0% found this document useful (0 votes)
213 views4 pages

Inspected by QCP Approval 1-APC 1 - APC 2 - DAR 2 - DAR Al-Handeseh 3 - Negemco 4 - Vendor 5 - Third Party

This document is an inspection test plan for a motor control center (MCC) for the Aqaba Screening Project task 5 of APC storing. It lists 12 items to be inspected including documentation, assembly, components, phasing, connections, grounding, mounting, alignment, cleanliness, and verification documentation. The inspection methods are listed as visual inspection and document review. Responsible parties include APC, DAR, NEGEMCO, vendor, and third party. Upon completion, the inspection will be approved, approved with comment, or not approved for resubmittal.

Uploaded by

Ahmad Dagamseh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
213 views4 pages

Inspected by QCP Approval 1-APC 1 - APC 2 - DAR 2 - DAR Al-Handeseh 3 - Negemco 4 - Vendor 5 - Third Party

This document is an inspection test plan for a motor control center (MCC) for the Aqaba Screening Project task 5 of APC storing. It lists 12 items to be inspected including documentation, assembly, components, phasing, connections, grounding, mounting, alignment, cleanliness, and verification documentation. The inspection methods are listed as visual inspection and document review. Responsible parties include APC, DAR, NEGEMCO, vendor, and third party. Upon completion, the inspection will be approved, approved with comment, or not approved for resubmittal.

Uploaded by

Ahmad Dagamseh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Project: J17082 Employer: ITP Ref No.

ITP-I

Engineer: Contractor: Date: August / 2

PO# 201902600 NEGEMCO Job No.: JV19-016 Rev: 00


Project: Aqaba Screening Project task 5 of APC storing
Inspection test Plan Motor Control Center (MCC)
Inspected By 1- APC Submitted By Amin Mohammad/Eyad N. A
1- APC QCP Approval
2- DAR Date
Field Insrument Junction Boxes 2- DAR Al-Handeseh
3- NEGEMCO ( )- Approved without Comment
4- Vendor ( )- Approved With Comment- Proceed
5- Third party ( )- Not Approved-Resubmitted
Control Activities
V- Verify
H- Hold Point
w- Witness
Item Activity Description Inspection/Test method Referance standard P- Patrol Point Verification Documentati
T- testing
N/A- Not App
EM DAR NEG TH.P VEN
1 Documentation
1_1 HSE Plan Document review HSE Policy R R H N/A N/A Project requirment
1_2 Related Installation insturuction Document review Vendor Procedure R R H N/A N/A Vendor Procedure
2 Execution

Check Entire assembly including Approved Shop Drawings,


2_1 auxilary devices for any apparent visual inspection Specification and R R H N/A N/A Visual Report
damage or missing parts Submittal

All the components circuits & rating Specification and


2_2 visual inspection R R H N/A N/A Visual Report
verified. approved submittal
Specification and
2_3 Phasing of buses are correct. visual inspection R R H N/A N/A Visual Report
approved submittal

Bus bar connections, supports & Specification and


2_4 visual inspection R R H N/A N/A visual report
tightness is checked. approved submittal

2_5 Space heater installed. visual inspection Specification and Drawings R R H N/A N/A Visual Report

Support & Termination of cables is Approved shop drawing


2_6 visual inspection R R H N/A N/A Visual report
checked. and approved submittal

Position of control switches, lamps Approved drawing and


2_7 visual inspection R R H N/A N/A Visual report
& push buttons are correct. approved submittal

Grounding connection to grounding Approved shop drawing


2_8 visual inspection R R H N/A N/A Visual report
grid. and approved submittal

Ground bus & Grounding


Specifications and
2_9 connection for electrical & visual inspection R R H N/A N/A Visual report
mechanical cintinuity is checked. approved Submittals

Check for proper mounting in Approved drawing and


2_10 visual inspection R R H N/A N/A Visual report
foundation. approved submittal
2_11 Check for alignment & levelling. visual inspection specifications R R H N/A N/A Visual report
2_12 Check for cleanliness of Panel. visual inspection Specifications R R H N/A N/A Visual report
ITP-I-10

ust / 2 /2020

00

Eyad N. Abu Adi

umentation

Accepted Rejected

You might also like