CHAPTER-5 - Project Management
CHAPTER-5 - Project Management
1. Introduction:
The project or task consists of many activities interrelated with each other. To perform the task,
it is required to arrange the activities I logical sequence with precedence and follow-up
relationships. These process of arranging activities in logical sequence for outlook and to
estimate time & tasks of project.
b. Mile stone chart: This is an improvement over Gantt chart. This becomes good bridge
between ‘Gantt Chart’ and ‘PERM & CPM’. Every task represented by bar in Gantt’s bar
chart, is subdivided in terms event or point of time.
c. PERT & CPM: As the network analysis undergone several changes due to variance in
Human & Physical systems, PERT and CPM continue to be very popular with handling of
time, cost, resources, probabilities & combinations. PERT is abbreviated as “Program
Evaluation Review Technique” and CPM is abbreviated as “Critical Path Method”.
resources. This path has ‘zero’ slack value. Slack is the time takes to delay the particular
event without affecting the project completion time.
Hence, Slack = LFT – EFT ; EFT = EST + Duration of activity ; LST=LFT – Duration of Activity
• Total float is the additional time which non critical activity can consume without
increasing the project duration. Total Float = LST – EST (or) LFT – EFT. However,
total float may affect the floats in previous and subsequent activities.
• Free float refers to the time by which an activity can expand without affect
succeeding activities. Free float = EST of Head event – Est of Tail event – Activity
duration. (FF=ESTHE – ESTTE – AD)
• Independent float means, the time by which an activity may be delayed or
extended without affecting the preceding or succeeding activities in any way.
IF=ESTHE – LFTTE – AD.
Activity A B C D E F
Predecessor - A B A D C,E
Duration in days 14 16 15 14 13 13
Critical Path:
Method-1
(a) 1 – 2 – 3 – 5 – 6 = 14+16+15+13=58 (Duration of critical path)
(b) 1 – 2 – 4 – 5 – 6 = 14+14+13+13=54
Management Science Notes by N.Aruna Kumari, Asst. Prof. Humanities & Sciences
Method-2
5.2 Draw the PERT diagram and find the critical path from the following data:
Activity A B C D E F G H I J
Predecessor - A A A D D E F,G C,H B
Duration in 1 4 2 2 3 3 2 1 3 2
(months)
Activity A B C D E F G H
Predecessor - - A A A,B C,D F E,G
Duration in weeks 6 8 3 9 10 7 8 4
5.4 Draw the PERT diagram and find the critical path from the following data:
Activity A B C D E F G H I J K L M N O P Q
Predecessor - - - A A B B C C D E F G H I J,K,L M,N,O
Duration in 4 8 5 4 5 7 4 8 3 6 5 4 12 7 10 5 8
weeks
Activity A B C D E F G
Predecessor - - A C D B,E F
Duration in 1 4 2 2 3 3 2
(months)
5.6 Draw the PERT diagram and find the critical path from the following data:
Activity A B C D E F G H I J K L M N
Predecessor - - A B A C,D F E,G H I J,L A K M
Duration in 8 9 7 6 5 4 6 8 9 3 4 4 1 6
(months)
Activity A B C D E F G H I J K L M N
Predecessor - - - B A A B C,D C E F,G,H F,G,H I K
Duration in 2 6 4 3 6 8 3 7 2 5 4 3 13 7
(months)
5.8 Draw the PERT diagram and find the critical path from the following data:
Job 1-2 3-4 5-8 7-9 2-3 3-5 6-7 8-9 2-4 4-6 6-10 9-10
Duration 2 3 5 4 7 5 8 1 3 3 4 7
in (Weeks)
Job 1-2 1-3 1-4 2-5 2-6 3-6 4-7 5-7 6-7
Duration in 3 2 6 2 5 3 3 1 2
(Weeks)
5.11 Find the estimated time duration from the following data and draw the network to
find critical path.
5.12 Find the estimated time duration from the following data and draw the network to
find critical path.
Problems on Crashing:
6.1. Find the optimal crashed project completion time with the following data consider and
indirect costs per week is INR 1500.
Critical Path:
1-3-5 = 12+8 = 20 weeks
1-2-3-5 = 6+8+8 = 22 weeks – Critical path
1-2-5 = 6+15 = 21 weeks
1-2-4-5 = 6+4+6 = 16 weeks
1-4-5 = 4+6 = 10 weeks
Priorities chart:
Priority – 1: Crashing 2-3 activity by 2 weeks as this activity has low cost slope per week
Critical Path:
1-3-5 = 12+8 = 20 weeks
1-2-3-5 = 6+6+8 = 20 weeks
1-2-5 = 6+15 = 21 weeks (Critical path)
1-2-4-5 = 6+4+6 = 16 weeks
1-4-5 = 4+6 = 10 weeks
According to the above priority the total cost increased upto INR 78500/- by reducing only
one week. Hence this priority is not preferable, instead we can crash this by only one week.
Priority – 2: Crashing 2-3 activity by 1 week
Critical Path:
1-3-5 = 12+8 = 20 weeks
1-2-3-5 = 6+7+8 = 21 weeks: Critical path
1-2-5 = 6+15 = 21 weeks: Critical path
1-2-4-5 = 6+4+6 = 16 weeks
1-4-5 = 4+6 = 10 weeks
Hence, the total cost is INR 73500 with 21 weeks duration after crashing 2-3 activity by 1
week, and it is high cost than normal total cost.
Priorities chart:
Critical Path:
1-3-5 = 12+8 = 20 weeks: Critical path
1-2-3-5 = 6+6+8 = 20 weeks: Critical path
1-2-5 = 6+14 = 20 weeks: Critical path
1-2-4-5 = 6+4+6 = 16 weeks
1-4-5 = 4+6 = 10 weeks
Hence, from all three priorities, that total cost is constantly increasing by decreasing only one
week. So, it is not advised to reduce more than 3 activities as we got 3 critical paths as of now.
But the total cost is reduced at priority 2 than priority 1 after crashing 2-3 activity by 1 week.
Hence it is considered as optimum cost and duration with 21 weeks and total cost of INR73500.
6.2. Find the optimal crashed project completion time with the following data consider and
indirect costs per day is INR 20000.
Critical Path:
1-2-5 = 4+5 = 9 days (Critical path)
1-2-4-5 = 4+2+2 = 8 days
1-3-4-5 = 2+3+2 = 7 days
Critical Path:
1-2-5 = 3+5 = 8 days (Critical path)
1-2-4-5 = 3+2+2 = 7 days
1-3-4-5 = 2+3+2 = 7 days
Critical Path:
1-2-5 = 3+3 = 6 days
1-2-4-5 = 3+2+2 = 7 days (Critical path)
1-3-4-5 = 2+3+2 = 7 days (Critical path)
Here, if project crashed by 2 days, total cost incurred INR 2,38,000 by reducing only one day. Hence it
is not acceptable priority, instead we can crash it by only one day.
Critical Path:
1-2-5 = 3+4 = 7 days (Critical path)
1-2-4-5 = 3+2+2 = 7 days (Critical path)
1-3-4-5 = 2+3+2 = 7 days (Critical path)
As all activities comes under critical activities, the priorities have changed according to the
cost slope which is next lowest.
Management Science Notes by N.Aruna Kumari, Asst. Prof. Humanities & Sciences
Priority-4: Crashing 2-5 activity by 1 day and 4-5 activity by 1 day simultaneously:
Critical Path:
1-2-5 = 3+3 = 6 days (Critical path)
1-2-4-5 = 3+2+1 = 6 days (Critical path)
1-3-4-5 = 2+3+1 = 6 days (Critical path)
Hence, the final optimum duration is 6 days with total optimum cost of INR 2,20,000/-
***
6.3. What is the critical path and the estimated complete time to shorten the project by 3
weeks, which tasks will be shortened and what will be the total cost.
6.4. Find the optimal crashed project completion time with the following data consider and
indirect costs per day is INR 2000.
Critical Path:
1-2-5-7 = 7+9+2 = 18 weeks (Critical path)
1-3-5-7 = 5+5+2 = 12 weeks
1-3-6-7 = 5+6+3 = 14 weeks
1-4-6-7 = 8+7+3 = 18 weeks (Critical path)
Total Costs = Direct cost + Indirect cost = 65000 + (2000X18) = 1,01,000 INR
Priorities chart: Critical path-1
Critical Path:
1-2-5-7 = 6+9+2 = 17 weeks (Critical path)
1-3-5-7 = 5+5+2 = 12 weeks
1-3-6-7 = 5+6+3 = 14 weeks
1-4-6-7 = 8+6+3 = 17 weeks (Critical path)
Total Costs = Direct cost + Indirect cost
Critical Path:
1-2-5-7 = 5+9+2 = 16 weeks (Critical path)
1-3-5-7 = 5+5+2 = 12 weeks
1-3-6-7 = 5+6+3 = 14 weeks
1-4-6-7 = 8+5+3 = 16 weeks (Critical path)
Total Costs = Direct cost + Indirect cost = 100750 +(500+1250) – 2000 = 1,00,500 INR
Management Science Notes by N.Aruna Kumari, Asst. Prof. Humanities & Sciences
Critical Path:
1-2-5-7 = 4+9+2 = 15 weeks (Critical path)
1-3-5-7 = 5+5+2 = 12 weeks
1-3-6-7 = 5+6+3 = 14 weeks
1-4-6-7 = 7+5+3 = 15 weeks (Critical path)
Total Costs = Direct cost + Indirect cost = 1,00,500 + (500+2000) – 2000 = 101000 INR
Hence, Priority -3 has higher total cost than priority-2 which suggest to stop crashing.
Therefore, optimum project duration is 16 weeks with total optimum cost of INR 100500/-
***