Problem No. 01
Moyna Ltd. applies Standard Costing & their records contain the following information:
Required:
Solution:
Required: a)
Moyna Ltd.
Statement of Cost
Moyna Ltd.
Variance Analysis Report
Standard Data:
Material Cost Tk. 40,000 ; Labor Cost Tk. ? ; Overhead Cost Tk. 30,000 ; Sales Tk. 1,25,000.
Actual Data:
Material Cost Tk. ? ; Labor Cost Tk. 35,000 ; Overhead Cost Tk. ? ; Sales Tk. 1,40,000.
Variance Data:
Material Cost Variance Tk.10,000 (Adverse) ; Labor Cost Variance Tk.5,000 (Favorable) ;
Overhead Cost Variance Tk.5,000 (Adverse) .
Required: Prepare a Cost Statement showing standard and actual cost per unit and also prepare a
Variance Analysis Report.
Problem No. 04
The following information has been taken from the records of Titir Ltd. for a particular period:
Budgeted Sales:
Actual Sales:
***