0% found this document useful (0 votes)
163 views5 pages

Calculate-Duration-pdf (1) - P6

This document discusses how to calculate activity duration in project scheduling based on either a duration-driven or resource-driven approach. [1] In a duration-driven schedule, the duration is fixed and the necessary resources are calculated based on productivity rates. [2] In a resource-driven schedule, the available resources determine the duration as productivity dictates how much of the activity can be completed each day. [3] Examples are provided to demonstrate calculating resource requirements or duration given scope, productivity, and resources.

Uploaded by

bishry ahamed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
163 views5 pages

Calculate-Duration-pdf (1) - P6

This document discusses how to calculate activity duration in project scheduling based on either a duration-driven or resource-driven approach. [1] In a duration-driven schedule, the duration is fixed and the necessary resources are calculated based on productivity rates. [2] In a resource-driven schedule, the available resources determine the duration as productivity dictates how much of the activity can be completed each day. [3] Examples are provided to demonstrate calculating resource requirements or duration given scope, productivity, and resources.

Uploaded by

bishry ahamed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Calculate Duration in P6 based on scope

what we have in construction projects?

Activity

Resources

Duration

A) Scenario 1 : Duration Driven Schedule


Duration Activity Resources

How These Variables should be arranged?


Fixed Duration + Fixed Scope of Work (activity) :

Duration Activity

flexible
Fixed

Example of Duration driven schedule:


Time Activity (scope) Resources

10 days ??
20 Isolated Footings

Now we need to calculate the required resources to finish the 20


isolated footings in 10 days!

Productivity Rates

?
Train?
what is this!
Productivity Rates are similar to train. where the train
can travel you from point x to point y in certain time,
productivity rate is the amount of time required to Finish
certain activity with a certain team. Let us see How this
works in our Example above?

Scope = 20 Isolated Footings Working team: 2 carpenters and 1 Steel Fixer

Team productivity: 2 isolated footings per day

With then given information can you tell the


required Man power?
Todacualate the requiredManpower use the Following formula

Total required Mondays scope 20 to


Productivity 2

Mondays 10
Dailyrequired teams Activitytime 10
p

we need 1team to work for todays to finish the 20 IsolatedFootings


what if the team can Finish 1 Footing only per day instead of 2?

Total required Mondays sp de.FIty 2f 2o

Mondays 20
Dailyrequired teams Activitytime 10
2

Weneed 2 teams to work for todays to Finish the 20 IsolatedFootings

Now it is your turn, try some


different productivity and Qty.
B) Scenario 2 : Resource Driven Schedule
what if you have an activity that requires certain skilled team or
special Equipment? in this case duration of Activity will be driven
from the Resources.

Example i assume that we have in our project 1 tower crane only.


This crane can serve 1.5 Isolated Footing per day only. How we
can calculate the activity duration?

Productivity I 5
at y 20

Duration
Productivity

79 13 33 14 days

I hope You found this lesson useful.

Best Regards,

later ismael
PlanningEngineer. Net

You might also like