2 Construction Work

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 53

2 Construction work

SL. Bidder's Rate


Item Description Unit Quantity
No (NPR)

Procument Item Details

Boring, providing and installing bored cast - in - situ RCC pile


1 in soft soil of diameter 600 mm including bentonite rm 150
as per specification and drawing etc all complete
Providing and placing Machine mixed cement
concrete[cement (1): sand(1.5) : aggregate (3) ] M20/20
2 including Formwork compaction, curing, testing and lead Cum 189.43
30m. etc. all complete as per specification and
drawing.( RCC Grade M20) 19,876.78
Providing and laying Reinforcement(TMT) including cutting,
3 bending, binding, fixing in position and lead kg 16027.12
30m. etc. all complete as per specification and drawing. 119.72
Providing and laying of Plain Cement Concrete M 10 ( or
4 1:3:6 for nominal mix) in Foundation complete as per cum 37.25
Drawing and Technical Specifications. 14,107.29
Earth work in excavation( Ordinary Soil) of foundation of
structures, including construction of shoring and
5 bracing, removal of stumps and other deleterious matter and cum 126.31
backfilling with approved Material as per Drawing and
Technical Specifications.( Manually) 2,821.77
Providing, Laying and Levelling dry stone soling works in
6 cum 26.56
foundation all complete. 6257.17
7 Providing and Laying flat bricks in foundation all complete sqm 182.01
936.83
Rubble random stone masonry work in 1:4 cement sand
8 mortar including supply of materials, mortar mixing Cum 216.65
and laying, carriage upto 30 m 13,101.28
Laying and fixing of Geo-Textile all complete as per
9 Sqm 874.7
specification. 457.30

Providing and laying weep holes in various structures with


110 mm dia HDPE pipe(4 kg/cm2) , extending through the
10 full width of the structure with slope of 1V :20H towards rm 155.79
drawing face Complete as per Drawing and Technical
Specifications.
636.35
Filling work in layers to maintain slope for protection of
11 existing structure with subgrade soil material cum 799.83
including compaction and watering all complete 444.19

Providing and Laying Brick Masonry in manual mixed cement


12 mortar (1:4) including preparation of mortar as per cum 23.02
specification with necessary lead all complete
Total Amount
(NPR)

3,765,258.52

1,918,778.83

525,496.53

356,417.47

166,190.54

170,512.12

2,838,392.96

399,998.12

99,137.36

355,274.49

-
10,595,456.93
1 Provisional Sum

SL.
Item Description Unit Quantity Unit Rate(NPR) Amount(NPR)
No

Procument Item Details

Provide, errect and maintain project site notice


1 board as P.S. 1 20000 20,000.00
specified.

Provide safety precautions during the


construction period erecting red flag, temporary
2 drainage, temporary diversion and other P.S. 1 100000 100,000.00
temporary fence work as per site requirement as
per instruction of the Engineer.

3 Provion for insurance as specified P.S. 1 150000 150,000.00

Laboratory tests ordered outside the project as


4 P.S. 1 150000 150,000.00
instructed.

5 Provision for unseen items P.S. 1 350000 350,000.00


Provision for the payment of performance
6 guarantee P.S. 1 10000 10,000.00
commission.
7 Provision for Payment of As Built Drawimgs PS 1 50000 50,000.00
Location Kathmandu
Rate
S.N. Description Unit 75/76 76/77 77/78
1 TMT Bar
a 8 mm kg 94 86 86
b 10,12,16,20 kg 91.5 84 84
c 25 mm kg 92.5 85 85
d 28,32 mm kg 92.5 85 85
2 Binding Wire kg 101.77 92 92
3 Mild Steel
a Angle kg 81.42 81.42 81.42
b Channel kg 83.19 83.19 83.19
c Plate kg 139.1 139.1 139.1
d I-Beam kg 82.3 82.3 82.3
e Black Sheet kg 139.1 139.1 139.1
f Square rod kg 70 70 70
4 G.I. Wire
a Heavy coated kg 107 105 105
b Medium coated kg 102 100 100
c Light coated kg 97 95 95
5 Barbed Wire
12 gauge kg 97.35 97.35 97.35
U hook nos 0.75 0.75 0.75
6 Nails kg 112 112 112
7 Nuts and bolts kg 165 165 165
8 Bricks
a Machine Per 1000 16700 16700 16700
b Chimney Per 1000 14910 14910 14910
c Terai Per 1000 16760 16760 16760
d Kaccha Per 1000 2500 2500 2500
9 Stone(Rubble) Cu. Ft. 67 67 67
10 Aggregate
a Fine Cu. Ft. 91 91 91
b 6-10 mm Cu. Ft. 92 92 92
c 10-20 mm Cu. Ft. 94 94 94
d 20-40 mm Cu. Ft. 95 95 95
e <6 mm Cu. Ft. 84 84 84
11 Base (40mm) Cu. Ft. 84 84 84
12 Sub-Base(63) Cu. Ft. 76 76 76
13 River Cobble 100 mCu. Ft. 105 105 105
14 Flag Stone(2.5") Sq. ft 111 111 111
15 Sand for void filling Cu. Ft. 45 45 45
16 O.P.C. Cement Bag 841 825 825
17 P.P.C. Cement Bag 743 725 725
18 R.M.C.
M20 Cu. M. 14500 15225 15225
M25 Cu. M. 15500 16275 16275
M30 Cu. M. 16300 17115 17115
M35 Cu. M. 17600 18382 18382
M40 Cu. M. 19000 19950 19950
19 HDPE NS-20 kg 240 255 255
20 Timber
Uttis timber Cu. Ft. 625 625 625
Jamun Timber Cu. Ft. 2150 2150 2150
Salla Timber Cu. Ft. 1550 1550 1550
Saj Timber Cu. Ft. 3350 3350 3350
Sal Timber Cu. Ft. 6600 6600 6600
21 Plywood
Standard
3 mm Sq. ft 36 36 36
8 mm Sq. ft 57 57 57
12 mm Sq. ft 80 80 80
18 mm Sq. ft 110 110 110
Waterproof
4 mm Sq. ft 52 52 52
6 mm Sq. ft 67 67 67
8 mm Sq. ft 63 63 63
12 mm Sq. ft 99 99 99
18 mm Sq. ft 139 139 139
21 Geotextile Sq. m 240 240 240
#REF!
Basic Rates

S.No. Description Unit Rate (NRs.) Remarks


A Labour Rate
1 Skilled Construction Labour man day 1,030.00 8 hrs/day
2 Semiskilled Construction Labour man day 845.00
3 Unskilled Construction Labour man day 750.00
3 Skilled workshop technician man day 1,500.00
B Material Rate

1 Cement Bag 825.00 OPC cement

Cement Bag 725.00 PPC cement

2 Sand Cum 3,213.67


3 Aggregates Cum 3,319.61
4 Stone Cum 2,366.11
5 Reinforcement bar Kg 84.00 78
6 Binding wire Kg 92.00
7 Gabion wire Kg 105.00
8 Salvage wire Kg 105.00
9 Nail Kg 112.00
10 Pipe kg 255.00
11 Brick Nos. 16.76
12 Plywood m2 1495.4176
13 Timber(uttis) m3 22054.7
14 GeoTextile m2 240.00
B Finished Work Rate
1 E/W Excav in pipeline m3 652.76
2 E/W Excav in pipeline, gullies m3 748.50
3 E/W Excav in foundation, soft soil m3 748.50
4 E/W Excav in foundation, BMS m3 589.23
5 E/W Excav in foundation, medium rock m3 3,916.58
6 E/W Excav in foundation, hard rock m3 10,444.20
7 E/W filling, common soil m3 435.18
9 Dry stone soling m3 5698.52
10 Dry stone masonry m3 3,270.00
11 Randon rubble masonry 1:4 m3 13,295.36
12 Randon rubble masonry 1:6 m3 12,485.14
13 PCC 1:3:6 m3 12,046.71
14 PCC 1:2:4 m3 17,270.39
15 PCC 1:1.5:3 m3 18,205.59
16 PCC 1:2:4 in plum concrete m3 Err:509
17 PCC 1:2:4 in 30% plum concrete m3 Err:509
18 PCC 1:2:4 in 50% plum concrete m3 Err:509
19 Gabion box 2 x 1 x 1 m m3 6,103.74
20 Cement plaster 12.5mm, 1:4 m2 434.26
21 Water stopper Rm 1,500.00
22 12mm thick Thermocoal m² 1,500.00
23 Sealant m 1,050.00
24 Geotextile m2 400.0
1. Description of the Items: Construction Site Clearance (Thick
Unit: 1 sq. m.
S.No.

4. Description of the Items:E/W Excavation in pipeline in all ty


Unit: 1.00 m3
S.No.
1

5. Description of the Items:E/W In Excavation in pipeline gully


Unit: 1.00 m3
S.No.

5. Description of the Items:Eathwork excavation in soft soil in


S.No.
6. Description of the Items:E/W In Excavation in foundation in soft soil including 15 m haulage and 3.0 m lift a)
Unit: 1.00 m3 b)

S.No. Description Unit Quantity Unit Rate Amount (NRs.) Remarks


(NRs.)

1 Man Power c)
Skilled Labour Md.
Unskilled Labour Md. 0.86 845.00 726.70

6. Description of the Items:Eathwork excavation in boulder m


Sub total 726.70
2 Materials S.No.
Sub total a)
3 Tools and Plants 3% of Labour cost 21.80 b)

Total of (1+2+3) 748.50


Contractor Overhead and profit 15% c)
Total 748.50

7. Description of the Items:Eathwork excavation in boulder mixed soil including 10 m haulage and 1.50 m lift 7. Description of the Items:Eathwork excavation in soft rock in
Unit: 1.00 m3 S.No.
S.No. Description Unit Quantity Unit Rate Amount (NRs.) Remarks
(NRs.) a)
1 1. Labour b)

Un-skilled Labor Md. 0.1882 845.00 159.03


Skilled Labor Md. 0.0213 845.00 18.00 c)
Sub-total 177.03
2 2. Materials
8. A) Description of the Items:Eathwork excavation in hard ro
Diesel lt 1.008 100 100.80
3 Lubricant LS 0.16 451.1625 72.19 S.No.
Sub Total 172.99 a)
3. Equipment b)

Excavator hr 0.0213 2444 52.0572


Wheel Loader hr 0.0316 2444 77.2304 c)
Tipper hr 0.0783 1404 109.9332
Subtotal 239.2208

8. B) Description of the Items:Eathwork excavation in hard ro


Total (1+2+3) 589.23
S.No.
8. Description of the Items:Eathwork excavation in Medium rock including 10 m haulage and 1.50 m lift a)

Unit: 1.00 m3
S.No. Description Unit Quantity Unit Rate Amount (NRs.) Remarks
(NRs.) b)
1 Man Power
Skilled Labour Md.
Unskilled Labour Md. 4.5 845.00 3,802.50
Sub total 3,802.50
2 Materials 0
Sub total
3 Tools and Plants 3% of Labour cost 114.08 c)
Total of (1+2+3) 3,916.58
Contractor Overhead and profit 15%
Total 3,916.58

9. Description of the Items:Boulder Breaking including 10 m h


Unit: 1.00 m3
S.No.

10. Description of the Items:Eathwork excavation in Hard roc


Unit: 1.00 m3
S.No.
1

3
11. Description of the Items:Eathwork in filling with common materials 11. Description of the Items:Eathwork in filling with common
Unit: 1.00 m3 S.No.
S.No. Description Unit Quantity Unit Rate Amount (NRs.) Remarks
(NRs.) a)
1 Man Power
Skilled Labour Md. b)
Unskilled Labour Md. 0.5 845.00 422.50 c)
Sub total 422.50 d)
2 Materials 0
Sub total
3 Tools and Plants 3% of Labour cost 12.68
Total of (1+2+3) 435.18
Contractor Overhead and profit 15%
Total 435.18

12. Description of the Items:Eathwork filling with river bed m


Unit: 1.00 m3
S.No.

13. Description of the Items:Dry stone Masonry (coursed rubb


Unit: 1.00 m3

15. Providing and laying Random rubble stone masonary in m


Unit: 1.00 m3
S.No.
1

14. Description of the Items:Dry stone masonry wall upto 5.00 m height
Unit: 1.00 m3
S.No. Description Unit Quantity Unit Rate Amount (NRs.) Remarks
(NRs.)
1 Man Power
Skilled Labour Md. 1 1,030.00 1,030.00
Unskilled Labour Md. 2 845.00 1,690.00 16. Description of the Items:Random rubbel masonry wall in (
Sub total 2,720.00 Unit: 1.00 m3
2 Materials S.No.
Stone m3 1.1 500 550.00 1
Sub total 550.00
Total of (1+2) 3,270.00
Contractor Overhead and profit 15%
Total 3,270.00 2

15. Description of the Items:Random rubbel masonry wall in mud mortar


Unit: 1.00 m3
S.No. Description Unit Quantity Unit Rate Amount (NRs.) Remarks
(NRs.)
1 Man Power 3
Skilled Labour Md. 1 1,030.00 1030
Unskilled Labour Md. 2.25 845.00 1901.25
Sub total 2931.25
2 Materials
Stone m3 1.1 500 550.00
Mud m3 0.42 Err:509 Err:509
Sub total Err:509 17. Description of the Items:Random rubbel masonry wall in (
Total of (1+2) Err:509 Unit: 1.00 m3
Contractor Overhead and profit 15% S.No.
Total Err:509 1

16. Description of the Items:Random rubbel masonry wall in (1:3) cement mortar 2
Unit: 1.00 m3
Unit Rate
S.No. Description Unit Quantity (NRs.) Amount (NRs.) Remarks

1 Man Power
Skilled Labour Md. 2 1,030.00 2,060.00
Unskilled Labour Md. 5.4 845.00 4,563.00
Sub total 6,623.00 3
2 Materials
Cement Mtn. 0.194 16,500.00 3,201.00
3
Sand m 0.42 3,213.67 1,349.74
3
Stone m 1.1 2,366.11 2,602.72
Sub total 7,153.45
Total of (1+2) 13,776.45
Contractor Overhead and profit 15% 18. Description of the Items:Random rubbel masonry wall in (
Total 13,776.45 Unit: 1.00 m3
S.No.
1

17. Description of the Items:Random rubbel masonry wall in (1:4) cement mortar 2
Unit: 1.00 m3
Unit Rate
S.No. Description Unit Quantity Amount (NRs.) Remarks
(NRs.)
1 Man Power
Skilled Labour Md. 2 1,030.00 2,060.00
Unskilled Labour Md. 5.4 845.00 4,563.00
Sub total 6,623.00 3
2 Materials
Cement Mtn. 0.159 16500.0 2,623.50
3
Sand m 0.45 3,213.67 1,446.15
Stone m3 1.1 2,366.11 2,602.72
Sub total 6,672.36
Total of (1+2) 13,295.36
Contractor Overhead and profit 15% 19. Description of the Items: P.C.C. (1:3:6) (M10/40) in founda
Total 13,295.36 Unit: 1.00 m3
S.No.
1

18. Description of the Items:Random rubbel masonry wall in (1:6) cement mortar 2
3
Unit: 1.00 m
Unit Rate
S.No. Description Unit Quantity Amount (NRs.) Remarks
(NRs.)
1 Man Power
Skilled Labour Md. 2 1,030.00 2,060.00
Unskilled Labour Md. 5.4 845.00 4,563.00
Sub total 6,623.00
2 Materials
Cement Mtn. 0.106 16500.0 1,749.00 3
Sand m3 0.47 3,213.67 1,510.42
Stone m3 1.1 2,366.11 2,602.72
Sub total 5,862.14
Total of (1+2) 12,485.14
Contractor Overhead and profit 15%
Total 12,485.14

20. Description of the Items: P.C.C. (1:2:4) (M15/40) (Machin


Unit: 1.00 m3
S.No.
19. Description of the Items: P.C.C. (1:3:6) in foundation of structure. 1
3
Unit: 1.00 m
Unit Rate
S.No. Description Unit Quantity Amount (NRs.) Remarks
(NRs.)
1 Man Power
Skilled Labour Md. 1 1,030.00 1,030.00 2
Unskilled Labour Md. 5 845.00 4,225.00
Sub total 5,255.00
2 Materials
Cement Mtn. 0.22 16500.0 3,630.00
3
Sand m 0.47 3,213.67 1,510.42
3
Aggregates m 0.89 3,319.61 2,954.45
Sub total 8,094.88
Total of (1+2) 13,349.88 3
Contractor Overhead and profit 15%
Total 13,349.88
21. Description of the Items: P.C.C. (1:1.5:3) (M20/20) (Mach
Unit: 1.00 m3
S.No.
20. Description of the Items: P.C.C. (1:2:4) 1
3
Unit: 1.00 m
Unit Rate
S.No. Description Unit Quantity Amount (NRs.) Remarks
(NRs.)
1 Man Power
Skilled Labour Md. 1.5 1,030.00 1,545.00 2
Unskilled Labour Md. 6.5 845.00 5,492.50
Sub total 7,037.50
2 Materials
Cement Mtn. 0.32 16500.0 5,280.00
Sand m3 0.445 3,213.67 1,430.08
3
Aggregates m 0.85 3,319.61 2,821.67
Sub total 9,531.75
Total of (1+2) 16,569.25
Contractor Overhead and profit 15% 3
Total 16,569.25

21. Description of the Items: P.C.C. (1:1:2) (M25/20) (Machin


Unit: 1.00 m3
S.No.
21. Description of the Items: P.C.C. (1:1.5:3) 1
Unit: 1.00 m3
S.No. Description Unit Quantity Unit Rate Amount (NRs.) Remarks
(NRs.)
1 Man Power
Skilled Labour Md. 1.5 1,030.00 1,545.00 2
Unskilled Labour Md. 7 845.00 5,915.00
Sub total 7,460.00
2 Materials
Cement Mtn. 0.4 16500.0 6,600.00
Sand m3 0.425 3,213.67 1,365.81
Aggregates m3 0.86 3,319.61 2,854.86
Sub total 10,820.67
Total of (1+2) 18,280.67
Contractor Overhead and profit 15% 3
Total 18,280.67

22. Description of the Items: P.C.C. (M30/20) (Machine mixed


Unit: 1.00 m3
S.No.
22. Description of the Items: P.C.C. (1:1:2) 1
3
Unit: 1.00 m
S.No. Description Unit Quantity Unit Rate Amount (NRs.) Remarks
(NRs.)
1 Man Power
Skilled Labour Md. 1.5 1,030.00 1,545.00 2
Unskilled Labour Md. 7 845.00 5,915.00
Sub total 7,460.00
2 Materials
Cement Mtn. 0.5 16500.0 8,250.00
Sand m3 0.425 3,213.67 1,365.81
Aggregates m3 0.85 3,319.61 2,821.67
Sub total 12,437.48
Total of (1+2) 19,897.48
Contractor Overhead and profit 15% 3
Total 19,897.48

23. Description of the Items: P.C.C. (1:2:4) in plum concrete


Unit: 1.00 m3
S.No.
1

24. Description of the Items: P.C.C. in plum concrete (1:2:4) w


Unit: 1.00 m3
S.No.
1

2
25. Description of the Items: P.C.C. in plum concrete (1:1:2) with 50% of Plum 25. Description of the Items: P.C.C. in plum concrete (1:2:4) w
3
Unit: 1.00 m Unit: 1.00 m3
Unit Rate
S.No. Description Unit Quantity Amount (NRs.) Remarks S.No.
(NRs.)
1 Man Power 1
Skilled Labour Md. 0.5 1,030.00 515.00
Unskilled Labour Md. 5 845.00 4,225.00
Sub total 4,740.00
2 Materials 2
Cement Mtn. 0.375 16500 6,187.50
3
Sand m 0.45 3214 1,446.15
3
Aggregate10-20 m 0.58 3320 1,925.37
Aggregate10 0.3 3320 995.88
3
Selected boulder m 0.5 Err:509 Err:509
Sub total Err:509
Total of (1+2) Err:509
Contractor Overhead and profit 15% Err:509
Total Err:509 26. Description of the Items: Cutting, bending and fixing of R
Unit: 1.00 Mtn.
S.No.
1

2
27. Description of the Items: Wooden formwork on wall, verti
Unit: 1.00 m2
S.No.
1

27. Description of the Items: Wooden formwork on wall, vertical surface height upto 4m. ( For 10 m2)
Unit: 1.00 m2
Unit Rate
S.No. Description Unit Quantity Amount (NRs.) Remarks 2
(NRs.)
1 Man Power
Skilled Labour Md. 1.72 1,030.00 1,771.60
Unskilled Labour Md. 2.57 845.00 2,171.65
Sub total 3,943.25
2 Materials

Timber m3 0.07 #REF! #VALUE!


strut m3 0.18 Err:509 Err:509
Nail Kg 2.5 112.00 280.00
Sub total #VALUE!
Total of (1+2) #VALUE!
Contractor Overhead and profit 15% 28. Description of the Items: Wooden formwork on wall, verti
Total #VALUE! Unit: 1.00 m2
Cost for (single use) 1.00 m2
#VALUE! S.No.
1

2
29. Description of the Items: Plywood formwork on pear and
Unit: 1.00 m2
S.No.
1

30. Description of the Items: Plywood formwork on pear and


Unit: 1.00 m2
S.No.
1

2
31. Description of the Items:Gabion crate making and filling b
Unit: 1.00 m3
S.No.
1

32. Description of the Items : Dewatering works


Unit: 1.00 hour
S.No.

2
33. Description of the Items : Dress stone linning (Five sides r
Unit: 1.00 m3
S.No.
1

34. Description of the Items : Dress stone linning (Three sides


Unit: 1.00 m3
S.No.
1

35. Description of the Items: 20 mm thick cement plastering w


Unit: 1.00 m2
S.No.
1

2
36. Description of the Items: 12.5 mm thick cement plastering
Unit: 1.00 m2
S.No.
1

37. Description of the Items: Fabrication, Transportation and


Unit: per Mtn
S.No.
1

3
38. CGI Roffing 26 Gaudge
S.No.
1

2
Contractor Overhead and profit 0%
1. Description of the Items: Construction Site Clearance (Thick Bush Cutting and removal)
Unit: 1 sq. m.
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks

Man Power
Skilled Labour Md.
Unskilled Labour Md. 0.06 845.00 50.70
Sub total 50.70
Materials
Sub total
Tools and Plants 3% of Labour cost 1.52
Total of (1+2+3) 52.22
Contractor Overhead and profit 15% -
Total 52.22

4. Description of the Items:E/W Excavation in pipeline in all type of soil including 10 m haulage and 1.50 m lift
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md.
Unskilled Labour Md. 0.75 845.00 633.75
Sub total 633.75
Materials
Sub total
Tools and Plants 3% of Labour cost 19.01
Total of (1+2+3) 652.76
Contractor Overhead and profit 15% -
Total 652.76

5. Description of the Items:E/W In Excavation in pipeline gully cutting in soft soil including 15 m haulage and 3.0 m lift
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks

Man Power
Skilled Labour Md.
Unskilled Labour Md. 0.86 845.00 726.70
Sub total 726.70
Materials
Sub total
Tools and Plants 3% of Labour cost 21.80
Total of (1+2+3) 748.50
Contractor Overhead and profit 15% -
Total 748.50

5. Description of the Items:Eathwork excavation in soft soil including 10 m haulage and 1.50 m lift (1m3)
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Un-skilled Labour md 0.9 845.00 760.50
Tools and plants 22.82 3% of labour cost
Standard specification
for Road and bridge
Subtotal 783.32
Contractor Overhead and profit 15% - Activity no. 9.02
Grand Total 783.32 Spec. Clause No. 905

6. Description of the Items:Eathwork excavation in boulder mixed soil including 10 m haulage and 1.50 m lift (1m3)

Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks


Un-skilled Labour md 1 845.00 845.00
Tools and plants 25.35 3% of labour cost
Standard specification
for Road and bridge
Subtotal 870.35
Contractor Overhead and profit 15% - Activity no. 9.02
Grand Total 870.35 Spec. Clause No. 905

7. Description of the Items:Eathwork excavation in soft rock including 10 m haulage and 1.50 m lift (1m3)
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Un-skilled Labour md 3 845.00 2,535.00
Tools and plants 76.05 3% of labour cost
Standard specification
for Road and bridge
Subtotal 2,611.05
Contractor Overhead and profit 15% - Activity no. 9.02
Grand Total 2,611.05 Spec. Clause No. 905

8. A) Description of the Items:Eathwork excavation in hard rock without blasting including 10 m haulage and 1.50 m lift (1m3)

Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks


Un-skilled Labour md 16 845.00 13,520.00
Tools and plants 405.60 3% of labour cost
Standard specification
for Road and bridge
Subtotal 13,925.60
Contractor Overhead and profit 15% - Activity no. 9.02
Grand Total 13,925.60 Spec. Clause No. 905

8. B) Description of the Items:Eathwork excavation in hard rock withblasting including 10 m haulage and 1.50 m lift (1m3)

Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks


Labour
Manual drilling (unskilled labour) md 4.5 845.00 3,802.50
Blaster md 0.12 Err:509 Err:509
Subtotal Err:509

Materials
Gelatin kg 0.25
Detonator no. 2
fusewire mtr 2
Subtotal 0
Tools and plants - 3% of labour cost
Standard specification
for Road and bridge
Subtotal Err:509
Contractor Overhead and profit 15% Err:509 Activity no. 9.02
Grand Total Err:509 Spec. Clause No. 905

9. Description of the Items:Boulder Breaking including 10 m haulage and 1.50 m lift


Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks

Man Power
Skilled Labour Md.
Unskilled Labour Md. 6 845.00 5,070.00
Sub total 5,070.00
Materials 0
Sub total
Tools and Plants 3% of Labour cost 152.10
Total of (1+2+3) 5,222.10
Contractor Overhead and profit 15% -
Total 5,222.10
10. Description of the Items:Eathwork excavation in Hard rock with chisel including 10 m haulage and 1.50 m lift
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md.
Unskilled Labour Md. 12 845.00 10,140.00
Sub total 10,140.00
Materials 0
Sub total
Tools and Plants 3% of Labour cost 304.20
Total of (1+2+3) 10,444.20
Contractor Overhead and profit 15% -
Total 10,444.20
11. Description of the Items:Eathwork in filling with common materials (depth upto 1.5m) (1m3)
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks

Un-skilled labour md 0.5 845.00 422.50

Vibrator roller (1-1.5t capacity) hr 0.11 - manual compaction


Diesel ltr 0.11 -
tools and plants 12.68 3% of labour cost
subtotal 435.18
Contractor Overhead and profit 15% -
Grand Total 435.18 as per norms of DOR

12. Description of the Items:Eathwork filling with river bed materials


Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks

Man Power
Skilled Labour Md.
Unskilled Labour Md. 0.7 845.00 591.50
Sub total 591.50
Materials
Filling material m3 1.1 Err:509 Err:509
Sub total Err:509
Tools and Plants 3% of Labour cost 17.75
Total of (1+2+3) Err:509
Contractor Overhead and profit 15% Err:509
Total Err:509

13. Description of the Items:Dry stone Masonry (coursed rubble) including dressing etc. complete as per specification, lead 30m
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Labour
Skilled md 1.25 1,030.00 1287.5
Unskilled md 2 845.00 1690
Sub- total 2977.50
Materials
Block stone (rubble) m3 1.15 2,366.11 2721.02
Sub-total 2721.02
Equipment
Standard specification
Total 5698.52 for Road and bridge
Contractor Overhead and profit 15% 0.00 Activity no. 26.01
Grand Total 5698.52 Spec. Clause No. 2602

15. Providing and laying Random rubble stone masonary in mud mortar lead 30m masoned height (0-5m)
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md. 1 1,030.00 1,030.00
Unskilled Labour Md. 2.25 845.00 1,901.25
Sub total 2,931.25
Materials
Stone m3 1.15 2,366.11 2,721.02
mud (clay) m3 0.40 50.00 20.00
water ltr 60.00 0.50 30.00
Sub total 2,771.02
Standard specification
Total of (1+2) 5,702.27 for Road and bridge

Contractor Overhead and profit 15% - Activity no. 26.01


Total 5,702.27 Spec. Clause No. 2602

16. Description of the Items:Random rubbel masonry wall in (1:3) cement mortar (machine mixing)
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md 1.5 1,030.00 1,545.00
Unskilled Laubour Md 3.5 845.00 2,957.50
Sub total 4,502.50
Material
Cement ton 0.19 16,500.00 3,135.00
Sand m3 0.4 3,213.67 1,285.47
Stone m3 1.15 2,366.11 2,721.02
Diesel lit 1 120 120.00

Sub total 7,261.49


Equipment
Concrete mixture hr 0.15 50 7.50
Sub total 7.50 Standard specification
Total of (1+2+3) 11,771.49 for Road and bridge
Contractor Overhead and profit 15% - Activity no. 26.03
Total 11,771.49 Spec. Clause No. 2602

17. Description of the Items:Random rubbel masonry wall in (1:4) cement mortar (machine mixing)
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md 1.5 1,030.00 1,545.00
Unskilled Laubour Md 3.5 845.00 2,957.50
Sub total 4,502.50
Material
Cement ton 0.155 16,500.00 2,557.50

Sand m3 0.45 3,213.67 1,446.15


Stone m3 1.15 2,366.11 2,721.02
Diesel lit 1 120 120.00
Sub total 6,844.67
Equipment
Concrete mixture hr 0.15 50 7.50
Sub total 7.50
Standard specification
Total of (1+2+3) 11,354.67 for Road and bridge
Contractor Overhead and profit 15% - Activity no. 26.03
Total 11,354.67 Spec. Clause No. 2603

18. Description of the Items:Random rubbel masonry wall in (1:6) cement mortar (machine mixing)
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md 1.5 1,030.00 1,545.00
Unskilled Laubour Md 3.5 845.00 2,957.50
Sub total 4,502.50
Material
Cement ton 0.105 16,500.00 1,732.50

Sand m3 0.5 3,213.67 1,606.83


Stone m3 1.15 2,366.11 2,721.02
Diesel lit 1 120 120.00
Sub total 6,180.35
Equipment
Concrete mixture hr 0.15 50 7.50
Sub total 7.50
Standard specification
Total of (1+2+3) 10,690.35 for Road and bridge
Contractor Overhead and profit 15% - Activity no. 26.03
Total 10,690.35 Spec. Clause No. 2606

19. Description of the Items: P.C.C. (1:3:6) (M10/40) in foundation of structure. (Machine Mixed)
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md. 0.5 1,030.00 515.00
Unskilled Labour Md. 3.5 845.00 2,957.50
Sub total 3,472.50
Materials
Cement ton 0.22 16,500.00 3,630.00

Sand m3 0.48 3,213.67 1,542.56


Aggregates (20-40) mm m3 0.65 3,319.61 2,157.75
3
Aggregates (10-20) mm m 0.25 3,319.61 829.90
petrol ltr 0.1 140 14.00
diesel ltr 3 120 360.00
Sub total 8,534.21
Equipment
Concrete mixer hr 0.6 50 30
vibrator hr 0.25 40 10
Sub total 40
Standard specification
Total of (1+2+3) 12,046.71 for Road and bridge
Contractor Overhead and profit 15% - Activity no. 20.01
Total 12,046.71 Spec. Clause No. 2000

20. Description of the Items: P.C.C. (1:2:4) (M15/40) (Machine mixed)


Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md. 0.9 1,030.00 927.00

Unskilled Labour Md. 9 845.00 7,605.00


Sub total 8,532.00
Materials
Cement ton 0.26 16,500.00 4,290.00
3
Sand m 0.46 3,213.67 1,478.29
Aggregates (20-40) mm m3 0.53 3,319.61 1,759.39
3
Aggregates (10-20) mm m 0.24 3,319.61 796.71
petrol ltr 0.1 140 14.00
diesel ltr 3 120 360.00
Sub total 8,698.39
Equipment
Concrete mixer hr 0.6 50 30
vibrator hr 0.25 40 10
Sub total 40
Total of (1+2+3) 17,270.39
Standard specification
Contractor Overhead and profit 15% - for Road and bridge
Total 17,270.39 Activity no. 20.02
Spec. Clause No. 2000

21. Description of the Items: P.C.C. (1:1.5:3) (M20/20) (Machine mixed)


Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour md 0.9 1,030.00 927

Unskilled Labour md 9 845.00 7605


Sub total 8532
Materials
Cement ton 0.33 16500.00 5445.00
3
Sand m 0.44 3,213.67 1414.0126
3
Aggregates (10-20 mm) m 0.58 3,319.61 1925.3738
3
Aggregates (10mm &down) m 0.3 1600 480
Petrol lit 0.1 138.54 13.85
Diesel lit 3 118.45 355.35
Water lit 198 0 0
9633.59
Equipments
mixer (0.28/0.20 m3) hr 0.6 50 30
vibrator hr 0.25 40 10
Sub total 40
Standard specification
Total of (1+2) 18205.59 for Road and bridge
Contractor Overhead and profit 15% 0.00 Activity no. 20.02
Total 18205.59 Spec. Clause No. 2000

21. Description of the Items: P.C.C. (1:1:2) (M25/20) (Machine mixed)


Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour md 0.9 1,030.00 927

Unskilled Labour md 9 845.00 7605


Sub total 8532
Materials
Cement ton 0.375 16,500.00 6187.50
3
Sand m 0.45 3,213.67 1446.14925
3
Aggregates (10-20 mm) m 0.58 3,319.61 1925.3738
Aggregates (10mm &down) m3 0.3 3,319.61 995.883
Petrol lit 0.1 140 14
Diesel lit 3.2 120 384
Water lit 225 0
Sub total 10952.91
Equipments
mixer (0.28/0.20 m3) hr 0.6 50 30
vibrator hr 0.25 40 10
Sub total 40
Standard specification
Total of (1+2) 19524.91 for Road and bridge
Contractor Overhead and profit 15% 0.00 Activity no. 20.02
Total 19524.91 Spec. Clause No. 2000

22. Description of the Items: P.C.C. (M30/20) (Machine mixed)


Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour md 0.9 1,030.00 927

Unskilled Labour md 9 845.00 7605


Sub total 8532
Materials
Cement ton 0.41 16,500.00 6765.00
Sand m3 0.44 3,213.67 1414.0126
3
Aggregates (10-20 mm) m 0.57 3,319.61 1892.1777
3
Aggregates (10mm &down) m 0.33 3,319.61 1095.4713
Petrol lit 0.1 140 14
Diesel lit 3 120 360
Water lit 246 0
Sub total 11540.66
Equipments
mixer (0.28/0.20 m3) hr 0.6 50 30
vibrator hr 0.25 40 10
Sub total 40
Standard specification
Total of (1+2) 20112.66 for Road and bridge
Contractor Overhead and profit 15% 0.00 Activity no. 20.02
Total 20112.66 Spec. Clause No. 2000
23. Description of the Items: P.C.C. (1:2:4) in plum concrete
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md. 0.5 1,030.00 515.00
Unskilled Labour Md. 4.5 845.00 3,802.50
Sub total 4,317.50
Materials
Cement Mtn. 0.32 16500.0 5,280.00
3
Sand m 0.425 3,213.67 1,365.81
3
Aggregate m 0.76 3,319.61 2,522.90
3
Selected boulder m 0.13 Err:509 Err:509
Sub total Err:509
Total of (1+2) Err:509
Contractor Overhead and profit 15% Err:509
Total Err:509
24. Description of the Items: P.C.C. in plum concrete (1:2:4) with 30% of Plum
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md. 0.5 1,030.00 515.00
Unskilled Labour Md. 4 845.00 3,380.00
Sub total 3,895.00
Materials
Cement Mtn. 0.2 16500.00 3,300.00
Sand m3 0.425 3,213.67 1,365.81
3
Aggregate m 0.6 3,319.61 1,991.77
Selected boulder m3 0.3 Err:509 Err:509
Sub total Err:509
Total of (1+2) Err:509
Contractor Overhead and profit 15% Err:509
Total Err:509

25. Description of the Items: P.C.C. in plum concrete (1:2:4) with 50% of Plum
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md. 0.5 1,030.00 515.00
Unskilled Labour Md. 5 845.00 4,225.00
Sub total 4,740.00
Materials
Cement Mtn. 0.15 16500.00 2,475.00
3
Sand m 0.2 3,213.67 642.73
3
Aggregate m 0.4 3,319.61 1,327.84
Selected boulder m3 0.5 Err:509 Err:509
Sub total Err:509
Total of (1+2) Err:509
Contractor Overhead and profit 15% Err:509
Total Err:509
26. Description of the Items: Cutting, bending and fixing of Reinforcement steel bar
Unit: 1.00 Mtn.
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md. 10 1,030.00 10,300.00
Unskilled Labour Md. 13 845.00 10,985.00
Sub total 21,285.00
Materials
Re-bar Mtn. 1.05 84,000.00 88,200.00
Binding wire Kg 10 92.00 920.00
Sub total 89,120.00
Total of (1+2) 110,405.00
Contractor Overhead and profit 15% -
Total 110,405.00

27. Description of the Items: Wooden formwork on wall, vertical surface height upto 4m. ( For 10 m2)
Unit: 1.00 m2
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md. 2.2 1,030.00 2266
Unskilled Labour Md. 2.2 845.00 1859
Sub total 4125
Materials
Ply wood 9mm thick m2 11 600 6600
strut, ballies m3 0.4 Err:509 Err:509
Nail, spikesetc Kg 2.5 112.00 280.00
Sub total Err:509
Total of (1+2) Err:509

Standard specification
Contractor Overhead and profit 15% Err:509 for Road and bridge
Total Err:509 Activity No. 18.02.01
2
Cost for (single use) 1.00 m Err:509 Spec. Clause No. 1805
Err:509 Using 8-12 times

28. Description of the Items: Wooden formwork on wall, vertical surface Ht. from 4.00m to 10.00 m ( For 10 m2)
Unit: 1.00 m2
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md. 5.19 1,030.00 5,345.70
Unskilled Labour Md. 7.5 845.00 6,337.50
Sub total 11,683.20
Materials
Timber m3 1.478 #REF! #VALUE! Local rate=Rs. 7064/m3
Nail Kg 6.93 112.00 776.16 No. of use = 3 times
Sub total #VALUE!
Total of (1+2) #VALUE!
Contractor Overhead and profit 15% #VALUE!
Total #VALUE!
Cost for 1.00 m2 #VALUE!

29. Description of the Items: Plywood formwork on pear and column for more than 4 m height (For 10 m2)
Unit: 1.00 m2
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Md. 4.00 1,030.00 4,120.00
Unskilled Labour Md. 5.00 845.00 4,225.00
Sub total 8,345.00
Materials
Plywood m2 10.00 Err:509 Err:509 19 mm thick
Local rate=Rs.
3
Battern/Bulley m 0.45 #REF! #VALUE! 12000/m3
Nail Kg 6.93 112.00 776.16 No. of use = 3 times
Sub total Err:509
Total of (1+2) Err:509
Contractor Overhead and profit 15% Err:509
Total Err:509
2
Cost for 1.00 m Err:509

30. Description of the Items: Plywood formwork on pear and column for less than 4 m height (For 10 m2)
2
Unit: 1.00 m
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power

Skilled Labour Md. 2.50 1,030.00 2,575.00


Unskilled Labour Md. 2.00 845.00 1,690.00
Sub total 4,265.00
Materials
Plywood m2 10.00 Err:509 Err:509 19 mm thick
Local rate=Rs.
3
Batten/Bulley m 0.45 #REF! #VALUE! 12000/m3
Nail Kg 6.93 112.00 776.16 No. of use = 3 times
Sub total Err:509
Total of (1+2) Err:509
Contractor Overhead and profit 15% Err:509
Total Err:509
Cost for 1.00 m2 Err:509

31. Description of the Items:Gabion crate making and filling by boulder (Size 2m*1m*1m)
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Skilled Labour Sq.m. 11.00 12 132.00 For making
Skilled Labour Md. 0.93 1,030.00 957.90 For filling
Unskilled Labour Md. 2.44 845.00 2061.80 For filling
Sub total 3151.70
Materials
Mesh wire 10 SWG Kg 30.60 105.00 3213.00
Selvege 7 SWG Kg 5.67 105.00 595.35
Binding wire 12 SWG Kg 0.50 84.00 42.00
Boulder m3 2.20 2,366.11 5205.43
Sub total 9055.78
Total of (1+2) 12207.48
Contractor Overhead and profit 15% 0.00
Total 12207.48
Cost for 1.00 m3 6103.74

32. Description of the Items : Dewatering works


Unit: 1.00 hour
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks

Man Power
Skilled Labour Md. 0.15 1,030.00 154.50 For making
Unskilled Labour Md. 0.10 845.00 84.50 For making
Sub total 239.00
Equipment
Pump 4" and accessories Hour 24.00 2.3 55.20 Rs.2.30/hour
Electriciry Hour 24.00 21 504.00
Sub total 559.20
Total of (1+2) 798.20
Contractor Overhead and profit 15% 0.00
Total in 24 hour 798.20
Cost for 1.00 hour 33.26
33. Description of the Items : Dress stone linning (Five sides rough and one side smooth dressed)
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Unskilled Labour Md. For collection & dressing
Skilled Labour Md. For linning
Unskilled Labour Md. For linning
Sub total
Materials
Cement Mtn.
Sand m3
Sub total
Total of (1+2)
Contractor Overhead and profit 15%
Total 0.00
34. Description of the Items : Dress stone linning (Three sides rough and one side smooth dressed)
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Unskilled Labour Md. For collection & dressing
Skilled Labour Md. For linning
Unskilled Labour Md. For linning
Sub total
Materials
Cement Mtn.
Sand m3
Sub total
Total of (1+2)
Contractor Overhead and profit 15%
Total 0.00

35. Description of the Items: 20 mm thick cement plastering work (1:4) for 100m2
Unit: 1.00 m2
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Unskilled Labour Md. 20.00 845.00 16900.00
Skilled Labour Md. 20.00 1,030.00 20600.00
Sub total 37500.00
Materials
Cement Mtn. 0.80 14,500.00 11600.00
Sand m3 2.10 0 0.00
Sub total 11600.00
Total of (1+2) 49100.00
Contractor Overhead and profit 15% 0.00
Total 49100.00
Cost for 1.00 m2 491.00

36. Description of the Items: 12.5 mm thick cement plastering work (1:4) for 100 m2
Unit: 1.00 m2
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power
Unskilled Labour Md. 19.00 845.00 16055.00
Skilled Labour Md. 19.00 1,030.00 19570.00
Sub total 35625.00
Materials
Cement Mtn. 0.54 14,500.00 7801.00
Sand m3 1.46 0 0.00
Sub total 7801.00
Total of (1+2) 43426.00
Contractor Overhead and profit 15% 0.00
Total 43426.00
Cost for 1.00 m2 434.26
37. Description of the Items: Fabrication, Transportation and Erection of Penstock Pipe with Materials
Unit: per Mtn
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
Man Power at site
Fabricator Md. 14.00 #REF! #VALUE!
Welder Md. 13.00 #REF! #VALUE!
Painter Md. 9.00 #REF! #VALUE!
Unskilled Labour Md. 22.00 845.00 18,590.00
Sub total #VALUE!
Materials
Steel Sheet Mt 1.05 70000 73,500.00
Welding Rods LS 3500 3,500.00
Sub total 77,000.00
Others
Transportation up to Manufacturer Mt 1.00 1200 1,200.00
Transportation to the Site Mt 1.00 1500 1,500.00
Acid bath/sand blasting and epoxy LS 20000 20,000.00
Site Erection LS 1400 1,400.00
Electricity Power LS 1075 1,075.00
Sub total 25,175.00
Total of (1+2+3) #VALUE!
Contractor Overhead and profit 15% #VALUE!
Total #VALUE!

38. CGI Roffing 26 Gaudge


Description Unit Quantity Unit Rate (NRs.) Amount (NRs.) Remarks
manpower
Skilled Labor Md 1.1 845.00 929.5
Unskilled Labor Md 1.25 1,030.00 1287.5
2217
Material
CGI Sheet Sqm 1.25 423.33 529.17
Nails LS 12 2.24 26.88
Sub total 556.05
Total of (1+2) 2773.05
Contractor Overhead and profit 15% 0.00
Total 2170.00
8. Rubble random stone masonry work in 1:4 cement sand mortar including supply of materials, mortar mixing and laying, carriage upto 30 m

Unit: 1.00 m3
S.No. Description Unit Quantity Unit Rate (NRs.) Amount (NRs.)

1 Man Power
Skilled Labour Md 1.5 1,030.00 1,545.00
Unskilled Laubour Md 3.5 845.00 2,957.50
Sub total 4,502.50
2 Material
Cement ton 0.155 16,500.00 2,557.50
Sand m3 0.45 3,213.67 1,446.15
Stone m3 1.15 2,366.11 2,721.02
Diesel lit 1 100 100.00
Sub total 6,824.67
3 Equipment
Concrete mixture hr 0.15 435 65.25
Sub total 65.25

Total of (1+2+3) 11,392.42


Contractor Overhead and profit 15% 1708.86
Total 13,101.28

5. Earth work in excavation( Ordinary Soil) of foundation of structures, including construction of shoring and bracing, removal of stumps and other
deleterious matter and backfilling with approved Material as per Drawing and Technical Specifications.( Manually)

S.No. Description Unit Quantity Unit Rate (NRs.) Amount (NRs.)


1 Labour
a) Site Clearance md 0.06 845.00 50.70
b) Excavation md 0.9 845.00 760.50
c) Backfiiling md 0.5 845.00 422.50
Sub-Total 1,233.70
b) Tools and plants 37.01
Subtotal 2,453.71
c) Contractor Overhead and profit 15% 368.06
Grand Total 2,821.77

4. Providing and laying of Plain Cement Concrete M 10 ( or 1:3:6 for nominal mix) in Foundation complete as per
Drawing and Technical Specifications.
Unit: 1.00 m3
S.No. Description Unit Quantity Unit Rate (NRs.) Amount (NRs.)

1 Man Power
Skilled Labour Md. 0.5 1,030.00 515.00
Unskilled Labour Md. 3.5 845.00 2,957.50
Sub total 3,472.50
2 Materials
Cement ton 0.22 16,500.00 3,630.00
Sand m3 0.48 3,213.67 1,542.56
Aggregates (20-40) mm m3 0.65 3,319.61 2,157.75
3
Aggregates (10-20) mm m 0.25 3,319.61 829.90
petrol ltr 0.1 110 11.00
diesel ltr 3 100 300.00
Sub total 8,471.21
3 Equipment
Concrete mixer hr 0.6 435 261
vibrator hr 0.25 250 62.5
Sub total 323.5

Total of (1+2+3) 12,267.21


Contractor Overhead and profit 15% 1,840.08
Total 14,107.29

Providing and placing Machine mixed cement concrete[cement (1): sand(1.5) : aggregate (3) ] M20/20
including Formwork compaction, curing, testing and lead 30m. etc. all complete as per specification and
drawing.( RCC Grade M20)
Unit: 1.00 m3

S.No. Description Unit Quantity Unit Rate (NRs.) Amount (NRs.)


1 Man Power
Skilled Labour md 0.9 1,030.00 927.00
Unskilled Labour md 4.5 845.00 3,802.50
Sub total 5580
2 Materials
Cement ton 0.41 16500.00 6765.00
3
Sand m 0.33 3,213.67 1060.51
Aggregates (10-20 mm) m3 0.5 3,319.61 1659.81
3
Aggregates (10mm &down) m 0.2 3,319.61 663.92
Petrol lit 0.1 110.00 11.00
Diesel lit 3 100 300.00
Water lit 198 0.26 51.48
10511.72
3 Equipments
mixer (0.28/0.20 m3) hr 0.6 435 261
vibrator hr 0.25 250 62.5
Sub total 80

Total of (1+2) 16171.72


Contractor Overhead and profit 15% 2425.76
Formwork 1279.31
Total 19876.78

X. Description of the Items: Ply Formwork on wall, vertical surface height upto 4m. ( For 10 m2)
Unit: 1.00 m2
S.No. Description Unit Quantity Unit Rate (NRs.) Amount (NRs.)

1 Man Power
Skilled Labour Md. 2.50 110.00 275.00
Unskilled Labour Md. 2.00 100.00 200.00
Sub total 475.00
2 Materials
Plywood m2 10.00 224.31 2,243.13
Batten/Bulley m3 0.45 435 195.75
Nail Kg 1.93 250.00 482.50
Form Oil Kg 1.00 80.00 80.00
Sub total 3,001.38
Total of (1+2) 3,476.38
Contractor Overhead and profit 15% 521.46
Total 3,997.83
Cost for 1.00 m2 399.78

3. Providing and laying Reinforcement(TMT) including cutting, bending, binding, fixing in position and lead
30m. etc. all complete as per specification and drawing.
Unit: 1.00 Mtn.
S.No. Description Unit Quantity Unit Rate (NRs.) Amount (NRs.)

1 Man Power
Skilled Labour Md. 10 1,030.00 10,300.00
Unskilled Labour Md. 13 845.00 10,985.00
Sub total 21,285.00
2 Materials
Re-bar Mtn. 1.05 78,000.00 81,900.00
Binding wire Kg 10 92.00 920.00
Sub total 82,820.00
Total of (1+2) 104,105.00
Contractor Overhead and profit 15% 15,615.75
Total 119,720.75
119.72

1. Description of the Items: Flat on brick soling


Unit: 1.00 sq. m.
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.
1 Labour
Skilled md 0.033 1,030.00 34.33333333
Unskilled md 0.133 845.00 112.6666667
Sub- total 147.00
2 Materials
Brick nos. 36 16.76 603.36
Sand cu.m. 0.02 3,213.67 64.27
Sub-total 667.63

Total 814.63
Contractor Overhead and profit 15% 122.19
Grand Total 936.83

9. Laying and fixing of Geo-Textile all complete as per specification.


Unit: 1.00 sq. m.
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.
1 Labour
Skilled md 0.030 1,030.00 30.9
Unskilled md 0.150 845.00 126.75
Sub- total 157.65
2 Materials
Geo-textile sq. m. 1 240.00 240.00
Sub-total 240.00

Total 397.65
Contractor Overhead and profit 15% 59.65
Grand Total 457.30

full width of the structure with slope of 1V :20H towards


drawing face Complete as per Drawing and Technical Specifications.
Unit: 1.00 sq. m.
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.
1 Materials
HDPE pipe rm 1 553.35 553.35
Sub-total 553.35

Total 553.35
Contractor Overhead and profit 15% 83.00
Grand Total 636.35

Providing, Laying and Levelling dry stone soling works in foundation all complete.
Unit: 1.00 m3
Description Unit Quantity Unit Rate (NRs.) Amount (NRs.)
1 Labour
Skilled md 1 1,030.00 1030
Unskilled md 2 845.00 1690
Sub- total 2720.00
2 Materials
Block stone (rubble) m3 1.15 2,366.11 2721.02
Sub-total 2721.02
3 Equipment

Total 5441.02
Contractor Overhead and profit 15% 816.15
Grand Total 6257.17

S.No. Description Unit Quantity Unit Rate (NRs.) Amount (NRs.)


1 Labour
Un-skilled labour md 0.5 750.00 375.00
2 Filling Soil cu. m. 1 150 150
3 Tamping Rammer( 2 Ton) hr 0.11 75 8.25
4 Diesel ltr 0.11 100 11
5 tools and plants 11.25
subtotal 386.25
Contractor Overhead and profit 15% 57.94
Grand Total 444.19
mortar mixing and laying, carriage upto 30 m

Labour
Remarks Contract

2000

6,824.67

65.25
65.25
Standard specification for Road and
bridge 8,889.92
Activity no. 26.03 133349%
Spec. Clause No. 2603 10,223.41

horing and bracing, removal of stumps and other


ations.( Manually)

Remarks

Per Sq. m

3% of labour cost
Standard specification for Road and
bridge
Activity no. 9.02
Spec. Clause No. 905

omplete as per

Remarks
Standard specification for Road and
bridge
Activity no. 20.01
Spec. Clause No. 2000

0/20
on and

Remarks

Mix Design

Standard specification for Road and


bridge
Activity no. 20.02
Considering Beam
Spec. Clause No. 2000

Remarks
Considering Reuse for 10-12 times

and lead

Remarks

Per kg

Remarks

Remarks
Remarks

PN-6

Remarks

Standard specification for Road and


bridge
Activity no. 26.01
Spec. Clause No. 2602

Remarks

3% of labour cost

as per norms of DOR

You might also like