.00
Tukang L.02 OH 0.1500 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.0150 150,000.00 2,250.00
Mandor L.04 OH 0.0150 125,000.00 1,875.00
Jumlah Tenaga Kerja 52,875.00
B BAHAN :
Sement Portland Kg 10.2240 1,539.00 15,734.74
Pasir Pasangan m3 0.0200 139,500.00 2,790.00
Jumlah Harga Bahan 18,524.74
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 71,399.74
E OVERHEAD ₰ PROVIT 10% x D 7,139.97
F HARGA SATUAN PEKERJAAN (D + E) 78,539.71
Jenis Pekerjaan : Plesteran 1 Sp : 3 Pp, Tebal 15 mm
Satuan / Unit : m2
Analisa : AHSP PU A.4.4.2.3
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.3000 100,000.00 30,000.00
Tukang L.02 OH 0.1500 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.0150 150,000.00 2,250.00
Mandor L.04 OH 0.0150 125,000.00 1,875.00
Jumlah Tenaga Kerja 52,875.00
B BAHAN :
Sement Portland Kg 7.7760 1,539.00 11,967.26
Pasir Pasangan m3 0.0230 139,500.00 3,208.50
Jumlah Harga Bahan 15,175.76
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 68,050.76
E OVERHEAD ₰ PROVIT 10% x D 6,805.08
F HARGA SATUAN PEKERJAAN (D + E) 74,855.84
Jenis Pekerjaan : Plesteran 1 Sp : 4 Pp, Tebal 15 mm
Satuan / Unit : m2
Analisa : AHSP PU A.4.4.2.4
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.3000 100,000.00 30,000.00
Tukang L.02 OH 0.1500 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.0150 150,000.00 2,250.00
Mandor L.04 OH 0.0150 125,000.00 1,875.00
Jumlah Tenaga Kerja 52,875.00
B BAHAN :
Sement Portland Kg 6.2400 1,539.00 9,603.36
Pasir Pasangan m3 0.0240 139,500.00 3,348.00
Jumlah Harga Bahan 12,951.36
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 65,826.36
E OVERHEAD ₰ PROVIT 10% x D 6,582.64
F HARGA SATUAN PEKERJAAN (D + E) 72,409.00
Jenis Pekerjaan : Acian Air Cement
Satuan / Unit : m2
Analisa : AHSP PU A.4.4.2.27
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.2000 100,000.00 20,000.00
Tukang L.02 OH 0.1000 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.0100 150,000.00 1,500.00
Mandor L.04 OH 0.0100 125,000.00 1,250.00
Jumlah Tenaga Kerja 35,250.00
B BAHAN :
Sement Portland Kg 3.2500 1,539.00 5,001.75
Jumlah Harga Bahan 5,001.75
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 40,251.75
E OVERHEAD ₰ PROVIT 10% x D 4,025.18
F HARGA SATUAN PEKERJAAN (D + E) 44,276.93
Jenis Pekerjaan : Pasang Lantai Ubin Warna Ukr 40 x 40 Cm
Satuan / Unit : m2
Analisa : AHSP PU A.4.4.3.4
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.2500 100,000.00 25,000.00
Tukang L.02 OH 0.1250 125,000.00 15,625.00
Kepala Tukang L.03 OH 0.0130 150,000.00 1,950.00
Mandor L.04 OH 0.0130 125,000.00 1,625.00
Jumlah Tenaga Kerja 44,200.00
B BAHAN :
Ubin Warna Bh 6.6300 11,584.00 76,801.92
Sement Portland Kg 9.8000 1,539.00 15,082.20
Sement Warna Kg 0.6000 5,300.00 3,180.00
Pasir Pasang m3 0.0450 139,500.00 6,277.50
Jumlah Harga Bahan 101,341.62
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 145,541.62
E OVERHEAD ₰ PROVIT 10% x D 14,554.16
F HARGA SATUAN PEKERJAAN (D + E) 160,095.78
Jenis Pekerjaan : Pengecatan Bidang Kayu Baru (1 Lapis Plamuur, 1 Lapis Cat
Dasar 2 Kali Cat Penutup
Satuan / Unit : m2
Analisa : AHSP PU A.4.7.1.4
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.0700 100,000.00 7,000.00
Tukang Cat L.02 OH 0.0090 125,000.00 1,125.00
Kepala Tukang L.03 OH 0.0060 150,000.00 900.00
Mandor L.04 OH 0.0030 125,000.00 375.00
Jumlah Tenaga Kerja 9,400.00
B BAHAN :
Cat Menie Kayu/ Besi Kg 0.2000 22,675.00 4,535.00
Plamuur Tembok Boyo Kg 0.1500 19,000.00 2,850.00
Cat Dasar Meni Kayu/ Besi Kg 0.1700 10,600.00 1,802.00
Cat Penutup Kayu Avian Kg 0.2600 42,100.00 10,946.00
Kuas Buah 0.0100 36,750.00 367.50
Pengencer ( Minyak Cat) Kg 0.0300 28,450.00 853.50
Amplas Lbr 0.2000 4,200.00 840.00
Jumlah Harga Bahan 22,194.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 31,594.00
E OVERHEAD ₰ PROVIT 10% x D 3,159.40
F HARGA SATUAN PEKERJAAN (D + E) 34,753.40
Jenis Pekerjaan : Pengecatan Tembok Baru (1 Lapis Plamuur, 1 Lapis Cat Dasar
2 Kali Cat Penutup
Satuan / Unit : m2
Analisa : AHSP PU A.4.7.1.10
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.0200 100,000.00 2,000.00
Tukang Cat L.02 OH 0.0630 125,000.00 7,875.00
Kepala Tukang L.03 OH 0.0063 150,000.00 945.00
Mandor L.04 OH 0.0030 125,000.00 375.00
Jumlah Tenaga Kerja 11,195.00
B BAHAN :
Plamuur Kg 0.1000 19,000.00 1,900.00
Cat Dasar (Mowilex) Kg 0.1000 10,600.00 1,060.00
Cat Penutup (Aquqlistik) Kg 0.2600 43,675.00 11,355.50
Jumlah Harga Bahan 14,315.50
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 25,510.50
E OVERHEAD ₰ PROVIT 10% x D 2,551.05
F HARGA SATUAN PEKERJAAN (D + E) 28,061.55
Jenis Pekerjaan : Pengecatan Permukaan Baja Dengan Meni Besi
Satuan / Unit : m2
Analisa : AHSP PU A.4.7.1.16
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.0200 100,000.00 2,000.00
Tukang Cat L.02 OH 0.2000 125,000.00 25,000.00
Kepala Tukang L.03 OH 0.0200 150,000.00 3,000.00
Mandor L.04 OH 0.0025 125,000.00 312.50
Jumlah Tenaga Kerja 30,312.50
B BAHAN :
Meni Besi Kg 0.1000 22,675.00 2,267.50
Kwas Bh 0.0100 36,750.00 367.50
Jumlah Harga Bahan 2,635.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 32,947.50
E OVERHEAD ₰ PROVIT 10% x D 3,294.75
F HARGA SATUAN PEKERJAAN (D + E) 36,242.25
Jenis Pekerjaan : Pemasangan Rangka Besi Holow 1.40.40. 2Cm Modul 60 x 120
Dinding Partisi
Satuan / Unit : m2
Analisa : AHSP PU A.4.2.1.20
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.1000 100,000.00 10,000.00
Tukang L.02 OH 0.1000 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.0100 150,000.00 1,500.00
Mandor L.04 OH 0.0050 125,000.00 625.00
Jumlah Tenaga Kerja 24,625.00
B BAHAN :
Metal Holow 40.40.2 mm m1 3.5000 18,400.00 64,400.00
(Aksesories Perkuatan Las Ls 100 % x 18,400.00 64,400.00
Dan Lain - Lain) Rangka
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.2000 100,000.00 20,000.00
Tukang L.02 OH 0.1000 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.0100 150,000.00 1,500.00
Mandor L.04 OH 0.0010 125,000.00 125.00
Jumlah Tenaga Kerja 34,125.00
B BAHAN :
Atap Genteng Metal Lbr 1.0200 42,750.00 43,605.00
Paku Seng Kg 0.2000 48,400.00 43,605.00
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.1400 100,000.00 14,000.00
Tukang L.02 OH 0.4000 125,000.00 50,000.00
Kepala Tukang L.03 OH 0.0400 150,000.00 6,000.00
Mandor L.04 OH 0.0700 125,000.00 8,750.00
Jumlah Tenaga Kerja 78,750.00
B BAHAN :
Profil C 75.100 m' 4.2600 19,500.00 83,070.00
Reng U 0.45 m' 4.9300 19,500.00 96,135.00
Baut Truss bh 14.0000 450.00 6,300.00
Jumlah Harga Bahan 185,505.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 264,255.00
E OVERHEAD ₰ PROVIT 10% x D 26,425.50
F HARGA SATUAN PEKERJAAN (D + E) 290,680.50
Jenis Pekerjaan : Memasang Konstruksi Kuda-Kuda, Kayu Kelas I
Satuan / Unit : M3
Analisa : AHSP PU A.4.6.1.14
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 6.7000 100,000.00 670,000.00
Tukang L.02 OH 20.1000 125,000.00 2,512,500.00
Kepala Tukang L.03 OH 2.0100 150,000.00 301,500.00
Mandor L.04 OH 0.3350 125,000.00 41,875.00
Jumlah Tenaga Kerja 3,525,875.00
B BAHAN :
Balok Kayu Kelas I m3 1.100 4,250,000.00 4,675,000.00
Besi Strip Tebal 5 mm Kg 15.000 1,603.76 24,056.40
Paku Kayu Kg 5.600 1,000.00 5,600.00
Jumlah Harga Bahan 4,704,656.40
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 8,230,531.40
E OVERHEAD ₰ PROVIT 10% x D 823,053.14
F HARGA SATUAN PEKERJAAN (D + E) 9,053,584.54
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 2.4000 100,000.00 240,000.00
Tukang L.02 OH 7.2000 125,000.00 900,000.00
Kepala Tukang L.03 OH 0.7200 150,000.00 108,000.00
Mandor L.04 OH 0.1200 125,000.00 15,000.00
Jumlah Tenaga Kerja 1,263,000.00
B BAHAN :
Balok Kayu Kelas I m3 1.100 4,250,000.00 4,675,000.00
Paku Campur m' 3.000 19,700.00 59,100.00
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.1000 100,000.00 10,000.00
Tukang L.02 OH 0.1000 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.0100 150,000.00 1,500.00
Mandor L.04 OH 0.0050 125,000.00 625.00
Jumlah Tenaga Kerja 24,625.00
B BAHAN :
Kaso-kaso (5 x 7 ) cm m3 0.014 2,360,000.00 33,040.00
Reng (3x4) cm m3 0.007 4,250,000.00 30,600.00
Paku Campur Kg 0.250 19,700.00 4,925.00
Jumlah Harga Bahan 68,565.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 93,190.00
E OVERHEAD ₰ PROVIT 10% x D 9,319.00
F HARGA SATUAN PEKERJAAN (D + E) 102,509.00
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.0750 100,000.00 7,500.00
Tukang L.02 OH 0.1000 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.0200 150,000.00 3,000.00
Mandor L.04 OH 0.0025 125,000.00 312.50
Jumlah Tenaga Kerja 23,312.50
B BAHAN :
Atap Genteng Metal Lbr 0.7000 42,750.00 29,925.00
Paku Seng Kg 6.0000 48,400.00 29,925.00
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.2500 100,000.00 25,000.00
Tukang L.02 OH 0.1500 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.0150 150,000.00 2,250.00
Mandor L.04 OH 0.0130 125,000.00 1,625.00
Jumlah Tenaga Kerja 47,625.00
B BAHAN :
Rabung Genteng Metal Lbr 1.1000 37,250.00 40,975.00
Paku Seng Kg 0.0500 48,400.00 40,975.00
Jenis Pekerjaan : Membuat dan Memasang Kusen pintu dan Kusen Jendela,
Kayu Kelas I
Satuan / Unit : M3
Analisa : AHSP PU A.4.6.1.1
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 7.0000 100,000.00 700,000.00
Tukang L.02 OH 21.0000 125,000.00 2,625,000.00
Kepala Tukang L.03 OH 2.1000 150,000.00 315,000.00
Mandor L.04 OH 0.3500 125,000.00 43,750.00
Jumlah Tenaga Kerja 3,683,750.00
B BAHAN :
Balok Kayu Kelas I m³ 1.1000 4,250,000.00 4,675,000.00
Paku Kayu Kg 1.2500 19,700.00 24,625.00
Lem Kayu Kg 1.0000 21,100.00 21,100.00
Jumlah Harga Bahan 4,720,725.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 8,404,475.00
E OVERHEAD ₰ PROVIT 10% x D 840,447.50
F HARGA SATUAN PEKERJAAN (D + E) 9,244,922.50
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 1.0000 100,000.00 100,000.00
Tukang L.02 OH 3.0000 125,000.00 375,000.00
Kepala Tukang L.03 OH 0.3000 150,000.00 45,000.00
Mandor L.04 OH 0.0500 125,000.00 6,250.00
Jumlah Tenaga Kerja 526,250.00
B BAHAN :
Papan Kayu Kls I m³ 0.0400 4,250,000.00 170,000.00
Lem Kayu Kg 0.5000 21,100.00 10,550.00
Jumlah Harga Bahan 180,550.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 706,800.00
E OVERHEAD ₰ PROVIT 10% x D 70,680.00
F HARGA SATUAN PEKERJAAN (D + E) 777,480.00
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.8000 100,000.00 80,000.00
Tukang L.02 OH 2.4000 125,000.00 300,000.00
Kepala Tukang L.03 OH 0.2400 150,000.00 36,000.00
Mandor L.04 OH 0.0400 125,000.00 5,000.00
Jumlah Tenaga Kerja 421,000.00
B BAHAN :
Papan Kayu Kls I m³ 0.0240 4,250,000.00 102,000.00
Lem Kayu Kg 0.3000 21,100.00 6,330.00
Jumlah Harga Bahan 108,330.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 529,330.00
E OVERHEAD ₰ PROVIT 10% x D 52,933.00
F HARGA SATUAN PEKERJAAN (D + E) 582,263.00
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.6700 100,000.00 67,000.00
Tukang L.02 OH 2.0000 125,000.00 250,000.00
Kepala Tukang L.03 OH 0.2000 150,000.00 30,000.00
Mandor L.04 OH 0.3350 125,000.00 41,875.00
Jumlah Tenaga Kerja 388,875.00
B BAHAN :
Papan Kayu Kls I m³ 0.0600 4,250,000.00 255,000.00
Lem Kayu Kg 0.1500 21,100.00 3,165.00
Jumlah Harga Bahan 258,165.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 647,040.00
E OVERHEAD ₰ PROVIT 10% x D 64,704.00
F HARGA SATUAN PEKERJAAN (D + E) 711,744.00
Jenis Pekerjaan :
Memasang Listplank Uk. 2 x 30 Cm Kayu Kelas I atau Klas II
Satuan / Unit : M2
Analisa : AHSP PU A.4.5.2.32
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.1000 100,000.00 10,000.00
Tukang L.02 OH 0.2000 125,000.00 25,000.00
Kepala Tukang L.03 OH 0.0200 150,000.00 3,000.00
Mandor L.04 OH 0.0050 125,000.00 625.00
Jumlah Tenaga Kerja 38,625.00
B BAHAN :
Papan Kayu Kelas II m3 0.0110 2,360,000.00 25,960.00
Paku Kayu Kg 0.0500 19,700.00 25,960.00
Jumlah Harga Bahan 51,920.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 90,545.00
E OVERHEAD ₰ PROVIT 10% x D 9,054.50
F HARGA SATUAN PEKERJAAN (D + E) 99,599.50
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.0150 100,000.00 1,500.00
Tukang L.02 OH 0.1500 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.0150 150,000.00 2,250.00
Mandor L.04 OH 0.0080 125,000.00 1,000.00
Jumlah Tenaga Kerja 23,500.00
B BAHAN :
Kaca Bening 3 mm m2 1.1000 156,400.00 172,040.00
Sealent Kg 0.0500 20,000.00 172,040.00
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.1500 100,000.00 15,000.00
Tukang L.02 OH 0.3000 125,000.00 37,500.00
Kepala Tukang L.03 OH 0.0300 150,000.00 4,500.00
Mandor L.04 OH 0.7500 125,000.00 93,750.00
Jumlah Tenaga Kerja 150,750.00
B BAHAN :
Kayu Kelas II m3 0.0154 1,835,000.00 28,259.00
Paku 5,7 & 10 Kg 0.2000 19,700.00 3,940.00
Jumlah Harga Bahan 32,199.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 182,949.00
E OVERHEAD ₰ PROVIT 10% x D 18,294.90
F HARGA SATUAN PEKERJAAN (D + E) 201,243.90
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.1000 100,000.00 10,000.00
Tukang L.02 OH 0.1000 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.0100 150,000.00 1,500.00
Mandor L.04 OH 0.0050 125,000.00 625.00
Jumlah Tenaga Kerja 24,625.00
B BAHAN :
Tripleks 3mm Lbr 0.3750 62,450.00 23,418.75
Paku Tripleks Kg 0.0300 35,100.00 1,053.00
Jumlah Harga Bahan 24,471.75
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 49,096.75
E OVERHEAD ₰ PROVIT 10% x D 4,909.68
F HARGA SATUAN PEKERJAAN (D + E) 54,006.43
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.0500 100,000.00 5,000.00
Tukang L.02 OH 0.0500 125,000.00 6,250.00
Kepala Tukang L.03 OH 0.0050 150,000.00 750.00
Mandor L.04 OH 0.0030 125,000.00 375.00
Jumlah Tenaga Kerja 12,375.00
B BAHAN :
Lis Kayu Profil Lbr 1.0500 17,100.00 17,955.00
Paku Campur Kg 0.0100 19,700.00 17,955.00
Jumlah Harga Bahan 35,910.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 48,285.00
E OVERHEAD ₰ PROVIT 10% x D 4,828.50
F HARGA SATUAN PEKERJAAN (D + E) 53,113.50
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.0100 100,000.00 1,000.00
Tukang Kayu L.02 OH 0.5000 125,000.00 62,500.00
Kepala Tukang L.03 OH 0.0500 150,000.00 7,500.00
Mandor L.04 OH 0.0050 125,000.00 625.00
Jumlah Tenaga Kerja 71,625.00
B BAHAN :
Kunci Tanam BH 1.0000 141,750.00 141,750.00
-
-
Jumlah Harga Bahan 141,750.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 213,375.00
E OVERHEAD ₰ PROVIT 10% x D 21,337.50
F HARGA SATUAN PEKERJAAN (D + E) 234,712.50
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.0150 100,000.00 1,500.00
Tukang Kayu L.02 OH 0.1500 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.0150 150,000.00 2,250.00
Mandor L.04 OH 0.0008 125,000.00 100.00
Jumlah Tenaga Kerja 22,600.00
B BAHAN :
Engsel Pintu BH 1.0000 26,250.00 26,250.00
-
-
Jumlah Harga Bahan 26,250.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 48,850.00
E OVERHEAD ₰ PROVIT 10% x D 4,885.00
F HARGA SATUAN PEKERJAAN (D + E) 53,735.00
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.0150 100,000.00 1,500.00
Tukang Kayu L.02 OH 0.1500 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.0150 150,000.00 2,250.00
Mandor L.04 OH 0.0008 125,000.00 100.00
Jumlah Tenaga Kerja 22,600.00
B BAHAN :
Engsel Jendela BH 1.0000 10,500.00 10,500.00
-
-
Jumlah Harga Bahan 10,500.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 33,100.00
E OVERHEAD ₰ PROVIT 10% x D 3,310.00
F HARGA SATUAN PEKERJAAN (D + E) 36,410.00
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.0150 100,000.00 1,500.00
Tukang Kayu L.02 OH 0.1500 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.0150 150,000.00 2,250.00
Mandor L.04 OH 0.0008 125,000.00 100.00
Jumlah Tenaga Kerja 22,600.00
B BAHAN :
Kait Angin BH 1.0000 6,563.00 6,563.00
-
-
Jumlah Harga Bahan 6,563.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 29,163.00
E OVERHEAD ₰ PROVIT 10% x D 2,916.30
F HARGA SATUAN PEKERJAAN (D + E) 32,079.30
HARGA JUMLAH
NO. URAIAN KODE SAT KOEF SAT HARGA
(Rp) (Rp)
A TENAGA :
Pekerja L.01 OH 0.0150 100,000.00 1,500.00
Tukang Kayu L.02 OH 0.1500 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.0150 150,000.00 2,250.00
Mandor L.04 OH 0.0080 125,000.00 1,000.00
Jumlah Tenaga Kerja 23,500.00
B BAHAN :
Grendel Pintu BH 1.0000 7,875.00 7,875.00
-
-
Jumlah Harga Bahan 7,875.00
C PERALATAN :
-
-
Jumlah Harga Alat -
D JUMLAH A + B + C 31,375.00
E OVERHEAD ₰ PROVIT 10% x D 3,137.50
F HARGA SATUAN PEKERJAAN (D + E) 34,512.50
TPQ AL - NADITA FASYAH
Jalan Poros Wabahara Desa Lagasa Kec. Duruka Kab. Muna
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pengukuran dan Pas. Bouwplank Ls 1.00 200,000.00 200,000.00
2 Dokumentasi ,Administrasi Dan P3K Ls 1.00 1,200,000.00 1,200,000.00
3 Papan Nama Kegiatan Ls 1.00 300,000.00 300,000.00
4 Pembongkaran Bangunan Lama Ls 1.00 2,676,000.00 2,676,000.00
Jumlah 4,376,000.00
II PEKERJAAN TANAH DAN PASIR
1 Pek. Galian Tanah Fondasi m3 14.38 106,562.50 1,532,454.00
2 Pek. Urugan Tanah Kembali m3 3.60 38,953.75 140,046.52
3 Pek. Urugan Tanah Alas Lantai m3 5.46 136,354.03 744,493.00
4 Pek. Urugan Pasir Alas Lantai m3 2.73 218,515.00 596,545.95
Jumlah 3,013,539.47
III PEKERJAAN PASANGAN
1 Pek Pasangan Batu Kosong m3 3.68 422,640.90 1,555,656.62
2 Pek Pasangan Batu Belah Dengan Mortared 1 : 4 m3 7.12 851,677.20 6,060,109.12
3 Pek. Pasangan Bata 1 : 4 m2 48.24 145,213.20 7,005,084.77
Jumlah 14,620,850.51
IV PEKERJAAN BETON
1 Pek. Sloof Ukr 15 x 15 Beton 1 : 2 : 3
- Pek. Bekisting Untuk Sloof m2 6.42 141,566.33 908,855.86
- Pembesian Dengan Beton Polos Kg 69.19 28,930.00 2,001,707.20
- Pek. Beton Mutu f'c = 19,3 Mpa (K225) m3 0.48 1,276,345.70 614,560.45
2 Pek.Kolom Ukr 15 x 15 Beton Camp. 1 : 2 : 3 m1 33.02 129,184.77 4,265,681.11
3 Pek.Ring Balok Ukr 15 x 15 Beton Camp. 1 : 2 : 3 m1 26.46 129,184.77 3,418,229.01
Jumlah 11,209,033.63
V PEKERJAAN PLESTERAN / ACIAN AIR CEMENT
1 Pek. Plesteran Dinding Camp 1 : 4 m2 76.08 72,409.00 5,508,514.37
2 Pek Plesteran Muka Fondasi 1 : 3 m2 6.21 74,855.84 464,555.35
3 Pek. Acian Air Cemen Muka Fondasi m2 6.21 44,276.93 274,782.60
Jumlah 6,247,852.31
VI PEK.KUSEN DAUN PINTU DAN JENDELA KAYU KELAS 1
1 Pek. Kusen Kayu Kelas 1 m3 0.55 9,244,922.50 5,086,556.36
2 Pek. Daun Pintu Kayu Klas 1 m2 3.06 777,480.00 2,382,665.21
3 Pek. Daun Jendela Kayu Klas 1 m2 4.42 582,263.00 2,573,602.46
4 Pek. Jalusi Kayu Kelas. I m2 5.72 711,744.00 4,074,022.66
Jumlah 14,116,846.68
VII PEKERJAAN ATAP
1 Pek. Kuda - Kuda Kayu Kelas 1 m3 0.60 9,053,584.54 5,433,889.01
3 Pek. Rangka Atap Kayu Kelas 1 m2 60.72 102,509.00 6,224,346.48
4 Pek. Atap Soka Abadi m2 87.88 91,478.75 8,038,914.71
5 Pek. Nok Atap Induk m1 7.59 142,532.50 1,082,106.74
6 Pek. Lesplank Kayu Kelas 1 Atap Induk m2 4.74 99,599.50 472,101.63
Jumlah 21,251,358.57
VIII PEKERJAAN PLAFOND DAN RANGKA KAYU KLS.II
1 Pek. Rangka Plafond Kayu Kelas II Modul 120 x 120 m2 36.69 201,243.90 7,382,833.72
2 Pek. Plafond Tripleks 3 mm Modul 120 x 120 m2 36.69 54,006.43 1,981,279.71
3 Pek. Les Plafond m2 2.58 53,113.50 137,209.88
Jumlah 9,501,323.30
IX PEKERJAAN LANTAI
1 Pek. Pasang Keramik Lantai 40 x 40 Cm m2 40.43 160,095.78 6,472,672.47
Jumlah 6,472,672.47
X PEKERJAAN PENGECATAN
1 Pek. Cat Dan Plamir Tembok Dll m2 96.48 28,061.55 2,707,378.34
2 Pek. Cat Kusen, Daun Pintu/ Jendela m2 27.52 34,753.40 956,330.16
3 Pekerjaan Pengecatan Plafond m2 36.69 34,753.40 1,274,963.23
Jumlah 4,938,671.74
XI PEKERJAAN INSTALASI TITIK ALIR
1 A Pemasangan Kembali Jaringan Listrik Ls 1.00 2,500,000.00 2,500,000.00
B Instalasi Titik Api Kontak, Instalasi termasuk kabel
NYA 2,5 mm dalam Pipa PVC dan Kelengkapan
Instalasi Terpasang Lantai Laboratorium Dan RKB Ls 1.00 550,000.00 550,000.00
Jumlah 3,050,000.00
XII PEKERJAAN KUNCI DAN KACA
1 Pek. Pasang Kunci Pintu 2 x Putar BH 2.00 139,458.00 278,916.00
2 Pek. Pasang Engsel Pintu Biasa BH 6.00 45,356.30 272,137.80
3 Pek. Pasang Engsel Jendela Biasa BH 24.00 45,356.30 1,088,551.20
4 Pek. Pasang Grendel Pintu BH 2.00 30,827.50 61,655.00
5 Pek. Pasang Grendel Jendela BH 12.00 30,827.50 369,930.00
6 Pek. Pasang Hak Angin Biasa BH 12.00 29,956.30 359,475.60
7 Pek. Kaca Mati 3mm m2 3.36 467,527.50 1,570,892.40
Jumlah 4,001,558.00
XIII PEK.KANOPI TERAS SAMPING
1 Pek. Kanopi Termasuk Rabat Lantai Dan Aksesoris Lainnya Ls 1.00 17,000,000.00 17,000,000.00
Jumlah 17,000,000.00
XIV PEK.FINISHING
1 Pek. Pembersihan Dari Sisa Pekerjaan Ls 1.00 200,300.00 200,300.00
Jumlah 200,300.00
TPQ AL - NADITA FASYAH
Jalan Poros Wabahara Desa Lagasa Kec. Duruka Kab. Muna
REKAPITULASI
PERKIRAAN HARGA PEKERJAAN
Pembangunan TPQ AL - NADITA FASYAH Untuk Memperkuat Program
KEGIATAN : Pendidikan RA AL - NADITA
FASYAH dan MI AL - NADITA FASYAH
PEKERJAAN : Pembangunan TPQ AL - NADITA FASYAH
LOKASI : Jalan Poros Wabahara Desa Lagasa Kec. Duruka Kab. Muna
TA : 2020
Jumlah Harga
No. Divisi URAIAN ITEM PEKERJAAN Pekerjaan
(Rupiah)
Diajukan Oleh :
Pembina Yayasan :
AL - NADITA FASYAH
MUH. AKHIRULLAH, SP
(Ketua)
NO SUDUT SIN COS TAN
1 0 0 1 0.01745506492822
2 30 0.5 0.9999619230642 0.01745440015785
3 45 0.7071067811865 0.9999238466116 0.01745373539593
4 60 0.8660254037844 0.9998857706424 0.01745307064246
5 90 1 0.9998476951564 0.01745240589745
Berat Per Meter Pnj Tot Berat/12m
Besi 6 44,641.00 0.22 Kg/m 12.00 2.64 Kg 16,909 Kg 44,641.00
Besi 8 70,041.00 0.39 Kg/m 12.00 4.68 Kg 14,966 Kg 70,041.00
Besi 10 100,521.00 0.62 Kg/m 12.00 7.44 Kg 13,511 Kg 100,521.00
Besi 12 139,891.00 0.89 Kg/m 12.00 10.68 Kg 13,098 Kg 139,891.00
Besi 14 171,641.00 1.54 Kg/m 12.00 18.48 Kg 9,288 Kg 171,641.00
Besi 16 222,441.00 2.01 Kg/m 12.00 24.12 Kg 9,222 Kg 222,441.00